Part 1: Job Description: Hydro testing on 28 bar Pressure for (WP) Water Produce
Location: FEC Area
Lines at FEC area
JRA Date: 19-02-2011 JRA No./ Revision: 11-193 JRA Leader: Michael Middleton Scribe: Abrar-ul-Hassan
Review Team: (e.g. Ops Review Team): Afsar, Malik Shoukat, Akmal, Ubeduulah, Abdul Rasheed and Abrar-ul-Hassan
List Associated Procedures/work instructions or Temporary WIs:
Hazard Check List (FRCP identified below must reference applicable FRCP Control Measures – refer to FRCP Handbooks)
√ Falls from Heights √ Access / Egress Confined Space √ Manual Handling √ Fatigue/Over Exertion √ Slips, Trips & Falls
√ Competence of
√ Falling Objects Collisions √ Noise Illumination Environmental
Personnel
Liquid/Gas Under Flaring/Hydrocarbon
Oil/Chemical Flammable Materials Moving Machinery Electricity
Pressure Release
Surface Mobile
√ Ignition Source Light Vehicles
Corrosive Substance Chemical Exposure Naked Flames Equipment
(Sparks/Electrical) (FRCP)
(FRCP)
Hazardous Materials Equipment Other
Isolation √ Working at Heights Lifting Operations (please specify)
Management Safeguarding
(FRCP) (FRCP) (FRCP)
(FRCP) (FRCP)
Step
Hazard Hazard Effect Hazard Controls Controls Acceptable
Job Steps Use Checklist as a Guide Injury/Damage or
No. Use Hierarchy of Controls/FRCP Control Measures Y/N
to be Specific Environmental Effect
01 Mobilization Un inducted Personal Ensure inducted and medically fit and Yes
of equipment people injury approved people from FEC Project HSEC
should be inter in the working area
& workers
Unauthorised Risk to No equipment to be used unless inspected
Hydro testing equipment/ property / and approved by BHPB FEC Project team.
machine, Air tools brought persons Ensure that all personnel prior to start the
Compressor & on to site have been inducted and oriented about the
Power Unskilled and hazard in the job site.
Generator un inducted Only trained personnel approved by DEL
personnel shall perform this activity.
CONTROLLED DOCUMENT
PF03.02 Page 1 of 8 Rev. 0
Printed copies of this document are not controlled.
To verify this copy is current, check on the intranet at HSE Portal
Health, Safety & Environment
Petroleum Management System
starting the
job
Workers Fatigue / All personnel must be undergone fitness
starting the under rest for work assessment through DEL doctor
job unfit to
work Ensure no one allowed continuous the
working due to Fatigue or under rest
because its major cause of
accidents/incidents.
Ensure that no worker shall work more
than 14 hours and shall have 8 hours
sleep
Take periodic rest during the working to
prevent the fatigue
CONTROLLED DOCUMENT
PF03.02 Page 2 of 8 Rev. 0
Printed copies of this document are not controlled.
To verify this copy is current, check on the intranet at HSE Portal
Health, Safety & Environment
Petroleum Management System
02 Water filling Creating wet Risk to Ensure all areas are free of electrical Yes
in Pipes to be areas around Property/ equipment during filling activity
electrical Personal
Hydro tested equipment Injury Use Electrical water filling pump and
(low shall be Inspected from FEC HSEC Team
pressure) power supply to be stipulated from DEL
Power Generator
Use of Manual Hydraulic Pump for stable
the line pressure
Equipment Ensure all hoses and clamps are in sound
Failure condition and securely fastened prior to
pumping
Competent person will be perform the
activity
Before start the activity operators must be
check the all equipments are in working
safely then he will be do the job
Safety observer to be depute to look the
nearest vehicle movement and restrict to
persons movement access in the working
CONTROLLED DOCUMENT
PF03.02 Page 3 of 8 Rev. 0
Printed copies of this document are not controlled.
To verify this copy is current, check on the intranet at HSE Portal
Health, Safety & Environment
Petroleum Management System
area
Improper Be care full movement during the job
Slip Trip
Access
Restricted access provide safe access to
workers and barricade the working zone
and non essential persons remain clear
working area
Maintain all the time proper and
appropriate safe access for working
03 Line Injury Risk to Verify QA records to ensure that all flanges Yes
pressurizatio resulting from Property / have been tightened and inspected prior to
localised test Personal starting test (temporary flanges)
n and failure (e.g. Injury
inspection Ensure all flanges are fully tightened prior
flange or to starting test (temporary flanges)
gaskets) Work to be planned so as to minimise
interaction with other work activities in
the area.
Standard PPE to be worn at all times
A barricaded 5m exclusion zone ‘envelope’
to be established and maintained around
each flange on the line.
An HSE team member to be stationed at
the activity to continuously patrol test
area to ensure exclusion zone is maintained
while testing at high pressure is in
progress.
Test pressure to be attained in stages –
depending on test pressure and volume
involved.
Test pressure to be maintained a minimum
of 10 minute prior to entry of barricaded
area by any personnel (including QA
inspectors, BHPB FEC Project Team
members).
Pressurise testing shall only be performed
CONTROLLED DOCUMENT
PF03.02 Page 4 of 8 Rev. 0
Printed copies of this document are not controlled.
To verify this copy is current, check on the intranet at HSE Portal
Health, Safety & Environment
Petroleum Management System
04 Air blowing Improper or Risk to Use standard and rated fittings to be used Yes
using Air sub standard Property / on site
fittings Personal
Compressors Injury
Make sure all hoses are connected for
correct flow direction to and from the air
compressor used
Make sure hoses and fittings are
undamaged and tight before stating the air
compressor
Hose Use rated hoses as per designed capacity
connection Ensure all hose connections are fitted with
failure web-check
CONTROLLED DOCUMENT
PF03.02 Page 5 of 8 Rev. 0
Printed copies of this document are not controlled.
To verify this copy is current, check on the intranet at HSE Portal
Health, Safety & Environment
Petroleum Management System
Bad Weather High Wind, Stop the job in case of high wind, rain,
Rain and dust storm and report to the BHPB FEC
Dust Storm Projects HSEC Team on radio- channel 6
site
CONTROLLED DOCUMENT
PF03.02 Page 7 of 8 Rev. 0
Printed copies of this document are not controlled.
To verify this copy is current, check on the intranet at HSE Portal
Health, Safety & Environment
Petroleum Management System
Alternatives Considered: What are the other possible means of achieving the job outcome?
Part 3: Contingency Plans: What rescue equipment, PPE etc could be needed if something went wrong? Reference Field ERP
Stand by ambulance with trained medic, means of communication, radio and verbal immediately inform to BHPB FEC Projects HSEC Team and
DESCON Doctor
All persons go through your Designated muster points