Professional Documents
Culture Documents
This lift plan is specific to the lifting operations described in the scope of works.
Company Name Facility/ Project title
Location Contract No.
Date of lifting operation From / / To / / Specific / /
Lift Plan Reference Number of Lifts to be
Number done
Routine Non-Routine- Non-Routine- Non-Routine-
Lift Plan Category
Simple Complicated Complex
Associated Permit
Number
Task Risk Assessment
Number
Method Statement
Number
Required Number of Appointed Lifting Crane
# Rigger #
Personnel to attend the Person Supervisor Operator
Lifting Operation and
their designation Banksman # Helper # Safety Rep. Third Party
Lift Planning Engineer (Appointed Person) preparing
this plan.
Date / / Signature
Single Point Authority
Signature
Name
Purpose
The purpose of the lifting plan is to identify the control measures necessary to negate the primary
hazards of:-
The crane collapsing or falling over
The load falling from the crane
The load or machine striking someone or any other identified hazard
Scope of Works
Sequence of Operation
Note: List the Sequence of Operation in a way to do the task safely e.g. (Crane comes first or Trailer, Lift Load # 2 before Load # 1
…etc.).
Contingency Plan
Note1: Basically it is Plan B should things changed i.e. (Crane 1 break-down and Crane 2 can be used with some changes in the
Plan). Note2: Emergency Response Team availability at site or nearest Hospital / Clinic …etc.
Drawings / Sketches
Note1: Scaled Drawings shal be available in Non-Routine Complex / Critical Lifts showing Plan / Elevation of Load and Crane Initial
and Final Position including Stages.
Note2: Sketches shall be available in Non-Routine-Simple and Non-Routine-Complicated Lifts.
Details of crane provider (if rented)
Company name
Address
Contact name Telephone/ radio
Details of Crane operators
Load Details
Net Weight of Load Gross Weight of Load
Dimension of Load Load COG Location
Reference shall be made to Lifting Data Tables which are required for all Lifts Categories (Refer to
Appendix W Offshore Crane) and Appendix X Onshore Cranes)
Other Details (centre of Gravity, Lifting points, Packaging, Palette
Details of Crane
Manufacturer’s Name Model # Crane Type
Required Crane
Max. Crane’s Capacity ID/No. / Plate # Capacity
Note: Reference shall be made to Lifting Data Tables which are required for all Lifts Categories (Refer to
Appendix W Offshore Crane) and Appendix X Onshore Cranes).
Hazard Control
Ground conditions must be suitable and sufficient and remain so during crane lifts to take the anticipated loads.
Include details of the ground conditions and any additional works required to the ground, including spreader mats
specification and any testing regime required (for example, CBR tests).
A temporary works design must be in place and checked off before any lifting operation or crane set-up takes
place.
Weather/environmental considerations
Indicate in this section detail of wind speeds/Sea state/ environmental conditions that have been
referenced/anticipated for the duration of the lifting operations and conditions that lifting operations must stop.
Access
Include travelling routes, road closures/highways notifications, and access problems.
Emergency/breakdown procedures
Signaling
Indicate whether hand signals or radios are to be used. Also indicate signalling source and radio
frequency/channel. This section can also include any unique slinger/signaller identification (that is, different
colour helmet/hi-vis) if required.
Include crane position, lay-down/rigging area, position of delivery vehicles, landing points, banksman positions,
ground and overhead hazards and exclusion zones. If required use elevation drawings.
Complex Lift Plan File Note shall be available following Asset Integrity Lifting Engineer (Lifting Technical
Authority) or Site SPA (Single Point Authority) Approval prior to commence the actual Lifting Operation
(Refer to Appendix V).
Site/project manager
Appointed Person
Crane operator
Slinger/signaller
In the event of any changes to circumstances, personnel or equipment, the plan should be reviewed and
revised by the Lift Planning Engineer (appointed person) and any changes recommunicated to the lift team.
Notes:
a. Routine lifts: Load Net Weight less than or equal to 80% SWL normal operating parameters of the lifting
equipment, permanently installed lifting equipment, certified lifting point or points, ample headroom to
complete lifting operations, not lifting over live plant or occupied areas or people, not lifting over or in close
proximity (less than 3 m) to active or energized hydrocarbon process or pressurized utilities process
equipment, load has known and uniformly distributed weight, uniform shape, identified Center of Gravity and
packaging robust, Center of Gravity below lifting points, lifts with pre-slung arrangement and/or not using
specialist lifting accessories, suitable lay down are is available, not lifting persons, single lifting appliance.
b. Non-Routine SIMPLE: Load Net Weight less than or equal to 80% SWL normal operating parameters of the
lifting equipment, temporary installed lifting equipment, certified lifting point or points, limited headroom to
complete lifting operations, not lifting over or in close proximity (less than 3m) to active or energized
hydrocarbon process or pressurized utilities process equipment, load has known and uniformly distributed
weight, uniform shape, identified Center of Gravity and packaging robust, center of gravity below the lifting
points, lifts without pre-slung arrangement, using specialist lifting accessories, attachments or slinging
methods (Non-standard rigging arrangements), suitable lay down area available, single lifting appliance, not
lifting persons, using proprietary lifting accessories or attachments for vehicle loading and unloading,
skidding operation using Skates & Ground Trolleys and cross-hauled the load or restrained using two or more
non powered lifting appliance with 100% redundancy.
