DAILY PROGRESS REPORT

DATE :- 7/24/2014

PROJECT :- FM BOILER, M/s Lanco A/c Mahagenco, Koradi, Nagpur


JOB NO. :- PF 1261

DAY PROGRESS:

Inputs
Sr. No. Activity planned
FROM
FROM Customer
Thermax

Manpower/
1 Box-up of steam drum to be done Engineer
Engineer/Tools

Boxup of deaerator & vapour tank to be Manpower/


2 Engineer
done. Engineer/Tools

Manpower/
3 Control panel charging to be done Engineer
Engineer/Tools

Manpower/
4 Trial of MSSV valve from Local Engineer
Engineer/Tools

Manpower/
5 Flushing of atomising air line to be done Engineer
Engineer/Tools

Soot blower trials to be done in manual Manpower/


6 Engineer
mode. Engineer/Tools

NEXT DAY’S PLAN:

Sr. No. Activity planned Inputs


FROM
FROM Customer
Thermax

Skilled Manpower
1 Trial of MSSV valve from Local Manpower/Engineer Engineer
/Tools.
Soot blower trials of 1 no LRSB be done Manpower/
2 Engineer
in manual mode. Engineer/Tools

Skilled
Manpower/Engineer
3 Flushing of boiler pressure parts. /Commissioning Engineer
Tools/UPS Power
supply/Walky Talky

Skilled
Manpower/Engineer
4 Load Trials of Scanner Fan 2 Engineer
/Commissioning
Tools/Power Supply

Skilled
Communication establishment between Manpower/Engineer
5 Engineer
the controler panels. /Commissioning
Tools/Power Supply

Skilled
Flushing & Cardboard blasting of LDO Manpower/Engineer
6 Engineer
line. /Commissioning
Tools/Walky Talky

Next milestone activity-


EPORT

LEGENDS:
· C – Completed
· NC – Not completed
· PC – Partially Complete

Activity
Status
Remarks / Reason for activity not completed
C / NC / PC

C Initial filling of the boiler is also completed

The panel has been charged and switched off


PC again due to late availibility of UPS power
supply

Power cable glanding for MSSV is not


NC
completed.

C The flushing of the line is completed.

Trials of all 4 RSB has been completed. 1 Nos


LRSB trials is pending because the poppet
PC
valve actuator link is fauling with insulation
cladding. Same is to be rectified.

Remarks