LIFTING PLAN
BATCHING PLANT EQUIPMENT
Name
Job Title Lifting Supervisor Construction Engineer Plants & Maintenance Manager
Signature
Date
1. Introduction 3
2. Purpose 3
3. General Note 3
4. Responsibility 4
5. Methodology 4
6. Lifting of Cement Silos 5
7. Lifting of Water Silos 9
8. Lifting of Conveyor 9
9. Lifting of Chiller 11
10. Load Charts 12
2. PURPOSE
This plan is to make sure that all personnel involved in the lifting, erection, and installation
of Concrete Batching Plant Equipment activity understand and familiar to do the work safely
and quality as per specification and requirement.
3. GENERAL NOTE
3.1 Inspection
As per the requirement, inspection shall be carried out under supervision of
Project Manager and the record maintained and kept.
3.2 Safety
3.2.1 A Pre-Task Briefing shall be conducted prior to the start of work to assign
responsibility. HSE officer and Lifting Supervisor shall be present during the
lifting activities.
3.2.2 Job Hazard Analysis (JHA) must be carried out for all crane lifts and all other
tasks that have potential risk to personnel and equipment.
3.2.3 Pre-lift study before any lifting activity.
3.2.4 Ensure all equipment and tools required for the installation is i.e. level
blocks, hammer, spanners, slings, etc.
3.2.5 Tag lines must be used to control lift
3.2.6 Ground conditions must be ready before activities.
3.2.7 Barricades and warnings signs shall be installed around lifting area of
cement silo.
3.2.8 Lifting equipment should be inspected and certified by third-party.
3.2.9 Mobile cranes and other machinery including the operators shall be
certified by third-party.
3.3 Lifting
All conditions in the procedure shall be followed. Checking of lifting equipment
shall be carried out prior to commencement of lifting works.
3.4 Assembly and erection
Assembly and erection of cement silo shall be in accordance relevant drawings and
plans.
5. METHODOLOGY
5.1 The lifting activities shall start once the concerned crews have attended the tool
box talks and pre-task briefing and understands their duties and responsibilities
and all relevant permits approved and available.
5.2 All equipment and tools to be used during the lifting shall be inspected and all
required documentations i.e. certificates and license available.
ii. The cement silos shall be shifted one by one from the temporary storage near
to the location where it shall be erected. A 50T crane and a trailer (long bed)
shall be utilized for these activities.
iii. The 50T crane shall be positioned beside cement silo temporary storage area.
Banksman # 1 shall guide the crane while positioning itself until the outrigger
are fully extended and securely planted on the ground.
iv. The trailer then positions itself near the crane guided by Banksman # 2.
v. The area shall be barricaded and signs posted to prevent access from
unauthorized personnel prior to any lifting.
vi. A cement silo shall be lifted using 2 shackles connected the eyebolts on the
side of the silo. One shackle near the top and one near the cone of the cement
silo.
vii. Sling shall be connected to the shackles. Riggerman # 1 shall guide the cement
silos while the Banksman # 1 signals the operator during lifting and loading to
waiting trailer bed.
viii. The Lifting Supervisor shall ensure loads, shackles and slings secured and
proper procedure followed during lifting.
ix. The cement silo shall be secured with slings and stopper onto the trailer bed by
Riggerman # 1 prior to removal of shackles. Shackles shall be removed by
Riggerman # 1.
x. The trailer shall move and positions near the foundation where it will be
erected. The trailer shall be guided by Banksman # 1.
xviii. Once the silo is on air the trailer can move back to the temporary area for the
next silo to be lifted. The trailer shall be guided by Banksman # 3.
xix. The silo shall be slowly tilted by lowering 50T crane while 110T crane holds it
position.
xx. The 50T crane then lower down the load until only 110T crane carries that
cement silo and load in vertical position. The 110T crane shall lift the cement
silo more if needed to ensure vertical position is achieved. Banksman # 2 shall
guide 110T crane during this process.
Releasing the hooks of the assistant crane. The silo will be totally lifted by the main crane.
xxi. The silo shall be lowered to the ground while Riggerman # 1 remove the
shackles connected to lower portion of the cement silo. A manlift guided by
Banksman # 1 shall be used when necessary if the shackle is too high to be
removed.
xxii. The cement silo shall then be moved by 110T crane lateral with moderate
lifting to the waiting foundation. The crane operator shall be guided by
Banksman # 2 while Riggerman # 2 ensures the cement silo remain vertical.
xxiii. Once the cement silo is on top of the foundation, it shall be lowered slowly
until the silo legs are centered on the steel plates in the foundation. Banksman
# 2 shall guide the operator during this process with the supervision of Lifting
Supervisor.
xxiv. The silo legs shall be welded by competent welder while the silo is being held
by 110T crane (main crane).
xxv. A man basket held by 50T crane guided by Banksman # 1 shall be used to
remove the shackles on top of the silo release the crane shackles. Riggerman #
1 shall remove the shackles and slings.
xxvi. The rest of the silos shall follow the procedure 5.3.i to 5.3.xxv.
For this lifting job: