PROJECT MANAGEMENT

ASSIGNMENT
Network Diagram
Question:

With the help of below data, draw the network diagram showing the LOT and EOT of each
event along with slack computation.

ACTIVITY NAME IMMEDIATE PREDECESSOR DURATION


(months)
A Market analysis ................... 1
B Product Design A 3
C Manufacturing study A 1
D Select best product design B, C 1
E Detailed marketing plans D 1
F Manufacturing process D 3
G Detailed project design D 3
H Test prototype G 1
I Finalize product design F, H 1.5
J Order components I 1
K Order production equipment I 3
L Install production equipment K 2

15.5, 15.5
Solution: 0,0
10
E (1)
J (1)
1, 4 4, 4 5, 5
10.5, 10.5
A (1) 0,0 B (3) 0,0
D (1) 0,0
1 2 F (3) I (1.5) 0,0
L (2)
4 5 7 8
0, 0 9, 9
C (1) D (0) H (1) 0,0
G (3) K (3)

9
3 2, 4 6 8, 8
Submitted By: 0,0 0,0 13, 13
0,0

Sangam Chopra

PGDM II- C