You are on page 1of 11

ARTICLE IN PRESS

Energy Policy 34 (2006) 2480–2490


www.elsevier.com/locate/enpol

Power sector reform in India: current issues and prospects


Anoop Singh
Department of Industrial and Management Engineering, Indian Institute of Technology, Kanpur 208 016, India
Available online 15 September 2004

Abstract

Power sector reforms in India were initiated at a juncture when the sector was plagued with commercial losses and burgeoning
subsidy burden. Investment in the sector was not able to keep pace with growing demand for electricity. This paper takes stock of
pre-reform situation in Indian power sector and identifies key concerns that led to initiation of the process of reform. The paper
discusses major policy and regulatory changes undertaken since the early 1990s. The paper also illustrates changes in the market
structure as we move along the reform process. We also discuss some of the major provisions of the recently enacted Electricity Act
2003 that aims to replace the prevailing acts which govern the functioning of the power sector in the country. In this context, we
discuss two issues arising out of it, namely open access and multi-year tariff that we think would have a significant bearing on the
performance of the sector in the near future. The paper also evaluates the reform process in the light of some of the regulatory
changes undertaken. Finally, the paper briefly discusses the issues involved in introduction of competition in the power sector
primarily through development of a market for bulk power.
r 2004 Elsevier Ltd. All rights reserved.

Keywords: Electricity sector reform; Bulk power market; Regulation

1. Introduction countries, Lamech and Saeed (2003) find that private


investors seek reform-minded governments that ensure a
Recent experience in Californian electricity market judicial and regulatory process free of arbitrary govern-
has elevated concern about the efficacy of power sector ment interference.
reform in developing countries. This has implications Taking the lead from the UK and the USA,
for the policies of privatisation and competition in the developing countries like Argentina, Chile, Brazil,
power sector in developing countries. The Indian power Pakistan and Philippines also initiated the reforms
sector presents immense opportunities for private process in the power sector. Restructuring in the Indian
investment in the generation, transmission and distribu- power sector commenced with the unbundling, corpor-
tion (T & D) segments. For a capacity addition target of atisation and privatisation of the Orissa power utility,
about 100,000 MW over the next 10 years, there is a and the setting up of a regulatory commission. Begin-
foreseeable investment requirement of about Rs. 8000 ning with the opening up of power generation for
billion1 (USD 170 billion). However, adequacy of the private investment and later through regulatory reforms,
regulatory structure and the roadmap of the reform the process has entered a new phase with the recent
programme has a significant bearing on the mindset of enactment of the Electricity Act 2003. While the
private investors. From a survey of international electricity industry in the country gears up for competi-
investors interested in power sector in developing tion through open access and multiple licensees, there
are a number of issues to be understood and adequately
Tel.:+91-512-259-7679; fax: +91-512-259-7553. addressed.
E-mail address: anoops@iitk.ac.in (A. Singh).
Joskow (1998a) proposes privatisation of the genera-
1
Including approximately half each for creation of generation, and T tion sector leading towards competition in bulk supply
& D assets. through transmission access, while the distribution

0301-4215/$ - see front matter r 2004 Elsevier Ltd. All rights reserved.
doi:10.1016/j.enpol.2004.08.013
ARTICLE IN PRESS
A. Singh / Energy Policy 34 (2006) 2480–2490 2481

network could remain a natural monopoly along with consumption in India,2 at around 350 kWh, is less than
availability of retail choices to consumers. Pollitt (1997) 1/25 of that prevailing in the US and less than half of
concludes that economic gains from electricity privatisa- that in China. After independence, the government took
tion across the world are expected to be positive. upon itself the task of developing the power sector.
Reform programmes in the UK, Chile and Power generation capacity in the country increased from
Argentina, with vertically integrated large and 1362 MW in 1947 to about 105,000 MW by the end of
inefficient public sector enterprises, have yielded March 2002. The T & D network also witnessed
significant gains in economies. Gains from privatisation commensurate growth, enabling the expansion of the
in developing countries are likely to be a function of network across the the country’s geographic space.
market reforms and the modernisation of the Officially 84% of the 587,000 villages have been
economic system in general. Using the data envelopment electrified;3 however, only 55% households have access
analysis (DEA) of productive efficiency of the to electricity.
power sector in 82 countries, Hawdon (1996) finds The power system faces high energy and peak demand
that the privatising group of eight countries shortages. These were 7.5% and 12.6%, respectively, in
exhibit significantly higher efficiency than the 2001–02. Peaking shortages have reached a high of
non-privatising group. Though gains from power sector 20.49% in 1992–93 and energy shortages reached a high
reform in India cannot be reliably measured now, a of 11.7% in 1996–97 (GOI, 2002a). Faced with
review of the reform process should help identify key continued power shortages, increasing tariffs due to
issues that can drive the success of reforms in the cross subsidy, and poor quality and reliability of supply,
country. a number of industrial consumers shifted to captive
The Indian power sector has witnessed significant power generation. While SEBs are losing their lucrative
changes since early 1990s. Continued power customers, they continue to subsidise domestic and
shortages, poor operational performance and precarious agricultural consumers by pricing the power to them
financial situation of state electricity boards (SEBs) much below what it costs to serve them.4 However,
prompted a number of policy and regulatory Chattopadhyay (2003) shows that under certain condi-
changes. Such policy changes of institutional and tions higher tariffs in the industrial sector may not
regulatory nature are expected to address technical induce greater cross subsidies. Apart from operational
and financial challenges facing the Indian power inefficiencies, reflected in poor energy efficiency and
sector. This paper takes brief account of the PLF of generating plants of SEBs, the T & D system
state of Indian power sector and of concerns that have poses the most serious burden on the performance of the
prompted various steps by the central and the state Indian power system.
governments for the development of the sector. The gap between the average cost of supply and the
Next, we take stock of the major policy and regulatory average tariff increased from 50 paise/kWh in 1996–97
changes in the power sector undertaken since 1991. to 110 paise/kWh in 2001–02. The commercial
The paper also delves into the major provisions losses of SEBs (without subsidy) during 2001–02 are
of the recently enacted Electricity Act 2003 and its estimated to be Rs. 331.77 billion as compared to
implications on future prospects in Indian power Rs. 113.05 billion during 1996–97. With subsidies
sector. It also puts these in perspective towards under- paid by state governments, the above figures are
standing the evolving market structure in the generation, Rs. 248.37 and 46.74 billion, respectively. The
T&D segments. Finally, we deliberate on two issues financial disorder in the SEBs could be attributed to a
arising out of Electricity Act 2003, i.e. open access and number of factors, including large T & D losses,
multi-year tariff, which could significantly affect the overstaffing, large unpaid consumer bills, political
market structure and performance of the Indian power interference, etc. Revenue arrears of SEBs deteriorated
sector. Finally, the paper briefly discusses the issues from Rs. 67.2 billion in 1992–93 to Rs. 247.73
involved in introducing competition into the power billion in 1999–2000. The financial losses of SEB
sector primarily through development of a market for resulted in burgeoning dues to power suppliers and the
bulk power. railways. As on 28, February 2001, the SEBs owed

