Professional Documents
Culture Documents
in the vertical direction. An E-Fire head operated by pressure During the qualification testing, the tractor demonstrated the
logic and a ball drop disconnect were run below the tractor. following:
On the Chayvo Z6 Well, a memory PLT (Production
Logging Tools) was also run. The PLT consisted of three sets • Maximum Pull: 9,700 lbs (190% of requirement)
of pressure/temperature gauges, spinner (flowmeter), and • Nominal Operating Speed: 950 ft/hour RIH.
various other components in case of tool failure. Because of • Operational Reliability
running the PLT blind, it is impossible to see at the surface if
data is being collected; additional back-up tools were deemed Job Operation – Chayvo Well Z6
necessary to assure that data is collected on every run. The
overall tool length was approximately 40 feet with the Well Profile, Conditions, and Operating Conditions. The
maximum OD of 4.5 inches. Z-6 well in the Sakhalin-1 project is a J-shaped double build
Bottom hole pressure and temperature gauges were well with a TD of 9,375 meters and TVD of 2,613 meters.
run several times in the Chayvo Z6 Well. The gauges were The horizontal well trajectory extends out 8.5 km to TD. A 7
run inside a dummy gun, for protection. With gauges in the inch 26 and 29 pound per foot completion string run to surface
hole, flowing and shut-in pressure and temperatures were with a Gas Lift Mandrel and Sub Surface Safety Valve
obtained. The pressure build-ups were later analyzed to provides a minimum restriction of 5.18 inches. Operations
evaluate the completion efficiency. No skin damage was were all performed in a live underbalanced well with well
noted in the pressure build-up analysis. head pressure varying between 700-1,400 psi depending on
In the future, potential wash tools may be utilized to which zones were perforated. Coiled Tubing operations
clean out any sand or fines that may accumulate in the well. started with Potassium Chloride (KCl) in the well bore which
Kick-over tools are also available at the wellsite should an was then displaced to diesel during the first run.
attempt to recover or change gas lift valves be made. If these
operations are performed on CT, they may also require a Summary of Gauge, Perforation Runs, and PLT Runs. For
tractor. runs that included the tractor, the BHA included elements to
create differential pressure with the circulation of the
Hydraulic Tractor. The Hydraulic Tractor consists of a intervention fluid to power the tractor and safety release
Control Assembly (CA) connected between two shaft equipment. Down hole differential pressure was created by
assemblies (see Fig A-6). The tractor is powered and either the E-Fire firing head with a 0.188 inch diameter flow
controlled by the differential pressure between the centerline restrictor or the Coil tubing Ball drop Firing head (CBF) with
flow channel (supplied by the CT) and the annulus at the a 0.159 inch diameter flow restrictor. Circulation rates of 1.2
tractor’s location. The CA inlet valve is pressure activated and to 1.3 barrels/minute were used to activate and run the tractor.
opens at approximately 1,000 psi differential (psid). The inlet Surface pump pressures ranged from 2,900 to 3,500 pounds
valve incorporates an index device so that it opens only on per square inch at the above circulation rates depending on the
alternate pressure cycles. The gripper/shaft cylinder tractor speed. The BHA included a motor head assembly with
assemblies move simultaneously in opposite directions on the dual flapper valves and an integrated ball drop disconnect
shafts in response to the CA sequencing, eg; they move toward above the tractor. A second ball drop disconnect was installed
the tool joints of the shafts or they move toward the CA. below the tractor in the event the lower part of the BHA
The tractor is 28 feet long, and 4.7 inches outside became stuck. In runs where the CBF was only used to
diameter with a centerline passage of 0.80 inches. Static load produce a differential pressure (no perforation string), all of
capacity is 8,800 lbs at 1500 psid. the firing components were removed for safety purposes.
Compatibility with the CBF was proven during down
Tractor Sequencing. The operational sequence is: hole functional testing at the beginning of operations. The ball
expand the forward gripper; command the cylinders to move drop disconnect normally made up below the tractor was
inward toward the CA (this forces the forward shaft down omitted and a 0.75 inch diameter ceramic ball was pumped
hole); collapse the forward gripper; expand the aft gripper; down the coil and over the gooseneck successfully. Even
command the cylinders to move outward toward the tool joints though the test was a success, the CBF was relegated to a back
(this forces the aft shaft down hole); and collapse the aft up role to the E-Fire firing head for reasons of safety.
gripper. This sequence repeats until the load on the tractor is Operational measures included consideration for
large enough to stall the tractor or the pressure differential is locating of the perforation string and firing procedures.
lowered below the start valve pressure threshold. Perforation strings were RIH with the tractor 50 meters past
shooting depth and Pulled Out Of Hole (POOH) to correlate
Tractor Qualification Testing. The extensive modeling back to depth logs obtained from POOH Gamma Ray / Casing
efforts emphasized the importance of reliable minimum Collar Locator / Cement Bond Log (GR/CCL/CBL) data. The
performance characteristics of the tractor for use Chayvo Field perforation strings were comprised of the perforation guns
in Sakhalin Island. Qualification testing requires verification with lengths up to 320 meters and fired with the E-Fire. The
of minimum pull of 5,000 pounds, advertised speed and E-Fire is triggered by a pressure pulse code from the surface
operational reliability. pump when at the shooting depth. The tractor did not interfere
The test consisted of nine runs over two days totaling with the pressure pulse code and successful triggering of the
4,530 cycles on the tractor. The operational flow rates were 55 E-Fire was accomplished 5 of 5 times.
gallons/minute with a 0.225 inch diameter flow restrictor.
________ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ____-----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------________________ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ _
When required, gauges were RIH with the tractor (if indicator trace as the injector rate is increased from start up to
necessary) 50 meters past Target Depth (TD) and then POOH normal operation. Constant or even slightly increasing
to desired Measured Depth (MD) based on correlated data. injector weight indicates that the RIH rate can be increased.
The CBF was installed below the tractor to create the Assessment of Fig. A-8 shows that at 10 feet/minute injector
differential pressure necessary for tractor operations. The weight remains constant but at injector rates above 15 feet per
gauges were installed below the CBF. minute, the injector weights begin to slack off. If this slacking
The single Memory Production Logging Tool run off were to continue, tractor speeds would continue to slow to
comprised of two passes with a BHA consisting of a motor the point where forward progress is halted. It was noted
head assembly, tractor, CBF, GR/CCL and a MPLT. A during operations that when this scenario happens, the tractor
combination of three redundant tools made up the overall may not pull the excess helical buckling out of the CT string
MPLT. Sufficient data was acquired with the 3 tool and begin to move again. The start up procedure may have to
combination assembly in two passes to analyze the inflow be repeated from the beginning.
performance of the well. During the well operation, the tractor’s operational
life was constantly being evaluated. Because of onsite
Operation Methods. Initially anticipated operational logistical support, the capability to diagnose and completely
methods for CT conveyed payloads required modification for refurbish the tractor enabled the development of a component
effective field operations. Prior to field operations, it was usage record and replacement schedule before functionality
expected that a typical procedure would include injecting the had been compromised. This process assured equipment
string into the hole until lockup occurred, then activating the availability.
tractor, over coming lock up and completing the run. It was
anticipated that there would be a significant difference in the Accomplishments and Lessons Learned
measured injector weights when the tractor was in operation.
This procedure was unsuccessful and was modified. Job Accomplishment Summary. Job accomplishments
Operationally, there is a small window of measured during the completion of the Sakhalin Island Z6 well are as
injector weights while RIH when tractor output exceeds CT follows:
forces. The procedure for running the tractor in this type of
deep, very extended well was refined to address these • One test run was performed that verified the Tractors
problems. Essentially, the tubing is RIH to lock up depth and Ball Drop compatibility
the CT is then POOH until the injector weight rolls over • Five successful perforations were completed with E-
(where the BHA is moving). The operator will then put the Fire triggering.
injector into a hold position. This will be the pick up weight • One PLT run covering 2,471 meters in 9.2 hours of
of the string where all of the tubing will be in tension. The tractor operation (881feet/hour average).
operator will then slowly start to RIH. While monitoring the • A total of thirteen runs while tractoring 4,360 meters
injector weight indicator, the operator will start pumping the (tractor operated during seven runs).
circulation fluid at a suitable rate (above 20 gpm) to activate • The Z-6 well set a world record run for a continuous
the tractor. During subsequent operations, an observation was length coiled tubing application.
made that even though the tractor can produce in excess of
9,000 pounds of pull, the injector weight indicator will not Lessons Learned. The challenges from the first well
show a load increase when the tractor is activated. The completion at Chayvo Field in Sakhalin Island provided
operator must continue RIH and monitor the injector weight valuable lessons and insight for future work.
for a decrease (i.e. the tubing is locked up and the tractor is
static) to indicate if the tractor is not activated. Lesson 1: Tractor Operation. One of the most
An example of this is seen by comparing the two significant insights into tractor operations beyond CT lock up
traces in Fig. A-7. This graph documents the injector weights was the lack of reassurance from gauges or computer monitors
associated with the third perforation run, which consisted of for verification. The tractor operator must look for the tell tale
320 meters of perforation guns. The traces are from two signs of activation and regulate RIH speed while continuously
sequential attempts to start the tractor. Notice the length of monitoring injector weights to maintain successful operation.
time for pressure to build given a stable flow rate at the
surface. The starting MD is the same for both attempts. Lesson 2: Tractor Performance Requirements.
Inspection of the plot shows that the difference between the Contrary to the extensive pre-operations analyses and
two plots is very small and appropriate action can only be subsequent qualification program, actual down hole conditions
made by service personnel with adequate tractor running resulted in the need for greater tractor capacity of up to 180-
experience. 200% more than anticipated. Greater tractor capacity means
As the operator RIH with the injector and the greater confidence to complete the mission.
circulation rate is adequate to operate the tractor, it will
engage the hole wall and begin to exert a pulling force. The Future Uses of CT with Tractors
BHA will begin to move when the loading condition of the
injector, CT, and BHA combined drops below the pulling Other potential applications for Tractors with long CT strings
force of the tractor. Movement of the tool sting can be seen are:
by inspection of Fig. A-8. Fig. A-8 shows the injector weight • Perforations
SPE 94208 5
• Logging
• Sand control
• Running screens
• Sliding Sleeves
• Acidizing
Acknowledgements
References
________ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ____-----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------________________ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ _
Appendix A
(m) 4,000
0 0 101.57
300 0 101.57
6,000
1478 76.56 101.57
7245 76.56 101.57
8,000
8052 90 101.57
10422 90 101.57
10,000
40,000 30
Injector weight maintained, even 2000 40,000 Injector Weight stays constant
as injector is continued RIH while RIH rate is increasing.
30,000
1500 30,000 20
20,000
1000
20,000
10,000 10
500
Injector weight continues to fall 10,000
indicating tractor not activated.
0 0
00:00 01:26 02:53 04:19 05:46 07:12 08:38 10:05 11:31
0 0
Time (min:sec) 00:00 07:12 14:24 21:36 28:48 36:00 43:12 50:24
Tractor Activated Tractor Not Activated Surface Pump Pressure Time (min:sec)
________ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ____-----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------________________ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ _