Site Inspection work Obstructions or Conduct a toolbox talk with all teamwork before work
preparation & restricted access, start to explain tasks and hazards associated to work
Transport of scaffold hot or cold surfaces, activities.
material to site moving of materials Follow safe scaffolding procedures and know JHA with
during operations and permit authorities to minimize exposure
transportation. to hazards, plan escape routes & be aware of wind or
heavy rain strength & direction.
1
Prepared by: CPECC HSE Department
Reviewed & Approved by: S. Sultan
Acting HSE Manager
MELUT BASIN OIL DEVELOPMENT
CPECC HSE DEPARTMENT
Palouge Power Plant II Project
Injury / damage due Plan route to avoid other personnel and equipment.
to collision / impact Signalman must give signals to move equipment in safe
with other directions.
workgroups / Be alert and observe the work environment pay attention
equipment from other team work.
Injury due to limited Ensure scaffold has adequate safe Access for work and
egress in egress for any emergency situation.
emergency Access/Egress must be free from any obstacles.
Injury / damage due Erect and dismantle all scaffolds to comply with all legal
to scaffold collapse and site requirements.
Scaffold must be erected on compacted, rigid & leveled
soil.
Scaffold must be Braced and anchored to a rigid fixed
supports.
2
Prepared by: CPECC HSE Department
Reviewed & Approved by: S. Sultan
Acting HSE Manager
MELUT BASIN OIL DEVELOPMENT
CPECC HSE DEPARTMENT
Palouge Power Plant II Project
Injury / damage Scaffold must have hand rail, mid-rail and fixed platform.
caused by Use Full body harness & to be tight 100% all time
personnel falling working at height.
from scaffolding
Serious Injury & Use independent fall arrest system. 1.8m fall limit when
Fatality caused by you are working outside of platform handrails.
persons falling
working outside
scaffolding and not
using full body
harness.
Handover of scaffold Injury as a result of Check scaffold properly before attaching scafftag. Tag
incomplete scaffold, must be signed by qualified person. Use scaffold
loose boards, checklist.
kick-plates, etc Scaffold platform must have handrail/midtrial and toe
causing slips, trips boards to prevent falling of personnel and tools.
and falls Be sure that scaffold has been erected and completed
and with safe access “Green Tag”.
3
Prepared by: CPECC HSE Department
Reviewed & Approved by: S. Sultan
Acting HSE Manager
MELUT BASIN OIL DEVELOPMENT
CPECC HSE DEPARTMENT
Palouge Power Plant II Project
Dismantle scaffold Non proper scaffold Stack scaffold gear in a safe area and remove any defect
storage material or damage scaffolding component from site. Keep site
components cause clean and in a good housekeeping.
Injury results.
Injury results from Maintain a good housekeeping at all times to reduce
untidy worksite hazards to a minimum.
4
Prepared by: CPECC HSE Department
Reviewed & Approved by: S. Sultan
Acting HSE Manager