2
After factoring in the ‘theft’ component of T & D losses, ‘true’ per
2. Indian power sector at cross roads and the pressure to capita consumption may be a notch higher than the existing levels.
3
reform Electrified villages may merely signify existence of transmission
lines and poles, enabling supply to rural consumers without adequately
Electricity is a prime mover of economic growth and serving them or having the ability to connect significant part of the
population of the respective village.
the expansion of the Indian economy would depend 4
Dubash and Rajan (2002) discuss the political context of cross
heavily on the availability of quality infrastructure subsidy and locate the seeds of crisis in the politicisation of subsidised
services, including electricity. Per capita electricity agricultural tariffs.
ARTICLE IN PRESS
2482 A. Singh / Energy Policy 34 (2006) 2480–2490

Rs. 414.73 billion to various Central Public Sector In 1995, these measures were further strengthened by
Undertakings (CPSUs) and the railways (GOI, 2001). a Mega Power Policy, whereby plants above 1000 MW
Such large outstanding dues severely constrain their capacity would receive additional incentives in the form
ability to raise finance for investment or to provide for of a 10-year tax holiday, exemption of customs duty for
credible power purchase agreements with private power imports, reduced hassles for clearances, etc. This also
producers. provided for the setting up of Power Trading Corpora-
The Indian power sector is poorly placed in terms of tion (PTC) to act as an intermediary between the private
the level of T & D losses which have swelled to developers of mega projects and the SEBs. Though
enormous proportions. Though official statistics placed independent power producers (IPPs) evinced interest for
T & D losses in most of the SEBs to be less than 25% adding generation capacity for about 95,000 MW, only
during early 1990s, lack of metering of all consumers 6500 MW was added during the eight and ninth five-year
and interface points make it a challenging task for the plans (1992–2002) (WEC, 2002). Out of a targeted
regulators to arrive at a reliable estimate of the same. capacity addition of 17,588 MW from the private sector
Post-reform exercises by State Electricity Regulatory during the nineth five-year plan (1997–2002), a mere
Commissions (SERCs) have found the levels to be about 5061 MW only materialised (GOI, 2002b).
twice as large as reported earlier (Table 1). These losses Assured returns, lack of transparency and over-
were often camouflaged as supply to un-metered whelming concessions have drawn criticism from
agricultural consumers, as discussed below. This not various quarters. Guaranteed rate of return on invest-
only represents the technical shape of T & D network, ment, and hence, covering even the normal business risk
but also reflects on non-technical losses, which are a for a private investor, has been termed excessive
euphemism for theft. (Srinivasan, 2002). Ranganathan (1996) asserts that
In Haryana, electricity consumption by un-metered the lack of competition in awarding private projects in
flat-rate agricultural consumers was estimated by the generation, without transparency, represents a high-cost
utility on the basis of an unrealistic pump operation of solution to the woes of the Indian power sector.
5.7 h per day. A realistic estimation of un-metered Having experienced successes in electricity supply
agriculture consumption based on a consumption profile industry restructuring in Latin American countries, the
similar to that exhibited by metered agricultural World Bank had put forth power sector reforms as a
consumption raises the underreported T & D losses in necessary condition for future assistance to the power
Haryana for 2000–01 from 35.76%as projected by the sector in recipient countries, including India. This was
utility to 47.71% (HERC, 2001). instrumental in initiating of comprehensive power sector
reforms in the State of Orissa.6 Nelson (1996) discusses
the role of multilateral financial institutions in promot-
3. First phase of power sector reforms5 ing policy reforms through conditions attaching to loan
disbursements. The choice of Orissa was guided by
The financial state of SEBs and ongoing power various factors, including the fact that agricultural
shortages in the country led the government, in 1991, consumers accounted for a small share of consumption
to amend the Indian Electricity Act, 1910 and the in the state, thereby reducing the political fallout of the
Electricity (Supply) Act, 1948 to attract private invest- reform process (Rajan, 2000).
ment in power generation (Fig. 1). This facilitated the The ‘Orissa Model’ was based on functional unbund-
tapping of domestic and foreign capital markets, ling and corporatisation of the SEB into two generation,
provided assured returns on investment and reduced one transmission and three distribution companies. The
legal hassles to allow the private investors to set-up distribution companies were subsequently privatised.
generation capacities or operate as licensee in distribu- The Orissa Electricity Regulatory Commission (OERC)
tion segments, which were hitherto a monopoly of the was set-up under the Orissa Electricity Reforms Act
SEBs. Private power initiative in generation banked on 1995. Subsequently, Haryana and Andhra Pradesh
long-term power purchase agreements. The financial followed suit but did not privatise the distribution
state of SEBs poses a serious threat to the long-term companies. The main functions of SERCs include
sustainability of state subventions, especially when there licensing for undertaking business in its jurisdiction
are competing objectives like education, health, etc. and the setting of tariffs for T & D businesses. For the
Power sector reform and introduction of a regulatory purpose of tariff determination, the SERCs follow cost
framework was proposed as one possible solution to of service regulation because a basis for costs-plus
improve the SEBs’ finances (Carstairs and Ehrhardt,
1995). 6
In the context of power sector reform in Orissa, Rajan (2000)
identifies certain factors leading to power sector reform in the country
5
Fig. 1 graphically presents a chronology of main events relating to and categorised them into contextual, triggering, and facilitating
the reform process in Indian power sector. factors.
ARTICLE IN PRESS
A. Singh / Energy Policy 34 (2006) 2480–2490 2483

1991 1992-5 1996 1997 1998 1999 2001 2002 2003 2004

Electricity Regulatory Commission; Act to setup

Act to allow private participation in transmission


Reforms in the state of Orissa; Setting up of

CERC and SERCs; Electricity Laws (Amend.)


