You are on page 1of 31

OISD-STD-141

First Edition April 1990


Amended Edition, September 2001
Revised Edition, September 2003

FOR RESTRICTED
CIRCULATION

DESIGN AND CONSTRUCTION REQUIREMENTS

FOR

CROSS COUNTRY HYDROCARBON PIPELINES

Prepared by

COMMITTEE ON
DESIGN AND INSPECTION OF
PIPELINES

OIL INDUSTRY SAFETY DIRECTORATE


7th FLOOR, “NEW DELHI HOUSE”
27, BARAKHAMBA ROAD
NEW DELHI -110001
NOTE

OISD publications are prepared for use in the oil and gas
industry under Ministry of Petroleum & Natural Gas. These are
the property of Ministry of Petroleum & Chemicals and shall not
be reproduced or copied and loaned or exhibited to others without
written consent from OISD.

Though every effort has been made to assure the accuracy


and reliability of the data contained in these documents. OISD
hereby expressly disclaims any liability or responsibility for loss or
damage resulting from their use.

These documents are intended to supplement rather than


replace their prevailing statutory requirements.
FOREWARD

The Oil Industry in India is 100 years old. Due to various collaboration
agreements, a variety of international codes, standards and practices are in vogue.
Standardisation in design philosophies and operating and maintenance practices at a
national level was hardly in existence. This, coupled with feed back from some serious
accidents that occurred in the recent past in India and abroad, emphasised the need
for the industry to review the existing state of art in designing, operating and
maintaining oil and gas installations.

With this in view, the then Ministry of Petroleum and Natural Gas in 1986
constituted a Safety Council assisted by Oil Industry Safety Directorate (OISD) staffed
from within the industry in formulating and implementing a serious of self regulatory
measures aimed at removing obsolescence, standardising and upgrading the existing
standards to ensure safer operations. Accordingly OISD constituted a number of
Functional Committees comprising of experts nominated from the industry to draw up
standards and guidelines on various subjects.

The present standard on “Design and Construction Requirements for Cross


Country Hydrocarbon Pipelines” was prepared by the Functional Committee on
“Design and Inspection of Pipelines”. This standard is based on the accumulated
knowledge and experience of industry members and the various national and
international codes and practices. This standard is meant to be used as a supplement
and not as a replacement for existing codes and practices. It is hoped that the
provision of this standard if implemented objectively, may go a long way to improve the
safety and reduce accidents in the Oil and Gas Industry. Users are cautioned that
no standard can be a substitute for the judgement of responsible and experienced
engineer. Suggestions are invited from the users after it is put into practice to improve
the standard further. Suggestions for amendments to this standard should be
addressed to:-

The Coordinator,
Committee on Inspection of “Design and Inspection of Pipelines”,
Oil Industry Safety Directorate,
7th Floor, New Delhi House,
27-Barakhamba Road,
New Delhi-110 001.

This standard in no way supersedes the statutory regulations of Chief Controller


of Explosive (CCE), Factory Inspectorate or any other Statutory body which must be
followed as applicable.
COMMITTEE
ON
DESIGN AND INSPECTION OF PIPELINES

( First Edition April 1990 )

-------------------------------------------------------------------------------------------------------
Name Organisation
-------------------------------------------------------------------------------------------------------

Leader
1. Sh.V.T. Karode Oil India Limited

2. Sh.R.A. Shanbhag ** Indian Oil Corporation Limited

Members
3. Sh.Rao Rudravajala Indian Oil Corporation Limited

4. Sh.S.K. Goyal Oil and Natural Gas Corporation Limited

5. Sh.C.N. Char Oil and Natural Gas Corporation Limited

6. Sh.E.M Bhumgara Hindustan Petroleum Corporation Limited

7. Sh.R.K. Mulla Hindustan Petroleum Corporation Limited

8. Sh.R.K. Dhadda Engineers India Limited

9. Sh.G.V.S. Saiprasad Gas Authority of India Limited

10. Sh.K.K. Dutta Oil India Limited

11. Sh.R.K. Baruah Oil India Limited

Member Coordinator
12. Sh.M. Bhandari Oil Industry Safety Directorate
-------------------------------------------------------------------------------------------------------
In addition to the above, several other experts from the industry contributed in the preparation, review
and finalisation of this document.

** (Took over as Leader w.e.f June/89 on Shri Karode’s retirement from Oil India
Ltd).
COMMITTEE
ON
DESIGN AND INSPECTION OF PIPELINES

( First Revision September 2003 )

-------------------------------------------------------------------------------------------------------
Name Organisation

Leader
1. Sh.A. Sengupta Indian Oil Corporation Limited

Members

2. Sh.G.S. Wankhede Bharat Petroleum Corporation Limited

3. Sh.KBS Negi Bharat Petroleum Corporation Limited

4. Sh.S.S.Patel GAIL India Limited

5. Sh.P.K.Pal Indian Oil Corporation Limited

6. Sh.C..K. Soman Kochi Refineries Limited

Member Coordinator
7. Sh.R.N.Mittal Oil Industry Safety Directorate
-------------------------------------------------------------------------------------------------------
In addition to the above, several other experts from the industry contributed in the preparation, review
and finalisation of this document.
DESIGN AND CONSTRUCTION REQUIREMENTS
FOR
CROSS COUNTRY HYDROCARBON PIPELINES

CONTENTS

Sl.No ITEM DESCRIPTION PAGE NO.


PART - I
1.0 INTRODUCTION 1

2.0 SCOPE 1

3.0 DEFINITIONS 1

4.0 DESIGN 1

4.1 Dynamic Effects 2

4.2 Weight Effects 2

4.3 Corrosion 2

4.4 Design of Components 2

4.5 Valves 2

4.6 Threaded Joints 2

4.7 Stress Values 2

4.8 Design of Pipe supporting Elements 2

5.0 MATERIALS 2

5.1 Steel 2

5.2 Materials for Sour Multiphase Service 3

6.0 DIMENSIONAL REQUIREMENTS 3

7.0 CONSTRUCTION, WELDING AND ASSEMBLY 3

7.1 Location 3

7.2 Handling, Hauling, Stringing and Storing 3

7.3 Ditching 4

7.4 Bends, Miters and Elbows 4

7.5 Installation of Pipe in the Ditch 4

7.6 Special Crossings 5

7.7 Pump Station, Tank Farm and Terminal 6


Construction
7.8 Storage and Working Tankage Storage 6

7.9 Pre-Operational Stresses 6

8.0 INSPECTION AND TESTING 6

8.1 Type and Extent of Examination Required 6

8.2 Testing 7

8.3 Commissioning 7

8.4 Record 7

9.0 OPERATION AND MAINTENANCE 7


PROCEDURES
10.0 CORROSION CONTROL 8

10.1 Protective Coating 8

10.2 Cathodic Protection System 8

10.3 Electrical Isolation 8

10.4 Temporary Cathodic Protection System 8

PART – II
11.0 DESIGN 11

12.0 PIPING SYSTEMS 11

13.0 MATERIALS AND EQUIPMENT 11

14.0 WELDING 12

15.0 PIPING SYSTEM COMPONENTS AND 12


FABRICATION DETAILS
15.1 Valves and Pressure Reducing Devices 12

15.2 Expansion and Flexibility 12

15.3 Combined Stress Calculations 13

15.4 Supports and Anchorage for Exposed Piping 15

15.5 Pre-Operational Stresses 15

16.0 DESIGN, INSTALLATION AND TESTING 15

16.1 General Provisions 15

16.2 Population Density Index 16

16.3 Corrosion Allowance 16

16.4 Cover Requirements for Pipelines 16


16.5 Clearance Between Pipelines or Mains and other 16
underground Structures
16.6 Casing, Requirements under Rail Roads, 16
Highways, Roads or Streets
16.8 Bends, Elbows and Miters in Steel Pipelines and 16
Mains
16.9 Miscellaneous Operations involved in the 17
Installation of Steel Pipelines and Mains
16.10 Water Crossings 17

16.11 Crossing of / or by Utilities 18

16.12 Testing after Construction 18

16.13 Control and limiting of Gas Pressure 20

16.14 Valves 20

16.15 Pipe Book 21

17.0 OPERATING AND MAINTENANCE 21


PROCEDURES
18.0 CORROSION CONTROL 21

18.1 Coating Requirements 21

18.2 Electrical Isolation 21

18.3 Electrical Connections and Monitoring Points 21

18.4 Electrical Interference 22

18.5 Existing Installations 22

18.6 Temporary Cathodic Protection System 22

18.7 Internal Corrosion Control 23

19.0 MISCELLANEOUS 23

20.0 REFERENCES 23
DESIGN AND CONSTRUCTION REQUIREMENTS
FOR
CROSS COUNTRY HYDROCARBON PIPELINES

1.0 INTRODUCTION Areas not covered by 'Offshore' as


defined in B 31.4 clause 400.2-
Definitions is defined as 'Onshore'. The
Safety in petroleum installations and definitions of 'Offshore' as per B 31.4 is
pipelines comes through continuous reproduced hereunder for easy
efforts at all stages and as such it can reference:
be ensured by observing that
installations and pipelines are designed, ‘Offshore - Areas beyond the line of
constructed and tested as per ordinary high water, along that portion
recognised engineering standards and of the coast that is in direct contact with
they are periodically inspected and the open seas and beyond the line
maintained. marking the seaward limit of inland
coastal waters’.
2.0 SCOPE
c) ON SHORE – GAS PIPELINES
This standard outlines the minimum
requirements for design, materials, Areas not covered by 'Offshore' as
construction, assembly, inspection, defined in B 31.8 clause 803.17 is
testing, commissioning, operation, defined as 'Onshore'. The definition of
maintenance and safety aspects of 'Offshore' as per B 31.8 is reproduced
cross country pipelines – onshore, (A) hereunder for easy reference:
transporting liquids such as crude oil,
condensate, natural gasoline, natural 'Offshore-Areas beyond the line of
gas liquids, and liquid petroleum ordinary high water, along that portion
products (B) transporting Natural Gas, of the coast that is in direct contact with
between producer lease facilities, tank the open seas and beyond the line
farms, natural gas processing plants, marking the seaward limit of inland
refineries, stations, terminals (marine, coastal waters.'
truck and rail) and other delivery and
receiving points. d) SHALL

For convenience 'ASME/ANSI Code B The word 'Shall' is used to indicate that
31.4 herein after is referred' as 'B 31.4'. the provision is mandatory.
and 'ASME/ANSI Code B 31.8 herein
after is referred' as 'B 31.8'. e) SHOULD

The word 'Should' is used to indicate


3.0 DEFINITIONS that the provision is recommendatory as
sound engineering practices.
a) MULTIPHASE FLUIDS
PART-I
Multiphase fluids means oil, gas or
water in any combination produced LIQUID PETROLEUM
from one or more oil wells or TRANSPORTATION SYSTEMS
recombined oil well fluids that may have
been separated in passing through 4.0 DESIGN
treatment/processing facilities. For the Design of cross country pipelines –
purpose of this standard, multiphase onshore shall be as per ANSI/ASME
fluids are considered to be low vapour B31.4.
pressure fluids.
4.1 DYNAMIC EFFECTS
b) ON SHORE – LIQUID PIPELINES
Other Loadings Supports, Braces and Anchors

Unusual loadings such as those caused 4.8.1 Wherever non integral attachments,
by scour, erosion, soil movement and such as pipe clamps and ring girders
slides, installation forces, vortex are used, adequate precautions shall be
shedding and other phenomena shall taken to prevent corrosion at or near
also be considered and provided for in the contact points.
accordance with sound engineering
practice. 4.8.2 If a pipeline is designed to operate at
stress level of more than 50% of the
4.2 WEIGHT EFFECTS specified minimum yield strength of the
pipe, all connections welded to the pipe
Live Loads shall be made to a separate cylindrical
member which completely encircles the
Weight of water during hydrostatic pipe, and this encircling member shall
testing shall also be considered while be welded to the pipe by continuous
designing. circumferential welds at both ends.

4.3 CORROSION 5.0 MATERIALS


Whenever internal or external corrosion 5.1 STEEL
is expected during the design life of the
pipeline, a suitable corrosion allowance 5.1.1 Carbon Equivalent shall be calculated
shall be made at the design stage. based on the formula given below:

4.4 DESIGN OF COMPONENTS CE = C + Mn + Cr+Mo+V + Ni+Cu


6 5 15
4.4.1 STRAIGHT PIPE Carbon Steels having a specified
carbon content in excess of 0.32% or a
The least nominal wall thickness (tn) for carbon equivalent in excess of 0.65%
steel pipe, as indicated in B 31.4 clause shall be preheated. API-1104 shall be
404.1.1 shall not be less than the referred for guidance.
dimensions indicated in the 5.1.2 Additional test requirements shall be as
specifications for line pipe approved by per Appendix-A of Part-I of this
B 31.4. Further, pipe having a D/tn ratio standard for steel pipes manufactured
greater than 150 shall not be used, by Electric Resistance Welding and/or
where D = outside diameter of pipe. Electric Induction welding.

4.5 VALVES 5.1.3 Mill Hydrostatic Testing of line pipe is


recommended as 90% of SMYS
Valves made of cast iron or ductile iron irrespective of grade of pipe material.
shall not be used. The pressure hold period should be 15
sec.
4.6 THREADED JOINTS
5.1.4 Ultrasonic testing for pipe skelp and
Threaded joints shall not be used in weld seam is 100%. Ultrasonic testing
cross country pipelines. for pipe ends is mandatory.

4.7 STRESS VALUES 5.2 MATERIALS FOR SOUR


MULTIPHASE SERVICE
Consideration shall be given to the use
of lower allowable design stress if there 5.2.1 Definition
is likelihood of repeated stress
changes giving rise to fatigue NACE Standard MR-OI-75 'Sulfide
conditions. Stress Corrosion Cracking Resistant
Metallic Materials for Oil Field
4.8 DESIGN OF PIPE Equipment defines limiting
SUPPORTING concentrations on hydrogen sulphide in
ELEMENTS the fluid transported' for it to be
considered as sour service.
All provisions of B 31.4 Chapter IV shall
Note: While past experience has apply.
indicated this to be the accepted
minimum concentration at which 7.0 CONSTRUCTION, WELDING
sulphide stress corrosion cracking may
occur, the presence of other AND ASSEMBLY
constituents in the phases making up
the multiphase fluid, such as carbon 7.1 LOCATION
dioxide in the gas and salt in the water
or larger amounts of free water or gas, The location of a new underground
may cause problems to occur at lower pipeline, when running parallel to an
concentrations of hydrogen sulphide. existing underground pipeline, should
be at a minimum clear distance of 5.0
5.2.2 General metres from the existing underground
pipeline when heavy conventional
In addition to the applicable construction equipment is excepted to
requirements of B31.4 and this be utilized. This distance may be
standard, all materials used in sour reduced after careful assessment of
multiphase service shall meet the construction methodologies so that it
following requirements. does not result in unsafe conditions
during construction. In any case the
a) Pipe, valve, fittings, flanges bolting minimum clear distance shall not be
and other equipment exposed to or less than 3.0 metres. These areas shall
which are necessary to contain sour be distinctly identified on ground during
multiphase fluids may be susceptible to construction.
stress corrosion cracking and hydrogen
induced stepwise cracking and thus due No pipeline should be located within
consideration shall be given to material 15.0 metres of any private dwelling or
selection in design. any industrial building or place of public
assembly in which persons work,
b) Materials for sour multiphase service congregate or assemble, unless it is
shall conform to the requirements of provided with at least 300 mm of cover
NACE Standard MR-01-75, 'Sulphide in addition to that provided in Table
Stress Corrosion Cracking Resistant 7.3.3 of this standard.
Metallic Material for Oil Field
Equipment'. Depending upon the 7.2 HANDLING, HAULING, STRINGING
service and the materials involved, the AND STORING
Sulphide Stress Corrosion Cracking
(SSCC) and Hydrogen Induced Pipe shall not be strung along the right
Cracking (HIC) tests should be of way in rocky areas where blasting
conducted as per NACE standards may be required, until all blasting is
referred in Clause 20.0 of this complete and the area cleared of all
standard. The acceptance criteria shall debris. Material other than line pipe
be based on current established shall not be strung on the right of way
industry practice. but shall be transported to site for use
only at the time of installation.
c) Pressure containing components
(excluding pipe) intended for sour 7.3 DITCHING
multiphase service shall be fully
identified with a permanent marking. 7.3.1 The width of trench shall be such that a
minimum clear distance of 200mm for
5.2.3 Pipes made of cast iron, ductile iron, trench in normal soil and 300mm for
bronze and other copper based trench in rock is maintained between
materials shall not be used in sour edge of pipe and the trench wall at the
multiphase service. bottom of trench.

6.0 DIMENSIONAL 7.3.2 Pipelines shall be buried below ground


REQUIREMENTS level, unless construction above ground
is found to be desirable for exceptional
technical, economic or topographical
reasons.
bending. The length of the straight
7.3.3 Minimum cover for Buried Pipelines section shall permit easy jointing.
Tangents approximately 1 metre in
The minimum cover shall be as per length shall be provided on both ends of
table 7.3.3 given below. cold bends.

TABLE 7.3.3 7.4.2 Pipes with longitudinal welds shall be


Minimum Cover for Buried Pipelines bent in such a way that weld lies in the
________________________________ plane passing through neutral axis of
Location Minimum the bend which shall be installed
Cover in positioning the longitudinal weld in the
metre upper quadrants.
________________________________
Industrial, Commercial 1.0 (2) 7.4.3 BENDS MADE FROM PIPE
and Residential Areas
The minimum radius of field cold bends
Stream, Canal and other 1.5 (4) shall be as follows:
Minor water crossings ________________________________
Nominal Pipe Minimum Radius of
Drainage ditches at 1.0 size In Bend in Pipe Diameter
Roadways and railroads ________________________________
NPS 12 and smaller 21D
Rocky Areas 1.0 (2) NPS 14 u/i 18 30D
NPS 20 and larger 40D
Uncased/Cased Road 1.2 (3)
Crossings 7.4.4 MITERED BENDS

Railroad Crossings 1.4 (3) A mitered bend is not permitted with the
exception of deflections upto 3 degrees
Other Areas 1.0 (2) that are caused by misalignment.

(1) The above mentioned minimum 7.5 INSTALLATION OF PIPE IN THE


cover requirements shall be valid for all DITCH
class locations.
Before lowering operations are
(2) Minimum depth of cover shall be commenced, particular attention shall
measured from the top of pipe coating be paid to the suitability of the trench to
to the top of undisturbed surface of the allow the pipeline to be lowered without
soil, or top of graded working strip, the coating being damaged and to give
whichever is lower. Fill material in a reasonably even support to the
working strip shall not be considered to pipeline.
add to the depth of cover.
When already coated pipes are being
(3) Cover shall be measured from the lowered, a complete check of the pipe
top of road or top of rail, as the case coating and field joint coating shall be
may be. carried out and all damages repaired.

(4) In case of rivers/water bodies, Wherever pipeline is laid under tension


which are prone to scour and erosion, as a result of an assembly error (for
adequate safe cover (minimum 1.5 example incorrect positioning of bends,
metre) shall be provided below the either horizontal or vertical), the trench
predicted scour profile expected during shall be rectified or in exceptional cases
the life time of the pipeline. a new assembly shall be carried out so
that it fits the excavation and the laying
7.4 BENDS, MITERS AND ELBOWS bed.

Bends made from pipe Care must be taken that during laying,
the deformation caused during the
7.4.1 The ends of each bent length shall be raising of the pipe from the support
straight and not involved any way in the does not exceed the values for the
minimum allowable radius of elastic remain within permissible limits in
curvature, so as to keep the stresses in accordance with B 31.4.
the steel pipe and on the coating within
safe limits. f) Whenever considered desirable,
the section of the pipeline
In laying parallel pipelines in the same corresponding to the river crossing
trench, the minimum clear distances should before installation be subjected
between the pipelines shall be 500 mm. to hydrostatic pre-testing. However, the
complete pipeline corresponding to river
7.6 SPECIAL CROSSINGS crossing shall be tested after
installation.
7.6.1 Water crossings
7.6.2 Crossing of or by Utilities
Special considerations shall be required
for submerged crossings which are a) A minimum clearance of 300mm
characterized by their perennial nature, shall be maintained at the point of
meandering course, steep and crossing and the utility or pipeline shall
potentially erodable banks, potentially be installed at a uniform depth for the
scouring bed, large erodable flood plain full width of the right of way. Where it
and wide water course (high water mark is not practicable to obtain the above
to high water mark) both during the mentioned clearance, special design
design and installation of such and construction shall be used.
crossings.
b) A clearance sufficiently large to
For river crossings such as those avoid electrical fault current interference
described and established above the shall be maintained between the
following additional requirements are to pipeline and the grounding facilities of
be considered. electrical transmission lines.

a) Hydrological and geotechnical c) Interference with, or from, other


surveys to establish the river bed and systems through the application of
water current profiles to predict the cathodic protection shall be dealt by
behaviour of the river with respect to mutual action of the parties involved.
change of course, scour of bed and
erosion of banks and to obtain all other d) When laid parallel to, along or near
parameters related to design and underground power and / or
installation of such crossings. communication cables, conductors or
conduit, underground pipes shall
b) The pipeline at such crossings maintain a vertical clearance of at least
shall be installed with extra depth of 300 mm. Where these clearances
cover. The cover provided shall be cannot be maintained, extra precaution
adequate to prevent exposure of the shall be taken to ensure the maximum
pipeline for the entire design life of the possible clearance and to prevent
pipeline. future contact. If pipelines and
communication and / or power utilities
c) To ensure the stability of the share the same trench, the above
underwater pipeline, it may be clearance shall be maintained with the
necessary to add weight to sink and pipeline preferably at a lower level.
hold the pipeline in position.
e) A minimum separation of 3.0 metre
d) A heavier wall thickness pipe should be maintained between pipeline
shall be provided for the river crossing and transmission tower footings, ground
section. cables and counter poise. Regardless
of separation, consideration should
e) A detailed stress analysis for the always be given to lightning fault current
pipe section for river crossings should protection of pipelines and safety of
be carried out, taking into consideration personnel.
the effect of all loads during laying and
it shall be ensured that the stresses 7.6.3 All crossings shall be made in such a
manner that the angle between the
centerline of the railway, highway, river,
stream, canal or utility being crossed constructed as an above ground
and the centerline of the pipeline shall installation or is buried in unstable
be as close as possible to 90 degree soils).
but in no case less than 45 degree .
8.0 INSPECTION AND TESTING
7.7 PUMP STATION, TANK FARM AND
TERMINAL CONSTRUCTION
8.1 TYPE AND EXTENT OF
EXAMINATION REQUIRED
7.7.1 Location
Construction
Minimum distances from property lines
and road allowance limits to buildings 8.1.1 Field pipeline coating shall be applied
and equipment etc. shall meet the on a properly prepared surface and
requirements of OISD Standard 118 visually inspected during application.
"Layouts for Oil and Gas Installations". Any cutting or removal of the coating
shall be promptly and carefully repaired.
7.8 STORAGE AND WORKING TANKAGE
STORAGE 8.1.2 Yard-coated pipe shall be examined
after field bending to ensure that the
Underground Storage quality of the coating has not been
impaired.
Prior to design and construction of an
underground storage chamber, an 8.1.3 Additional precautions such as double
engineering and geological investigation coating, rock shield, selected backfill,
shall be carried out to determine the and ditch padding shall be taken where
feasibility of such a system at the conditions are such that damage to the
proposed site. Such chambers shall be pipe coating could occur.
constructed and operated in
accordance with GPA Publication 8175, 8.1.4 If moisture is present on the surface of
Method for Underground Storage of the pipe, no coating materials shall be
National Gas Liquids applied.

