Study on the Wellhead Sampling Method for SAGD of Heavy Oil


Yongwei Guo* & Zhiping Li
China University of Geosciences Energy Institute, Beijing, China

Yugang Lv
Jinzhong Vocational and Technical College, Jinzhong, Shanxi, China

ABSTRACT: Aiming at the existing problems of the SAGD sampling method, based on the sampling SAGD
production liquid requirements, through the analysis of advantages and disadvantages of extraction pipeline sam-
pler and DC cooling type sampler, the bypass pipeline sampler is finally designed which meets the requirements
of SAGD sampling. The sampler is suitable for the water content of SAGD sampling, and provides some guid-
ance for the development of SAGD matching technology.

Keywords: SAGD; sampling; moisture content

1 INTRODUCTION conventional wellhead high temperature sampler has


the following problems:
For the development of oil field, it is a very important 1) When using the wellhead high temperature sam-
routine work to collect samples of flowing medium in pler, the fluid in the pipeline enters the normal tem-
pipeline, analyze the samples of a certain quantity of perature and pressure environment at high temperature
medium in the pipeline, and determine its composi- and high pressure environment, resulting in the gasi-
tion, water and sediment content, density and viscosi- fication of high temperature production liquid because
ty. However, because of the special production pro- of the rapid change of environmental pressure, which
cess of ultra-heavy oil field, a large number of super- does not make the sample representative.
heated steam is being injected into the underground oil 2) Severe vaporization not only leads to the failure
output liquid temperature at 160°C - 180°C, mean- to get samples during the sampling process, but also a
while in order not to make the water flash vaporization potential safety hazard in the whole sampling process
in produced fluid, the pipeline pressure must be main- because there is a lot of high temperature steam during
tained at the saturation water vapor pressure above, the sampling process.
which increased the difficulty of sampling.

3 METHODS OF CURRENT HEAVY OIL


2 PROBLEMS EXISTING IN HEAVY OIL SAM- SAMPLING
PLING
At present, the manual pipeline sampling method used
Due to the special production process, high tempera- in ordinary heavy oil fields is only suitable for uni-
ture and high pressure conditions of heavy oil field, form liquid, and its composition and quality do not
which adds much difficulty for sampling, especially in change obviously with time. The automatic sampler is
SAGD mining process, a large number of superheated common from the line of continuous or repeated ex-
steam is being injected into the underground oil output traction of multiple sample, thus to ensure that any
liquid temperature at 160°C ~ 180°C, wellhead pres- changes in the composition of the bulk liquid can be
sure 1.5MPa ~ 2.0MPa, resulting in SAGD well using represented by the sample. In order to make the sam-
ple as representative as possible, it must meet the re-
quirement of uniform sampling point of liquid extrac-
*Corresponding author: 619669564@qq.com tion and sample frequency. But at present the working

155
temperature of automatic sampler is below 100°C, easily causes the extraction of residual; it’s inconven-
which does not meet the requirements. ient to keep warm.

3.1 Well opening sampler

3.1.1 Wellhead common sampler


In the early stage of construction of SAGD test area,
the wellhead common sampler is used. The working
principle is to open the sampling gate counterclock-
wise and connect the sample cup under the sampling
Figure 1. Manual oil well sampler.
opening, and close the sampling gate after the sam-
pling is completed.
The outflow of the high temperature production liq- 3.2.2 QYQ-35 automatic high temperature sampler
uid will result in flash vaporization because of pres- The QYQ-35 high temperature sampler is installed on
sure relief, which will affect whether the sample can some SAGD manifold oil-gathering lines(see figure
represent the real produced liquid. The high tempera- 2). When sampling began, close the lofting valve,
ture and pressure of the produced liquid with a large open the sampling valve, and move the piston cylinder
amount of steam bring some risks to the personal to suck the crude oil to the cylinder. When the col-
safety of employees. lected sample reaches a certain amount, close the
sampling valve, open the lofting valve, then start the
3.1.2 Pressure gauge vent cock natural air cooling system to cool the cylinder to be-
When the wellhead sampler becomes abnormal (fro- low 100°C, monitor the cylinder pressure gauge, ad-
zen in winter, rust or sampling cock release), using the just the position of the piston in the cylinder to make
pressure gauge vent cock or single well oil line pres- the pressure value close to the atmospheric pressure,
sure gauge pressure gauge vent cock head on wellhead and then open the lofting valve and discharge the oil
sampling. In the process of sampling, the sample cup sample.
is spliced below the sample opening. Then anticlock-
wise open the vent cock of pressure gauge which is
closed, after the sampling finishes.
Pressure gauge vent cock sampling and wellhead
common sampler have the same shortcomings, namely
the outflow of high temperature production liquid will
cause flash because of pressure relief, which can affect
whether the sample can represent the real produced
liquid. The high temperature and high pressure of the
produced liquid with a large amount of steam bring
some risks to the personal safety of the employees.

3.2 Pipeline suction sampler

3.2.1 Manual high temperature sampler


In the early stage of the construction of SAGD, a
manual handwheel sampler was installed on the single
well production line (see Figure 1). The principle is to
open the sampling gate when sampling, anticlockwise
rotate the handwheel to move the piston backward,
Figure 2. The high temperature structure and working princi-
and then the produced liquid enters into the cylinder
ple of QYQ-35 high temperature and high pressure sampler.
barrel. When the temperature drops down to 80 de-
grees, open the sampling gate, and clockwise rotate
the handwheel to extrude the liquid into the cup. The problems of QYQ-35 high temperature auto-
Manual high temperature sampler is placed at the matic sampler are that the automation control system
horizontal, and the sampling opening is located in the is prone to malfunction, for example, the piston stroke
middle of the horizontal flowing pipeline. The fol- is often out of control, and the control of inlet and
lowing problems are found after use: because take outlet gates is disordered; the adaptability of the envi-
samples in the horizontal flowing pipeline, of which ronment temperature is poor, and too high or too low
the medium distribution is very heterogeneous, the temperature will lead to a failure in sampling.
representativeness is poor; small diameter pipeline Based on the operating situation at worksite, the
that accompanies sampling system is longer, which sampling quantity of the pipeline suction sampler is

156
small and the sampling accuracy is not high. The main As shown in Figure 3, the system consists of DN50
reasons are as follows: pipeline, DN100 pipeline, DN50 ball valve, DN100
1) When the piston is moved back on the cylinder, ball valve, mixer, sampling assembly, and cooling
the negative pressure occurs within the cylinder, and system.
the cylinder pressure is lower than the pressure in Its working process is to make the liquid flow to a
pipe, which results in flashing within the cylinder. specific pipe section through the reverse process, then
Because the piston makes the volume of cylinder con- intercept the whole material of the pipe flow section to
stant, which results in that most volume of cylinder is sample, and then cool the sampling system by wa-
occupied by gas, the sampling amount is reduced and ter-cooling.
sometimes even no sample is available. When sampling is required, open the gate of the
2) Because the sampling opening is directly con- bypass sampler, and close the straightway gate, so that
nected to the pipeline, and the flow pattern of the liq- the liquid mixed evenly by the phase mixer flows to
uid inside the pipeline cannot be determined, which the sampling cylinder of the sampling assembly along
may result in the stratified flow state of fluid, the liq- the bypass pipeline, then flows out from the sampling
uid on the cross section of the pipeline cannot be taken cylinder and enters into the system through the out-
out uniformly, which affects the sampling accuracy. flowing bypass pipeline. When the temperature of
sampling cylinder is the same with that of the pro-
duced liquid three minutes later, turn off the gate,
4 BYPASS PIPELINE SAMPLER open the straightway gate, start the water circulating
cooling system to cool the sampling cylinder. When
Because the suction sampler exists above, we con- the temperature of sampling cylinder cools to below
clude that when sampling must meet 4 conditions: the 80°C three minutes later, close the cooling system,
interception of a representative sample; into sampler place the sampling cup under the sampling opening,
without phase mixer will be fully mixed sample; the open the sampling cock, and rotate the handwheel, to
sample needs into the first cooling after the decom- make the sample liquid in cylinder flow into the cup.
pression process, ensure the flash phenomenon does
not occur the sample; the sampler should be a heat
exchange device is arranged, the samples were cooled. 5 FIELD APPLICATION
To this end, we develop pipeline bypass type sampler
according to the main points. In July 2011, the bypass pipeline sampler was in-
The design pressure is 1.6MPa, the working pres- stalled at 1 pipe sinks in the heavy 37SAGD test are,
sure is 1 MPa, the design temperature is 200 degrees, as shown in Figure 4.
and the medium is the high temperature production
liquid of heavy oil. The basic principle is: firstly,
move the piston of suction unit to the end of oil
chamber, so as to make room for storage; open the
bypass flow and close the main process, so that the oil
chamber of suction unit is filled with the liquid in
pipeline; reverse operation flow to intercept all mate-
rial flowing through the oil chamber, and start the
cooler to cool the liquid in; when the temperature
cools below 100°C, which does not reach the boiling
point of the water vapor under atmospheric pressure, Figure 4. The installation drawings of bypass pipe samplers.
the pressure suddenly decreases, which can prevent
the samples flashing, and through pushing the piston
of suction unit, the liquid can be completely removed, 5.1 Comparison between bypass pipeline sampler
which is the real sample of the original liquid pro- and QYQ-35 sampler
duced from oil well. In order to verify the technological adaptability of the
bypass pipeline sampler, a bypass pipeline sampler is
installed on the measuring pipeline in SAGD test site,
take 5 samples from the same test well in September
28, 29 and 30 in succession, and begin to take 1 sam-
ple from each well every day from October 1. Mean-
while, the QYQ-35 high temperature sampler contin-
ues to maintain the original sampling system, which is
to take 2 samples from each well per day. When two
samplers are used to take sample from the same well,
only the second sample instead of the first one is used
Figure 3. Structure of pipe bypass sampler. every time (See Table 1).

157
Table 1. The comparison of bypass pipeline sampler and QYQ-35 sampler.
Date Moisture content (%)
Sampling methods
Well 9.3 10.1 10.2 10.3 10.4 10.5 10.6
Bypass pipeline sampler 94 80 78 75 80 80 77 86 83 74 64
Well-1
Manual high temperature sampler 80 78 75 71 89 77 77
Bypass pipeline sampler 87 89 87 79 84 91 87 73 81 73 72
Well-2
Manual high temperature sampler 75 79 73 83 82 70 71
Bypass pipeline sampler 81 88 81 81 78 89 62 79 75 81 73
Well-3
Manual high temperature sampler 83 79 75 74 86 83 78
Bypass pipeline sampler 85 81 79 87 88 87 86 81 68 80 83
Well-4
Manual high temperature sampler 80 84 83 85 75 81 65

Table 2. by-pass pipeline sampler and wellhead sampler water data comparison table.
Date Moisture content (%)
Sampling methods
Well 11/6 11/9 11/10 11/11 11/13 11/14 11/15 11/16 11/22 Ave
Bypass pipeline sampler 73.1 81.3 82.4 79.3 65.8 80 77.6 72.5 74.6 75.7
Well-1
Wellhead common sampler 77.8 72.6 76.2 80.5 76.5 66.8 77 80.7 71.7 74.7
Bypass pipeline sampler 75.7 79.8 86.1 81.9 77.2 84.1 78.6 80.1 86 80.3
Well-2
Wellhead common sampler 75.5 79.9 73.5 84.1 83 82.2 83.6 79.6 86.4 79.8
Bypass pipeline sampler 79 87.5 89.4 83.2 83.2 77.3 78.7 80.9 80.9 79.5
Well-3
Wellhead common sampler 78.1 77.5 68.7 80.6 77.3 75 78.1 74.6 69.6 74.2