Orissa Electricity Regulatory Commission

Reforms in the state of AP; Setting up of AP


Reforms in the state of Haryana; Setting up of
Haryana Electricity Regulatory Commission

Electricity Act 2003: De-licensing thermal


IE Act and ES Act Amended to attract IPPs

Benefits of Mega Power Policy Extended;


Availability Based Tariff introduced in

Restructuring and Privatisation of Delhi

generation and to allow open access to


Electricity Bill introduced in Parliament
Energy Conservation Act; Accelerated

Accelerated Power Development and


Mega Power Policy;

Power Development Programme


(Private Power Policy)

Western Region

Conference of Chief Ministers

Reform Programme launched

usher in a competitive era.


Vidyut Board (DVB)B
Fig. 1. Chronology of Indian power sector reform.

tariff-setting was already existing (Sankar and Rama- Policy & Regulatory Functions: Ministry of

chandra, 2000). This was also necessary due to the SEBs CPSUs Pvt. Licensees Generation
Power (GOI), CEA, State Governments

inheritance of a system that was not only performing


badly, but was also ill equipped to provide adequate
information for performance-based regulation.7 The GRIDCO SEBs Pvt. Licensees Transmission
presence of a regulatory framework is deemed necessary
for an industry characterised by natural monopoly, at
least for some of its segments, and which could be SEBs Private Licensees Distribution
owned by private interests. Hence, the power sector was
evolving from a quite rigid market structure (Fig. 2) to a
more open yet regulated one (Fig. 3). Apart from the
Dom. Ind. Agri. Comm. etc. Consumers
prevalent ad hoc inter-state sale of electricity, PTC also
began to provide an interface between buyers and - Power Flow
sellers, which included the state power companies as well
as private entities. Fig. 2. Indian power sector (pre reform).
While the reform process in the UK and the US was
primarily oriented towards introducing competition in
Policy & Regulatory Functions: Ministry of
GENCOs CPSUs Pvt. Licensees IPPs Captive
the sector,8 at the beginning it was initiated to facilitate
private investment, and to alleviate the financial Power Trading Corp. Power (GOI), CEA, CERC, SERCs, State
condition of the power sector. Since electricity is in the
concurrent list of the Indian constitution, both union
Governments
Central Transmission State Transmission Pvt. Licensees /
Utilities (GRIDCO) Utilities (Transco) New Trans. Lic.
and state governments have the power to make policies
for the sector. While generation and transmission has
participation from both the central and the state Discoms Private Licensees
governments, distribution segments fall within the
purview of respective state governments. Beginning with
Orissa, so far, 22 states have set-up SERCs and 13 Dom. Ind. Agri. Comm. etc. - Power Flow
SERCs have issued tariff orders and nine states have - Contracts
unbundled/corporatised their SEBs. Reforms at the
Fig. 3. Indian power sector (current scenario).
7
However, there are traces of performance-based regulation in the
existing system as well. Cost components approved by the SERCs/ central level that span generation and transmission-
CERC are often based on certain norms or ‘‘perceived best practices’’. related issues covering more than one state were
In some states, approved T & D losses are based on SERCs
projections, which may differ from the actual ones.
initiated in 1998, through the enactment of the
8
Newbery and Green (1996), and Gilbert and Kahn (1996) and electricity Regulatory Commissions Act, which provided
Joskow (1997), respectively. for the setting up of the Central Electricity Regulatory
ARTICLE IN PRESS
2484 A. Singh / Energy Policy 34 (2006) 2480–2490