7.9 PRE-OPERATIONAL STRESSES 8.1.5 Unless special procedures can be


taken, no coating shall be applied when
It is desirable to limit stresses during the ambient temperature might have a
pre-operational manipulation of the pipe detrimental effect on the coating either
so as to avoid damage that might impair during or after application.
the operability of the line. The designer
shall ensure that pre-operational 8.2 TESTING
stresses are controlled and that they
are non-injurious to the pipe. 8.2.1 A gauging pig shall be passed through
Consideration shall be given to, but not the pipeline to prove the internal
restricted to, the effect of the following diameter of the entire line. The gauging
pre-operational loads: plate shall have a diameter of 95% of
the internal diameter of the pipeline.
a) Transportation and stockpiling of
the pipe; 8.2.2 All sections which have been previously
hydrostatically tested viz. road/rail
b) Stringing, coating and wrapping, crossings and river crossings shall be
and laying.; retested alongwith the completed
mainline sections.
c) Backfilling;
Water used for testing should be dozed
d) Loads imparted by construction with suitable corrosion inhibitor, if
traffic; required.

e) Field bending; 8.2.3 Test Pressure

f) hydrostatic test pressure loads Hydrostatic Testing of Internal


(particularly when the pipeline is Pressure Piping
then dried as thoroughly as possible.
The test pressure shall be decided as After drying, the pipeline shall be filled
per B31.4. The duration of hydrostatic with the liquid. Care shall be taken to
proof test shall be minimum 24 hours. clear pockets of water from valves and
fittings.
8.2.4 Acceptance of Test
8.4 RECORD
The test is successful when the pipeline
has withstood the strength and leak Pipe Book
tests and during the test period there is
no observable drop in pressure that A pipe and welding book shall be
cannot be accounted for by temperature maintained for all projects. The purpose
changes. of the pipe book shall be to indicate and
maintain as a permanent record the
8.2.5 Termination of Testing exact position in the pipeline of each
pipe length and each pipeline material
The pipeline shall be slowly like valves, scraper traps, bends,
depressurized at a moderate and flanges, and other fittings installed in
constant rate. During dewatering, care the project. Each item shall be
shall be taken to properly dispose the recorded by its identification number.
discharging water in order to avoid Location of each weld including weld
pollution, damages to fields under number, welder number, type of welding
cultivation and/or existing structures and electrode, weld treatment and
and interference with the traffic. details of equipment used for
radiography shall be recorded in the
8.2.6 Pre- tested Pipe pipe book.

Pipe used for making repairs shall be 9.0 OPERATION AND


pre-tested to a pressure equal to or MAINTENANCE PROCEDURES
greater than the original pipeline
strength test pressure. All provisions of B 31.4-Chapter-VII and
OISD-STD-138 shall apply.
8.2.7 Preservation of Pipeline
10.0 CORROSION CONTROL
If the pipeline is to be preserved for a
specified duration before it can be 10.1 PROTECTIVE COATING
commissioned, the pipeline shall be
completely filled with water with a) Coatings shall electrically isolate
sufficient quantities of corrosion the external surface of the piping
inhibitors depending upon the quality of system from the environment.
water and the period of preservation
and at a suitable pressure. b) All joints, fittings, repairs and tie-ins
shall be coated with a material
8.3 COMMISSIONING compatible with the existing coating.

8.3.1 Commissioning shall consist of 10.2 CATHODIC PROTECTION SYSTEM


displacing the hydrostatic test water
from the pipeline by pumping in the a) Existing Bare Pipelines Systems
liquid to be transported. Batching pigs
or spheres shall be used not only to Investigation shall be made to
minimize mixing at the interface but determine the extent or effect, of
also to enable the progress of the corrosion on existing bare pipeline
interface to be followed. systems. When these investigations
indicate that continuing corrosion will
8.3.2 In cases where the water has to be create a hazard, corrosion control
cleared from the pipeline before measures or other remedial action shall
commissioning because of possible be undertaken.
chemical or physical action between the
water and the liquid to be transported, b) Cathodically Protected Pipeline
the pipeline shall be first drained and Systems Temporarily Out of service
B.1.
Cathodic Protection system shall be
maintained on any pipeline that is
temporarily out of service.

10.3 ELECTRICAL ISOLATION

Whereas such insulating devices are


installed, they shall be properly rated for
temperature, pressure, electrical
properties, and shall be resistant to the
commodity carried in the pipeline
systems.

10.4 TEMPORARY CATHODIC


PROTECTION SYSTEM

When considered necessary a


temporary cathodic protection system a) Selection of Mandrel
with sacrificial anodes shall be installed
to ensure adequate protection of The reverse bend test shall be carried
pipeline from external corrosion from out with a mandrel, whose radius(R),
the time the pipeline is laid in the trench width(A) shall be calculated for any
till the permanent cathodic protection combination of diameter, wall thickness
system is commissioned. and grade with the formula.

The temporary CP system shall A = 2R = 1.4 (D-t) t


preferably be installed simultaneously ------------- -t
keeping pace with the pipeline laying / e(D-2t)-1.4t
installation work and shall be monitored
periodically. where, D - Outside diameter of pipe
t - Wall thickness of pipe
10.5 Safety appliances shall be provided 1.4 - Peaking factor
against lightning, stray current inter- e - Strain
ference from foreign objects at HT
pipeline crossings. Minimum values of 'e' shall be as
follows:
----------------------------------------------------
APPENDIX - A Grade of Steel Min 'e' value
----------------------------------------------------
ADDITIONAL REQUIREMENTS FOR ASTM A53 B 0.1425
ELECTRIC RESISTANCE/ELECTRIC ASTM A 135 B 0.1425
INDUCTION WELDED LINE PIPE API 5L B 0.1425
API 5L X-42 0.1375
B.1 Reverse Bend Tests API 5L X-46 0.1325
API 5L X-52 0.1275
Reverse bend tests shall be performed API 5L X- 56 0.1175
on the pipe piece cut from the crop end API 5L X- 60 0.1125
from the front end of the first length and API 5L X- 65 0.1100
the back end of the last length API 5L X- 70 0.1025
produced from each coil. The API 5L X- 80 0.0900
specimen shall be 100mm to 115mm ----------------------------------------------------
long and shall be reverse bend tested in
accordance with procedure given below b) Procedure
and Figure
The mandrel is to be plugged into the
specimen, with the weld in contact with
mandrel, to such a depth that the angle
of engagement between mandrel and
0
specimen reaches 60 (see Fig. B1). If
the combination of diameter and wall
thickness of pipe, and radius of mandrel A test specimen shall be taken across
is such that the angle of engagement the longitudinal weld from one length of
0
does not reach 60 , the mandrel shall finished pipe from each lot of maximum
be plugged into the specimen until 50 lengths from the same heat
opposite walls of the specimen meet. manufactured from the same process.

c) Acceptance Criteria These specimens shall be polished and


etched for micro-examinations. The
A specimen which fractures completely examinations shall provide evidence
prior to the specified engagement of that heat treatment of weld zone is
mandrel and specimen, or which adequate and there is no untempered
reveals cracks and ruptures in the weld martensite left.
or heat affected zone longer than 4mm,
shall be rejected. Cracks less than The Manufacturer shall make hardness
6mm long at the edges of the specimen measurements on each specimen as
shall not be cause for rejection. indicated in Fig. B.2 in accordance with
ASTM E-32. The maximum difference
B.2 Micrographic and Hardness in hardness between base material and
Examination any reading taken in the heat affected
zone shall be less than 80 points
Vicker's HV10.
PART-II

