You are on page 1of 1

Critical Lifting Operation Plan

Current Colour Code

Facility PSK
Work Location CPF
Permit to Work Number

Lift Category Non Routine - Critical


Weight of load 1t Actual or Estimated Estimated
Crane Type and Capacity 25T Crane Registration DNO Approved

Description of Task Including the Load

UTILIZING 25T CRANE TO LIFT PIPES OVER THE SEPARATOR OUTLET LINES TO CONNECT TO SEPARATOR DUMPLINES

Lifting Equipment to be use (Size of Chains, Slings, Shackles include rigging configuration and WLL for each lift)

1 x 25T MOBILE CRANE


Radius:16m
Boom Length: 24m
Crane capacity: 2.65T SWL
2 X 2T SWL x 6tmtr WEBBING SLINGS(minimum)
1 x Taglines

Hazard Analysis On Site Pre-Lift Checklist


Yes/No Yes/No
Are there any Cultural or Communication Difficulties Identified Yes Tool Box Talk Complete Lifting Operation Explained to Team
Conflicting Tasks SIMOPS Power lines Excavations in Area No Pre-Start Inspection of Crane and Checklist Complete
Has the Centre of Gravity of the Load Been Assessed Yes Lifting Equipment/Accessories Inspected
Will the Load or Crane Pass Over Live Equipment No Lifting and Landing Areas Inspected
Are there Approved Lifting Points on Load Yes Check Environmental conditions and Wind Speed
Is the Crane Operator Certified Yes Ensure Timber dunnage or Pads are Under Outriggers
Is the Banksman Slinger Certified No Inspect Load for Dropped Objects
Method of slinging/attaching/detaching the load assessed Yes Check for Adequate Tail Swing of Crane
Is Working Under a Suspended Load Required No Barricades and Information Tags in Place
Will the Operator Have Full Visibility of the Load Yes Will Taglines be Used to Control the Load
Lifting Operation Sequence (Step by step)
1. All persons involved in the lifting operation to attend the TBT and go through the step by step details of the lift plan.
2. Barricade off the work area.
3. Rigger/Banksman to inspect all the lifting gear as mentioned above.
4. Crane operator to complete daily inspection checklist on the crane before lifting operations.
6. Crane operator to set required boom length on initial set up of the crane.
7. Crane operator to carry out dry run from pick up point over to the end completion point of the lifting operation with no load.Set boom lenght and radius.
8. Crane operator check outrigger pads for ground movement. (stability)
8. Rigger/Banksman to attach lifting sling set to the cranes aux hook.
10. Rigger/ Banksman to instruct crane operator using hand signals to slowly take the known weight of the load inching slowly up on hook.
11. When crane operator has full weight of the load signal to crane operator to stop hooking up and Rigger/Banksman then checks for dropped objects and balance of the
secure load.
12. Once load is fully secured attach 1 taglines to the lift for control/orient the load.
13. Rigger/Banksman at end point of the lift to give clear hand signals to crane operator and lift load as mentioned.
14. Repeat steps above until all loads into position
15. On completion of the lifting operation Rigger/Banksman to derig lifting gear and carry out a post -use inspection of the lifting accessories pack up crane and demobilize
utilizing a flagman.
16. Ensure the lifting site is clear and tidy then carry out debrief and learning outcomes with team.

Note: Ensure crane operator does not exceed 90% of the crane load charts SW
Any change to the lifting plan must be reviewed, agreed, and communicated to the work party involved in the operation.

Communication Methods to be used

Radio Verbal Hand Signals

Yes Yes

Lift Plan Prepared By

Name Saman Date 19-10-2022 Signed Saman

Approved By Rigging and lifting Advisor

Name Jiyar Adam Date 19-10-2022 Signed

Authorized By Field manager or Site Controller when lifting over Live Lines

Name Date Signed

You might also like