You are on page 1of 12

Safe Pre-commissioning and Commissioning of

a Multi-Product Syngas and Ammonia Facility


This paper will discuss the various technical and safety challenges associated with pre-commissioning
and commissioning of a new multi-product syngas facility. It also focuses on the subtle nature of
developing an effective site safety culture to enable safely working in excess of 10,000,000 man-hours
with a multinational workforce in the Middle East.

Omer Hashmi
Selas Linde North America

Nrup Patel
Linde Engineering India

Fernando Rivera
Linde Jubail Industrial Gases Factory LLC

Introduction ensure a continuous supply of product to the cli-


ent during any scheduled or unscheduled down-

T
he Linde Group’s Engineering Division
has engineered, delivered and construct- time. Other process units enable recovery and
ed a new state-of-the-art multi-product purification of additional gas products, such as
syngas and ammonia facility at the new high-purity carbon monoxide (CO).
SADARA Chemical Company complex in Al
Jubail, Kingdom of Saudi Arabia (KSA). Upon A multinational team of commissioning engi-
successful commissioning and start-up, Linde neers from various Linde Engineering (LE) of-
Group’s Gases Division will own and operate fices combined on this project to execute safe
the plant to supply hydrogen, carbon monoxide and efficient pre-commissioning, commission-
and ammonia to SADARA. ing and start-up of this facility.

The syngas ammonia facility is comprised of a


dual-train Syngas Generation section feeding a Process Description
single train of ammonia production. Additional-
ly, a refrigerated atmospheric ammonia storage A dual-train concept was chosen for syngas
tank of 20,000 ton capacity is included to generation in this facility. The two trains are
physically identical; however, one train gener-
ates clean export steam according to customer's

2016 221
219 AMMONIA TECHNICAL MANUAL
specification, whereas the other train generates ic separation and purification of CO within the
process steam for internal use only. The steam coldbox. The purified CO is compressed and
system of the latter recycles the process conden- sent to battery limit as one of the products, and
sates of both trains to reduce effluent flows for the remaining process gas is directed to a Pres-
environmental reasons as well as economic effi- sure Swing Adsorption (PSA) unit to produce
ciency. pure hydrogen (H2).

Natural gas from battery limit is compressed The product H2 is then mixed and compressed
and distributed to the reforming section of the with high pressure nitrogen (N2) from battery
two syngas trains. Downstream of the reform- limit and fed to a Casale ammonia converter.
ers, the hot syngas is cooled down by a series of The converted gas is passed through heat ex-
heat exchangers before being fed to the carbon changers for energy efficiency before being
dioxide (CO2) removal amine wash process. condensed and refrigerated for storage as liquid
The separated CO2 is compressed and recycled ammonia product. The product ammonia is then
back to the process as feed to the reformer on an vaporized before it is finally distributed to bat-
as-need basis. tery limit. Figure 1 summarizes the described
process in a block flow diagram.
A Temperature Swing Adsorption (TSA) unit
then removes all moisture and any residual CO2
from the syngas, in preparation for the cryogen-

Figure 1. Block Flow Diagram of the HyCO Ammonia Plant

AMMONIA TECHNICAL MANUAL 222


220 2016
Planning and Workflow
During the course of an engineering, procure-
ment, construction (EPC) project, Linde Engi-
neering divides a plant into separate “hand-over-
systems” (HOS) based on Linde's vast experi-
ence in pre-commissioning and commissioning
of chemical and petrochemical plants. Each
HOS is handed over from construction to pre-
commissioning as soon as a system is “ready for
pre-commissioning”. Similarly, upon comple-
tion of the planned pre-commissioning activi-
ties, a system is declared “ready for commis-
sioning”.

For the Al Jubail syngas ammonia facility, the


plant was split into nearly seventy (70) different Figure 2. Workflow for Confined Space Entry
HOSs. The size and complexity of these indi- Work Permit
vidual systems varied greatly ranging from a
small system within the syngas cooling chain to The confined space is first recognized as an en-
the large intricate coldbox. closed area and the hazards are assessed. A risk
assessment is then performed to identify haz-
Each hand-over-system had its own procedure ards, analyze and evaluate the risks, identify
for executing the required pre-commissioning control measures and assess the method of
activities. However, some activities such as work. Some critical considerations during this
checking the construction against the P&ID, in- assessment include, but are not limited to, iso-
ertisation of piping and equipment, and carrying lating energy sources, sufficient Lockout/Tagout
out tightness tests were common for all HOSs. (LOTO), purging of systems and equipment,
lighting requirements, atmospheric testing for
Right from the onset of construction on this pro- oxygen content, ventilating with air blowers,
ject, no activities were executed without a prop- providing a means for access and/or any addi-
er permit to work. One of the key factors in the tional personal protection equipment (PPE).
safety success of Linde here is the thoroughly
implemented “permit to work” system. The dif- A clear definition of “how” the work will be
ferent pre-commissioning and commissioning performed is also a part of this permit issuing
activities required different permits, which in- process. Items such as number of workers re-
cluded, but were not limited to, a General Work quired inside the confined space, personal gas
Permit, a Hot Work Permit, a Confined Space monitoring requirements, tools and equipment
Entry Permit and a Working at Height Permit. to be used, emergency control and arrangements
etc. are all valuable parts of preparing such a
Each one of these individual permits requires its permit. Prior to the activity, the roles and re-
own series of steps to be followed in order to sponsibilities of each concerned individual were
plan, supervise and execute the task safely. As clearly explained to allow the task to proceed as
an example, Figure 2 shows the general work- smooth as possible. Upon completion of the
flow of how a task requiring a confined space permitted task, the system is returned back to its
entry permit is managed. “normal” operating state.

2016 223
221 AMMONIA TECHNICAL MANUAL
A noteworthy item in the permit to work system
for this project was the emphasis on adequate
training and timely refresher courses on safe ex-
ecution of critical tasks such as confined space
entry. The Linde team, along with the construc-
tion workforce, was able to establish a number
or interconnected codependent teams training,
intelligently challenging, discussing and work-
ing together to achieve excellence in safety by
taking ownership and responsibility for them-
selves as well as for others.

Based on the size, complexity and criticality of


the HOS, and the nature of activities, the com- Figure 3. The DuPont Bradley Curve
(Image copyright © 2016 DuPont. All rights reserved)
missioning management team assigned man-
power and developed a time schedule. Addi-
In this project, the stakeholders, the project
tionally, great importance was placed on vendor
management team, the execution team, the con-
packaged units such as compressors and pumps
struction and the site team, all the contractors as
to ensure similar activities were also executed
well as the client, all worked together towards
for those units with an equal emphasis on safety.
achieving the unified goal of a world-class safe-
ty performance. The project as a whole has been
Establishing a Safety Culture able to achieve in excess of 10,000,000 man-
hours without a Lost Time Incident (LTI), and
One of the key success factors in this story was counting.
the establishment at site of a positive safety cul-
ture. Rather than seeking to “catch and punish” An example that depicts the camaraderie of the
personnel who might be performing an unsafe teams in this project to achieve such a milestone
act, Linde sought to switch the mindset of every was the transfer of the site safety responsibility
person on site from the traditional reactive / pu- from the Engineering Division to the Gases Di-
nitive / independent mode, to a pro-active, sup- vision after Mechanical Completion (MC) of the
portive, and inter-dependent mode. This is ac- project. Despite the transfer of responsibility
complished when team members not only look being achieved only after MC, both Linde Gas
after their own safety performance, but the safe and Linde Engineering have worked together
actions of others as well. from the beginning of this project as one team
not accepting low standards of safety or risk tak-
This kind of a safety culture has been best de- ing. The two entities truly believed and strived
scribed by “The DuPont Bradley Curve”, shown for long term sustainable improvement to
in Figure 3, which was designed in 1995 to achieve the target of zero injuries.
benchmark the path to a world-class safety per-
formance. Pre-commissioning
Given the large size and the diverse nature of
the various sections of this plant, pre-
commissioning posed not only technical chal-
lenges, but also scheduling concerns.