GAS TRANSPORTATION SYSTEMS


11.0 DESIGN a) The minimum design
temperature shall be taken as the
Design of cross country pipelines – lowest expected operating pipe or
onshore shall be as per ANSI/ASME metal temperature when the hoop
B31.8. stress exceeds 50 MPa (7000 psi),
having due regard to past recorded
temperature data and the minimum
12.0 PIPING SYSTEMS gas temperature that may occur. The
minimum design temperature shall
12.1 The Pipe wall thickness less than 6.4 take into account the effect of lower air
mm should not be used for cross or ground temperatures in the area.
country pipelines in the city limits.
b) The maximum design
12.2 Pipe diameter 4” and above shall be temperature shall be taken as the
used for cross country pipelines. highest expected operating pipe or
metal temperature, having due regard
12.3 All cross country pipelines shall be to past recorded temperature data and
piggable. the possibilities of higher temperatures
occurring.
13.0 MATERIALS AND
EQUIPMENT 13.3 MATERIAL SPECIFICATIONS

13.1 When the maximum design 13.3.1 Carbon Equivalent


temperature exceeds 120 deg.C (250
deg. F), particular attention shall be Carbon Equivalent shall be calculated
given to the tensile properties of the based on the formula given below:
material to ensure that the derating for
temperature is adequate. CE = C + Mn + Cr+Mo+V + Ni+Cu
6 5 15
13.2 OPERATING CONDITIONS, Carbon Steels having a specified
TEMPERATURE AND NOTCH carbon content in excess of 0.32% or
TOUGHNESS REQUIREMENTS a carbon equivalent in excess of
0.65% shall be preheated. API-1104
13.2.1 For steel pipes smaller than 2" NPS shall be referred for guidance.
and steel valves, fittings and flanges
smaller than 2" NPS, proven notch 13.3.2 If steel pipe is intended to be heated
toughness properties are not during fabrication and/or installation,
mandatory. the effect of the time-temperature
relationship on the mechanical
13.2.2 For steel pipes and associated steel properties of the pipe shall be
components of size 2" NPS and larger, determined and taken into
Notch toughness values shall be consideration.
determined to provide protection
against fracture initiation and 13.3.3 Additional test requirements shall be
propagation. Notch toughness valves specified as per Standards /
(minimum absorbed energy valves) Guidelines mentioned in Appendix-A,
shall be specified based on the design Part-I of this standard for steel pipes
operating stress and the minimum manufactured by Electric Resistance
design temperature. Welding and/or Electric Induction
Welding.
13.2.3 The minimum and maximum design
temperatures shall be determined as 13.3.4 Mill Hydrostatic Testing of line pipe is
follows: recommended as 90% of SMYS
irrespective of grade of pipe material.
The pressure hold period should be 15 tests should be conducted as per
sec. NACE standards mentioned in Clause
20.0 of this standard. The acceptance
13.3.5 Ultrasonic testing for pipe skelp and criteria shall be based on current
weld seam is 100%. Ultrasonic testing established industry practices.
for pipe ends is mandatory.
d) Pressure containing components
13.4 REQUIREMENTS FOR SOUR GAS (excluding pipes) intended for sour gas
SERVICE service shall be fully identified with a
permanent marking.
13.4.1 Definition
e) Cast iron line pipe shall not be used
NACE standard MR-01-75 "Sulphide to convey sour gas.
Stress Corrosion Cracking Resistant
Metallic Material for Oil Field 14.0 WELDING
Equipment" defines specific
conditions, which a gaseous Carbon equivalent (CE) wherever
hydrocarbon shall be considered to be referred in this chapter, shall be
sour. calculated based on the following
formula:
Note: While the limiting conditions
defined in NACE standard MR-01-75 CE = C + Mn + Cr+Mo+V + Ni+Cu
for considering gaseous hydrocarbons 6 5 15
as sour is the normally accepted
minimum concentration of hydrogen Carbon Steels having a specified
sulphide at which material problems carbon content in excess of 0.32% or
occur, the presence of other a carbon equivalent in excess of
constituents in the gas stream, such 0.65% shall be preheated. API-1104
as CO2 and Salts in water, may cause shall be referred for guidance.
problems at lower concentrations of
hydrogen sulphide. 15.0 PIPING SYSTEM
13.4.2 General
COMPONENTS AND
FABRICATION DETAILS
a) In addition to the applicable
requirements of B 31.8 and this 15.1 VALVES AND PRESSURE
standard, all materials used in sour REDUCING DEVICES
gas service shall also meet the
following requirements. Valves made of cast iron or ductile iron
shall not be used in gas piping
b) Pipe, valves, fittings, flanges, systems.
bolting and other equipment exposed
to or which are necessary to contain 15.2 EXPANSION AND FLEXIBILITY
sour gas may be susceptible to
Sulphide Stress corrosion cracking 15.2.1 This section is applicable to both
and hydrogen induced step-wise above ground and buried piping and
cracking and thus due consideration covers all classes of materials
shall be given to material selection in permitted by this standard. Formal
design. calculations shall be required where
reasonable doubt exists as to the
c) All materials used in sour gas adequate flexibility of the piping.
service shall conform to the material
requirements of NACE standard MR- Note : For the purpose of this
01-75, "Sulphide Stress Corrosion standard, 'unrestrained' means that
Cracking Resistant Metallic Material the pipe is able to strain along its
for Oil Field Equipment". Depending length, move laterally, or both. Pipe
upon the service and the materials that does not meet both of the above
involved, the Sulphide Stress requirements is referred to as
Corrosion Cracking (SSCC) and 'restrained'. Typically, long straight
Hydrogen Induced Cracking (HIC) lengths of buried pipe and above
ground pipe on closely spaced rigid
supports are classified as restrained, (a) Internal pressure;
whereas buried pipelines adjacent to
bends or unanchored end caps could (b) Thermal expansion and
be regarded as restrained or contraction;
unrestrained, depending on specific
circumstances. (c) Differential support movements;

15.2.2 EXPANSION AND FLEXIBILITY (d) Self-weight and gravity dead


loads;
a) Expansion calculations are
necessary for buried lines if significant (e) Static wind loads and static fluid
temperature changes are expected. loads.
Thermal expansion of buried lines may
cause movement at points where the ii) In addition to the requirements of
line terminates, changes in direction, Clause 15.3.2(i) above, consideration
or changes in size. Unless such shall be given, where applicable, to the
movements are restrained by suitable service conditions to which the pipe
anchors, the necessary flexibility shall and support system are to be
be provided. subjected. Consideration shall also be
given to, but not necessarily limited to
b) Means of providing Flexibility the effects of the following additional
loadings:
If expansion is not absorbed by direct
axial compression of the pipe, (a) Overburden loads;
flexibility shall be provided by the use
of bends, loops, or offsets or provision (b) Live loads;
shall be made to absorb thermal
strains by expansion joints or (c) Buoyancy;
couplings of the slip joint, ball joint, or
bellows type. If expansion joints are (d) Dynamic and seismic loads:
used, anchors or ties of sufficient Seismic load consideration for
strength and rigidity shall be installed earthquake prone areas should be
to provide for end forces due to fluid taken after proper seismic survey to
pressure and other causes. determine liquefaction factor of soil.
The pipeline cover will be decided
15.3 COMBINED STRESS considering the above factor.
CALCULATIONS
(e) Cyclic and vibratory loads
including the effect of Stress
15.3.1 General
Intensification. Factors on the fatigue
life of components;
In addition to satisfying the
requirements of clause 841 of B 31.8,
(f) Internal pressure fluctuations;
it may be necessary to calculate the
longitudinal, axial, and bending
(g) External hydrostatic pressure
stresses, the torsional stresses, the
(including collapse, wave loadings and
hoop stresses, the stress interactions
all significant fluid loads to which a
and the reactions at significant points
submerged line might be submitted);
in the system. In calculating these
stresses and reactions and the effects
(h) Geotechnical loads (including
of various loadings on the piping the
slides, differential settlement,
designer shall use established
loss of support, and thermal effect of
fundamental analysis methods.
the pipeline on soil properties).
15.3.2 Loading Considerations
15.3.3 Stress Values
i) Consideration shall be given to the
stresses and reactions caused by, but a) General
not necessarily limited to the following
loadings:-
There are fundamental differences in
loading conditions for the buried, or Stresses due to expansion for those
similarly restrained positions of the portions on the piping without
piping and the above ground portions substantial axial restrain shall be
not subject to substantial axial combined in accordance with the
restraint. Therefore, different limits on following equation:
allowable longitudinal expansion
2 2
stresses are necessary. SE = Sq. Root of (Sb + St )

b) Restrained Lines Where,

The net longitudinal compressive SE = Stress due to expansion.


stress due to the combined effects of
2 2
temperature rise and fluid pressure Sb = Sq. Root of{( i1 M1) + ( i0 M0) }/Z
shall be computed from the equation:
=equivalent bending stress, psi
SL = Ea (T2-T1) - v Sh (MPa)

in which, St = Mt/2Z = torsional stress, psi(MPa)

SL = The longitudinal compressive M1 = Bending moment in plane of


stress, psi(MPa) member (for members having
significant orientation, such as elbows
Sh = Hoop stress due to internal fluid or tees, for the latter the moments in
pressure, psi (MPa) the header and branch portions are to
be considered separately) in.lb. (N.m)
T1 = Temperature at time of
installation degrees F(degrees C) M0 = bending moment out of, or
transverse,to plane of member, in lb.
T2 = Maximum or minimum (N.m)
operating temperature degrees
F(degrees C) Mt = torsional moment, in lb. (N.m)

E = Modulus of Elasticity of steel, ii = stress intensification factor


psi (MPa) under bending in plane of member (B
31.8 Appendix E)
a = Linear coefficient of thermal
expansion, inch per inch per degree F io = stress intensification factor under
(mm per mm per degree C) belonging out of, or transverse to,
plane of member (B 31.8 Appendix E)
v = Poisson's ratio = 0.30 for steel
Z = Section modulus of pipe,
3 3
Note that the net longitudinal stress inch (mm )
becomes compressive for moderate
increases of T2 and that according to The maximum computed expansion
the commonly used maximum shear stress range, SE without regard for
theory of failure, this compressive fluid pressure stress, based on 100
stress adds directly to the hoop stress per cent of the expansion, with
to increase the equivalent tensile modulus of elasticity for the cold
stress available to cause yielding. condition, shall not exceed 0.72 times
This equivalent tensile stress shall not the specified minimum yield strength
be allowed to exceed 90 per cent of of the pipe.
the specified minimum yield strength
of the pipe, calculated for nominal pipe The total of the following shall not
wall thickness. Beam bending exceed the specified minimum yield
stresses shall be included in the strength, S.
longitudinal stress for those portions of
the restrained line which are supposed a) the combined stress due to
above ground. expansion, SE.

c) Unrestrained Lines b) the longitudinal pressure stress.


d) Loads imparted by construction
c) the longitudinal bending stress due traffic;
to external loads, such as weight of
pipe and contents, wind etc. e) Field bending;

The sum of the longitudinal stresses f) hydrostatic test pressure loads


due to pressure, weight, and other (particularly when the pipeline is
sustained external loadings shall not constructed as an above grade
exceed 0.75 time the allowable stress installation or is buried in unstable
in the hot condition. soils).

The sum of the longitudinal stresses 16.0 DESIGN, INSTALLATION


produced by pressure, live and dead
AND TESTING
loads, and those produced by
occasional loads, such as wind or
earthquake, shall not exceed 80 per 16.1 GENERAL PROVISIONS
cent of the specified minimum yield
strength of the pipe. It is not The selection of design for pipeline
necessary to consider wind and system shall be based on the following
earthquake as occurring concurrently. evaluation of the properties and
required flow rate of the fluid to be
Stresses due to test conditions are not transported, together with the
subject to the above limitations. It is environment in which the pipeline is to
not necessary to consider other be installed.
occasional loads, such as wind and
earthquake, as occurring concurrently a) Sweet or sour natural gas, single
with the live, dead and test loads or multiphase flow conditions, vapour
existing at the time of test. phase LPG.

15.4 SUPPORTS AND ANCHORAGE FOR b) Operating pressures and


EXPOSED PIPING temperatures.

Attachment of supports on Anchors c) Gathering system, transmission


system, distribution system, or service
Due consideration shall be given to the lines.
effect of such attachments on possible
fatigue failures and local stress d) Onshore or offshore pipeline.
concentrations.
16.2 POPULATION DENSITY INDEX
15.5 PRE-OPERATIONAL STRESSES
A Class 4 location ends 220 metre
It is desirable to limit stresses during from the nearest building with 4 or
pre-operational manipulation of the more stories above ground.
pipe so as to avoid damage that might
impair the operability of the line. The 16.3 CORROSION ALLOWANCE
designer shall ensure that pre-
operational stresses are controlled and Whenever internal or external
that they are non-injurious to the pipe. corrosion is expected during the
Consideration shall be given to, but not design life of the pipeline, a suitable
restricted to, the effect of the following corrosion allowance shall be made at
pre-operational loads: the design stage.

a) Transportation and stockpiling of


the pipe; 16.4 COVER REQUIREMENTS FOR
PIPELINES
b) Stringing, coating and wrapping,
and laying; Refer Table 7.3.3 for cover
requirements.
c) Backfilling;
16.5 CLEARANCE BETWEEN PIPELINES The minimum radius of field cold
OR MAINS AND OTHER bends shall be as follows:
UNDERGROUND STRUCTURES _______________________________
Normal Pipe Minimum Radius of
16.5.1 In laying parallel pipelines in the same Size (in) Bending in Pipe
trench, the minimum clear distances Diameters
between the pipelines shall be 500 _______________________________
mm. NPS 12 and smaller 21 D
NPS 14 u/i 18 30 D
16.5.2 The location of a new underground NPS 20 and larger 40 D
pipeline, when running parallel to an _______________________________
existing underground pipeline should
be at a minimum clear distance of 5.0 16.8.1 The ends of each bent length shall be
metre from the existing underground straight and not involved anyway in the
pipeline when heavy conventional bending. The length of the straight
construction equipment is expected to section shall permit easy jointing.
be utilized. This distance may be Tangents approximately 1 metre in
reduced after a careful assessment of length shall be provided on both ends
construction methodologies, which do of cold bends. A field bend shall not
not result in unsafe conditions during be made within two pipe diameters of
construction. In any case the a field weld. Tangent lengths should
minimum clear distance shall not be not be reduced in the field.
less than 3.0 meter. These areas
shall be distinctly identified on ground 16.8.2 Pipes with longitudinal welds shall be
during construction. bent in such a way lies in the plane
passing through neutral axis of the
No pipeline should be located within bend which shall be installed
15.0 metre of any private dwelling, or positioning the longitudinal weld in the
any industrial building or a place of upper quadrants.
public assembly in which persons
work, congregate or assemble, unless 16.8.3 A mitered bend is not permitted with
it is provided with atleast 300 mm of the exception of deflections upto 3
cover in addition to that provided in degrees that are caused by
clause 16.4 of this standard. misalignment.

