Professional Documents
Culture Documents
1.Cut and cover- In this type of tunnels, the tunnel structure is cast-in-situ or
precast in an excavation. After construction, the structure is back-filled with new
or excavated soil. Cut and cover construction is adopted when the depth of tunnel
is shallow and the safe excavation is possible from the surface with out collapsing
the walls of excavation and when it is economical and acceptable. This
methodology is usually used for the construction of underpasses, approach sections
of other tunnels & tunnels in flat terrain or shallow depth.
The tunnels may be constructed in place or by using precast sections. Two types of
cut and cover construction are; bottom-up and top-down.
2. Bored or Mined Tunnels - These tunnels are built without excavating the
ground surface. These tunnels are named according to the type of material through
which the tunnel is being excavated. When a tunnel passes through different types
of material it is known as mixed face construction. In bored tunneling , the
excavation takes place at the portal or at a shaft, thus there is a minimum impact on
usual traffic, air & noise quality, and utilities. Linings are the most important
component of these kind of tunnels. For depths 10 m to 12 m, cut-and-cover is
usually more economical and practical than mined tunneling
3. Rock Tunnels- Rock tunnels are excavated through the rocks either by drilling
or by blasting. The tunneling method utilizes mechanized excavators in case of soft
rocks or rock tunnel boring machines (TBM). Sequential Excavation Method
(SEM) is also used in some cases. The behavior of rocks can change place to place
and type to type so depending on this stabilization measures ranging from no
support at all to anchor bolts to steel sets to even heavily reinforced concrete lining
and combination of all these are used. It is one of the most challenging tunneling
geology.
The following relations refer to geometrical properties of mouth profiles. With the
initial parameters r1, r2, r3 it is obtained:
r 1−r 2
sin β = r 3−r 2
c = √ r 32−2 r 2 ( r 3−r 2 ) −r 12
π 2 π 2
( 2
)
Cross section area= A = 2 r 1 + 2 −β r 2 + β r 3 −( r 1−r 2 ) c
Height H= r1+r3-c
Span D =2r1
Procedure-
1- Choose r1
b
2- Evaluate Cos β= 2 r 1
2
1 2 b
3- Evaluate r3 = sin β (a+ c−√ r 1 − 4 )
4- Choose r2,
Fig- Example of mouth profile
Q 3- Standard norms of ventilation and illumination in tunnels.
1. Ventilation in tunnels :
Concerning tunnel ventilation, two different systems of ventilation have to be
distinguished: ventilation during construction (i.e. during the heading of the tunnel)
and service ventilation (i.e. during the operation of the tunnel). Expenditures on the
latter amount up to 30 % of the total construction costs.
1.1 Ventilation during construction :
Ventilation during construction has the following aims:
Supply with oxygen: The O2-content of air should not fall below 20 vol. %. Below
18 vol. % breathing is not possible and protection masks should be used. The lack
of oxygen is due to:
o Combustion motors
o Breathing
o Oxidation of wood, coal etc.
o Groundwater dissolves more O2 than N2
Cleaning of air: The following pollutants have to be removed
Dust from rock excavation and shotcreting
Combustion motors
Blasting fumes
Gas egression from rock
Radon decay products.
With respect to air pollution in working environments, maximum allowable
concentrations apply (MAC).3 These refer to exposures of 8 hours per day and up
to 42 hours per week. In addition, there are short time limits (Kurzzeitgrenzwerte,
KZG), which should not be exceeded in short exposures, and also instantaneous
values (Momentanwerte, R), which should never be exceeded.
Pollutants MAC
CO2 5000 cm3/m3
NOx 5 cm3/m3
CO 30 cm3/m3
SO2 5 cm3/m3
H2S 10 cm3/m3
Fine dust 4 mg/m3
Fine quartz 0.125 mg/m3
Asbestos fibres 10000 fibers/m3
The ductings are extendable tubes made of synthetic or steel sheets (Fig. 2.1).
Their cross section amounts to ca 1/60 to 1/30 of the tunnel cross section. The
required amount for fresh air is:
per person: 2,0 m3 /min,
per kW of diesel motors: 4,0 m3 /min.
Leaking from the ductings should be taken into account when estimating
the fresh air supply. Old ductings can loose up to 2/3 of the initially
introduced air due to leaking.
In case of drill & blast heading toxic blasting fumes are created. Therefore
work should not be resumed after blasting for 15 to 20 minutes. The
required fresh air supply is approx. 2 m 3 /(min · kg explosive), and the air
velocity averaged over the tunnel cross section should amount at least
0.3 m/s. Usually the fresh air is introduced near the face, so the most
polluted air is found near the portal.
Note that the ventilation can reduce the moisture of the shotcrete and
of the freshly excavated soil. A consequent loss of the ’apparent’ (or
capillary) cohesion of soil may cause collapse of the face if it is not
supported.
CO concentration < 100 ppm
NO x concentration < 25 ppm
Opacity: extinction < 7 · 10 −3 m − 1
coefficient
Air velocity (averaged over the cross section) < 10 m/s
In rail tunnels (in particular metros), cooling, i.e. the removal of warm
air (e.g. due to locomotives), is another task of ventilation.
Road traffic produces the maximum pollution at speeds of 10 to 15
km/h. The increase in the number of vehicles equipped with catalysers
resulted in a considerable reduction of fresh air requirements of road
tunnels which, de-pending on the ratio of trucks and on the slope,
amounts to between 30 and 50%.
Four types of ventilation techniques can be distinguished:
Natural longitudinal ventilation: This ventilation is accomplished by
the pressure difference between the portals and also by the piston
action of the vehicles.
Fans: These have a spacing of ca 10 tunnel diameters and produce a
longi-tudinal ventilation. The blowing direction is reversible. Large
ventilators achieve a higher thrust related to installation costs.
Fi g.Ventilation fans
F i g. Supply and extract channels above the carriageway. The separating vertical
wall has not yet been mounted.14
Tunnel length in km
bidirectional one-directional ventilation
1 tube 2 tubes
< 0, 4 < 0, 7
natural ventilation with CO-warning
< 2 < 4 longitudinal ventilation
< 4 < 6 - fans
- fans and ventilation shaft
< 0, 5 < 2 semi-transverse ventilation
< 1 < 2 - reversible
< 2 < 6 - semi-transverse ventilation
transverse ventilation
• Firstly, to allow traffic to enter, pass through and exit the enclosed
section safely.
CIE guidance (CIE 88-1990)states that the amount of light required within a
tunnel is dependent on the level of light outside and on the point inside the
tunnel at which visual adaptation of the user must occur. When planning the
lighting of a tunnel, there are 5 key areas to consider:
1 Access zone
Not within the tunnel itself, this is the stretch of road leading to its entrance.
From this zone, drivers must be able to see into the tunnel in order to detect
possible obstacles and to drive into the tunnel without reducing speed.
The driver’s capacity to adapt in the access zone governs the lighting level in the
next part of the tunnel. One of the methods used by CIE to calculate visual
adaptation is the L20 method, which considers the average luminance from
environment, sky and road in a visual cone of 20°, centred on the line of sight
of the driver from the beginning of the access zone (see below).
2 Threshold zone
This zone is equal in length to the ‘stopping distance’. In the first part of this
zone, the required luminance must remain constant and is linked to the outside
luminance (L20) and traffic conditions. At the end of the zone, the luminance
level provided can be quickly reduced to 40% of the initial value.
3 Transition zone
4 Interior zone
This is the area between transition and exit zones, often the longest stretch of
tunnel. Lighting levels are linked to the speed and density of traffic, as
Highway 4 to 10cd/m2
Urban 4 to 10cd/m2
5 Exit zone
The part of the tunnel between interior zone and portal. In this zone, during the
day time, the vision of a driver approaching the exit is influenced by brightness
outside the tunnel. The human eye can adapt itself almost instantly from low to
high light levels, thus the processes mentioned when entering the tunnel are not
reversed. However, reinforced lighting may be required in some cases where
contrast is needed in front of or behind the driver when the exit is not visible, or
when the exit acts as entrance in case of emergency or maintenance works
where part of a twin tunnel may be closed. The length is a maximum 50m
Ans. Selection and design of the support system are only two of many
interrelated factors in the overall design of a serviceable and economical tunnel.
The type of support, the method of excavation, and the character of the ground
are inseparable considerations. If the route is laid out to encounter the worst
rather than the best geological features, or if the construction method is ill-
suited to the geology, no amount of refinement of the lining can appreciably
influence the economy of the job. Nevertheless, for each tunnel layout and each
construction method, some types of lining are preferable to others. Initial
support during construction and final support during the functional life of the
tunnel pose separate requirements; sometimes both are best satisfied by a single
support system. Rational design presupposes a knowledge of the demands on
support systems, criteria for successful performance, familiarity ,~vith the
capabilities of available systems, and methods of analysis verified by
experience. Improved practice in the future is likely to have its roots in a clear
understanding of the shortcomings and requirements of today's practices. This
paper summarizes several current studies on the various aspects of design of the
support systems for transportation tunnels.
Planning and design decisions are of two classes, conceptual and detailed.
Decisions of the first class are based on considerations of such factors as the
purpose of the project; the depth, alignment, and geometry of the opening; the
external environment; and the required watertightness. The results of these
decisions constitute the conceptual design of the underground opening. It may
include several alternatives. The detailed design is then performed to provide
several alternate construction methods and support systems that meet the
requirements of the conceptual design. The tunneling scheme that results in the
lowest total cost for the project is selected.Few decisions in the design process
can be made completely independently of each other. The geology associated
with alternate axes at different depths and alignment should be a fundamental
consideration in the conceptual design. The selection of the depth and alignment
determines the geologic materials that must be tunneled. The materials
encountered, in turn, dictate which types of construction methods are feasible.
Other construction niethods, even though intrinsically cheaper, no longer can be
considered. The support system must be compatible with the geology and the
construction method. Hence, with the geology and construction method fixed,
only a few support systems can be considered.
The selection of the route alignment and grade is one of the most important
decisions to be made. If unfavorable conditions will be encountered, the
resulting high construction costs cannot be offset by refinements in the design
of the support system.
more complex than indicated by Tables 1 . Throughout planning and design, the
engineer needs to be aware that the geology of the material to be tunneled is the
most important variable in establishing the design, construction, and, ultimately,
the cost of the tunnel.
MODERN CONCEPTS OF THE DESIGN OF TUNNEL SUPPORT
SYSTEMS:
During excavation, most of the existing stresses in the ground are redistributed
around the opening by mobilization of the strength of the soil or rock. The
redistribution is often described as arching. Usually only enough support must
be added within a short time after excavation to help the soil or rock hold itself
up. Current soil and rock mechanics practice is to recognize and treat the
behavior of any system as a complex function of the interaction of the behavior
of the individual components of the system. In contrast, previous concepts and
theories for the design of tunnel supports have been based solely on assumed
loading diagrams; hence, they are unsatisfactory. Furthermore, because the soil
or rock being tunneled does not meet the appropriate assumptions, elastic and
elastic-plastic theories are rarely satisfactory for predicting the loads in tunnel
supports. The designer must somehow account for the deformation in both the
soil or rock and the support. The best way to visualize this interaction
phenomenon is by the simplified ground reaction curve shown in Figure 1.
The inevitable deformation that occurs before the supports can be installed is