Lifting Operations Plan PAGE: 1

No: NLNG-LP- 017


LIFT PLAN
LOCATION: OFF PLANT AREA: IA AMENITIES BUIDING SITE

PERMIT TO WORK No.: 402505 JSR/RISK ASSESSMENT No. JHA 402506

GENERIC LIFTING PLAN No.: B.54.151 Rev B METHOD STATEMENT No.:

DIAGRAM/SKETCH OF OPERATION ATTACHED? YES ACTUAL WEIGHT OF LOAD: 1.95 TONS

DESCRIPTION & CLASSIFICATION OF LIFTING OPERATION: ROUTINE /SIMPLE- COMPLICATED- COMPLEX/CRITICAL- HEAVY LIFT–

Reference
(1) PMS 2 JHA-23 (2) LOLER (3) NIOSH (4) PRD.15.05.255 (5) 15.05.255.05 (6) PRD.15.05.255.20.
CONFIRMATION THAT CLASSIFICATION OF LIFT HAS BEEN DETERMINED BY FOLLOWING LOLER GUIDANCE FLOWCHART: Y

LIFTING EQUIPMENT & ACCESSORIES TO BE USED (SPECIFIES TYPE, SWL & COLOUR CODE) _80 Tons mobile Crane, webbing sling,
all in white colour code____________________________

ALL LIFTING OPERATIONS REQUIRE THE FOLLOWING TO BE CONSIDERED BUT THIS LIST IS NOT EXHAUSTIVE

Pre-use equipment checks by operator Working under suspended loads


Weight, size, shape and centre of gravity of load Conflicting tasks in area/adjacent worksites
Overturning /load integrity/need for tag lines Proximity hazards, obstructions, path of load, lay down area
Method of slinging/ attaching/detaching the load Experience, competence and training of personnel
Availability of approved lifting points on load Number of personnel required for task
Availability of certified lifting points Responsibilities clearly defined e.g. slingers/banks-man
Environmental conditions including weather Communication requirements
Max radius of hoisting the load Mobile crane load chart/LMI available and in use
Have you the experience to lift such weight of load Hoisting over live equipment facility
Is there a suitable space for crane set-up
Have the lifting operation been performed before visibility of lift (blind lift
This Lifting Plan has been formulated to ensure that the scope of work to be carried out is undertaken by competent
personnel in a safe manner and in accordance with BS-7121 Mobile Crane best practice & Lifting Equipment Regulations
1998 (LOLER) satisfying the health and safety requirements in meeting the requirement of NLNG BONNY Site complex:
CONTRACTORS ERDIS/POINT ENGINEERING
NAME:
TASK TITLE: Lifting and installation roof trusses TASK LOCATION: NLNG IA REQUESTOR No:
amenities
site
EQUIPMENT TAG: N/A UNIT: N/A OPERATION No:
BRIEF DESCRIPTION OF LIFTING & HOISTING OPERATION:
Scope of work:

Lifting, offloading, supporting and installation of roof trusses at IA Amenities building site using 80 ton mobile crane

Method(s) of communication to be used Radio Yes Verbal Hand Signals Yes

Steps taken to eliminate danger to personnel involved and others, including barriers where appropriate.

ORIGINATED BY LIFTING
NAME: Benjamin Hart Signature: Date: 30/07/2021
ENGINEER:
REVIEWED BY CONTRACTOR
NAME: Eno George Akpanama Signature: Date: 04/08/2021
LIFTING FOCAL:
APPROVED BY NLNG LIFTING
NAME: Signature: Date:
(SME) FOCAL:
APPROVED NLNG BY PROJECT
NAME: Signature: Date:
FOCAL:

