Professional Documents
Culture Documents
CPM Pert PDF
CPM Pert PDF
i C
v D
i
E
t
y F
B Grantt
Bar chard
C
D
0 1 2 3 4 5 6 7 8
A
1 2
B
3 4 5 Milestone
C Chart
6 7
D 8 9 10
0 1 2 3 4 5 6 7 8
4) Nework :
This is an arrow diagram (consisting of only arrows & circles) drawn to represent the inter-relation
ships & sequence of all the read construction activities of a project.
Network rules :
1) Network has b - types of event
Intial event : has only tail arrow & marks begining of project. There must be only one initial
eventy in the project network.
Final event : has only arrow heads indicating the end of project. This is also only one event in
the project
Dual event : All intermediate events having at least one tail & are head arrow are called dual
events. It indicates completion & starting of a activities.
2) A project consists of number of activities which passes through number of events, According to
sequence or order of event we have.
Vision Engineering Academy Pune Contact : 9545804444 8
Predecessor Event : It is the event which happen before another event
- An event that immediately happen before another event without any intervening event in betn is
called immediate predecessor event.
Successor event : The event that follow anothr event is called successor event
The event that immediately follows another events is called immediate presecessor event.
1 4 5
3) Predecessor activity :
- Activity or activities that need to be performed before an activity under consideration are called
predecessor activity and activities that need to be performed immediately before an activity are
called immediate predecessor activity
Successor Activity :
Activities that need to be performed after competion of an activity under consideration are called
successor activites and immediate successor activity is an activity that need to be performed
immediately after completion of an activity under consideration
A D
B E G
5 6
C F
A B Q
C
R
2) Dangling error :
Project is complete when all activities are complete but the duration of activity R as shown in fig has
no effect on project time, This kind of error is called as “Dangling error”.
- To avoid dangling error network must be analysed in such a way that all events except initial & final
events must have at least one activity entering & one leaving them
Q T
P S U
R
G
EOT 10 LOT
00 10 11 15 16 26 26 31 31
A E J
1 3 5 7 8
10 5 5
2 D
B 5 I 4
55 10 F
2 4 6
C 7
22 22
B C I
7 F H1
3 4
5
G
4 4
3
9 9 12 13
Slack = 13-12 = 1
5 10
2
A5 C5
0 0 15 15
B5 D F10
1 3 4 6 25 25
10
10
E G
5
5
10 14
B D F
Critical path 1 3 4 6
5=0
15 15
3 3
0 -7
-2 -1
5 = 0 4-9 7
5=0 8 5=0
5 5 13 13
0 0 23 23
2-5-8 4-7-16 7-10-13
1 2 4 6
5 10
8-
11
0 4 2-3-10
-2
12
0
3-5-13 2-4-6
5 7 8 31 31
6 4 5=0
17 21 27 27
5=4 5=0
t a 4t m t b
expected mean time, t e
6
tb ta
std deviation, St
3
Variance, Vt (St ) 2
Least slack value = 0
Crirtical path 1 1-2-3-6-7-8
Critical path 2 1-2-4-6-7-8
minimum
cost
Here, objective is to find the project duration which will keep total project cost at minimum.
- Cost increases if project so as indefititely & if project is expedited.
Cost is minimum at some optimum project duration.
Total project cost : is the sum of two separate costs.
a) the direct cost for accomplishing the work and
b) the indirect cost related to control or duration of that work financial overhead lost production 7
the hike.
Total cost
Indirect cost :
- Consists of those expenditure which con’t be clearly allocated to the individual activities of project
but assessed as a whole.
- It includes the expenditure related to establishment & administration charges over head supervision
loss of recencue loss pendlty, etc.
- Indirect cost rieses whith increased duration.
Project duration
----------------------------------------------------------------------
duration
Cc
Direct
Direct cost curve
cost
Cn
tc tn
crash normal
duration duration
Duration
Normal time (tn) : It is the standard time which estimator would usually allow for an activity.
Crash time (tc) : minimum possible time in which an activity cab be completed by empoloying extra
resources.
Normal cost (Cn) : direct cost required to complete activity in normal time.
Crash cost (Cc) : direct cost corresponding to crash time
cost
optimum normal
crash
Duration
Rersource Allocation :
Management cab defined as art and science of preparing organising and directign human
efforts to control the forces and utilise the materials of nature for the benefit of human race.
Characteristics or features of mgt :
1) management is an activity.
2) management is purposeful.
3) management is a social process.
4) management is intangible .
5) management is an integrative process.
6) management is a multi-disciplinary discipline.
7) management is an universal activity.
