UPPER TAMAKOSHI HYDROELECTRIC PROJECT

(Lot - 4) Khimti Substation


ELECTRICAL WORKS
Weekly Progress Report (14 Feb-21 Feb 2021)

Date: 7 march -14 March 2021


Engineer: Pradip Dahal/Shushil adhikari

Site Location: New Khimti Substation, Ramechhap

Time: 8 a.m. to 6 p.m.


Contractor's Site Activities:

Manpower:
ELECTRICAL MANPOWERS

HVAC Installation

Fire Fightening
Asst. Engineer

Unskilled labour
Skilled labour
Supervisor
Engineer

Foreman

Team

Team
Number 1 2 0 0 29 1 0 6 KEC/Friendship
CRM Test of isolators is going on.

Testing of Circuit Breaker of Line in Bay in 132kv yard was done.

Gas leakage test was done inside GIS duct.


Connection of High volatge Cable is gong on.(six connection is completed in
220kv yard)
Burried Cable termination ig going on in 132kv yard.Three numbers of cable
termination is completed in transformer side.
Fire Fightening Pipe laying is on progress.(Holiday test is going on)
steel Structure of CVT and CT reached at site.
Glanding and control cable termination is on progress.

Reason for Delays:

Manpower

Equipment

Others

Discussion With Contractor:

Contractor representative & location: Er.Madhab Maity/Er.Prabesh aryal

Testing Engineer:Er.Abishek pal/Er.Satish (From ModPro)


Points of Discussion:

Instructions:

If Any: VISTORS

SITE PHOTOGRAPHS