5.2 Comparison between bypass pipeline sampler heavy oil in the pipeline.
and common sampler
The oil production station decided to install the bypass 6 CONCLUSION
pipeline sampler in No. 2 measuring pipeline of man-
ifold in a SAGD test site in November, 2011, to real- (1) This sampler combines the principles of bypass
ize the accurate sampling of 4 wells of manifold. pipeline sampler and suction sampler, and changes the
In order to study the influence of flash on the mois- operating process of suction unit to achieve the pur-
ture content when the common wellhead sampler is pose of sampling. (2) The interception pipeline sam-
used, a two-week comparison test between the ordi- pler takes the liquid in a certain pipeline section,
nary sampler and bypass pipeline sampler are carried which is the whole sample in the certain pipeline, and
out. ensures the integrity of sample components. (3) Low-
From the Table 2, it can be seen that the moisture ering the temperature before decompression can effec-
content of samples taken by two samplers from Well-1 tively reduce the flash, and the sampling method can
and Well-2 isn’t much different, and the moisture satisfy the condition of accurate sampling, which can
content of samples taken by wellhead sampler is about avoid all kinds of sampling errors, and take sample
1% lower than by bypass pipeline sampler. The meas- repeatedly and accurately.
ured moisture content of sample taken nu two sam-
plers from Well-3 are very different, and the moisture
content of sample taken by wellhead sampler is 5% REFERENCE
lower than by bypass pipeline sampler.
The study found that during comparing the moisture [1] GB/T 4756 - 19898. Method for Manual Sampling of
content of two samples, the wellhead output liquid of Petroleum Liquids.
Well-1 and Well-2 has about 7 degrees Sub-coll, so [2] Xu Jingrun, Niu Li, Han Xiaoqiang, Cai Jiangang. 2010.
the output liquid exists in liquid form before flowing The study of water content of the output liquid of SAGD
pilot test area of Xinjiang oilfield. Xinjiang Petroleum
into the wellhead sampler, which flashed slightly
Technology, (04): 25-28.
when flowing out of sampler to a place under atmos- [3] Cheng Yi. 2006. Research on the Sampling Technique of
pheric pressure, so that its measured moisture content Natural Gas Hydrate. Hangzhou: Zhejiang University.
should be slightly lower than that of sample taken by [4] He Chenglin. 2016. Simulation of Sealed Sample Device
bypass pipeline sampler. Meanwhile, the wellhead for Produced Liquid Containing Hydrogen Sulfide from
output liquid of Well-3 was in saturation state, that is, Heavy Oil Well. Daqing: Northeastern Petroleum Uni-
a certain mass percentage of steam existed, of which versity.
the presence is not acceptable for the wellhead sam- [5] Ding Xin. 2011. The Distribution Characteristics of
Two-phase Flow through Sampling Holes. Xi'an: Xi'an
pler. All components in the pipe can be intercepted by
Petroleum University.
bypass pipeline sampler, so the measured moisture [6] Xiu Liqun. 2016. Analysis of Influencing Factors of
content of sample taken by wellhead sampler is about Manual Sampling Technology in Wellhead of Heavy Oil
5% lower than by bypass pipeline sampler. Well. Daqing: Northeast Petroleum University.
The field experiments showed that this sampler can [7] Zhao Yunting. 2015. Factors Analysis of Influencing
directly extract the liquid from the pipeline constantly, about Heavy Oil Well Wellhead Manual Sampling Pro-
which can completely reflect the moisture content of cess. Daqing: Northeast Petroleum University.

158
[8] Liu Jian. 2010. Structure Study on the Natural [11] Wang Jie. 2016. The development and application of
Gas-hydrate Drilling Coring Fidelity Sampler. Beijing: automatic sampler for well oil production fluid. Tech-
China University of Petroleum. nology Supervision in Petroleum Industry. 12: 40-42.
[9] Xiao Yong. 2013. Discussion on the localization of Pe- [12] Zhu Haiyan. 2009. The current study and development
troleum pipeline automatic sampler. Electronic Instru- of natural gas hydrate sampling device. Natural Gas In-
mentation Customers. (6): 72-76. dustry, 29(6): 63-65.
[10] Tian Ming. 2013. Research and application of high
pressure sampler. Complex Hydrocarbon Reservoirs,
6(4).

159