AMMONIA TECHNICAL MANUAL 224


222 2016
Additionally, due to delays in the supply of
some major utilities, the safe execution of
scheduled tasks required added planning and
watchful efforts. One such effort was the organ-
ization of compressed air supply by means of a
temporary air compressor and a dryer station.
Such temporary sources, while very helpful, al-
so meant increased operational and safety con-
cerns during the various pre-commissioning ac-
tivities of the plant. Each pre-commissioning
activity brought about its own unique safety
challenge thereby requiring the entire team to
constantly improvise and work together to
maintain the site safety culture.
Figure 5. 100% tie off on elevated structures
Initial Check of HOS against the P&ID
Cleaning of Equipment and Piping
Once a system was deemed “ready for pre-
commissioning”, a commissioning engineer Cleaning of equipment and piping is one of the
checked the system for consistency of construc- most critical activities in pre-commissioning of
tion against the P&ID. While this activity any plant. In the case of this facility, the dusty
sounds fairly straightforward, one of the biggest weather and surrounding desert meant that extra
safety challenges was dealing with the scaffold- attention had to be paid to cleaning of lines.
ing that covered most of the plant at the time,
especially the pipe rack, as seen in Figure 4. After a preliminary check confirmed that tie-ins
were as per the P&ID, and that correct valves
and piping components had been installed, the
lines and equipment were cleaned by air blow-
ing, Figure 6, water flushing or sand blasting.

Figure 4. Scaffolding around main pipe rack

Site rules required 100% tie-off using a safety


harness when on a temporary structure. In fact,
for even permanent structures such as platforms Figure 6. Air blowing of lines
and vessels, until the safety department had
thoroughly inspected the integrity of the struc- Safe execution of cleaning requires a lot of
ture itself, a safety harness was mandatory for planning and preparation. The blow-out points
all personnel. This was followed strictly both were temporarily barricaded and a horn was
by Linde personnel as well as the construction sounded to ensure that those in the vicinity were
contractor’s workforce, as seen in Figure 5. not caught off-guard or without any form of ear

2016 225
223 AMMONIA TECHNICAL MANUAL
protection. In general, the team managing and confined spaces and they must be dealt with ex-
supervising such line blowing activates utilized treme caution.
ear plugs and/or ear muffs rated between 95 and
105 decibels, as in Figure 7a. In the case of As part of the pro-active interdependent ap-
steam blowing, to minimize the noise generated, proach for maintaining a world class safety cul-
the steam was blown into the atmosphere via a ture in the facility, as an absolute minimum,
silencer, as shown in Figure 7b. each individual entering any confined space was
required to carry a personal gas detector with
alarms to ensure continuous gas monitoring, a
ventilation source was made available to ensure
sufficient oxygen content, a watchman was
available outside the confined space maintaining
an entry/exit log sheet, and an adequate lighting
source was organized as well.

One of the key success elements of this project


was the training and ownership of designated
watchmen for confined space work. Their du-
ties, which they were duly trained in, included
an awareness of activities inside the confined
space, verbal communication with authorized
entrants to ensure their well-being, maintaining
an entry-exit log, remaining vigilantly placed
outside the confined space during entry opera-
Figure 7a. Use of ear muffs for protection tions, including when entrants leave for breaks
unless all openings are properly secured to pre-
vent unauthorized access. These watchmen were
a great example of the interdependent safety
culture that the Linde Group achieved in this
project. Most of their responsibilities focused
on the safety of other personnel involved in the
task but their responsible ownership of safety
was a highlight of this project.