c. Non-Routine COMPLICATED: Load Net Weight “without any Factor of Safety” more than 80% SWL but less
than 90% SWL with exception of Overload Testing of Fixed and Mobile Lifting Appliances, temporary installed
lifting equipment, non-certified lifting point or points, limited headroom to complete lifting operations, Lifting
in close proximity (less than 3m) to active or energized hydrocarbon process or pressurized utilities process
equipment but not over life plant / line, load is unknown or not uniformly distributed weight, or not uniform
shape, or difficult to identify Center of Gravity and not robust packaging, Center of Gravity above lifting
points, Use of special lifting accessories, attachments or slinging methods (Non-standard rigging
arrangements), unsuitable or unavailable laydown area, use of 2 or more lifting appliances including tailing
pipe using winch and crane, lifting persons by crane including drill floor Man-Riding winch operations, load
lowered into or lifted from a confined space, if wind load is calculated with applicable Crane wind speed
limitation deduction as per OEM, lifting & transferring loads from one offshore vessel to another and Overload
testing,
d. Non-Routine COMPLEX / CRITICAL: Recovery of a failed lifting operation, Load Net Weight “without any
Factor of Safety”=>90% of SWL; however Dynamic Lift Load which is compared to Load Chart shall not
exceed 100% SWL considering all applicable Factors of Safety, temporary installed lifting equipment, non-
certified lifting point or points, limited headroom to complete lifting operations, lifting over active or
energized hydrocarbon or pressurized utilities process equipment, load is unknown or not uniformly
distributed weight, or not uniform shape, or difficult to identify Center of Gravity and not robust packaging,
Center of Gravity above lifting points, large loads (surface area / volume) requiring specialist lifting and
slinging requirements, tandem lift with 2 cranes or more, dangerous goods cargo lifting such as explosives,
propane tanks etc., load is special and / or expensive the loss of which would have a serious impact on
production operations, snatching a load from untied vessel for non-DPII Vessel, transferring the load from
one lifting appliance to another, lifting with a helicopter and subsea lifting (All the load to be submerged in
the water regardless of Crane's hook block).
ADNOC Classification: Internal
Pick-up
Revolving
Drop-off
Copyright © 2021 Abu Dhabi Company for Offshore Petroleum Operations Ltd– ADNOC Offshore. All rights reserved
All parties consent to this document being signed electronically -TID/INT/2021/4938
ADNOC Classification: Internal
Hook-1
Crane Utilization Ratio
Position Radius Crane capacity
(DLL X 100) / Crane Capacity
Pick up
Revolving
Drop off
Hook-2
Pick up
Revolving
Drop off
Copyright © 2021 Abu Dhabi Company for Offshore Petroleum Operations Ltd– ADNOC Offshore. All rights reserved
All parties consent to this document being signed electronically -TID/INT/2021/4938
ADNOC Classification: Internal
RIGGING DETAILS
Item-5
Items-6
Items-7
Copyright © 2021 Abu Dhabi Company for Offshore Petroleum Operations Ltd– ADNOC Offshore. All rights reserved
All parties consent to this document being signed electronically -TID/INT/2021/4938
ADNOC Classification: Internal
Pick-up
Revolving
Drop-off
Copyright © 2021 Abu Dhabi Company for Offshore Petroleum Operations Ltd– ADNOC Offshore. All rights reserved
All parties consent to this document being signed electronically -TID/INT/2021/4938
ADNOC Classification: Internal
Tilt 3%
Yaw 5%
COG shift
5%
Hook-1
Crane Utilization Ratio
Position Radius Crane capacity
(DLL X 100) / Crane Capacity
Pick up
Revolving
Drop off
Hook-2
Pick up
Revolving
Drop off
Copyright © 2021 Abu Dhabi Company for Offshore Petroleum Operations Ltd– ADNOC Offshore. All rights reserved
All parties consent to this document being signed electronically -TID/INT/2021/4938
ADNOC Classification: Internal
RIGGING DETAILS
Rigging Utilization
Leg Tension
Ratio
Description Rigging SWL* (As per Lift Remarks
(Leg Tension X 100) /
Analysis)
SWL
* The following
Shackle factors to be
Sling considered for SWL
Spreader beam of each item
Item-1
Pad eye
Pad ear Mode Factor
Trunnion D/d Ration
Choker Hitch
Basket Hitch
Shackle
Sling
Spreader beam
Item-2
Pad eye
Pad ear
Trunnion
Shackle
Sling
Spreader beam
Items-3
Pad eye
Pad ear
Trunnion
Copyright © 2021 Abu Dhabi Company for Offshore Petroleum Operations Ltd– ADNOC Offshore. All rights reserved
All parties consent to this document being signed electronically -TID/INT/2021/4938
ADNOC Classification: Internal
LOAD DETAILS – Static Lifting (Overhead Crane or Monorail with Single Hook)
Item Net weight Contingency Factor Gross Weight Hook Block Rigging weight Crane or Hoist
(10% for calculated (Net weight X Weight (Sling, Shackle “Monorail”
Crane or Hoist
3% for weighed) Contingency Spreader bar) Static Hook Utilization Ratio
“Monorail”
Factor) Load (SHL) (SHL X 100) / Crane
capacity
or Hoist “Monorail”
Capacity
Static Hook Load = Gross Weight + Hook Block Weight (If applicable) + Rigging Weight
RIGGING DETAILS
Copyright © 2021 Abu Dhabi Company for Offshore Petroleum Operations Ltd– ADNOC Offshore. All rights reserved
All parties consent to this document being signed electronically -TID/INT/2021/4938
Issue Date: March-2021 Page 16 of 543
Copyright © 2021 Abu Dhabi Company for Offshore Petroleum Operations Ltd– ADNOC Offshore. All rights reserved
All parties consent to this document being signed electronically -TID/INT/2021/4938