Document No: NLNG/NO-000000 Revision No: 3 Document Life Cycle: 3 Years

LIFTING PROCESS Page 1


METHOD STATEMENT (STEP BY STEP):
 TBT-meeting (PTW) (JHA) (LMRA) discussion with crew:
 All lifting accessories, pad eye, lifting point, lugs (where available)to be visually checked prior to use:
 Only current color coded/certified lifting equipment with SWL shall be use:
 Ensure lifting crew understand the nature of task and has the ability to carry out such task in a safe manner prior to
job commencement:
 The Crane must be setup within specified work location to ensure task is carried out safely: see rigging sketch below
 The lift supervisor to ensure the crane check list is ticked and completed by the crane operator prior to use of
equipment:
 Crane operator setting up the Crane with outriggers fully extended and ensure leveled ground maintaining the
center of gravity on the center of the load.
 The crane must be positioned closed to the load as per the radius of crane load chart to avoid overloading of the
crane when lifting.
 The load weight is about 1.95 Tons to allow mobile crane radius of 15m which allow safe lifting of 8.6 Tons.
 The riggers then attached the rigging gears to the roof structure to be lifted using choker hitch method and other
side to the crane hook and also confirm its secured and balance. A tag line shall be attached to the roof
structure before lifting.
 The banksman shall then inform the crane operator to lift the load slowly telescoping to the installation point and
suspend the load till the installation is completed before the rigging gears can be detached from the load.

 Only the designated banksman in a reflective vest is permitted to signal the operator except in emergency.
 The operation shall be closely supervised by the lifting supervisor / person in-charge lifting operation.
 No personnel are allowed to work under suspended load.

THE LIFT SUPERVISOR: If for any reason the lift cannot be conducted as per the method statement, then all lifting to be safely PAUSE / STOP
to review the PTW or appointed person to be consulted:

Checklist of inclusion in plan and document attachments (tick relevant):


Crane layout Plan Categorization /Flow Chart GBP Source/Calculation
Rigging hook up attachment JHA/Risk Assessment Project Scope
Crane Chart Extract Method Statement/Work pack Load Weight/CG Source Info
Foundation Details/Calculation Wind weather Forecast Crane and Load Clearance
Crane Cribbing Arrangement Load Schematic Others
BRIEF INFORMATION OF THE LOAD:

Description Available Lifting Load Dimension (m)=L”W” Centre of Gravity


Point:
Steel Trusses No 5 m x 0.1m known
LOAD WEIGHT CALCULATION ( including weight contingency + any factors such as DAF) Note: Utilization >75%
=Non Routine complex :
Load wt. (t) Rigging wt. Hook Block wt. Weight Total load wt. (t) Maximum utilization (crane capacity
(t) (t) contingency usage) % (TOTAL LOAD SWL)
1.95 0.2 0.75 0.3 3.2 35
LIFTING EQUIPMENT & ACCESSORIES TO BE USED **** (SPECIFY TYPE WITH S.W.L) CURRENT COLOUR CODE:
Lifting Appliances (crane information):
Model /Serial Crane Length Crane Width Inspection Mobile crane S.W.L (t) W.L.L (t) Max capacity
No: (m) (m) date: self wt. (t) (t/m)
TEX707076 16.74 3.2 18/08/2020 47.75 43 80 80
Onshore Data:
Maximal acceptable wave N/A Maximal acceptable wind N/A
height (Hs) speed (Knot)

Hoisting Rope information: Other lifting Equipment/Accessories:


Manufacturer: Serial No: Wire Rating Inspection date: Number Falls Used Block—S.W.L
Capacity:
N/A 707076 5.46 T 18/08/2020 8 80

LIFTING PROCESS Page 2


Mobile crane set-up info:
Mobile Crane Boom Max Operating Installation Total counter Boom Angle Size of Crane Rated Capacity
Type and Model Length Radius (m): Radius (m): weight used (deg): Mat: (m) at Max Radius
(m): (t): (m):
QUAD STAR 24.70 15.0 8.0 8.90 78.0 1 x 1 x 0,1 8.95
1075L
Ground Stability:

Slings Specifications:
Sling Type Identification Safe Working Sling Length: Diameter (mm): Sling Quantity: Sling Weight:
Number: Load (t):
Webbing sling 005, 003, 3.0 3m 150 mm 4 0.1
23245, 4521

Shackle Specifications:
Shackle Type Identification Number: Safe Working Shackle Weight : Shackle Diameter (mm):
Load (t) Quantity :
Safety pin bow 001, 002, 003, 004 3.5 tons 0.1 4
shackle

Eye-Bolt Size:
Size Safe Working Load Outside Eye Outside Eye Quantity: Weight:
N/A (t) Diameter Diameter

Lifting Beam:
Type: Identification Safe Working Load length: (m) Quantity: Weight:
Number: (t)
N/A

THE LIFT SUPERVISOR: If for any reason the lift cannot be conducted as per the method statement, then all lifting to be safely PAUSE / STOP
to review the PTW or appointed person to be consulted:

Crane Capacity Analysis:


Hoist Place
Total Load to crane 3.2 T
Planned Radius 15 m
Chart Radius 15 m
Chart Capacity 8.95 T
% of chart capacity 35
MAXIMUM CRANE CAPACITY PLANNED TO BE USED IS:
Any Other Accessories Required:

None

Toolbox Talk Topic: See permit to work


Date:
Presented By:
Position:

LIFTING PROCESS Page 3


LEARNING FROM THIS L&H ACTIVITY (Incl. Management of Change details if applicable) – ATTACH ADDITIONAL PAGES IF REQUIRED

PIC
CRANE OPERATOR BANKSMAN RIGGER/SLINGER/LOAD HANDLER

Eno George Akpanama Innocent Oba Benjamin Hart Kurubo J.


George Onimim
LIFTING CATEGROIZATION FORM FOR RIGGING AND LIFTING OPERATION
The object of the risk assessment is to identify and PART 2 – SIMPLE LIFT
eliminate or reduce to an acceptable level, any hazards in BASIC QUESTIONS YES NO
the lifting operations. It should also determine the level of 1 Is the lifting operation to be undertaken ✓
difficulty of the task and the skill level of the personnel by a single lifting appliance?
required to perform that particular activity safely. This 2 Do you know the weight of the load and ✓
document will also highlight any need for further training does the lifting operations appear to be
straight forward?
Description of Lift ☒ Routine, ☐ Simple, ☐ Complex 3 If the load is heavier than you normally ✓
Location of lift IA Amenities building site handle, do you have the relevant
Personnel involved Eno George, Innocent Oba, Benjamin permission and /or permit to operate
Hart, George o., Kurubo J. the lift equipment to be used?
Proposed date of Lift TBA
4 Is there a crane or certified support ✓
ASSESSMENT steelwork (e.g. Runway beam or lifting
PART – 1 – ROUTINE LIFTS eye) directly above the load?
BASIC QUESTIONS Y NO 5 Does the load have certified lifting ✓
E points (lifting eye/ collars eyepoint, etc.)
S fitted and if not, can sling be wrapped
1 Has the lifting operation been performed? ✓ around easily? (e.g. no sharp edges, load
not fragile etc.).
2 Is there a document, lifting plan, and lifting ✓
operation risk assessment in place and on 6 Is there ample headroom for the lifting ✓
site? appliance and sling?
3 Are you experienced with the lifting

7 Is the lift stable (e.g. centre of gravity ✓
equipment to be used? below lifting points)?
8 Is the lift balanced (e.g. centre of gravity ✓
4 Has the load been checked and made ready
✓ in the middle) of fitted with special
for lifting (e.g. load fastening released, hold
down belt removed)? slings to compensate?
5 Have you the experience to lift a load of this

9 Is the load free to be lifted (e.g. load ✓
weight? fastening released, all hold down bolts
removed, not jammed, etc)?.
6 Is the lift in an area free of obstructions and

other possible hazards? 10 Is the removal route suitably controlled/

cordoned off and clear of any
7 Can the lifting operations be carried out
✓ obstruction?
without the use of set of soft eye flat
webbing slings? 11 Is the removal ((lift transfer and landing)

If the answer to any of the above is “NO”, proceed with be performed without cross-hauling
PART 2 of this assessment 12 Is there a suitable lay down area and

If the answer to all seven questions above is “YES” does the load come within the allowable
proceed with the lifting operations in accordance with load bearing capacity of the ground/
the lifting plan, 10 questions for Safe Lift and JHA deck?
13 Are you experienced in using all the

lifting equipment and gears involved?
14 Can the lifting operations be carried out

Part 1 Assessed by 04/08/21 without the use of soft eye flat webbing
Date
Eno George slings
If the answer to any of the above is “NO”, proceed with
PART 3 of this assessment
If you can answer “YES” to all the above questions,
proceed with the lifting as per requirements for simple
lift

Note 1
To supervisors: If you can give solutions to the above negatives
to allow the lift to proceed safely, write the instruction in the

LIFTING PROCESS Page 4


box below and if you cannot supply a solution, seek guidance
from the appropriate competent person(s)

SOLUTION TO OVERCOME THE ABOVE PROBLEMS

Part 2 Assessed by 04/08/20


Date
ENO GEORGE A. 21

THE LIFT SUPERVISOR: If for any reason the lift cannot be conducted as per the method statement, then all lifting to be safely PAUSE / STOP
to review the PTW or appointed person to be consulted:
Mobile Crane Working Load Chart:

LIFTING PROCESS Page 5


kindly attach a sketch showing
clearly
1. The shape of the trusses
2. identified lift points
3. sling attachment method
4. identified CoG
5. included angle formed.
9 Receiving of container at laydown area. Forklift Opt
10 Unslinging of rigging gears from container. Rigger 2/3/4
11 Container movement from drop off point to Installation point Forklift Opt
12 Lifting of and installation Crane Opt
13 Good House keeping. Rigger
LIFTING & RIGGING PRE JOB CHECKLIST
S/ FOCUS YES NO
N
1 Is there an approved Lift Plan for the job and does the team understand the job and precautions? Note: x
The planning of individual routine lifting operations may be the responsibility of those who carry them out
(e.g. a rigger or crane operator)
2 Is everyone in the team aware of and do they fully understand the NLNG lifting procedure? x
3 Does everyone in the team know the person in charge of the lift? x
4 Is the capacity of the lifting appliances (cranes, beams etc.) sufficient for the load? x
5 Are the lifting appliances and lifting accessories certified for use and with current colour code/inspection x
sticker?
6 Are lifting accessories tagged with SWL and unique ID numbers? x
7 Are all the lifting accessories checked for damages before commencing the job? x
8 Are all the brakes of the lifting appliance working and effective? x
9 Are all limit switches on the lifting appliance working and effective? x
1 Are the emergency stop buttons on the lifting appliances working? x
0
1 Is everyone in the team competent and aware of his /her task? x
1
1 Does everyone in the team know the environmental limits e.g. maximum permissible wind speed for the x
2 lift?
1 Is the lift area controlled and is everyone clear if the load falls or swings? x
3
1 Are signalling methods and communication agreed and clear to all? x
4
If you answer no to any of the above questions, do not proceed, contact the rigging supervisor.
BANKSMAN……………………………………….
SIGNATURE………………………………………. DATE…………………………….
THIS PAGE MUST BE SIGNED OFF ON SITE PRIOR TO JOB COMMENCEMENT BY THE LIFT SUPERVISOR AND RETURN SIGNED
COPY AT COMPLETION OF TASK TO THE (AP):
Signature: Date:
SUPERVISOR NAME:

TEAM LEAD /BANKSMAN NAME: Signature: Date:

CRANE OPERATOR: Signature: Date:

Signature: Date:
TEAM MEMBER:

TEAM MEMBER: Signature: Date:

HDV-DRIVER: Signature: Date:

AREA SITE REP NAME: Signature: Date:

LIFTING PROCESS Page 9


Z

LIFTING PROCESS Page 10


LIFTING PROCESS Page 11
LIFTING PROCESS Page 12
kindly provide evidence of the
trainer (EGASCON)
accreditation with LEEA and
IADC as reference below

LIFTING PROCESS Page 15


kindly provide evidence of the trainer
(EGASCON) accreditation with LEEA and
IADC as reference below
kindly provide evidence of the trainer
(EGASCON) accreditation with LEEA
and IADC as reference below
LIFTING PROCESS Page 16