In certain special cases of confined space activi-


ties, additional safety efforts were required. In
the case of the reformer refractory inspection for
Figure 7b. Steam Blowing via Steam Silencer example, the danger is compounded because not
only are the people working in a confined space,
Inspection of Equipment but also working at height. Even though it may
not have been very comfortable at the time of
Most large sized equipment needs to also be these inspections, all personnel maintained a
cleaned and inspected to minimize complica- safety harness during this inspection inside the
tions during commissioning and start-up. Reac- reformer furnace, as shown in Figure 8.
tors, separator vessels, drums and furnaces need
to all be checked thoroughly. The challenge
with this kind of equipment is that these are all

AMMONIA TECHNICAL MANUAL 226


224 2016
Figure 8. Use of safety harness inside furnace

Filling of Catalyst and Adsorbent Materials Figure 9. Dust masks during catalyst loading
In parallel to systems that were still under con- Additionally, catalyst and adsorbent loading
struction or under cleaning, hand-over-systems meant lifting of heavy drums to elevated struc-
whereby catalyst and adsorbent loading was re- tures. In addition to safety coordination and
quired were also catered. These activities posed skillful lifting, as shown in Figure 10, this re-
a completely different safety challenge – dealing quired organization of working areas, providing
with hazardous chemicals. the workers with sufficient space to execute the
task properly, as well as barricading areas at
In order to minimize exposure to catalyst dust, grade, directly under the lifting radius to prevent
all workers assigned to the catalyst handling and people from working directly under a lifting ac-
loading jobs, were specifically required to wear tivity.
a dust mask in addition to the regular personal
protection equipment (PPE), shown in Figure 9.

To improve on efficiency and avoid duplication


of efforts; the same crew of workers was main-
tained for catalyst loading activities wherever
possible.

Figure 10. Lifting of empty catalyst drums

2016 227
225 AMMONIA TECHNICAL MANUAL
Final Check of HOS against the P&ID
Following the line and equipment cleaning, the
HOS was reassembled and a more thorough
check was done to ensure that the system was
ready for pressurizing and testing for tightness.
During this check, subtle details of the piping
are verified to ensure that the system is ready to
be pressurized. This was one of the greatest
strengths of the commissioning team on site.

When dealing with a facility of this magnitude,


it is not uncommon that some items are missed
during construction due to time constraints and
emphasis on getting the job done. However,
sufficient time and effort was scheduled for the
final checks of each HOS. Some of the interest-
ing findings included loose flanges, leftover
temporary construction blinds, damaged gas-
kets, missing insulation etc, shown in Figures
11a. and 11b.
Figure 11b. Damaged gasket
Finding these items upfront meant that the HOS
was handed back to the construction department
for further reinstatement. This minimized future Testing of the Control and Trip System
issues whereby the system may have already
Another parallel and very critical item during
been pressurized.
pre-commissioning was plant-wide safety func-
tion testing. Prior to charging process gas into
the system, the control philosophy and the trip
system were verified at length.

For the testing of Safety Instrumented Functions


(SIFs), a HART communicator was used to
simulate inputs from the transmitters in the
field. In the case of pressure transmitters and
differential pressure type flow transmitters, a
pressure calibrator was additionally used to veri-
fy the working of the transmitter. The testing of
each SIF was carried out based on individual
SIF Protocols prepared by the engineering team.
These tests comprised of manually testing the
final element first, followed by the testing of the
transmitter and lastly the testing of the control
logic implementation and verification of final
Figure 11a. Loose flange on PSV inlet element action.

AMMONIA TECHNICAL MANUAL 228


226 2016
One distinct Safety Instrumented System (SIS) pressure compressed air, in most cases to nearly
was the flame detection system for the reformer 20-30% of normal operating pressure, and the
burners. With fuel gas not available on site, this pressure drop of the system was monitored over
was done using a portable gas cylinder. A de- time, to determine if the system was “tight” i.e.
tailed Job Safety Analysis (JSA) was performed holding pressure.
in preparation of the activity. Based on this, a
flint lighter was to ignite a flame, Figure 12a, in During pre-commissioning, this was considered
the presence of a fire extinguisher and only one of the more monotonous tasks – pressuriz-
100% fire retardant clothing was permitted for ing each HOS with low pressure compressed air
this activity, Figure 12b. and searching for leakages in the system by us-
ing a soap solution bubble test, as shown in Fig-
ure 13.