16.6 CASING, REQUIREMENTS UNDER 16.8.4 Field-cut segments of elbows NPS 12"
RAILROADS, HIGHWAYS, ROADS, and larger are not recommended.
OR STREETS
16.9 MISCELLANEOUS OPERATIONS
Pipeline, casing pipe and vent pipes INVOLVED IN THE INSTALLATION
shall be at least 1.2 metre away OF STEEL PIPELINES AND MAINS
(vertically) from aerial electrical wires
and shall be suitably insulated from 16.9.1 Handling, Hauling, and Stringing
underground conduits carrying electric
wires on railway land. Pipe shall not be strung on the Right-
of-Way in rocky areas where blasting
16.7 Design and construction of may be required, until all blasting is
gas pipelines crossing Railroads, complete and the area cleared of all
Highways, Roads or Streets shall be debris. Material other than line pipe
done in accordance with the provisions shall not be strung on the Right-of-way
of "Recommended Practice for Liquid but shall be transported to site for use
Petroleum Pipelines Crossing only at the time of installation.
Railroads and Highways" API RP 1102
and applicable clauses of B31.8 and
this standard. 16.9.2 Installation of Pipe in the Ditch

16.8 BENDS, ELBOWS AND MITERS IN Pipelines shall be buried below ground
STEEL PIPELINES AND MAINS level, unless construction above
ground is found to be desirable for
exceptional technical, economic or (a) Hydrological and geotechnical
topographical reasons. surveys to establish the river bed and
water current profiles, to predict the
Before lowering operations are behaviour of the river with respect to
commenced, particular attention shall change of course, scour of bed and
be paid to the suitability of the trench erosion of banks and to obtain all other
to allow the pipeline to be lowered parameters related to design and
without the coating being damaged installation of such crossings.
and to give a reasonably even support
to the pipeline. (b) The pipeline at such crossings
shall be installed with extra depth of
When already coated pipes are being cover. The cover provided shall be
lowered, a complete check of the pipe adequate to prevent exposure of the
coating and field joint coating shall be pipeline for the entire design life of the
carried out and all damages repaired. pipeline.

Wherever pipeline is laid under tension (c) To ensure the stability of the
as a result of an assembly error (for underwater pipeline, it may be
example, incorrect positioning of necessary to add weight to sink and
bends, either horizontal or vertical), the hold the pipeline in position.
trench shall be rectified or in
exceptional cases a new assembly (d) A heavier wall thickness pipe
shall be carried out so that it fits the shall be provided for a river crossing
excavation and the laying bed. section.

Care must be taken that the (e) A detailed stress analysis for
deformation caused during the raising the pipe section for river crossings
of the pipe from the supports does not should be necessary taking into
exceed the valves for the minimum consideration the effect of all loads
allowable radius of elastic curvature, during laying and it shall be ensured
so as to keep the stresses on the steel that the stresses remain within
pipe and on the coating within safe permissible limits in accordance with B
limits. 31.8 and this standard.

The width of trench shall be such that (f) Whenever considered


a minimum clear distance of 200mm desirable, the section of the pipeline
for trench in normal soil and 300mm corresponding to the river crossing
for trench in rock is maintained should, before installation, be
between edge of pipe and the trench subjected to hydrostatic pretesting.
wall at the bottom of trench. However, the complete pipeline
corresponding to river crossing shall
16.10 WATER CROSSINGS be tested after installation.

Special considerations shall be 16.11 CROSSING OF / OR BY UTILITIES


required for submerged crossing by
pipelines of rivers which are 16.11.1 A minimum clearance of 300mm shall
characterized by their perennial be maintained at the point of crossing
nature, meandering course, steep and and the utility or pipeline shall be
potentially erodable banks, potentially installed at a uniform depth for the full
scouring bed, large erodable flood width of the right-of-way, provided that,
plain and wide water course (high where it is not practicable to obtain the
water mark to high water mark) both above mentioned clearance, special
during the design and installation of design and construction shall be used.
such crossings:
16.11.2 A clearance sufficiently large to avoid
For river crossings such as those electrical fault current interference
described and established as above, shall be maintained between the
the following requirements are to be pipeline and the grounding facilities of
considered: electrical transmission lines.
16.11.3 Interference with, or from, other Hoop Stresses of 30% or More of
systems through the application of the Specified Minimum Yield
Cathodic Protection shall be dealt with Strength of the Pipe:
by mutual action of the parties
involved. a) All test assemblies used in testing
shall be fabricated and installed in
16.11.4 When laid parallel to along or near accordance with provisions of B 31.8
underground power and/or covering permanent assemblies and
communication cables, conductors, or fabrications.
conduit, underground pipes shall,
maintain a vertical clearance of at For all buried and submerged piping,
least 300mm. Where these the test pressure shall be maintained
clearances cannot be maintained, for a period of 24 hours after
extra precaution shall be taken to temperature stabilization and
ensure the maximum possible stabilization of surges from
clearance and to prevent future pressurizing operations. The test
contact. If pipelines and pressure for above ground piping and
communication and/or power utilities offshore platform piping shall be
share the same trench, the above maintained for a minimum period of 4
clearance shall be maintained with the hours, during which time the piping
pipeline preferably at a lower level. shall be inspected for leaks.

16.11.5 A minimum separation of 3.0 metre All sections, which have been
should be maintained between pipeline previously hydrostatically tested viz.
and transmission tower footings, road/rail crossings and river crossings,
ground cables and counter poise. shall be retested along with the
Regardless of separation completed mainline sections.
consideration should always be given
to lightning fault current protection of A guaging pig shall be passed through
pipelines and safety of personnel. the pipeline to prove the internal
diameter of the entire line, the guaging
16.11 6 All crossings shall be made in such a plate having a diameter of 95% of the
manner that the angle between the internal diameter of the pipeline.
centreline of the railway, highway,
river, stream, canal or utility being When water is used as the test
crossed and the centreline of the medium, inhibited water, i.e. water to
pipeline shall be as close as possible which suitable doses of corrosion
to 90 deg. but in no case less than 45 inhibitors are added depending upon
deg. quality of water, shall be used.

16.12 TESTING AFTER CONSTRUCTION b) Pipelines and mains located in


class 1 and class 2 location shall be
16.12.1 General Provisions tested with air, gas or water to at least
1.25 times the maximum operating
a) All Pipelines, mains, and service pressure. Testing, wherever
lines shall be tested in place after practicable, shall be by means of
construction, except as provided for in water rather than a gaseous medium.
(b) below. Where a gaseous medium is used, the
test pressure shall not exceed 1.25
b) Tie-ins times the maximum operating
pressure. Sour gas shall not be used
For pipelines intended to operate at as a test medium.
hoop stresses of 30% or more of the
specified minimum yield strength c) Compressor station, regulator
pretested pipe shall be used in tie-in station and measuring station gas
sections and for those sections where piping, including the piping connecting
in-place testing is not practicable. the station to valving employed for
isolating the station from the pipeline
16.12.2Test Required to Prove Strength of and designed in accordance with
Pipelines and Mains to Operate at Type-C construction (Design factor =
0.5) shall be tested to atleast class 3 31.8 and all such piping is retested
location test requirements. with the main offshore pipeline to class
1 location test requirements.
d) Where testing of offshore platform
gas piping and pipe riser cannot be e) Test Requirements for Pipelines
accomplished separately from the and Mains to Operate at Hoop
main offshore pipeline, the piping Stresses of 30% or More of the
components shall be pretested to Specified Minimum Yield Strength of
atleast 1.4 times the maximum the Pipe
operating pressure, provided that all
final welds are inspected in
accordance with the provisions of B

GENERAL NOTES: f) In such cases an air test to 1.25


times the maximum operating
mop = Maximum operating pressure (not pressure shall be made and the
necessarily the maximum allowable limitations on operating pressure
operating pressure) imposed by Table 16.12.2.5 of this
dp = design pressure standard do not apply.
tp = test pressure
g) Records

This table brings out the relationship The operating company shall maintain
between test pressures and maximum in its file for the useful life of each
allowable operating pressures pipeline and main, records showing
subsequent to the test. If an operating the procedures used and the data
company decides that the maximum developed in establishing its maximum
operating pressure will be less than allowable operating pressure.
the design pressure, a corresponding
reduction in prescribed test pressure The record shall contain at least the
may be made as indicated in the following information:
pressure Test Prescribed, Minimum,
column. However, if this reduced test i. Time and data of Test;
pressure is used, the Maximum
operating pressure cannot later be ii. Pipe Specifications of sections
raised to design pressure without under test;
retesting the line to the test pressure
prescribed in the Pressure Test
Prescribed.
iii. Elevation profile and the location 16.13 CONTROL AND LIMITING OF GAS
of the test section and testing points, PRESSURE
if applicable;
Maximum Allowable Operating
iv. Testing medium used; Pressure for Steel or Plastic Pipelines
or Mains Consistent with Table
v. Test pressure at lowest elevation; 16.12.2.5 of this standard shall be
adhered to.
vi. Test duration;
16.14 VALVES
vii. Pressure and temperature
recording charts, if applicable; Notwithstanding the foregoing
provisions of this clause, sectionalizing
viii. Pressure-Volume chart, if block valves equipped with automatic
applicable; closing devices should be provided for
sour gas pipelines in order to minimize
ix. Location of leaks or failures and the volume of hydrogen sulphide that
description of repair action taken. could be released in the event of a
pipeline failure.
h) Acceptance of Test
16.15 PIPE BOOK
The test is successful when the
pipeline has withstood the strength A pipe and welding book shall be
test, and during the test period there is maintained for all projects. The
no observable drop in pressure that purpose of the pipe book shall be to
cannot be accounted for by indicate and maintain as a permanent
temperature changes. record the exact position in the
pipeline of each pipe length and each
16.12.3 Termination of Testing pipeline material like valves, scraper
traps, bends, and flanges and other
The pipeline shall be slowly fittings installed in the project. Each
depressurized at a moderate and item shall be recorded by its
constant rate. During dewatering, care identification number. Location of
shall be taken to properly dispose the each weld including weld number,
discharging water in order to avoid welder number, type of welding and
pollution, damages to fields under electrode, weld treatment and the
cultivation and/or existing structures details of used equipment for
and interference with the traffic. radiography shall be recorded in the
pipe book.
16.12.4 Pre-tested Pipe
17.0 OPERATING AND
Pipe used for making repairs shall be
pre-tested to a pressure equal to or
MAINTENANCE
greater than the original pipeline PROCEDURES
strength test pressure.
All provisions of B 31.8 Chapter V and OISD-
16.12.5 Preservation of Pipeline STD-138 shall apply.

If the pipeline is to be preserved for a 18.0 CORROSION CONTROL


specified duration before it can be
commissioned, the pipeline shall be 18.1 COATING REQUIREMENTS
completely filled with water with
sufficient quantities of corrosion Coatings shall:
inhibitors, depending upon the quality
of water and the period of a) Electrically isolate the external
preservation, or with a non-flammable, surface of the pipeline system from the
non-toxic gas and at a suitable environment;
pressure.
b) Have sufficient adhesion to 18.3 ELECTRICAL CONNECTIONS AND
effectively resist underfilm migration of MONITORING POINTS
moisture;
18.3.1 Where a higher current carrying
c) Be ductile to resist cracking; capacity is required, a multistrand
conductor shall be used and the
d) Have a strength or otherwise be strands shall be arranged into groups
protected to resist damage due to no larger than No.6 AWG. Each group
normal handling (including concrete shall be attached to pipe with a
coating application, or river weight separate charge. Attaching test leads
installation, where applicable) and soil directly to the pipe by other methods of
stress; brazing is prohibited.

e) Be compatible with cathodic 18.3.2 The following paragraph is added:


protection system.
When a thermit welding process is
18.2 ELECTRICAL ISOLATION used for electrical lead installation on
pressurized pipelines, precautions
a) This clause shall not take shall be taken to avoid possible failure
precedence over recognized electrical of the pipeline during installation due
safety practices and codes. to loss of material strength at the
elevated welding temperatures. Where
b) Where insulating devices are a thermit welding process is not
installed to provide electrical isolation deemed suitable. Consideration shall
of pipeline systems to facilitate the be given to other methods of
application of corrosion control, they installation.
shall be properly rated for
temperature, pressure, and electrical 18.4 ELECTRICAL INTERFERENCE
properties, and shall be resistant to the
commodities carried in the pipeline 18.4.1 Fault Current Interference
systems. These devices shall not be
installed in enclosed areas where Fault current interference shall be
combustible atmospheres are likely to taken into consideration.
be present unless precautions are
taken to prevent arcing. (Refer Clause NOTES:
18.4 of this standard)
a) Fault current resulting from
c) Pipeline system shall be installed lighting or upset conditions of electrical
so that the belowgrade or submerged facilities could result in serious
portions are not in electrical contact damage to coating and pipe wall and
with any casing, foreign piping danger to personnel. These adverse
systems or other metallic structures. effects may occur where a pipeline is
This shall not preclude the use of close to the grounding facilities of
electrical bonds where necessary. electrical transmission line structures,
sub-stations, generating stations or
d) Provision shall be made to prevent other facilities that have high short
harmful galvanic action at below-grade circuit current-carrying grounding
or submerged connections between networks.
copper and steel piping.
b) Where a buried pipeline system
Consideration should be given to: is close to grounding facilities,
remedial measures may be necessary
i) Installing an insulated coupling or to control the effect of these fault
insulating gasket set between the currents in order to reduce the
copper and steel, or resultant rise in potential gradient in
the earth near the pipeline system to
ii) Protecting the piping with an an acceptable level.
insulating coating material to provide a
spatial separation of not less than c) Safety appliances shall be
0.5m between bare copper and steel. provided against lightning, stray
current interference from foreign measures or other remedial action
objects at HT pipeline crossings. shall be undertaken.

18.4.2 Induced Potential Interference 18.5.3 Cathodically Protected Pipeline


Systems Temporarily out of Service
Pipelines paralleling alternating current
electrical transmission lines are Cathodic Protection systems shall be
subject to induced potentials as well maintained on any pipeline system
as the effects mentioned in Notes to temporarily out of service.
Clause 18.4.1 above.
18.6 TEMPORARY CATHODIC
a) When studies or tests show that PROTECTION SYSTEM
alternating current potentials will be or
are being induced on a buried pipeline When considered necessary, a
system, devices shall be installed to temporary Cathodic Protection system
reduce these potentials to a tolerable with sacrificial anodes shall be
level. installed to ensure adequate protection
of pipeline from external corrosion
b) When such pipelines are under from the time the pipeline is laid in the
construction, or when personnel are in trench till the permanent Cathodic
contact with the pipelines, special Protection system is commissioned.
precautions shall be taken to nullify the
possible effects of induced alternating The temporary cathodic protection
current potentials. system shall preferably be installed
simultaneously keeping pace with the
18.4.3 Safety Requirements pipeline laying/installation work and
shall be monitored periodically.
Following precautions shall be taken:
18.7 INTERNAL CORROSION CONTROL
a) Employ blowdown connections
that will direct the gas away from the
electric conductors; 18.7.1 Any gas whose water dew point is at all
times below the minimum pipeline
b) Install bonding across points operating temperature is considered to
where the pipeline is to be separated be non-corrosive, unless tests or
and maintain this connection while the experience indicate otherwise.
pipeline is separated;
18.7.2 Any gas whose water dew point
c) Make a study in collaboration with exceeds the minimum pipeline
the electric company on the common operating temperature is considered to
problems of personnel safety, be corrosive, unless tests or
corrosion, electrical interference and experience indicate otherwise.
lighting problems.
18.7.3 Any gas containing hydrogen sulphide
18.5 EXISTING INSTALLATIONS or carbon dioxide whose water dew
point exceeds the minimum pipeline
18.5.1 Existing Coated Pipeline Systems operating temperature is considered to
be corrosive, unless tests or
Cathodic Protection shall be applied experience indicate otherwise.
and maintained on all existing coated
pipeline systems. 18.7.4 Any gas containing hydrogen sulphide
or carbon dioxide whose water dew
18.5.2 Existing Bare Pipeline Systems point is maintained below the minimum
pipeline operating temperature by
Investigations shall be made to dehydration, or is suitably inhibited, is
determine the extent or effect of considered to be non-corrosive, unless
corrosion on existing bare pipeline tests or experience indicate otherwise.
systems. Where these investigations
indicate that continuing corrosion will 19.0 MISCELLANEOUS
create a hazard, corrosion control

You might also like