You are on page 1of 4

Lifting plan

LIFTING APPOINTED PERSON / SUPERVISOR SITE INSPECTION


Appointed Person/Lifting Supervisor:
Employed by: Date and Time :

Standard Lift √ Contract Lift Complex Lift

Single Crane Position √ Complete Part 1 only Multiple Crane Positions Complete Parts 1 & 2
Description of Works:
Assembly of tower crane jib

LOAD DETAILS
Max. Weight: 11.92 Ton for assembled jib section Max. Size of Load: 56.8x1.6x1.6 meter
Max. Radius: 8 meter Max. Lift Height: 42 meter
Shape of the Load: Wooden/Steel boxes– Rectangular Shape Others e.g. Unusual Centre of Gravity, Lifting Points etc. Yes

CRANE / BOOM TRUCK DETAILS


Capacity and Type: Mobile Crane 160 ton liebherr LTM1160/2
Max. Available Boom Length: 60 meter Max. Boom Length to Be Used For Lift: 56.3 meter
Counterweight Req: 50 ton Hook Block Reeving (No. of Falls): 4
Outrigger Spread (Centre to Centre): 8.5 meter Outrigger Pad Size (without mats):
Max. Outrigger Load:

SITE SURFACE CONDITIONS


Access for Crane: Clear Access for Transport: Good
Lifting Position: Parallel to the load / 360° Laydown Area: Compacted Soil
Ground Condition: Compacted Soil Assessed by:

LIFTING ACCESSORIES REQUIRED (State type and safe working load)


Wire ropes : N/A Chains : SWL 32 ton
Web Slings : SWL 6 ton/10 meters/2 Nos Shackles : SWL 5 ton/2 Nos
Beams : N/A Outrigger Crabbing (state size) : 0.9 Sq.M
Others (including specialist equipment) :
Operational Requirements e.g. road closures/possessions/site clearance : Road closure / Site Clearance
Details of Crane Company
Company Name: AL-RAWDA Equipment Rental Company
Address: SADAT City
Contact Name: Mr. Mohammed Ramzy Tel:
Appointed Person / Lifting Supervisor: Mr. Ibrahim Ragab Sign: Date:
Site Chief / Site Engineer: Sign: Date:
Confirmation of the Lifting team to be completed at site
Crane Operator : Sign: Date:
Rigger / Slinger: Sign: Date:
Hazard Control

Abrupt movements  Watch out for objects in the way of the load movement and be sure that the area
is safe for load movement
 Improper handling rigging of load  Ensure riggers, supervisor, crane operator are qualified/certified and load should
be properly check before lifting
Defective lifting equipment  Ensure lifting equipment (appliances and accessories) has valid certification (3rd
party certificates), inspect equipment prior to use.
Unstable, uneven ground  Position crane on stable and even ground
 Ensure the outriggers are set correctly sufficient and positioned properly
 Use mats under the outriggers to distribute ground pressure
 Keep sufficient distance from the edge of excavation if available in the site.

Emergency / Breakdown Procedures Refer to HSE Management Plan


Access / Traffic premises Traffic Diversion plan to be implemented if required
Signaling Hand signal to be use and only rigger is authorize to give signaler to the operator
Wind Speeds No lift will take place if the wind speed is higher than 32km/hr
Everyone to stand in safe distance from the lifting area and lifting area should be
Exclusion zones barricaded proper.

PART B. SET-UP CHECKLIST (To be completed by Operator)


1.) Crane set on level ground & outriggers fully extended? ---------------------------
YES NO
2.) Pick up and drop paths identified? -------------------------------------------------------
------- YES NO
3.) Rigging equipment inspected by 3rd Party & correctly color coded? -------------
----- YES NO
4.) Lifting area isolated and controlled? -----------------------------------------------------
------- YES NO
5.) Daily crane checklist completed & safe to commence work? ----------------------
------ YES NO
6.) Current wind speed:
Meter/second
7.) Crane Manufacturer’s wind speed limit: Meter/second (if
none stated, work suspended whenever wind speed reaches 9.8 m/s)

Site Conditions and Hazards

The following non-exhaustive list should be considered during the lift plan along with any other factors which could affect
any aspect of the lift.
PART C. CALCULATIONS

A = 56.3 meters

B = 10 meters

C = 0.6
. tons

D = 11.9 T tons
2
Total Weight (C+D) = 12.5 tons

Maximum Weight Capacity = 21.5 tons

Current % Crane Capacity = 58 %


(At crane set -up)
Crane SWL = 120 ton s

 ARRANGEMENTS FOR MULTIPLE CRANE POSITIONS

I agree that the crane described in part 1 may be re-positioned within the constraints defined within the Lift Plan provided
that each time it is set up in a new position the items in the list below are checked and signed for by the Crane Supervisor.
When the crane is being operated by a Contractor, each entry shall be countersigned by an COMPANY person, authorized by
the Project Manager. The signature(s) shall be entered on this form prior to allowing the crane to operate in the new position.

....... .......... .......... Appointed Person / Lifting Supervisor Date

This form shall remain in the crane cab during lifting operations and be returned to the COMPANY Project Manager on completion of
the lifting operations as described in part 1.

All Outriggers on Mats as Defined in


Outriggers Extended Crane Platform
Lift Plan Correctly Additional items to be Crane Lift COMPANY
to Spread Stated in and Within
Position Ref. Time Date Placed inserted by Supervisor Authorized
Lift Designated Lifting
as Lift Plan Under Each AP, if required Signature Signature
Plan Area Defined in
Lift Plan Outrigger

You might also like