Commission (CERC) and state level regulatory commis- immediate financial woes of electricity utilities, long-
sions. The main functions of CERC include regulating term sustainability of the Indian power sector needs
tariffs of generating companies, owned or controlled by deepening of the reform process, alongside providing a
the Government of India and any other generating long-term vision to stimulate investor confidence.
company catering to more than one state, and also
tariffs for the inter-state transmission of electricity.
Apart from this, two significant steps taken by CERC
4. Electricity Act 20039
include introduction of Availability Based Tariff (ABT),
and Indian Electricity Grid Code. ABT has been
Recognising the need for a paradigm shift in the
instrumental in bringing discipline to the grid by
reform process rather than the piecemeal approach
providing frequency linked incentives and disincentives.
being followed in a number of states, a comprehensive
In the ABT, a two-part tariff is supplemented with a
Electricity Bill was drafted in 2000 following a wide
charge for Unscheduled Interchange (UI) for the supply
consultative process. After a number of amendments,
and consumption of energy in variation from the pre-
the bill finally sailed through the legislative process and
committed daily schedule and depending on grid
was enacted on 10 June 2003. It replaces the three
frequency at that point of time.
existing legislations governing the power sector, namely
The regulatory changes have brought transparency to
Indian Electricity Act, 1910, the Electricity (Supply)
the tariff-making process. They have also led to the
Act, 1948 and the Electricity Regulatory Commissions
rationalisation of distribution tariffs, thereby arresting
Act, 1998. Apart from consolidating such laws relating
increases of cross-subsidy in the system. Public hearings
to generation, transmission, distribution and use of
have been able to give voice to consumers in raising their
electricity, the main additional provisions of the act are:
concerns and contribute constructively to the regulatory
process. In order to address the consumer complaints,  De-licensing of thermal generation and captive
SERCs have come up with a complaint-handling system generation.
for the utilities and have provided a similar platform  Provision for license-free generation and distribution
with respect to themselves. This has given a much- in rural areas and provision for management of rural
needed voice to consumers’ point of view which has distribution by Panchayats, Cooperative Societies,
hitherto been missing from the system. non-government organisations, franchisees, etc.
Due to poor capacity realisation by the IPPs, the need  Non-discriminatory open access in transmission.
for distribution reforms was recognised. Some level of  Multiple licensing in distribution.
political convergence concerning the reforms was  Open access in distribution to be introduced in
demonstrated in the Meeting of the Chief Ministers on phases. Provision for across-subsidy surcharge on
Power held in March 2001. The Accelerated Power direct sale to consumers untill cross subsidies are
Development & Reform Programme (APDRP) was gradually phased out.
introduced in February 2001 by the union government  Power Trading recognised as a distinct activity with
to promote distribution reforms and provide transi- ceilings on trading margins to be fixed by the
tional finance for the SEBs undertaking reforms. The Regulatory Commissions.
main objectives pertaining to distribution reform are  Provision for payment of subsidies through budget.
aimed at achieving 100% metering, conducting energy  Setting up of an Appellate Tribunal to hear appeals
audits, improving HT/LT ratio, replacement of distribu- against the decisions of the CERC and the SERCs.
tion transformers and the use of IT solutions to ensure  Mandatory metering of all electricity supplies.
accountability. Most of the SEBs were on the verge of  Adoption of multi-year tariff principles.
financial collapse. Large amount of SEBs debts to
CPSUs and the railways cast a shadow on their balance The Act provides a less-constrained environment for
sheet. One-time settlement of SEB debts was initiated potential investors in the power sector by removing
and came into effect from 17 April 2002 as a tripartite administrative hurdles to the development of power
agreement between the respective state government, the projects, apart from some control over hydroelectric
Ministry of Finance and the Reserve Bank of India projects due to a multitude of issues related to water
(RBI). As per this scheme, 60% of the surcharge and utilisation, flood control, etc. The Act envisions a phase
interest on delayed payment as of 30 September 2001 is shift in the reform process, providing a necessary
waived. The scheme securitises the remaining surcharge impetus to the sagging momentum for distribution
and interest and the full principal amount through tax- reforms in the country. Apart from this, a wider
free bonds to be issued through RBI by the respective mandate for bulk power market with de-licensing of
state governments. It also provides for recovery of thermal generation, open access and multiple licensing
future defaults exceeding 90 days from the funds due to
9
the state. While such measures help alleviate the Hereafter referred to as the Act.
ARTICLE IN PRESS
A. Singh / Energy Policy 34 (2006) 2480–2490 2485

central transmission utility, to move the power to be


GENCOs CPSUs Pvt. Licensees IPPs Captive
imported from the Tala hydroelectric project from

Policy & Regulatory Functions: Ministry of


Power (GOI), CEA, CERC, SERCs, State
Bhutan. Lack of adequate investment in transmission

Governments, Appellate Tribunal


PTC & Other Traders
could delay the development of a bulk power market in
Central Transmission State Transmission Pvt. Licensees /
Bulk Power Market

Utilities Utilities New Trans. Lic. the country and make open access only a legislative
Direct Sale

gesture.
The Electricity Act 2003 provides for generators being
Discoms Private Licensees Rural Co-op. etc. able to sell power directly to consumers, bypassing the
Multiple Distribution distribution licensees. This could lead to the skimming
Licensees of the creamy layer of consumers, usually the large
Dom. Ind. Agri. Comm. etc. - Power Flow subsidised consumers. Such skimming may leave the
- Contracts state utility with less number of subsidised consumers
and could place added pressure on it to raise tariffs for
Fig. 4. Indian power sector (Post Electricity Act 2003).
the remaining consumers. To compensate for this, the
act provides for the levying of a cross-subsidy surcharge.
To avoid the continued burden of such a surcharge, the
sets the tone for a competitive environment in the Indian act provides for a timely phasing out of cross subsidies.
power sector. The emerging market structure that takes However, the lack of a clear definition of a cross subsidy
into account these provisions is envisioned in Fig. 4. and any specific principle for determining the surcharge
This is expected to provide competing supply options to for a cross-subsidy may open up another debate.10
the consumers and is expected to bring down electricity
prices, at least for those consumers who would be in a
position to bargain with competing suppliers. Two
4.2. Multi-year tariff
aspects of the Act, namely open access and multi-year
tariff are discussed further. While the former one is
Even though the regulatory model adopted in India
instrumental in the development of competitive power
was based on the one operating in the US, the Indian
markets, the latter one is expected to bring in necessary
regulatory system in all states has come to mean more or
incentives for performance improvement and to reduce
less ‘mandatory’ annual review of tariffs even though
regulatory risk.
their respective legislations do not make this very
obvious. This is in contrast to the practice in the US
4.1. Open access
where tariffs are reviewed only at the insistance of the
utility or the consumers. This not only adds costs to the
Open access and an ISO are crucial for the develop-
regulatory costs but also increase regulatory risk borne
ment of bulk power market in the country. This,
by power utilities (Gupta et al., 2002).
however, raises additional issues in terms of transmis-
Regulatory risks, pertaining to allowance of cost
sion pricing, investment in redundant transmission
elements and fixation of T&D losses due to unavail-
capacity and congestion management. Open access per
ability of correct data, are high. Incentive mechanism
se would not foster a competitive environment unless
built with a multi-year tariff regime is useful in
adequate transmission capacity is put in place, often
addressing regulatory risk (Alexander and Harris,
with some redundancy, in the system in order to manage
2001). Post regulatory reforms, electric utilities have
congestion and enhance competition. As the number of
been submitting annual revenue requirement and tariff
players would increase, this could jeopardise grid
applications. An incentive-based multi-year tariff has
discipline and would require an efficient ISO. With the
been under discussion in some of the states (APERC,
absence of Availability Based Tariff (ABT) at the state
2003). However, a number of issues including data
level, the captive generators could still pump power into
inadequacy and benchmarking of various parameters
the state grid even when the system does not desire it. As
especially controllable costs needs to be resolved.
the number of captive generators, especially those
APDRP programme has specific incentives for the state
utilising open access to transmit power across the
electric utilities for introduction of multi-year tariff
transmission assets of the state, are expected to rise,
regimes. Electricity Act 2003 has clearly mandated for
applicability of a mechanism similar to ABT in states
the introduction of a multi-year tariff regime. The Tariff
should be examined.
Policy to be formulated under the Act would provide
Even though private participation in transmission was
broad guidelines for multi-year tariff principles, while
permitted in 1998 through the Electricity Laws (Amend-
ment) Act, there has been a feeble response to it. Only 10
Though such details are to be specified in the document, Tariff
one private initiative was realised through a joint Policy, the initial draft available with the Ministry of Power has not
venture with POWERGRID, the government-owned been able to address all such apprehensions.
ARTICLE IN PRESS
2486 A. Singh / Energy Policy 34 (2006) 2480–2490

