Ref. No.

IH-MYP-MOM-MK-0002_Rv0
Minutes of Meeting Issued date July 18, 2018
Meeting date July 17, 2018 16:00-17:30
Meeting place Kajima Office/ Yankin Township, Yangon
Attendee Kajima Myanmar Company Limited (hereafter: Kajima) ;
Mr, Myo Thet Soe, Mr. Chikubu, Mr. Zin Win Htet
Hoa Binh Construction Group (hereafter: HBCG) ;
Mr. Tommy Pham, Mr. Leo Thiha,
I&H Engineering Co., Ltd. (hereafter: I&H) : KAN’O
Subject Responsible

Kick-off meeting for mock-up test in Yankin PPP Project was held and following subjects
was discussed and settled in this meeting.

1, Purpose of mock-up test


Kajima settled the purpose of mock-up test by I&H as followings.

- Confirmation of I&H production capacity


- Confirmation of validity of PCa shape
- Confirmation according to the latest design drawing
- Confirmation of validity of each tolerance
- Flow up result of mock-up test by High Tech Precast Co., Ltd.

Kajima commented that applicable tolerance value for PCa member shall be developed
due to execution of mock-up test since the tolerance has not been specified in Project till
now.

2, Schedule for mock-up test


Based on submitted schedule as shown in Attachment-1, the detail for each work was
confirmed.

The latest planning schedule achieved already to the following condition which Mr.
Yamamoto PD requested as collateral condition in Contract.

Email body dated on 12th of July 2018 from Mr. Yamamoto PD;
At least each 1 set of column/ beam to be complete your fabrication, ready for
inspection by Kajima Tokyo, VMD scheduled for 12/ SEP.

The target date for starting of installation work was settled as 27th of Sep. 2018 in this I&H and HBCG
meeting.

3, Submittal document
Kajima requested and settled following submittal and submittal date as shown in Table 1 I&H
below. The detail to be described in each document is shown in Attachment-2.

Table 1 Submittal document and date


No. Submittal Item Submittal date
1 Quality control By 20th of July 2018
2 Method Statement of Production By 27th of July 2018
3 Method Statement of Rectification By 27th of July 2018
4 Safe Work Procedure By 27th of July 2018
4, Flow-up result of mock-up test by High Tech Precast Co., Ltd.
Kajima distributed the following reports (Attachment-3, -4 and -5) as feedback item in Kajima, I&H and
Mock-up test dealt by I&H and HBCG HBCG

Instruction Comments from Mr. Brian (KYP) for;


- Precast Mock Up (Attachment-3)
- Precast Mock up Installation at High Tech Precast Factory (Attachment-4)
- Precast Mock up Grouting at High Tech Precast Factory (Attachment-5)

5, Others

1) Propping point on column member


In order to arrangement for installation of necessary embedded item into column
member, I&H requested Kajima to give the information regarding of the number and
location of embedded item, which connecting with propping connector HBCG will install.
HBCG will inform the information to I&H due to going through by Kajima by 21st of July Kajima
2018.

2) Necessary area of working platform for installation work


I&H introduced the planning of working platform for installation work with Attachment-6.
The location is planned in I&H Hmawbi factory and the size is width; 17m, length; 4m
such that the area may cover the shape of mock-up member after installation.
As result of discussion, it was settled that the stick-out part; (300mm height) from
concrete basement does not need to be installed since the joint part with upper column
will be grouted after the new floor will be made as equal level with lower column top.
I&H requested Kajima to confirm the necessary area for Installation working platform Kajima
since I&H will start to prepare the execution.

3) Visiting on I&H Hmawbi factory I&H


To know the detail of working area in I&H Hmawbi factory, both, Kajima and HBCG
offered to visit on I&H Hmawbi factory as planned.

For Kajima; 20th of July 2018


For HBCG; Within this week (one day from 18th to 21st of July 2018)

In the case of Kajima visiting, Kajima requests to see the concreting procedure including
of quality control for PCa Girder production.

6, Attachments
Attachment-1: Attachment-3 Overall schedule for Mock-up test in Contract
Attachment-2: I&H Meeting Agenda dated on 17th of July 2018
Attachment-3: Instruction Comments from Mr. Brian (KYP) for Precast Mock Up
Attachment-4: Instruction Comments from Mr. Brian (KYP) for Precast Mock up
Installation at High Tech Precast Factory
Attachment-5: Instruction Comments from Mr. Brian (KYP) for Precast Mock up
Grouting at High Tech Precast Factory
Attachment-6: Draft of working platform for installation work