Professional Documents
Culture Documents
Omer Hashmi
Selas Linde North America
Nrup Patel
Linde Engineering India
Fernando Rivera
Linde Jubail Industrial Gases Factory LLC
T
he Linde Group’s Engineering Division
has engineered, delivered and construct- time. Other process units enable recovery and
ed a new state-of-the-art multi-product purification of additional gas products, such as
syngas and ammonia facility at the new high-purity carbon monoxide (CO).
SADARA Chemical Company complex in Al
Jubail, Kingdom of Saudi Arabia (KSA). Upon A multinational team of commissioning engi-
successful commissioning and start-up, Linde neers from various Linde Engineering (LE) of-
Group’s Gases Division will own and operate fices combined on this project to execute safe
the plant to supply hydrogen, carbon monoxide and efficient pre-commissioning, commission-
and ammonia to SADARA. ing and start-up of this facility.
2016 221
219 AMMONIA TECHNICAL MANUAL
specification, whereas the other train generates ic separation and purification of CO within the
process steam for internal use only. The steam coldbox. The purified CO is compressed and
system of the latter recycles the process conden- sent to battery limit as one of the products, and
sates of both trains to reduce effluent flows for the remaining process gas is directed to a Pres-
environmental reasons as well as economic effi- sure Swing Adsorption (PSA) unit to produce
ciency. pure hydrogen (H2).
Natural gas from battery limit is compressed The product H2 is then mixed and compressed
and distributed to the reforming section of the with high pressure nitrogen (N2) from battery
two syngas trains. Downstream of the reform- limit and fed to a Casale ammonia converter.
ers, the hot syngas is cooled down by a series of The converted gas is passed through heat ex-
heat exchangers before being fed to the carbon changers for energy efficiency before being
dioxide (CO2) removal amine wash process. condensed and refrigerated for storage as liquid
The separated CO2 is compressed and recycled ammonia product. The product ammonia is then
back to the process as feed to the reformer on an vaporized before it is finally distributed to bat-
as-need basis. tery limit. Figure 1 summarizes the described
process in a block flow diagram.
A Temperature Swing Adsorption (TSA) unit
then removes all moisture and any residual CO2
from the syngas, in preparation for the cryogen-
2016 223
221 AMMONIA TECHNICAL MANUAL
A noteworthy item in the permit to work system
for this project was the emphasis on adequate
training and timely refresher courses on safe ex-
ecution of critical tasks such as confined space
entry. The Linde team, along with the construc-
tion workforce, was able to establish a number
or interconnected codependent teams training,
intelligently challenging, discussing and work-
ing together to achieve excellence in safety by
taking ownership and responsibility for them-
selves as well as for others.
2016 225
223 AMMONIA TECHNICAL MANUAL
protection. In general, the team managing and confined spaces and they must be dealt with ex-
supervising such line blowing activates utilized treme caution.
ear plugs and/or ear muffs rated between 95 and
105 decibels, as in Figure 7a. In the case of As part of the pro-active interdependent ap-
steam blowing, to minimize the noise generated, proach for maintaining a world class safety cul-
the steam was blown into the atmosphere via a ture in the facility, as an absolute minimum,
silencer, as shown in Figure 7b. each individual entering any confined space was
required to carry a personal gas detector with
alarms to ensure continuous gas monitoring, a
ventilation source was made available to ensure
sufficient oxygen content, a watchman was
available outside the confined space maintaining
an entry/exit log sheet, and an adequate lighting
source was organized as well.
Filling of Catalyst and Adsorbent Materials Figure 9. Dust masks during catalyst loading
In parallel to systems that were still under con- Additionally, catalyst and adsorbent loading
struction or under cleaning, hand-over-systems meant lifting of heavy drums to elevated struc-
whereby catalyst and adsorbent loading was re- tures. In addition to safety coordination and
quired were also catered. These activities posed skillful lifting, as shown in Figure 10, this re-
a completely different safety challenge – dealing quired organization of working areas, providing
with hazardous chemicals. the workers with sufficient space to execute the
task properly, as well as barricading areas at
In order to minimize exposure to catalyst dust, grade, directly under the lifting radius to prevent
all workers assigned to the catalyst handling and people from working directly under a lifting ac-
loading jobs, were specifically required to wear tivity.
a dust mask in addition to the regular personal
protection equipment (PPE), shown in Figure 9.
2016 227
225 AMMONIA TECHNICAL MANUAL
Final Check of HOS against the P&ID
Following the line and equipment cleaning, the
HOS was reassembled and a more thorough
check was done to ensure that the system was
ready for pressurizing and testing for tightness.
During this check, subtle details of the piping
are verified to ensure that the system is ready to
be pressurized. This was one of the greatest
strengths of the commissioning team on site.
2016 229
227 AMMONIA TECHNICAL MANUAL
Vendor Packaged Units This isolation was required to allow testing the
trip logic of the different compressors without
For any plant, a particular area of concern, both having to actually run the machine. This al-
technically as well as from a safety standpoint, lowed safe testing of the packaged units without
is the tie-in of vendor packaged units to the bal- risking the safety of the machines.
ance of the plant. This plant had several vendor
packaged units of this nature, ranging from sim- Commissioning
ple centrifugal pumps and reciprocating com-
pressors to the more complex refrigeration Commissioning and start-up of any plant in-
screw compressors. volves take-over of utilities and start of nitrogen
circulation within the process units. Prior to in-
Each of these packaged units was treated as its troduction of any flammable gases, the flare unit
own hand-over-system. This meant that it was needs to be ready for commissioning and start-
individually checked for construction against up.
the P&ID, the lines were cleaned, and the con-
trol logic was verified. An important item of This facility comprised of two individual flares
safely testing such units was the electrical isola- – one for the dual syngas generation trains and a
tion of the motor in the Motor Control Center separate one for the ammonia production sec-
(MCC) and temporary wrapping of the wiring tion. However, in preparation of charging the
with insulation tape, as shown in Figure 14. fuel gas header, the safety process and require-
ments were revisited. Several new requirements
were mandated in addition to the existing rules
and regulations, such as:
Flare Systems
The commissioning of the flares presented a
new technical and safety challenge. A few pilots
on the flare dedicated to the syngas section of
the facility did not ignite upon introduction of
pilot fuel gas. Since safely accessing and re-
pairing these pilots from the platform was con-
sidered risky, despite the necessity to meet a va-
riety of commissioning schedules, a scaffold
had to be erected on top of the flare, approxi-
mately 60 meters (200 feet) tall, to inspect and
Figure 14. Electrical isolation of power supply troubleshoot the pilots, shown in Figure 15.
2016 231
229 AMMONIA TECHNICAL MANUAL
the entire team. By paying attention to delicate Acknowledgements
details, the entire project team successfully es-
tablished a culture of interdependent safety at The authors gratefully acknowledge the contri-
the site. butions of the following individuals and organi-
zations, without whom this paper would not
The entire workforce, comprising of Linde En- have been possible:
gineering Division, Linde Gases Division and
the construction contractor, has worked together • Linde Jubail Industrial Gases Factory
as one team with a common goal of achieving • Selas Linde North America
excellence in safety by taking ownership and re- • Linde AG Engineering Division
sponsibility for themselves as well as for others. • Linde Engineering India
Adhering to all safety regulations, the site team
• Kenneth Lamb
has successfully achieved in excess of
• Jamil Amir Baduwi
10,000,000 man-hours without a Lost Time In-
cident. • Winfried Leclaire
• Bernd Klein
The world class safety culture achieved by the • Nirav Gabani
team in this project can be attributed to a num- • Florian Darchinger
ber of key success factors, such as: