Method Statement: Fabrication of Rebar Cages in Caisson

You might also like

You are on page 1of 3

METHOD STATEMENT

FABRICATION OF REBAR CAGES IN


CAISSON

MAJU STRUCKTUR SDN. BHD.


Maju Strucktur Sdn Bhd
Project Hand Dug Caisson
Method Statement – Fabrication Of Rebar Cage In
Title: Caisson
n

1.0 Introduction
Method of fabricate rebar cage in caisson to be adopted when the conventional method
of rebar cage place in cannot be used. (fabricate rebar cage outside and lifted into the
caisson hole by service crane). This could be happened to the congested area, heavy
traffic or on the hill where is inaccessible by the service crane.

2.0 Manpower
Site personnel who involved in this work are:

a) Site Supervisor
b) Generator
c) Barbender
d) Authorized gas tester (A.G.T)
e) Entry Supervisor (E.S)

3.0 Machineries
a) Air Compressor.
b) Generator Set.
c) Electrical Chain Hoist.
d) Bar Cutting and Bending Machine
e) Temporary Hoisting Frame.
f) Ventilator Fan
g) Crane Lifted Work Platform
h) Gas Detector Machine

4.0 Sequence of Work


a) Cutting steel bar to request size and bending spiral link as per construction drawing.
b) Using lifting frame to lift down 1st layer spiral link and rebar into caisson.
c) Start tie 1st layer spiral link with rebar.
d) Install scaffolding to continue tie to higher level.
e) Drilling hanging bar (Normally T20) for hanging second layer spiral link.
f) Lifting down second layer main bar by mobile crane.
g) Start tie 2nd layer rebar with spiral link.
h) Install scaffold up to 3rd layer high.
i) Drilling higher level (3rd layer) hanging bar for hanging 3rd layer spiral link.
j) Lifting down 3rd layer main bar (Internal).
k) Fabricate spiral link with internal main bar.
l) Lastly fabricate external main bar and spiral link.
m) Submit RFWI to consultant for inspection.
n) Dismantle lifting frame and ready for concreting.

MAJU STRUCKTUR SDN. BHD.


Maju Strucktur Sdn Bhd
Project Hand Dug Caisson
Method Statement – Fabrication Of Rebar Cage In
Title: Caisson
n

5.0 SAFETY PRECAUTIONS AND MEASURES


Caisson excavation work involves a high degree of risk due to the unexpected underground
conditions such as gasses, erosion of soil, failing objects and careless acts of workers.
Therefore, works must always be carried out with great caution and with sufficient safety
equipment, to ensure full proof ventilation system with standby equipment provision.

a) Caisson work platform protection :

 The work platform must be erected with full design, complete tools and
supervise by PIC

 Construct 600mm high toe boards or timber around the work platform to
prevent debris or equipment and workers from falling during the fabrication
rebar cage.

b) Workers Safety :

 All caissons workers must see safely helmet, safety belt whistle, body harness,
working shoes, dust mask and proper clothing.

 Workers inside the caisson hole must be attended with hoist controller on top
and shall be alert at all times
.
 Smoking is prohibited inside all caissons.

 Workers must attach safety harness to mancage when going up or down


caisson and must be careful when ascending or descending equipment..

 Adequate lighting and fresh air must be provided at all times to workers inside
the caisson hole.

c) Equipment, tools and machineries :

 All equipment and tools must be inspected regularly and properly maintained
by the workers and supervisors.

 All hoists shall be checked regularly and service from time to time.

 Inspected safety system to be verified safe by safety personnel.

d) Hazard Identification, Risk Assessment and Determining Control (HIRADC) :


 Refer to Appendix 1 for HIRADC

MAJU STRUCKTUR SDN. BHD.

You might also like