Figure 12a. Flint lighter for ignition


Figure 13. Soap Solution bubbles forming at
gas leakages

However, in retrospect, this proved to be one of


the most valuable investments of time and re-
sources; especially after high pressure nitrogen
was received later on and the systems were test-
ed for leakages at higher pressures. The systems
in the dual syngas generation trains were leak
tested at normal operating pressure with high
pressure nitrogen. However, due to the high op-
Figure 12b. Flame scanner testing erating pressure of the ammonia generation
loop, these systems were only leak tested to
Once again, the motivation of the workforce and about 20% of the normal operating pressure.
entire site team was that of achieving unparal-
leled safety success. If that meant taking some Once again, this was a prudent collaboration of
time, planning and only then executing a task, several teams working together – first team
this was never compromised on. working to find these leaks, then recording and
maintaining tracking lists of these leaks, and
Tightness Tests lastly the team rectifying these leaks well in ad-
vance of actual pressurization with combustible,
Once the final reinstatement of a HOS was toxic process gases.
completed, the system was pressurized with low

2016 229
227 AMMONIA TECHNICAL MANUAL
Vendor Packaged Units This isolation was required to allow testing the
trip logic of the different compressors without
For any plant, a particular area of concern, both having to actually run the machine. This al-
technically as well as from a safety standpoint, lowed safe testing of the packaged units without
is the tie-in of vendor packaged units to the bal- risking the safety of the machines.
ance of the plant. This plant had several vendor
packaged units of this nature, ranging from sim- Commissioning
ple centrifugal pumps and reciprocating com-
pressors to the more complex refrigeration Commissioning and start-up of any plant in-
screw compressors. volves take-over of utilities and start of nitrogen
circulation within the process units. Prior to in-
Each of these packaged units was treated as its troduction of any flammable gases, the flare unit
own hand-over-system. This meant that it was needs to be ready for commissioning and start-
individually checked for construction against up.
the P&ID, the lines were cleaned, and the con-
trol logic was verified. An important item of This facility comprised of two individual flares
safely testing such units was the electrical isola- – one for the dual syngas generation trains and a
tion of the motor in the Motor Control Center separate one for the ammonia production sec-
(MCC) and temporary wrapping of the wiring tion. However, in preparation of charging the
with insulation tape, as shown in Figure 14. fuel gas header, the safety process and require-
ments were revisited. Several new requirements
were mandated in addition to the existing rules
and regulations, such as:

• 100% Flame Retardant Clothing (FRC)


• Personal gas detectors
• Usage of only non-sparking tools

The facility is currently in the middle of its


commissioning and the experience during this
phase is still being gathered. Safety of the pro-
cess, plant and personnel continues to remain a
top priority during these ongoing activities.

Flare Systems
The commissioning of the flares presented a
new technical and safety challenge. A few pilots
on the flare dedicated to the syngas section of
the facility did not ignite upon introduction of
pilot fuel gas. Since safely accessing and re-
pairing these pilots from the platform was con-
sidered risky, despite the necessity to meet a va-
riety of commissioning schedules, a scaffold
had to be erected on top of the flare, approxi-
mately 60 meters (200 feet) tall, to inspect and
Figure 14. Electrical isolation of power supply troubleshoot the pilots, shown in Figure 15.

AMMONIA TECHNICAL MANUAL 230


228 2016
syngas train. The CO2 compressor was initially
left isolated to minimize the potential of carry-
ing over dilute amine into the compressor in
case the regenerator column had foaming and/or
a sharp level increase. While doing so, the op-
erations team was advised to monitor the CO2
vent silencer closely.

