Project Execution Plan
RUI-OPF-WP-003
Installation Temporary Rental Generator
TABLE OF CONTENTS
1. INTRODUCTION ..................................................................................................................... 3
2. OBJECTIVE ............................................................................................................................ 3
3. ACRONYMS & ABBREVIATIONS.......................................................................................... 3
4. REFERENCES ........................................................................................................................ 3
5. SCOPE ................................................................................................................................... 3
5.1. SCOPE OF DOCUMENT ........................................................................................................ 3
5.2. SCOPE OF WORK ................................................................................................................. 3
7. PROJECT MANAGEMENT..................................................................................................... 4
7.1. ORGANIZATION ..................................................................................................................... 4
7.2. WORK PREPARATION .......................................................................................................... 5
7.3. ENGINEERING WORK ........................................................................................................... 5
7.4. MANPOWER DISTRIBUTION ................................................................................................ 5
7.5. PLAN AND SCHEDULE ......................................................................................................... 6
8. PLACEMENT STRATEGY ...................................................................................................... 7
9. RISK ANALYSIS AND JOB HAZARD ANALYSIS ................................................................. 8
12. COMMISSIONING .................................................................................................................. 8
APPENDIX 1 – DRAWING ............................................................................................................. 9
APPENDIX 2 – RISK ASSESTMENT AND JOB HAZARD ANALYSIS ....................................... 10
APPENDIX 3 – JOB PLAN .......................................................................................................... 11
APPENDIX 4 – LIFTING EQUIPMENT......................................................................................... 12
This document is intended for the sole use of the recipient and must not be copied or transmitted by any form (electronic,
mechanical, reprographic or otherwise) without the prior written consent of PT Supraco Lines
Page 2 of 13
Project Execution Plan
RUI-OPF-WP-003
Installation Temporary Rental Generator
1. INTRODUCTION
SPL Mahakam have three engine generator Cummins, Type 6CTA83 – GIM, 150 KVA and this
equipment installed on Engine Room (Generator #1 & Generator #2) and Main deck (Generator #3)
On August, 31 2018 We found Generator #1 is over heat at turbocharger after We have performed
engine in > 1 hours.
2. OBJECTIVE
This Project Execution Plan (PEP) defines the methods and project management elements used to
manage the execution of this PROJECT. It establishes the critical baseline documents based
execution philosophy, and defines the organization, work processes, and systems necessary for
management of this project.
CONTRACTOR’s major objective is to perform the work safely and efficiently within the project
schedule in accordance with project specifications, criteria and procedures.
4. REFERENCES
5. SCOPE
5.1. SCOPE OF DOCUMENT
This document only applies to work related withConstruction and Installation of Temporary Rental
Generator Set for C.B SPL Mahakam. Document explain about Project Management Plan,
Placement Strategy, Risk Analysis, Job Hazard Analysis, Lifting Plan, and Commissioning
This document is intended for the sole use of the recipient and must not be copied or transmitted by any form (electronic,
mechanical, reprographic or otherwise) without the prior written consent of PT Supraco Lines
Page 3 of 13
Project Execution Plan
RUI-OPF-WP-003
Installation Temporary Rental Generator
6. TECHNICAL SPECIFICATION
Genset Type : Mitsubishi DCA-220 SP Silent type
Capacity : 200 KVA
Specification : 50 Hz, 220/380-440 Volt, 3 Phase, PF 0.8
RPM : 1500
Fuel Consumption : 29 Ltr/H
Length : 3650 mm
Width : 1300 mm
Height : 1750 mm
Weight : 3670 kg
7. PROJECT MANAGEMENT
7.1. ORGANIZATION
In this work, Engineering team will be coorperation with Operation Team in office and on site. The
Project Leader in managing and collecting all information from site during work.
All information and reports shall be submitted by the assigned personnel to the Project Leader in
timely manner.
To ensure the smooth execution of the project, CONTRACTOR has set the following three project
offices:
a. Field Offices Samarinda that are located in Jl Kemangi Blok RS No. 6 will be used for:
Overall construction management including site engineering activity
Field Quality Assurance / Quality Control
HSE and Security Control
c. Balikpapan Office PHM Office will be used for coordination project with COMPANY
This document is intended for the sole use of the recipient and must not be copied or transmitted by any form (electronic,
mechanical, reprographic or otherwise) without the prior written consent of PT Supraco Lines
Page 4 of 13
Project Execution Plan
RUI-OPF-WP-003
Installation Temporary Rental Generator
This document is intended for the sole use of the recipient and must not be copied or transmitted by any form (electronic,
mechanical, reprographic or otherwise) without the prior written consent of PT Supraco Lines
Page 5 of 13
Project Execution Plan
RUI-OPF-WP-003
Installation Temporary Rental Generator
b. Installation on site by on duty reguler manpower C.B SPL Mahakam, helping by Office
Mechanic and leading by Barge Master
This document is intended for the sole use of the recipient and must not be copied or transmitted by any form (electronic,
mechanical, reprographic or otherwise) without the prior written consent of PT Supraco Lines
Page 6 of 13
Project Execution Plan
8. PLACEMENT STRATEGY
Structural activities focus are on the installationTemporary Rental Generator Set specific location:
CONTRACTOR choose to placement Temporary Rental Generator Set on main deck because on top
deck have a bad structural and below top deck is accommodation deck. If placement of Generator Set
install on top deck, it can disturb operational production because crew have a bad rest and top deck
have a potential crack cause Generator Set Vibration. Installation of Temporary Rental Generator will be
complete with exhaust system. For detail drawing and exhaust Installation will be explained in Appendix
-1
This document is intended for the sole use of the recipient and must not be copied or transmitted by any form (electronic,
mechanical, reprographic or otherwise) without the prior written consent of PT Radiant UtamaInterinsco, Tbk
Page 7 of 8
Project Execution Plan
At every work activities that performed on Vessel, PT. Supraco Lines has made risk
assessment and mitigation measures. There are several activities with fairly high level of risk :
a. Lifting and mobilization Temporary Rental Generator Set
b. Loading Temporary Rental Generator Set from Boat to C.B SPL Mahakam
c. Placement Temporary Rental Generator Set on Main Deck. For detail risk assessment will be
explained in Appendix– 2
12. COMMISSIONING
Commissioning will be conducted in 2 place, onshore shop and vessel. Both commissioning using same
methods, but on shop using load test while on site don't using it. The method is load test for knowing
centre of gravity position. The thinks used for knowing centre of gravity that required during lifting
activity. Commissioning activity on this project will be planned into Commissioning Plan and cover by
three stages of handover:
a. CONTRACTOR after due checks on completion of the equipment prior to resuming pre-
commissioning checks, followed by performing static tests onshore after completion fabrication.
b. After material on site (C.B SPL Mahakam), the work will start after handover document sign off by
operation authority to maintenance team. In the case maintenance team are CONTRACTOR. Before
constructionbegan, overall equipment safety must ready to use and attached (fire extinguisher,
barrier line).
c. Commissioning activity have been conducted when Item in onshore workshop CONTRACTOR and
when tools and lifting equipment ready. After commissioning Generator Set will be install on Vessel
The Control and monitoring of Pre-/com activities shall utilize by CONTRACTOR and review by
CONTRACTOR Commissioning system.
This document is intended for the sole use of the recipient and must not be copied or transmitted by any form (electronic,
mechanical, reprographic or otherwise) without the prior written consent of PT Radiant UtamaInterinsco, Tbk
Page 8 of 8
Project Execution Plan
APPENDIX 1 – DRAWING
This document is intended for the sole use of the recipient and must not be copied or transmitted by any form (electronic,
mechanical, reprographic or otherwise) without the prior written consent of PT Supraco Lines
Project Execution Plan
This document is intended for the sole use of the recipient and must not be copied or transmitted by any form (electronic,
mechanical, reprographic or otherwise) without the prior written consent of PT Supraco Lines
Project Execution Plan
This document is intended for the sole use of the recipient and must not be copied or transmitted by any form (electronic,
mechanical, reprographic or otherwise) without the prior written consent of PT Supraco Lines
Project Execution Plan
This document is intended for the sole use of the recipient and must not be copied or transmitted by any form (electronic,
mechanical, reprographic or otherwise) without the prior written consent of PT Supraco Lines