SERCs would follow up with detailed guidelines on the tion, restructuring, regulator, IPP entry and divestiture.
same. Though the Orissa model followed a similar sequence, it
Bakovic et al. (2003) propose ‘regulation by contract’ was perhaps rushed through in a fast-forward mode.
as an alternative to ‘independent regulatory commis- Asymmetric information also proved to be risky for
sions’ incorporating specific formulas rather than private investors in privatised distribution zones. In
general tariff principles. This provides better regulatory spite of being the pioneering state, a recent ranking of
certainty for the privatised utility over a multi-period reforms in power sector across 26 states places Orissa at
horizon. It incorporates the features of a multi-year 14th spot (ICRA/CRISIL, 2003). The Orissa experiment
tariff regime. Success of privatisation also has significant also highlighted the role of regulatory risk in the reform
bearing on the incentives being provided for improve- process. Learning from this, major changes were
ment of performance and reduction in regulatory risk brought in the privatisation model of the DVB.
through a multi-year horizon. These aspects have been Prior to privatisation, T&D businesses were bestowed
incorporated in the privatisation process of Delhi with a single state owned enterprise. In spite of broad
Vidyut Board (DVB). Introduction of multi-year tariff similarity with the reform process in the successful
regime highlights urgency to compile reliable and efforts in the UK and Argentina, the reform process in
verifiable data. This would necessitate wider application Orissa was fraught with information asymmetry, reg-
of IT solutions along the supply chain of the electricity ulatory uncertainty and prior escrow commitments. The
supply industry. presence of escrow accounts and long-term PPAs could
prove to be a hurdle to privatisation as private investors
taking over these state utilities would be burdened with
5. An evaluation of the reform process these revenue-draining mechanisms, which did not have
their participation.
Power sector reform is a long process and its impacts In the case of Orissa, post privatisation, the opera-
are both short-term and long-term in nature. Though tions of distribution companies are not viable at the
one cannot pass a judgment about the outcome of the tariffs fixed by the regulator, which were fixed on the
reform process, a mid course review of developments basis of a normative T & D loss of 35% against the
could, however, help learn from the past mistakes and actual losses that were estimated to be around 45–47%.
take some mid-course corrective measures. The concerns In contrast to this, ‘actual’ losses have been permitted in
about the reform process in most of the countries have tariff fixation by the regulators in Haryana. Premature
been on the process followed, the transition manage- privatisation of distribution businesses increases the risk
ment and the final destination of the reform process. borne by private investors due to information asymme-
Timing as well as sequencing of major reform steps try, especially with regard to assets, T & D losses and
has important bearings on the efficacy, acceptability, revenue arrears.
continuity and success of the reform process. Liberal- These lacunae were addressed in the ‘Delhi model’ to
ising private investment in generation was an incomplete some extent. Regulatory involvement and commitment
step. Given the single-buyer model, in which IPPs need in the privatisation process, and a long-term tariff
to operate, the financial health of the sole customers of profile reduced the regulatory uncertainty. However, it
these IPPs did not bode well for sustained investment continues with the single-model buyer approach as in
climate, let alone those being enticed in on account of the case of Orissa and other restructured state utilities.
incentives in the form of assured returns, tax holidays Phased reduction in T&D losses and revenue collections
and selective counter guarantees. While initial effort was and transitional financial assistance (subsidy) are the
placed on the generation side, most of the ills lay on the three crucial interrelated issues in privatisation process
distribution side. Distribution level reforms in states in the Delhi model. Revenues from sale of the
were given an impetus through incentivised schemes like government stake in Orissa were not ploughed back
APDRP. Such schemes are aimed at improving opera- into the sector. This limited the government’s ability to
tional efficiency and rationalisation of tariffs in various influence the future developments in the sector. How-
states. Even though many states unbundled and ever, Orissa provided a powerful demonstration effect
corporatised their SEBs, political sensitivity to privati- for other states to follow and learn from its experiences.
sation has forced many state governments to postpone Independence, transparency, accountability, expertise
the same in their respective states. and credibility have been cited as some key attributes of
Bacon and Besant–Jones (2001) advocate relying on a good regulatory institution. General guidelines for
privatisation of the distribution and supply functions designing regulatory structure in infrastructure sectors
first. This facilitates the entry of potential investors in can be found in Joskow (1998b). The initial phase of the
the generation by improving the creditworthiness of reform that emphasised the setting up of ‘independent’
buyers of power from the generators. They identified the regulatory commission was duplicated in almost all the
following reference sequence of six steps—corporatisa- reforming states. This brought about some amount of
ARTICLE IN PRESS
A. Singh / Energy Policy 34 (2006) 2480–2490 2487