The CO Compressor housing had CO leakages


in spite of thorough leak checks and successful
tightness tests. Fixing these leakages was new
safety challenge given the toxic nature of CO,
a.k.a. “silent killer”. The compressor shelter
was left open to dilute the atmosphere inside
and the exhaust fans were switched ON. Addi-
Figure 15. Scaffold for flare troubleshooting tionally, an instrument air hose was used to con-
tinuously purge the area of activity and the
Once again, a detailed JSA was performed and flange being worked on. The number of person-
special emphasis was placed on the climatic nel inside the compressor housing was mini-
conditions of Al Jubail, due to extreme windy mized for the duration of this activity and each
conditions. Even at acceptable wind speeds, individual was carrying a personal CO detector
work on the flare was sometimes suspended to with alarms.
ensure that the safety of personnel and plant was
not compromised. One unit at a time, process gas was introduced
to different sections within the syngas train.
Syngas Section Slowly, several online analyzers were also
commissioned and on spec production of H2 and
Following the modification of the syngas flare, CO was confirmed.
the feed gas introduction to the plant was possi-
ble and the first reformer was fired up. Positive Ammonia Section
isolation was implemented by closing perma-
nent blinds on the second syngas train to prevent Due to slight schedule delays, the commission-
unplanned pressurization. ing activities of the ammonia section have not
yet commenced. The planned activities include,
Despite leak tests that were performed during but are not limited to, replacement purge of the
pre-commissioning, some small leakages were nitrogen atmosphere with ammonia, commis-
detected via portable individual gas detectors on sioning of the compressor packages, Casale
the fuel piping of individual burners. convertor, refrigeration unit and the ammonia
tank.
Additionally, the amine wash process for re-
moval of CO2 posed a totally different chal- Conclusions
lenge. A chemical suit was to be worn for the
dilution and loading of the solvent into a storage Linde Engineering has engineered, delivered
tank. and constructed a new multi-product syngas and
ammonia facility at the new SADARA Chemi-
The combination of young commissioning engi- cal Company in Al Jubail, KSA. Throughout
neers and senior engineers provided a very pro- the pre-commissioning and commissioning ac-
active approach to the commissioning of the tivities so far, safety has been a top priority for

2016 231
229 AMMONIA TECHNICAL MANUAL
the entire team. By paying attention to delicate Acknowledgements
details, the entire project team successfully es-
tablished a culture of interdependent safety at The authors gratefully acknowledge the contri-
the site. butions of the following individuals and organi-
zations, without whom this paper would not
The entire workforce, comprising of Linde En- have been possible:
gineering Division, Linde Gases Division and
the construction contractor, has worked together • Linde Jubail Industrial Gases Factory
as one team with a common goal of achieving • Selas Linde North America
excellence in safety by taking ownership and re- • Linde AG Engineering Division
sponsibility for themselves as well as for others. • Linde Engineering India
Adhering to all safety regulations, the site team
• Kenneth Lamb
has successfully achieved in excess of
• Jamil Amir Baduwi
10,000,000 man-hours without a Lost Time In-
cident. • Winfried Leclaire
• Bernd Klein
The world class safety culture achieved by the • Nirav Gabani
team in this project can be attributed to a num- • Florian Darchinger
ber of key success factors, such as:

• Valuable investment of time and re-


sources in pre-commissioning during
tightness tests and P&ID checks to min-
imize downstream complications
• Distribution of roles and responsibilities
between the entire team resulting in
ownership and an interdependent work-
ing relationship
• Functional implementation of a detail
oriented permit to work system
• Comprehensive training of the work-
force and efficient specialization of their
working skills (like watchmen for con-
fined space entry works)
• Planning, discussing, supporting and
challenging each task to ensure that the
safest practices are followed

Throughout the project, the entire team has truly


believed and strived for long term sustainable
safety practices to achieve the target of zero in-
juries. As milestones have been achieved, the
entire team continues to work towards the exe-
cution of commissioning activities with the
same diligence, and is committed to achieving
the next safety landmark.

AMMONIA TECHNICAL MANUAL 232


230 2016

You might also like