Duration Personnel
Work Breakdown / Description of Work PIC Man Power / Resources (3rd Party) Qty Status
(Hour) Name
Preparation
Preparation to Shipyard 1 Engineering SPL Engineer Adit/Ridwan 1
2 Electrical Technicial SPL Eko 1
1 Site Inspection actual condition CB. SPL Mahakam SPL Hrs 3 Mechanic Senior Senior Mechanic Sriyanto/Ali 1
2 Quotation and Material Request SPL Hrs 4 Rigger SPL Mahakam 4
3 Work Plan and Repair List SOW SPL Maintenance SPL Hrs 5 Crane Operator SPL Mahakam 1
4 Preparation Tools List SPL Hrs
TOTAL MAN POWER 8
Rev. by