Prepared By: Muhammad Imran (Civil Surveyor)

Tripodsurveyors@gmail.com
www.youtube.com/c/CivilSurveyor
Note: Changes can make only in Yellow Cells, please don’t change in any other Cell.
Maximum Superelevation (%) 6 Speed Factor 06+470.000 Full S.E 06+407.663
Start Full S.E END Full S.E
Design Speed KM/Hr 80 60 0.600 After PC
1/4,1/3 etc
PC Station of Curve 6400 80 0.500 06+190.000 06+687.663
Start S.E 3/4,2/3 etc PC PT END S.E
PT Station of Curve 6477.663 100 0.380
Before PC
Half Width or Half Pavment of Road 7.300 Diagram
Cross Slope or Normal Crown (%) 2
Speed Factor 0.500
Transition Length 116.800
IF Transition Length Given in the Drawing 280.000
Length of Transtion Before PC 3 (3/4 , 2/3 etc)
Length of Transition After PC 1 (1/4 , 1/3 etc)
Superelevation Start Station 6190.000
Maximum Superelevation Start Station 6470.000
Maximum Superelevation END Station 6407.663
Superelevation END Station 6687.663
INCREASING THE SLOPE OR S.E DIST from Start S.E to Full S.E SLOPE
REQUIRED STATION SLOPE 6375.000 185.000 3.286
DECREASING THE SLOPE OR S.E DIST from Full S.E to End S.E
REQUIRED STATION SLOPE 6525.000 117.337 -2.648