transparency in its functioning that was absent from the countries would not only differ across income categories
previous system. However, the umbilical relationship of but also across urban and rural area. While the former
the power sector with the government has raised would be affected by a rise in the tariffs, the latter ones
apprehensions about the independence of the regulatory are better off by reduction in access cost. Powell and
system (Sankar and Ramachandra, 2000). The impor- Starks (2000) observe that urban poor stand a greater
tant lacuna in the institutional set-up that brings about chance of benefiting from power sector reform. For the
regulatory structure are—financial dependence of reg- rural poor, off-grid solutions may be required. In the
ulatory bodies on the government, powers to appoint or Indian context, studies (World Bank, 2001) have also
influence appointment of members of regulatory institu- revealed the farmers’ willingness to pay for quality
tions, and ‘missing teeth’ to rein in those who continue power. Poor quality of power not only leads to loss of
to default of regulatory orders.11 agricultural productivity but also inflicts indirect cost
Disguising and window-dressing of the revenue gap through motor and transformer burnouts. This raises
by some of the state commissions have deferred tariff doubts about continuing with subsidised prices for all
hikes for the consumers through mechanisms like consumers in domestic and agricultural categories, and
‘regulatory asset’ and ‘deferred subsidy’. These carry signifies better targeting of power subsidy to needy
forward the revenue gap to a future year to be made consumers only and effective monitoring of the same.
good either by efficiency gains or is added to future Foster (2000) discusses some welfare indicators to
revenue requirements. These two elements serve as a measure the impact of energy sector reform, including
‘regulatory tool’ to bail out the government from selling electricity sector reform, on the poor and asserts that it
tariff hikes to the consumers. The commitment of the is not only necessary to know the impact of reform on
state government to pay the promised subsidy has also the poor but also help focus on poverty-related issues
not stood the test of time. In the case of Haryana, the before such interventions are made. The proposed
level of unpaid subsidy by the state government for the methodology takes into account coverage, reliability,
previous years stood at Rs. 15.71 billion. This is affordability, total cost, health impact, etc. Dubash and
significant compared with the approved annual revenue Rajan (2002) expressed concern about the failure of
requirement of about Rs. 26 billion for the distribution market-led power sector reform process in developing
and retail supply business for 2002–03 (HERC, 2002). countries to take into account the social and environ-
Electricity tariff, at least for domestic and agricultural mental concerns.
consumers, is expected to rise initially along the reform Wamukonya (2003) warned against recipes imported
process. Due to significant power shortages, additional from developed countries where conditions are far from
electricity supply would occur at higher costs from new those prevailing in developing countries and emphasised
power plants. This could further delay tariff decline, till the need for progressive government intervention to
significant gains are made through improvement in shift the reform process towards a more responsible
operational efficiency and financial management, and development path that take into account the social and
untill competitive bulk markets lead to decline in power environmental issues. The ongoing process of reform in
procurement costs for distribution companies. Untill the most of the developing countries has been initiated in
realisation of such benefits, the most trying times for the response to financial concerns of the sector or towards
stakeholders are during this transition period. The development of ‘markets’. There seems to be less
transition shocks could be alleviated if winners com- consideration of social and environmental issues.12
pensate the potential losers so that all major interest Pollitt (1997) provides an exposition of the impact of
groups have a stake in promoting and not opposing reform in power sector in various developed and
reforms (Joskow, 1998a). In the Electricity Act 2003 developing countries. While performance-based regula-
scenario, large consumers who would have potential to tion has been rated as more successful, rate of return
tap cheap electricity outside the system of state utilities regulation has been criticised for obvious reasons.
would continue to contribute towards a cross-subsidy Kwoko (1996) reviews some of the studies and finds
surcharge till this is eliminated from the system in a that costs are not significantly lower in private electric
time-bound manner. utilities as compared with their public counterparts. This
In the case of Poland, Freund and Wallich (1995) puts the continuance of rate of return regulations into
observed that household energy subsidies help the rich serious doubts. The emergence of incentive-linked
more than they help the poor. Not only do the wealthy privatisation in Delhi raises hopes for achieving better
consume more energy in absolute terms than the poor, performance. This may not be reflected in an early
but they also spend a larger portion of their income on
energy. The impact of power sector in developing 12
In the case of the state of Karnataka, tariff policy suggests
consideration of the paying capacity of the consumers. In the case of
11
See Bakovic et al. (2003) for further discussion on regulatory the State of Gujarat, environmental considerations found explicit
independence in developing countries. mention in state’s reform Act.
ARTICLE IN PRESS
2488 A. Singh / Energy Policy 34 (2006) 2480–2490

decline in consumer tariffs. Recently, Gorini de Oliveira have an opportunity to participate in such a market
and Tolmasquim (2003) find that the inequality of mechanism.
benefits from the restructuring of the British power The availability of adequate and reliable transmission
sector severely affected fuel suppliers and benefit infrastructure, transparent and non-discriminatory
investors and shareholders. When regulation is similar transmission tariffs, and independent system operator
under private or public ownership, exposure to market (ISO) and regulatory structure are crucial to the
forces through liberalisation can bring in larger im- development of a bulk power market.13 Transmission
provement in performance than privatisation per se flexibility is necessary for an efficient market for power
(Newbery, 1997). Competitive and contestable bulk trading. This implies that there needs to be some
electricity market appears to be a necessary step for redundancy in the system. The five regions of the
enhancing efficiency and transferring such gains to country currently face varying degrees of power
consumers (Newbery, 2000). shortages, with the eastern region remaining in a surplus
Lack of appropriate and verifiable data creates ample situation, in general. Inter-regional trade in power in the
problems for regulators as well as investors. Baron and country has been constrained by the availability of
Myerson (1982) emphasise the information problems, transmission and the poor financial health of importing
especially those related to cost components. Imperfect utilities. Variations in weather, including rainfall,
information about the true costs of the utilities leaves temperature, and load profiles due to the structure of
ample space for hiding possible cost reductions. In the economic activity and consumer tariffs would provide
case of privatised utilities, imperfect information also opportunities for power trading even if supplies keep
posed significant regulatory risk in fixing T & D losses pace with demand in general. The present inter-regional
and this added to the woes of privatised utilities as in the transmission capacity is 8000 MW. Five regional grids
case of Orissa. in the country are interconnected through back-to-back
Because of the pressure to manage the deficit in states, HVDC links, having a cumulative capacity of 5000 MW.
the APDRP programme acts as a carrot to induce Further work to strengthen the existing transmission
favourable developments towards reforming the state capacity towards a National Grid is in progress.
power sector. However, the long-term sustainability of POWERGRID expects to achieve an inter-regional
the sector would depend on how soon there can be a transmission capacity of 30,000 MW by the year 2012
political will to cut the umbilical cord of politics off with through the involvement of private investors.
the power sector. Political interventions are a part and Appropriate pricing of transmission services is useful
parcel of the system rather than exceptions and the in providing economic signals for efficient short-run
power sector is not unique in this respect. Given the operation, recovery of costs, long-term capital invest-
recent experience regarding interventions in the telecom ment and fair allocation of costs among participants
and petroleum sectors influencing the regulatory pro- (Lai, 2001). Open access to transmission should be
cess, it is a long wait for the investors to find less accompanied with appropriate transmission pricing that
political linkages with the functioning of the sector. not only recovers the investment but also provides
Political decoupling could be the single most important appropriate signals for further investment in transmis-
factor in rejuvenating the power sector in the country. sion infrastructure. Liquidity, efficiency and complete-
ness of market are necessary elements towards
development of competitive power markets (Hunt,
6. Towards a market for bulk power 2002). Large number of players could ensure sufficient
liquidity in the market, and this could curb market
With a view to developing a power market in the power to some extent. Adequacy of information is
country, PTC was set-up in 1999 under the joint necessary for the development of efficient power market.
ownership of power producers, the central transmission Completeness of markets requires a full set of spot and
utility and a number of financial institutions. It has since forward market for each specific product, time and
then facilitated power exchange among various state place. This would also require availability of risk
utilities and a few private generators in the country. management tools to avoid extreme price shocks.
Such trade has grown from 43.77 million kWh in Since a sufficient quantity of power to be pushed into
2000–01 to 4178 million kWh in 2002–03. ABT has been the bulk power market would come only after contrac-
instrumental in promoting power trade by providing tual bilateral agreements have been met, the existing
correct commercial signals in the current environment. public as well private sector players may continue to
With trading being recognised as a distinct activity operate on the margin in the bulk power market. Long-
under Electricity Act 2003, there is a clear vision term power purchase agreements are in place for almost
towards development of a bulk power market in the
country (Fig. 4). Power generators, traders, captive 13
See Chao and Huntington (1998) for a discussion on issues related
generators and emerging cooperative producers would to design of power markets.
ARTICLE IN PRESS
A. Singh / Energy Policy 34 (2006) 2480–2490 2489

all of the existing power generation capacity. Apart efficiency, including reduction in T & D losses, would
from merchant power plants,14 part of the future help improve the financial condition of the Indian power
capacity creations, which are chiefly meant to serve sector. However, transition management may prove to
bilateral contracts, could be made available in the be the most difficult task while trying to balance the
market place. A market for bulk power can also induce commercial goals and social obligations facing the
the desired changes in distribution tariff structure to sector. This requires balancing commercial prudence at
reflect price variability across time of day and seasons of one end and the social acceptability of the reform at the
the year, and design of interruptible/firm supply other, which is linked to the political fallout of the
contracts with consumers. Entrepreneurial ingenuity reform process.
would pave its own path to sell power in a competitive
environment.
Acknowledgements

7. Conclusions The author would like to thank Puneet Chitkara and


two referees for their valuable suggestions.
With an annual gross domestic product (GDP)
growth target of 8% set for the Tenth Five-Year Plan,
electricity demand in India is expected to grow sign- References
igicantly. Rural electrification is targeted for completion
by the end of Tenth Plan (2007), whereas full coverage Alexander, I., Harris, C., 2001. Incentive regulation and multi-year
price controls: an application to the regulation of power distribu-
of all households is targeted for completion by the end tion in India. International Journal of Regulation and Governance
of Eleventh Plan (2012) (GOI, 2002b). Ongoing reforms 1 (1), 25–46.
in the power sector are expected to help meet such APERC, 2003. Order on Long-term Tariff Principles. Andhra Pradesh
targets. While the main objective of the power sector Electricity Regulatory Commission (APERC), Hyderabad.
reform in developed countries has been to enhance Bacon, R.W., Besant-Jones, J., 2001. Global Electric Power Reform,
Privatization and Liberalization of the Electric Power Industry in
competition in the sector, the need to improve financial Developing Countries, Energy and Mining Sector Board. The
state and to attract private investment to the power World Bank, Washington, DC.
sector, has been the main driving force for undertaking Bakovic, T., Tenenbaum, B., Woolf, F., 2003. Regulation by Contract:
reform in India. This has so far included functional A New Way to Privatize Electricity Distribution? The World Bank,
Washington, DC.
separation of generation, T&D, setting up of federal and
Baron, D.P., Myerson, R.B., 1982. Regulating a monopolist with
state regulatory commissions and selective privatisation unknown costs. Econometrica 50 (4), 911–930.
of distribution segments in a few states. Regulatory Carstairs, J., Ehrhardt, D., 1995. Financial structure in the Indian
changes have been able to bring about tariff rationalisa- power sector. Energy Policy 23 (11), 981–990.
tion, and transparency and consumer participation in Chao, Hung-po., Huntington, H.G. (Eds.), 1998, Designing Compe-
the regulatory process. titive Electricity Markets. Kluwer, Massachusetts.
Chattopadhyay, P., 2003. Cross-subsidy in electricity tariffs: evidence
The Electricity Act 2003 holds many promises for the from India. Energy Policy, in press, Corrected Proof—Available
sector. Licensee-free thermal generation, non-discrimi- Online.
natory access to the transmission system and the gradual Dubash, N.K., Rajan, S.C., 2002. India: electricity reform under
introduction of open access for the distribution system political constraints. In: Dubash, N.K. (Ed.), Power Politics:
would go a long way in developing a power market. Equity and Environment in Electricity Reform. World Resources
Institute, Washington, DC, pp. 11–30.
These, along with multiple licensees, could help usher in Foster, V., 2000. Measuring the Impact of Energy Reform—Practical
competitive environment in the Indian power sector. Options in World Bank (Ed.), Energy and Development Report
This, however, is not a panacea to all the ills of the 2000—Energy Services for the World’s Poor. The World Bank,
power sector. The improvement of distribution segments Washington, DC,pp. 34–52.
is the key to long-term sustained growth of the power Freund, C. L., Wallich, C. I., 1995. Raising household energy prices in
Poland—who gains? who loses? Policy Research Working Paper
sector. This would significantly depend on decoupling 1495. The World Bank, Washington, DC.
the power sector from politics. Efforts must flow to Gilbert, R.J., Kahn, E.P., 1996. Competition in institutional change in
address the issues that relate to the distribution segment US electric power regulation. In: Gilbert, R.J., Kahn, E.P. (Eds.),
along with ensuring competition in the unbundled International Comparisons of Electricity Regulation. Cambridge
segments of the sector, especially for bulk power. University Press, Cambridge.
GOI, 2001. Report of the Expert Group: Settlement of SEB Dues.
Gradual reduction in the cross-subsidy burden on the Planning Commission, Government of India, New Delhi.
sector and improvement in operational and commercial GOI, 2002a. Annual Report on The Working of State Electricity
Boards & Electricity Departments (2001–02). Planning Commis-
14
In fact, the concept of a merchant power plant is not new in India. sion (Power & Energy Division), Government of India, New Delhi.
Already, a private hydro power plant of 86 MW is operating as a GOI, 2002b. Tenth Five- Year Plan (2002–2007). Planning Commis-
merchant power plant without any long-term PPA with buyers. sion, Government of India, New Delhi.
ARTICLE IN PRESS
2490 A. Singh / Energy Policy 34 (2006) 2480–2490

Gorini de O.R., Tolmasquim, M.T., 2003. Regulatory performance international investors in the power sector. Energy and Mining
analysis case study: Britain’s electricity industry. Energy Policy. in Sector Board Discussion Paper No. 6. The World Bank,
press, Corrected Proof—Available Online. Washington, DC.
Gupta, P., Lamech, R., Mazhar, F., Wright, J., 2002. Mitigating Nelson, J.M., 1996. Promoting policy reforms: The twilight of
Regulatory Risk for Distribution Privatization—The World Bank conditionality. World Development 24 (9), 1551–1559.
Partial Risk Guarantee Energy and Mining Sector Board Discus- Newbery, D.M., 1997. Privatization & liberalisation of network
sion Paper No. 5, The World Bank, Washington, DC. utilities. European Economic Review 41, 357–383.
Hawdon, D., 1996. Performance of power sectors in developing Newbery, D.M., 2000. Privatization, Restructuring and Regulation
countries—a study of efficiency and world bank policy using data Network Utilities. MIT Press, Cambridge, MA.
envelopment analysis. Energy Economics Centre Discussion Paper, Newbery, D.M., Green, R., 1996. Regulation, public ownership and
No. 88. Surrey. privatisation of the english electricity industry in Gilbert. In:
HERC, 2001. Order on Annual Revenue Report for Distribution and Richard, J., Kahn, E.P. (Eds.), International Comparisons of
Retail Supply Business for 2001–02 and Distribution and Retail Electricity Regulation. Cambridge University Press, Cambridge.
Supply Tariffs. Haryana Electricity Regulatotry Commission, Pollitt, M.G., 1997. The impact of liberalization on the performance of
Panchkula. the electricity supply industry, an international survey. The Journal
HERC, 2002. Order on Annual Revenue Report for Distribution and of Energy Literature III 2, 4–31.
Retail Supply Business for FY 2002–03. Haryana Electricity Rajan, A.T., 2000. Power sector reform in Orissa: an ex-post analysis
Regulatotry Commission, Panchkula of the causal factors. Energy Policy 28 (10), 657–669.
Hunt, S., 2002. Making Competition Work in Electricity. Wiley, New Ranganathan, V., 1996. Electricity privatisation revisited: a commen-
York. tary on the case for new initiatives in India. Energy Policy 24 (9),
ICRA/CRISIL, 2003. Report on Rating of State Power Sectors, 821–825.
submitted to Ministry of Power. Government of India, New Delhi. Sankar, T. L., Ramachandra, U., 2000. Regulation of the Indian
Joskow, P., 1997. Restructuring, competition and regulatory reform in the power sector ASCI Journal of Management 29(2).
US electricity sector. Journal of Economic Perspectives 11 (3), 119–138. Srinivasan, T. N., 2002. Analytical and Regulatory Issues in the
Joskow, P.L., 1998a. Electricity sectors in transition. Energy Journal Competition for Private Investment Between and Within Devel-
19 (2), 25–52. oping Countries. Unpublished paper downloaded from http://
Joskow, P. L., 1998b. Regulatory priorities for reforming infrastruc- www.econ.yale.edu/srinivas/ on 21st September 2002.
ture sectors in developing countries. Annual World Bank Wamukonya, N., 2003. Power sector reform in developing countries:
Conference on Development Economics. Washington, DC, April mismatched agendas. Energy Policy 31 (12), 1273–1289.
20–21 1998. WEC, 2002. India Energy Market Reforms: WEC Report. World
Lai, L. L., 2001. Power System Restructuring and Deregulation: Energy Council.
Trading, Performance and Information Technology, Wiley, Chiche- World Bank, 2001. India—Power Supply to Agriculture, vol 1. The
ster. World Bank,Washington, DC.
Lamech, R., Saeed, K., 2003. What international investors look for
when investing in developing countries: results from a survey of

You might also like