3x660MW KORADI THERMAL POWER STATION

Unit # 10 AOH Progress Review Status


Section :TURBINE MAINTENANCE

S PROGRESS REVIEW STATUS, as on


N
OVERHAUL ACTIVITY PERMIT NO
Friday, November 13, 2020
S PROGRESS REVIEW STATUS, as on
N OVERHAUL ACTIVITY PERMIT NO

LPT-1 Gland leakage attending work.

TM-01

From To
Scheduled 15-Nov 23-Nov
Actual
Status NOT YET STARTED

CRH NRV (LHS&RHS) onternal inspection , servicing and guide


bush bearing fabrication and installation work

TM-02

From To
Scheduled 13-Nov 28-Nov
Actual 11-Nov
Status WIP

EH Oil System oil filteration and filters replacement work.

TM-03

From To
Scheduled 10-Nov 18-Nov
Actual
Status NOT YET STARTED

HPSU system oil filteration and filter replacement work.

TM-04
From To
Scheduled 10-Nov 14-Nov
Actual
Status NOT YET STARTED

Hot well make-up CV's servicing and internal isnpection work

TM-05 5759400%

From To
Scheduled 11-Nov 20-Nov
Actual
Status NOT YET STARTED

Deaerator control station CV's internal inspection & servicing.

TM-06

From To
Scheduled 10-Nov 23-Nov
Actual 12-Nov
Status WIP
S PROGRESS REVIEW STATUS, as on
N
OVERHAUL ACTIVITY PERMIT NO

Deaerator internal inspection & spray nozzel checking jointly


with Sr. Chemist
TM-07

From To
Scheduled 15-Nov 20-Nov
Actual 12-Nov
Status WIP

Hign Energy Drain Valves for MS/HRH/CRH lines replacement


work as per POG reoprt.
TM-08

From To
Scheduled 15-Nov 25-Nov
Actual
Status NOT YET STARTED

HPH inspection work as per POG Report and HPH Dump Line
& Drip CV servicing work
TM-09

From To
Scheduled 13-Nov 2-Dec
Actual
Status NOT YET STARTED

Condenser Tube Cleaning by High pressure Hydro jetting &


Bullet Shot method and Condenser fill test & joint inspection
with Sr. Chemist.
TM-10

From To
Scheduled 12-Nov 3-Dec
Actual 12-Nov
Status WIP

Provision of interconnection loop in Condenser inlet to


condenser outlet (at transformer area) for achieving pressure
relief
TM-11

From To
Scheduled 18-Nov 4-Dec
Actual 12-Nov
Status WIP
S PROGRESS REVIEW STATUS, as on
N OVERHAUL ACTIVITY PERMIT NO

CW Header discharge line to Condenser Inlet dewatering,


internal inspection and debris removal work
TM-12

From To
Scheduled 13-Nov 6-Dec
Actual 12-Nov
Status WIP

NDCT Pond Basin & peripheral cleaning work including gate


isolation work.
TM-13

From To
Scheduled 13-Nov 3-Dec
Actual 12-Nov
Status WIP

NDCT refurbishment and drift eliminator installation work


( work will be carry out by Project team.)
TM-14

From To
Scheduled 11-Nov 6-Dec
Actual 12-Nov
Status WIP

TDBFP A&B Lub oil system pump servicing, Governing trip


block servicing, Suction strainer cleaning, coupling inspection
and alignment, barring gear assembly servicing work.
TM-15

From To
Scheduled 10-Nov 5-Dec
Actual 11-Nov
Status WIP

TDBFP B Turbine Turning gear wheel inspection and repairing


work.
TM-16 From To
Scheduled 11-Nov 1-Dec
Actual 11-Nov
Status WIP

CEP B&C Overhaul Work (to resolve high vibration issues.)

TM-17
From To
Scheduled 10-Nov 4-Dec
Actual 10-Nov
Status WIP
S PROGRESS REVIEW STATUS, as on
N
OVERHAUL ACTIVITY PERMIT NO

WDC A&B Valve internal inspection & Servicing work

TM-18

From To
Scheduled 14-Nov 25-Nov
Actual
Status NOT YET STARTED

HP&LP Vacuum Pumps servicing work & PHE Cleaning.

TM-19
From To
Scheduled 10-Nov 23-Nov
Actual 11-Nov
Status WIP

DMCW TG&SG Pumps servicing & PHE Cleaning

TM-20

From To
Scheduled 11-Nov 30-Nov
Actual 10-Nov
Status WIP

CW Pump B servicing work.

TM-21

From To
Scheduled 13-Nov 3-Dec
Actual 11-Nov
Status WIP

ACW Pump Servicing & strainer cleaning work.

TM-22

From To
Scheduled 14-Nov 4-Dec
Actual 11-Nov
Status WIP

DG Set Servicing Work

TM-23

From To
Scheduled 13-Nov 24-Nov
Actual
Status NOT YET STARTED
S PROGRESS REVIEW STATUS, as on
N OVERHAUL ACTIVITY PERMIT NO

Air Compressors servicing work ( Instrument & Service Air)

TM-24

From To
Scheduled 9-Nov 21-Nov
Actual 12-Nov
Status WIP

Misc and Other section work

TM-25

From To
Scheduled 9-Nov 6-Dec
Actual 9-Nov
Status WIP