8) management is getting thing done through others.
9) management is separate from ownership.
10) management is dynamic.
Principles of management :
These are guiding rules formanagerial action.
1) Division of work.
2) Authority & responsibhility
3) Discipline
4) Unity of commaned (one supervisor)
5) Unity of direction - one plan forwork
6) Subordination of individual interest to general interest.
7) Remuneration
Vision Engineering Academy Pune Contact : 9545804444 20
8) Centralization of authority.
9) Scalar chain - unbroken lie of authority
10) Order (sequvence) - “ a place fir everything and everything in its place”.
11) Equity - unblased, meantngfol kind & equal treatment to all workers.
12) Stability : - stable & secure work force is an asset to the enterprise.
“ An avg employee who stays with concern is much better than outstanding emplyee who
merely come & go”.
13) Intiative - should be allowed since it brings self confidence in workers.
14) “Espirit de corps”.
Functions of mgt :
1) Planning
2) Organizing
3) Staffing - maching the jobs with individual
4) Directing
Direction has threee essential components
a) issuing of instruction & orders b) Guiding the people, &
c) Supervising the people.
5) Direction involves following four functions
1) leadership 2) Communication 3) motivation 4) supervision
6) Co-ordinating
7) Countrolling
a) establishing standards b) Appraising performance
c) Taking corrective actions
Scienctific Management :
- FW Taylor is known as father of scientific mgt who has introduced a rational & systematic ap
proach to management
- The primary emphasis of scientific managementwas on planning standardisng and improving human
efforts at the operation level so as to maximise output with minimum input, By doing this earrings of
employees & employees have been incresed
- When entered the industry taylor found following (1850-1915)
1) mgt not aware of scientific techiques of work .
2) Much of waste & in efficiency is due ot lack of orders & system in the methods of mgt.
3) Management anaweer of amount of work to be expected from average work
100
90
80
70
% of total 60
inventory 50
cost 40
30
20
10
A B C
10 30 100
% of items
- Thus, ABC analysis separates items from one another & tells flow much valued the item is and to
what extent controlling is needed in the interset of organization
- But, all categories of control are based an two principles only,
1) To keep high cost inventories as low as practicable, &
2) To ensure that all the material are available when needed
Control policies for A items
Causes of an accident
1) technical causes -usafe conditions mechanical factors
2) Human causes (usafe acts) - presonal
3) Management factors
1) Technical causes
Mechabucak factors:
It indicates usafe conditions, diffeciancies in plant, equipment, tools material handing syotm, etc .
These are listed below
1) unsafe mechanical design or construction
2) Heandous arrangement (pilling, over loading etc)
3) Improper machine gurding
4) Defective devices
5) Improper material handling
6) Broken safety guards
7) Protrding vails
Protective equipments :
- Protective equipment reduces the accident hazardous to great extent
- These includes the following,
a) Helment b) Gum boots c) gloves d) Goggles
e) Apron f) safty sovelles g) portable lightlamp h) fire extinguisher
i) Gas mask k) oxygen apparatas l ) face mask m) ear protector, etc
Safty lacunae in India constrution industry :
Safety measures for storage & handling of building materials:
- All building materials should be stored in such a manner so as to prevent their deteration or intrusion
of foreign matter and to ensure the preservation of their quality & fitness of use.
- Storage of materials on site depends upon their individual characteristics
Depreciation :
- Depreciationn is defined as loss in value of asset with passage of time.
- This loss must be known during the life of asset with a reasonable amount of profit on it.
- Depreciation is used to determine the recoverywhich cab be due capital cost from a property under
n m 1
Dm (Ci Cs )
n (n 1)
2
n - life
m - year mth
Example :
The initial lost of an equipment is Rs. 11,00 salvage value is Rs. 100. life of equipment is 5 years.
The rate of interest for sinking fand is 8 % Calculate the yearly depreciation & book value at the
end of each years by all methods Present the value to tabular form & graphically.
Straight line method
Ci Cs
D1 D 2 D3 D 4 D5
n
1100 100
200
5
B1 = 1100 - 200 = 900
B2 = 900 - 200 = 700
B3 = 700 - 200 = 500
B4 = 500 - 200 = 300
B5 = 300 - 200 = 100
Decling balance method :
Cs C1 (1- FDB) n
1/n
C
FDB 1 s
Ci
100
1 1 / 5 0.381
1100
419.1
B1 C1 D1 1100 419.1
B1 680.9
B2 396
B4 142.56
D1 D 170
B1 930
B2 746.4
B3 548.112
B4 333.962
B5 102.682
======================================================================