You are on page 1of 3

GEA PROCESS ENGINEERING

Project Name - ESP erection & commissioning(birla copper dahej) Document No:- HIL/JSA/EHS-01

Activity- Fabrication & erection of assembly bed


Rev-0

JOB SAFETY ANALYSIS


Location of Work : Smelter -1 ,ESP
JSA No- 01

Sr. Sub Activities / Tasks Hazards Impact in case of exposure Risk Control measures (There can be multiple control measure for one hazard) Responsibility
No.

1 Work start-up preparation & Un authorized work Physical Injury Must be followed HIL permit system site engineer and
obtaining work permit Invalid permit Supervisor must insure that all work activities are carried out by competent Supervisor
Lack of competency person
Poor communication Property damage Conduct tool box talk meeting
Hast or shortcuts stuck worker in case of Review the method
Don’t aware with plant emergency emergency Responsible person will conduct inspection
Consider all potential hazards: weather, wet or slippery conditions, overhead
hazards, proximity to trails and/or visitor traffic patterns/volume, slope, loose
footing, elevation, fatigue, hazardous insects or plants, etc.
awarness regarding HIL emergency procedure

2 shifting of materilas from storage Toppling or Falling of material Physical Injury Only competent and approved operator shall be deployed for equipment Rigger and Site
area to esp area by hydra & trailor Mechanical failure of lifting tools and operations. engineer and
tackles Equipment to be tested and certified by competent person before deployment. Supervisor
Property damage No overloading allowed.
Improper lifting pinch point Follow procedures.
Procedure Training and assistance of Banks man / Rigger
using of defective equipment ( Tools and Must be followed HILPermit
Tackles ) approved lifting plan must for crane / hydra lifting
Over loading. All equipment must be third party certified.
traffic accident Operators should be certified and valid license holder Equipment to be
inspected daily and all defects reported

3 Grinding cutting & welding of Radiation can damage Must be followed HIL hot work procedure fire watch and Site
structure platform Burns eyes and skin Use specified shielding devices and other PPE engineer/
Fire hazard Explosion may occur of correct specifications Supervisor/site hse
Explosion May cause fire Cylinder Move out any leaking cylinder
Tripping may burst Keep trolley for transportation of cylinders and chain them
Leaking gas cylinder or hoses Welders cataract Use flash back arresters
Rotating equipment sparks Burn Injury Use double stage regulatores
Damage / burst grinding wheel Lung ailments Purge regulators immediately and then turn off.
Electrocution Dermatitis Never use grease or oil on oxygen line connections and copper fittings on
Dust Hit injury / crush injury acetylene lines
Flying object eye injury Electric ShockFire / Work area should be barricated and sigage posted.
Welding radiates invisible ultraviolet Explosion Asphyxiation only trained and competent person only allowed
and infrared rays use dust mask
Improper placement of oxygen and use job specific ppe's
acetylene cylinders
Leakage / cuts in hoses
Opening – up of cylinders
Radiation harmful to naked eyes
Splinters / slag
Toxic fumes

4 Housekeeping and material Personal injury Incident / Injury Site Supervisor


removal after job complete Slip and trip Property Damage.
Dust exposure Must be used dust mask
ergonomic Followed material handling technique
Proper communication
Housekeeping awareness program to all employee

Approved By-

Prepared & Analysis by :- Danish (HSE),s.mujmdar(site incharge),


P.chinnamaharaja(site eng)
GEA PROCESS ENGINEERING
Project Name - ESP erection & commissioning(birla coper dahej) Document No:- HIL/JSA/EHS-09
Activity- fitup & assembely of 1st & 4th field
Rev-0
JOB SAFETY ANALYSIS

Location of Work : Smelter -1 ,ESP JSA No- 03


Sr. Sub Activities / Tasks Hazards Impact in case of exposure Risk Control measures (There can be multiple control measure for one Responsibility
No. hazard)
1 Work start-up Un authorized work Physical Injury Must be followed HIL permit system site engineer and Supervisor
preparation & Invalid permit Supervisor must insure that all work activities are carried out by site hse person
obtaining work permit Lack of competency competent person
Poor communication Property damage Conduct tool box talk meeting
Hast or shortcuts worker stucjk in emergency Review the method
plant emergency Responsible person will conduct inspection
Consider all potential hazards: weather, wet or slippery conditions,
overhead hazards, proximity to trails and/or visitor traffic
patterns/volume, slope, loose footing, elevation, fatigue, hazardous insects
or plants, etc.
proper communication

2 shifting & lifting of Toppling or Falling of material Physical Injury Only competent and approved operator shall be deployed for equipment Rigger teamand Site engineer and
casing panel by 80T Mechanical failure of lifting tools operations. Supervisor
mobile crane/farrana and tackles Equipment to be tested and certified by competent person before
Property damage deployment. hse person
pinch point No overloading allowed.
Improper lifting Procedure fatal Follow procedures.
using of Training and assistance of Banks man / Rigger
defective equipment ( Tools and Must be followed HILPermit
Tackles ) approved lifting plan must for crane / hydra lifting
Over loading. All equipment must be third party certified.
traffic accident Operators should be certified and valid license holder Equipment to be
Overloading due to load oscillation inspected daily and all defects reported
Collision with structure & lifting plan shall be prepare before work start
pipelines

3 Erection of scaffold for Collapsing of Scaffolding Personal Injury, followed HIL Procedure for Scaffold site engineer and Supervisor
casing panel Fall of person Fatal accident Competent scaffolding team scaffold team
assemble/work at hight Slip & trip Material damage Scaffolding Training hse person
Unauthorized modification in Property damages Scaffolding Inspection Check list before work start
scaffolding Electrocution Cordoning / barricade of Area
Erection of non standard Proper tying & handling of loose scaffolding materials
Scaffolding Use of good condition & sufficient Scaffolding materials
Gap between two scaffolding Weekly re-inspection of certified scaffold
planks maintain good housekeeping
Fall of Loose scaffolding / other Use of standard and certified full body safety harness with 100% tie off
loose Materials Proper Supervision shall be ensured
Un trained worker Suitabale & Sufficient Access at even low height provided wherever
Non inspected scaffold possible.
Improper communication
Scaffold nearby live electrical cable
Slip from ladder

4 Grinding ,cutting & Burns Radiation can damage eyes Must be followed HIL hot work procedure fire watch and Site engineer/
welding of structure Fire hazard and skin Use specified shielding devices Supervisor/site hse
platform Explosion Explosion may occur and other PPE of correct specifications
Tripping May cause fire Cylinder may Move out any leaking cylinder
Leaking gas cylinder or hoses burst Keep trolley for transportation of cylinders and chain them
Rotating equipment sparks Welders cataract Use flash back arresters
Damage / burst grinding wheel Burn Injury Use double stage regulatores
Electrocution Lung ailments Purge regulators immediately and then turn off.
Dust Dermatitis Never use grease or oil on oxygen line connections and copper fittings on
Flying object eye injury Hit injury / crush injury acetylene lines
Welding radiates invisible Electric ShockFire / Work area should be barricated and sigage posted.
ultraviolet and infrared rays Explosion Asphyxiation only trained and competent person only allowed
Improper placement of oxygen and use dust mask
acetylene cylinders use job specific ppe's
Leakage / cuts in hoses
Opening – up of cylinders
Radiation harmful to naked eyes
Splinters / slag
Toxic fumes
5 Housekeeping and Personal injury Incident / Injury Site Supervisor
material removal after Slip and trip Property Damage.
job complete Dust exposure Must be used dust mask
ergonomic Followed material handling technique
Proper communication
Housekeeping awareness program to all employee

Approved By-
Prepared & Analysis by :- Danish (HSE),s.mujmdar(site
incharge), P.chinnamaharaja(site eng)

You might also like