UNIT 1 MAINTENANCE OUTAGE ACTIVITIES 9-10 Dec 2023 (48H)

09-Dec-23 10-Dec-23
No Description Trouble Indication Inspection Method WO No.
00:00 08:00 12:00 14:00 17:00 18:00 21:00 08:00 12:00 14:00 16:00 17:00 00:00

DESYNCHRONIZING
MECHANICAL

1 ID Fan Impeller Rectification Repair after service during last outage Patching metal compound 129154

2 Bag Filter Inspection & Replacement - Inspection and Replacement Bag Filter 129155

- Grinding existing welding point


- Bevelling
3 Desuperheater 3A repair work Passing 128989
- Fit up welding
- Heat treatment & welding

DRAIN CONTROL HP VALVE - Disassembly Limit Switch by I&C


4 Passing 129156
12MAA10CG285 - Disassembly Valve and Check Valve

ELECTRICAL

Check Heater MCB in panel CB 150kV Open and Check Heater MCB in panel
1 Alarm MK Heater MCB Trip 129157
BAY TO GSUT Unit 1 CB 150kV BAY TO GSUT Unit 1

- Disassembly motor
2 BOILER - COAL WEIGHING FEEDER A Bearing Indication Poor Lubrication 129158
- Replacement bearing motor

- Disassembly motor
3 BOILER - COAL WEIGHING FEEDER E Bearing Indication Poor Lubrication 129159
- Replacement bearing motor

I&C

LOOP SEAL HP BLOWER B DRIVE SIDE - Check DCS module


1 The value is hunting 129160
VIBRATION Y-AXIS - Replace or change chanel DCS module

- Check DCS module


2 CWP-2 VIBRATION(MOTOR NDE-Y) The value is hunting 129161
- Replace or change chanel DCS module

U1 LP FWH NO.2 INL EXTR STM DRN-2 - Check solenoid valve


3 Leakage 129162
VLV - Replace solenoid valve

- Check cable from shelter to DCS


The point did not register yet on DCS
4 Mercury Monitoring System Unit 1 - Create new point and display on DCS 129163
HMI
HMI

START UP
SYNCHRONIZING

Note : PM Regularly published as per schedule in system.