CB SPL MAHAKAM

Date : 2015/5/19 Originator: Aditya Permana P Role : Engineering

Lifting Plan of Generator Set


At C.B SPL Mahakam

REV. DATE PURPOSE CHECKED BY CHECKED & REVIEWED BY APPROVED BY

0 1st ISSUE
Benny Y/Denny P J.H. Djati/Herry M Irwan
MPP HSEM Officer MPP OIM
TABLE OF CONTENTS

1. INTRODUCTION ............................................................................................................................... 3
2. CLASSIFICATION OF LIFT TYPES ..................................................................................................... 4
3. PURPOSES ........................................................................................................................................ 5
4. SCOPES ............................................................................................................................................. 6
5. RESPONSIBILITIES............................................................................................................................. 6

6. LIFTING PREPARATIONS .................................................................................................................. 6


7. DESCRIPTION OF LOAD TO BE LIFTED .......................................................................................... 7

8. LIFTING PROCEDURE TEMPORARY RENTAL GENERATOR FROM BOAT TO MAIN DECK.......... 9


9. LOAD CHART LIEBHERR CRANE BASED ON MANUAL BOOK.................................................... 10

Page 2 of 10
1. INTRODUCTION

Generator units in C.B SPL Mahakam is a very important and critical equipment which we
have to maintain availability and reliability of the engine. Generator a main function for
lighting and rotating winch.

In C.B SPL Mahakam there are 3 Generator, Generator #1 for winch and Generator #2 &
#3 for lighting. And recently Generator #1 turbocharger is over heat then we plan to
overhaul Generator #1 & #2.

Prior to perform engine exchange Generator, it is necessary to do the lifting from supply
Boatto C.B SPL Mahakam. Total load calculation is 3670 KG for engine.

Maximum radius for crane with safety factor for this maximum load is 47 meters with
working angle 45 degree are still able to lift with the maximum load = 15100, (please see
load chart attached).

Page 3 of 10
2. CLASSIFICATION OF LIFT TYPES
There are generally two types of lift, Routine and Non-Routine. Categorizing the type
of lifts before planning the lift and documenting in a lifting plan is critical because it
allows for the proper assessment of the amount of risk present in the lifting operation
and the level of control required in mitigating the risks involved. And for Temporary
Rental Generator it is categorizing to non-routine lift with, please see below flowchart
for Identification of Routine or Non-Routine Lifting Activities

Page 4 of 10
3. PURPOSES
The Purposes of this lifting procedure are:
1. To provide guidance or safety procedure to lift Temporary Rental Generator unit
until it has been installed in the enclosure
2. To ensure lifting equipment that utilized are appropriate, safe & comply to safe
lifting procedure.

Page 5 of 10
4. SCOPES
This lifting plan is applicable for Temporary Rental Generator Installation from supply
boat to its enclosure.

5. RESPONSIBILITIES
SPL’s responsibilities during this lifting activity:
1. Provide valid certificates for Crane at SPL Mahakam Vessel
2. Provide valid certificates for lifting gears that will be used for this lifting activity
(Chain block, came long/lever block, shackle, webbing sling, wire rope sling, etc.)
3. Provide valid certificate for miogas crane operator from independent party.
4. Pre-inspection for Crane and lifting gears that will be used for this lifting activity.
5. Pre-job meeting prior to start activity

6. LIFTING PREPARATIONS
Preparations for this lifting activity:
1. Safe Working Load (SWL), identification, tag number must be clear and must be
marked.
2. Load shall not exceed the lifting gear Safe Working Load (SWL) when being tested
by an independent officer/party.
3. SPL Mahakam HSE Officer & Lifting Coordinator must ensure that all lifting activity
use lifting Gears/ Equipment is complying with presence legal requirements and
legislation when this activity held.
4. If some of the anomalies found during the lifting process, operator must stop the
activity and report to Lifting Coordinator/SPL Mahakam HSEM Officer. Lifting
Coordinator must conduct an investigation and recommendations on any
measures to be taken so that the incident did not happen in the future.
5. Lifting Coordinator/HSEM Officer shall immediately report to the Barge
Master/company representative when they observe / discover some discrepancies.
Barge Master/Representative of the company shall take the necessary measures to
Lifting Coordinator who responsible for preventing the occurrence of the incident.
6. See Table.1. For some things are permissible and prohibited when operating the
crane.

Page 6 of 10
Table.1. Allowed & Not allowed activities for lifting plan activity

NO Allowed Activities Not allowed activities


Requested permission from the company Banned from un-related activity during
1 representative before starting the working with cranes .
operation.

Inform each supervisor immediately if Do not work with tools, hooks ,


2 there is some defect or damage to the shackles , ropes , chains and others
lifting gear with defect criteria.

Use proper PPE during operate the Prohibited for standing under lifted
3
cranes. material.

Use barricade for the affected zone Prohibited for standing while loading
4
before working with crane or lifting gears. conditions in hanging state.

Always raise the load slowly to prevent Do not allow to lift the load with
5
shock. sloping condition

6 Always Follow SOP during lifting activity.

7. DESCRIPTION OF LOAD TO BE LIFTED

The load which will be lifted for this activity described as bellow:

A. Lifting Machine Liebherr Crane HS 885 HD


SWL 16.5 ton
B. Lifting Gear

C. Crane Details
Crane Liebherr Crane HS 885 HD
Configuration Main Boom
Boom Length 76 Meter
Working Radius 48 Meter
Corresponding SWL

Page 7 of 10
D. Load Details
Description Generator estimation weight is 3670 kg
Lifting Points Generator has 4 lifting points, using 4
wire sling connected to hook block
Dimension L 3650 x W 1300 x H 1750 (mm)
Center of Gravity Given

E. Load Calculation
Total Load weight 3670 kg
Lifting Gear weight 100 kg
Hook block weight 500 kg
Total weight 4270 kg

Safety Factor 1.25

Load/SWL 5337.5

Crane Capacity Usage (Load/SWL) 67.7 % Safe

Page 8 of 10
8. LIFTING PROCEDURE TEMPORARY RENTAL GENERATOR FROM BOAT TO MAIN DECK
1. Moored up Vessel boat to C.B SPL Mahakam.
2. Prepare to lift the Temporary Rental Generator from Boat to C.B SPL Mahakam
main deck
3. The supply vessel should be positioned according to safe angle of crane; the safe
angle for this activity is 45o with working radius 33 meters.
4. Attach master link to the hook of main block of Crane. See Figure 1 as illustration

Figure 1Lifting illustration of half container

5. The boom crane will be positioned at 50o, where the SWL is 11000 kgs.
6. Lift the load 30 cm above boat deck and ensure stability of crane with this load
before lift and move the load to C.B SPL Mahakam main deck
7. Crane will be swung to the right direction and the angle set on position 60o. The
Crane swing until generator to main Deck
8. At this position, the boom crane shall be set at angle60o. In this position, the SWL
of crane is15,100 kgs.

Page 9 of 10
9. LOAD CHART LIEBHERR CRANE BASED ON MANUAL BOOK

Page 10 of 10