Professional Documents
Culture Documents
IQBAL
NAME: MHAMMAD ABULLAH IBRAHIM ALI
SIGNATURE
CONTENTS
1.0 Purpose
3.0 Responsibilities
5.0 Supervisor
6.0 Execution
1,0 PURPOSE
This document replaces the “Method Statement for Lifting Operation up to 10 Tones”
with current tile “Lifting Plan for Tower Components (Transmission tower lattice)” to
provides the procedure to be used for crane operational practices. The key to safe
crane operation is having AHC Competent Person using the correct equipment in a safe
manner. This procedure will outline the issues relating to the selection of the correct
people for the task. It will describe the operational practices to be used by these people
as part of a safe and effective crane and rigging program. In particular, below standards
of Lifting Operations shall be complied. Safety manager shall ensure that every Lifting
operation involving Lifting equipment is:
Lifting of Transmission tower lattice from 1.5 TONS to 7.00 TONS USING 60 T MOBILE
CRANE.
This procedure applies to all AHC lifting operations. The lift plan process describes the
systematic assessment of important load factors and site factors. It is as applicable to
“simple” routine lifts as well as non-routine lifts. Planning a non-routine lift requires
considerable effort. In a lift determined to be non- critical, many of the elements can be
determined "by inspection"; and the depth involved in a non-routine lift will not be
required. Nevertheless, the planning process must be followed. This procedure
prohibits a person from riding or travelling on the load, lifting hook, sling, platform or
other lifting medium.
This document should be used as a reference, to aide for Lifting operations and Lifting
equipment and AHC workers to consider the safety factors when they assess, plan,
supervise and carry out Lifting activities.
3.0 RESPONSIBILITIES
PROJECT MANAGER
Responsible for the overall execution of the project and ensure the full implementation
of the work Safety Plan in accordance with the project specification.
CONSTRUCTION MANAGER
Responsible for Work Planning, Organizing, Control the execution of the work and
evaluate the construction department under the direction of the project manager and
ensure that all works are carried out as per project drawings and specification,
Responsible for giving assign task and giving correct instruction to Site Engineers, Site
Supervisors including assigned Lifting Supervisors.
SAFETY ENGINEER
Responsible for Implementation of SEC Safety Standards to all AHC personnel and All
workers with coordination to Project and Construction Manager.Monitor all Safety
Incident Report and take proper action with clear and effective control measures.
Direct report to project manager and call of immediate stop works if there this
imminent danger occurring to lifting operations.
SAFETY OFFICER
Safety officer Must make themselves aware of this guidance document ;
understand their responsibilities with regard to Lifting operations and Lifting
equipment and the links to the relevant health and safety legislation around
Lifting operations. Monitor safe system of works and all the lift calculation sheets
ensure TBT is been implemented.
Conduct pre-task briefing and Tool Box meeting prior to start of lifting activities.
All Lifting equipment within their areas of control are identified. Ensure that all Lifting
equipment used for Lifting operations is appropriate for the task, used correctly and that
employees involved in the organizing, planning and use of Lifting equipment are suitably
trained. Report all incident happen involving workers to Unsafe act and near messes. Call
immediate temporary stop works if imminent danger is arising during lifting process and
direct report to AHC Site Manager.
Verifying that the crane certification and inspection records are up to date before
allowing the crane on the project. Organizing a pre-lift meeting and ensuring all the
appropriate people are present.
Cones, warning tape or barricades are positioned to prevent entry into hazardous areas
around and especially behind the crane.
Access to the lift area is prohibited and barricades are available. Supervising all work
involving the crane. Determining the correct load weight and radius, and informing the
operator.
Ensuring that the rigger 3 experienced and competent. They must be capable of
establishing weights; judging distances, heights and clearances; selecting tackle and
lifting gear suitable for the loads; and rigging the load safely and securely.
Supervising the Lifting Activity. Ensuring that the load is properly rigged.
Ensuring that the signalpersons are competent and capable of directing the crane and
load to ensure the safety and efficiency of the operation. Knowing the international
hand signals is a must. Designating signalpersons and ensuring that the operator
knows who they are. Ensuring the safety of the rigging crew and all other personnel
affected by the rigging operation. Controlling the movements of all personnel within
the area affected by the lift. Ensuring that all required safety precautions are taken
when the lift is in the vicinity of power lines.
Ensuring that all personnel involved in the operation understand their jobs and
responsibilities. Ensuring that an emergency response plan is in place and is
communicated to all relevant personnel.
CRANE OPERATOR
Knowing the machine well. The operator must understand its functions and limitations
as well as its particular operating characteristics.
Following the manufacturer's operating instructions in accordance with the load chart.
Considering all factors that might reduce crane lift capacity and adjusting the load
weight to suit. This will include such factors as weather conditions and ground
conditions. Knowing basics of rigging procedures and ensuring that they are applied
(this is possible only when the load is visible to the operator). Maintaining
communication with signalpersons. Operating in a smooth, controlled, and safe
manner.
Shutting down and securing the machine properly when it is unattended. Exercising
the right to refuse to operate the crane if there is cause to suspect the lift might be
unsafe.
RIGGER LEVEL 3
Responsible for signaling for lifting work and secure the lifting and moving of
materials, and machines, while utilizing power operated equipment such as hoists,
winches, cranes, etc. Assists and determines the proper method of lifting equipment for
each assigned project; Assists with the set-up of crane; Conducts basic loading of heavy
lift projects by rigging the crane equipment and ensuring the proper use of each
equipment method. Directs crane operators to move equipment to and from work
areas. Ability to optimize resources (manpower, equipment and materials) to ensure
efficient and timely completion of the project. Ensures that work crews are properly
supplied with tools, equipment and materials. Prevents the misuse of equipment,
materials and tools. Ability to read, interpret and follow procedures. Competent in
reading and understanding specifications, Keeps records of all work completed.
Specifies locations for movement of machinery using knowledge of various methods of
sliding and lifting equipment. Directs workers engaged in splicing ropes and metal
cables to form hoisting slings. Familiar with and enforces strict compliance with all
Safety procedures, including all Company rules and regulations.
Performs other duties as assigned.
AHC LINEMAN
Been given the responsibility for planning lifting operations should have the
sufficient technical, practical and theoretical training, knowledge and experience
of the work they are like to plan lifts for. These linemen (persons) will vary
depending on the type of lifting work being carried out and are likely to be
different to the other labors referred to in regulation
.
They should:
Be capable of identifying the hazards and risks associated to lifting operations
within their area of work or the environment where the lifting operation will
take place/and fixing towers. Be able to select the correct fixing equipment for
the work .Understand the characteristics of the tower lattice fixing equipment they
are selecting and the nature of the work it will be carrying out.
5.0 EXECUTION
AHC Construction will Lift the ground assembled transmission tower parts to the point
of the towers, and it is divided in to different components, as shown in the drawing e.g.
tower parts No.1, No.2, No.3, No.4 & No.5 with a travel distance as per radius mention
on drawing 4 Meter to 8 Meters from fixing point of the towers to the Mobile crane.
Lifting operations shall be conducted in strict accordance with the approved by SEC lift
plan. Any variation from the lift plan shall result in the job being stopped and
reassessed to ensure continued safe operation. The lifting operator shall obey an
emergency stop signal at all times, no matter who gives it. When lifting operations
need to be controlled by signals, a designated signal person/Rigger shall be assigned.
Signals between the lifting crane operator and the designated signal person (rigger)
shall be audible or visible at all times. The appropriate load-radius chart for the lifting
appliance configuration in use shall be visible to the operator. Load to be lifted shall be
confirmed to be within the rated capacity of the lifting equipment and attached by
means of suitable lifting accessories. The operator of the lifting appliance shall not
leave the operating controls while the load is suspended.
Tower is been on sequence step start from Tower part No. 1, 2 ,3, 4 & 5 the lifting area
must be barred and Lifting Signage should be installed with the present rigger
AHC Safety Engineer/Officer must ensure that the lifting area is been properly
barricaded and all workers must wear proper PPE’S
One hook, Slings as required, Shackles. Signal Flag (Red & Green)
Barricades, Full body harness, Life line, Warning Signage (e.g. On Going Lifting)
PPE (Adequate personal protective equipment)
Crane 60 T, Ambulance, First Aider.
WORK METHODOLOGY:
Prior to carry out any work all materials & equipment shall be ready and inspected at
site by rigger, operator including AHC Safety Engineer/Officer. All workers involve in
this job should be oriented properly by pre-task briefing prior to start lifting process
and tool box meeting. The planned positions of the crane must be marked before
working. A safety clear zone consisting of the radius + 10m should be identified 360
degrees around all cranes. The load must be controlled by tag line only. The operator
must make sure that the safe angle inserted in the crane computer. Use chain pullers to
connect the lifting belt & chiller body in the bump side to avoid any swinging. Control
the length of the hook to get perfect balance by using spirit level for indication.
Note:
All workers must use helmet, safety shoes, vest, gloves & glasses. The communication
must be by the rigger only by using lifting signals.
All critical lifting parameters (e.g. weather, (raining, sand storm, visibility, stability and
slope, surrounding operations and installations, site access and egress, Lifting
Equipment, personnel) shall be identified during the risk assessment and preparation
of the Lift Plan.
AHC Safety will not allowed any lifting activities in site, if the present wind speed will
above 32KPH all lifting activity in site shall be suspended. During heavy sand storm and
zero visibility condition AHC Site lifting activity will be suspended not and less if the
climate and weather condition will be on normal condition including wind speed.
The AHC Safety ensure that these conditions are monitored as lifting operations
proceed to ensure continued safety of Lifting Process. If, as part of the operation and
maintenance of equipment, the computer system shuts down the operation, the load
must be placed on the ground and a new lift plan must be developed, eliminating the
condition that caused the shutdown. Procedures for recovering and landing the load in
the event of the lift being aborted shall be clearly identified.
6.0 CRANE
These inspections must be performed and documented by the CRANE operator prior to
first use each day or shift the CRANE is used. These checks ensure that audible and
visual warning equipment is working correctly by carrying out function tests prior to
any lifting operations.
Drive at speeds limit which 20 KPH in al SEC Construction Site for the existing
conditions (space, load, lighting, surface conditions, etc.) and at or below
posted limits Keep all parts of the body inside the Operator compartment
during operations Not start or operate the crane or any of its attachments from
any place other than from the Operators position Ensure other personnel are
not in the swing radius prior to performing turning maneuvers, Sound the horn
when approaching, locations where pedestrians may step into the path of
crane travel.
When parked:
The engine shall be switched off, the key removed and the hand-brake applied.
The keys shall be kept in a secure place and only issued to authorized
operators for the duration of the duty period or task. They shall be parked in
secure areas to deter access by unauthorized personnel. They do not block
access to fire aisles, stairways, or fire equipment
While refueling, the engine shall be stopped. No Lifting operation will be take
place, is not allowed.