Compliance Monitoring

Report (CMR) Online System


Presented by:
JOSEPHINE J. GALLO
EMS I, EMB-DENR Region 6
Legal Basis
Section 9.2 of the Revised Procedural Manual for DENR Administrative
Order No. 30, Series of 2003 or the Implementing Rules and
Regulations (IRR) for the Philippine Environmental Impact Statement
(EIS) System.
The proponent shall also conduct regular self-monitoring of specific
parameters, indicated in the EMP through its environmental unit. The
proponent’s environmental unit shall submit a semi-annual monitoring
report within January and July of each year.
Legal Basis
• MC 2016-001 issued on January 18, 2016 Requiring Online
Submission of Compliance Monitoring Report under the Philippine
Environmental Impact Statement System for Environmentally
Critical Projects (ECPs)

• MC 2018 – 004 issued on November 26, 2018 Amending Section 1 of


MC 2016-001 to include non-Environmentally Critical Projects (non
ECPs)
2. Login to the system
(same account in ECC Online)
If the applicant has
manual issued ECC,
Click sign up.
3. Fill out the registration form.

Proponent’s Name
Representative’s Name
User Name Password
Attachments:
1. Government/Company ID
2. Notarized Authorization Letter
3. SEC/DTI Registration
4. Click New CMR (Assume new
Application)
5. Fill up the Forms from Step 1 – 11

• Step 1: System Validate the ECC Number


Note: Add ex: “ECC-R12-“ before the ECC Number
• Step 2: Basic Information
• Step 3: Executive Summary
• Step 4-8: Results and Discussions
• Step 9: Conclusions and Recommendations
• Step 10: Attachments
- Sworn and Accountability Statement
- Laboratory Results of Analysis from DENR-EMB recognized laboratory
Step 1. System Validate the ECC
Number
Step 2. Basic Information
5. Fill up the Forms from Step 1 – 11

• Step 1: System Validate the ECC Number


Note: Add ex: “ECC-R12-“ before the ECC Number
• Step 2: Basic Information
• Step 3: Executive Summary
• Step 4-8: Results and Discussions
• Step 9: Conclusions and Recommendations
• Step 10: Attachments
- Sworn and Accountability Statement
- Laboratory Results of Analysis from DENR-EMB recognized laboratory
6. Proponent will review the Summary of the
CMR Application
Step 7. Forward this report to your managing
head for approval

Step 8. Enter the email of the managing


head.

Step 9. Managing head will receive the link to


the system and one time password to the
system (OTP)
Thank you!
EMB/Evaluator Side
1. The application is now in the default receiver of
the region if managing head approved the
application (Default Receiver will be designate by
region)
- The default receiver will evaluate the application
or assign it to the designate evaluator.
2. Evaluator will review the application.
3. Evaluator will forward the application to the Section Chief
4. Section Chief will forward the application to the EMED Chief
5. EMED chief will forward the application to Regional Director
for Approval.
6. Regional Director will approve or disapproved the application
• If Approved - A certification letter will be generated by the
system and receive by the proponent in their account
• If Disapproved - Application will be returned to the proponent
for additional compliance
http://online.emb.gov.ph/cmrdemo