B. BAHAN
C. PERALATAN
1. Dozer E.16 Unit / Jam 0,0090 343.750,00 3.093,75
2. Vibro Roller E.40 Unit / Jam 0,0178 375.000,00 6.675,00
B. BAHAN
C. PERALATAN
1. Excavator E.11 Unit / Jam 0,0283 315.000,00 8.914,500
2. Dozer E.16 Unit / Jam 0,0200 343.750,00 6.875,000
3. Vibro Roller E.40 Unit / Jam 0,0178 375.000,00 6.675,000
4. Dump Truck E.08 Unit / Jam 0,0783 93.750,00 7.340,625
B. BAHAN
1. Tanah Pilihan M09 M3 1,2000 112.500,00 135.000,00
(Tanah Merah)
C. PERALATAN
1. Excavator E.11 Unit / Jam 0,0101 315.000,00 3.181,50
3. Vibro Roller E.40 Unit / Jam 0,0042 375.000,00 1.575,00
4. Dump Truck E.08 Unit / Jam 0,0362 93.750,00 3.393,75
B. BAHAN
1. Bambu Btg 0,2000 18.500,00 3.700,000
2. Gebalan Rumput M2 1,0000 71.500,00 71.500,000
C. PERALATAN
Dibuat Oleh :
CV / PT
.......................................
Direktur