Professional Documents
Culture Documents
(Contract No.)
May, 2019
Table of Contents
INTRODUCTION ..................................................................................................................................... 1
Project Background ....................................................................................................................... 1
Project Location and Description .................................................................................................. 1
Scope of Investigation ................................................................................................................... 1
PHYSIOGEOGRAPHY OF THE PROJECT AREA......................................................................................... 3
Soils and Topography .................................................................................................................... 3
Geology ......................................................................................................................................... 4
2.2.1 Regional Geology .................................................................................................................. 4
2.2.2 Local Geology ........................................................................................................................ 4
Climate .......................................................................................................................................... 5
SOILS AND MATERIALS INVESTIGATION ............................................................................................... 7
General.......................................................................................................................................... 7
Subgrade Soils Alignment ............................................................................................................. 7
3.2.1 Sampling of Subgrade Soil Alignment ................................................................................... 7
3.2.2 Testing of Subgrade Soils Alignment..................................................................................... 8
3.2.3 Problem Soils on the Subgrade Alignment ........................................................................... 9
Homogenous Sections ................................................................................................................ 10
3.3.1 The CUSUM Method to Establish Homogeneousness ........................................................ 10
3.3.2 Calculation of CUSUM against Chainage............................................................................. 11
Borrow Material sources............................................................................................................. 13
3.4.1 Introduction ........................................................................................................................ 13
3.4.2 Sampling and Testing Method for Borrow pits ................................................................... 14
3.4.3 Laboratory Tests and Classification of Borrow pit materials .............................................. 15
3.4.4 Materials for Embankment and Natural gravel .................................................................. 15
3.4.5 Cemented Materials............................................................................................................ 16
Quarry Sources............................................................................................................................ 17
Sand Sources ............................................................................................................................... 18
Water Sources ............................................................................................................................. 20
i
Other Construction Materials ..................................................................................................... 21
EVALUATION AND PROPOSED USE OF CONSTRUCTION MATERIALS ................................................. 23
General........................................................................................................................................ 23
Surfacing aggregates ................................................................................................................... 23
Base course crushable materials................................................................................................. 23
Subbase Construction ................................................................................................................. 23
Capping layers for improved subgrade or embankment ............................................................ 23
Water and Sand materials .......................................................................................................... 23
TRAFFIC ANALYSIS AND PAVEMENT DESIGN ...................................................................................... 24
Baseline Traffic Studies ............................................................................................................... 24
Hourly Adjustment Factor ........................................................................................................... 24
Monthly/Seasonal adjustment Factor. ....................................................................................... 24
Traffic growth projection. ........................................................................................................... 24
Generated traffic......................................................................................................................... 25
Diverted traffic ............................................................................................................................ 25
Pavement Design Standard ......................................................................................................... 25
Estimation of Cumulative Standard Axle Loading ....................................................................... 25
5.8.1 Vehicle Equivalent Factors standard axle loading on the project road .............................. 25
5.8.2 Estimated cumulative standard axle loading ...................................................................... 26
5.8.3 Traffic loading Analysis ....................................................................................................... 26
Proposed Pavement Structure .................................................................................................... 27
Design Sub grade......................................................................................................................... 27
5.10.1 Non- problematic Soils ........................................................................................................ 27
5.10.2 Low strength Sub- grade Soils. ............................................................................................ 28
APPENDICES ........................................................................................................................................ 30
Appendix 1: Trial pits log for subgrade soil alignments .............................................................. 30
Appendix 2: Detailed laboratory test results for subgrade soils alignment ............................... 31
Appendix3: Borrow pit loggings and detailed laboratory test results ....................................... 32
6.3.1 Borrow pit Logs ................................................................................................................... 32
6.3.2 Detailed Laboratory test results ......................................................................................... 33
Appendix 4: Sand pit loggings and detailed laboratory test results ........................................... 34
6.4.1 Sand pit logs ........................................................................................................................ 34
ii
6.4.2 Laboratory test results ........................................................................................................ 35
Appendix 5: Water sources- Detailed laboratory test results .................................................... 36
Appendix 6: Laboratory test results- Initial Consumption of Lime ............................................. 37
Appendix 7: Borrow pit Soil Plan................................................................................................. 38
LIST OF FIGURES
Figure 1- 1 : A map showing project route location .......................................................................................................1
LIST OF TABLES
Table 3- 1: Problem areas along the road section. ......................................................................................................10
Table 3- 2: Location of Borrow pit areas and estimated quantities .............................................................................14
Table 3- 3: Quality Classification of Borrow pit Materials ...........................................................................................15
Table 3- 4: Requirement for fill and improved subgrade .............................................................................................15
Table 3- 5: Requirement for cemented materials ........................................................................................................16
Table 3- 6: Location of Sand pits and estimated quantities .........................................................................................18
Table 3- 7: Sand source test results and specification requirements ...........................................................................20
Table 3- 8: Summary test results for water samples collected ....................................................................................21
iii
LIST OF ABBREVIATIONS
BS British Standard
LL Liquid Limit
PI Plasticity Index
LS Linear Shrinkage
CM Cemented Materials
iv
INTRODUCTION
Project Background
This Soils and Materials Report is the part of the Detailed Engineering Design report prepared for
pavement design purposes. The report also represents observations on the characteristics of insitu
soils, materials investigations and the design of the pavement structure using applicable Tanzanian
standards (Pavement and Materials Design Manual-1999).
All procedures for the materials investigations and pavement design are in accordance with the
Pavement and Materials Design Manual (PMDM-1999), Laboratory Testing Manual -2000 and Field
Testing Manual -2003.
Scope of Investigation
The field investigation has been conducted through the proposed project route locations. The
reconnaissance and materials investigations was conducted in relation to the soils and materials
1
investigation to ensure pavement design is conducted taking into consideration the prevailing
conditions of in-situ soils and intrinsic characteristics of the construction materials. In essence it
includes;
Desk study for the purpose of obtaining previous data and information on the availability and
properties of the existing material sources in Mafia Island including the as-constructed data
on the existing roads.
Reconnaissance of the existing roadways to acquaint with the dominant features of the roads
or villages including surface type and their service condition, location, top and visual in-situ
soils properties
In situ soils sampling along the identified road and villages at intervals of 250 meters for the
section starting from Kilindoni to Bweni village, Kanga.
Identification of Borrow pits and quarry sites for sampling including identification of existing
and new sites in the Mafia Island. The materials to be investigated in the laboratory in
compliance with the Laboratory Testing Manual - 2000.
Sampling of water and sand sources for construction works. The water and sand samples shall
undergo laboratory investigations to determine existence or non-existence of deleterious
salts and organic matter.
2
PHYSIOGEOGRAPHY OF THE PROJECT AREA
Furthermore, from km 28 to about 42km of this section is dominated by mostly light brown to blackish
clay and silty clay with some areas consisting of gravels. The blackish clay (black cotton soil as known),
is very plastic fine grained soils exhibiting low permeability, and thus poor drainage. These areas forms
swamps around the road due to poor drainage and topography of the area itself. Extending towards
Rasmkumbi about 10km, light brown to blackish silty SAND soil mixed with gravel mainly found. The
soil exhibits non-plastic (NP) properties with good drainage properties but poorly graded (GP).
3
Geology
In Tanzania, coastal basins include the whole of Tanzania coastal belt from Kenyan border (north) to
the Mozambique border (south). It includes the series of sub-basins e.g. Ruvu-Tanga, Mandawa and
Ruvuma basins and the Islands Offshore. The basin consists of sedimentary rocks of Upper Mesozoic
which include limestone, sandstone, shale, marls and local evaporate (gypsum, anhydrite and salt).
Most Offshore areas around the Island composed of mainly Whitish beach sands influenced by sea
wave action. Weathering and sea waves’ action on the rocks along the coastline resulted into
formation on sediments. These sediments consist of gravelly-sized limestone clasts embedded by silty
SAND matrix/groundmass to form conglomeritic limestone rocks/boulders.
The limestone strata resulted from lithification of accumulated sediments (shells and skeletal debris
of marine organism) that contain calcium carbonate forming in marine environment. These strata is
found at Kanga offshores towards the sea. This area is found suitable for extraction of construction
materials (stone quarry) for this project.
4
Figure 2- 2: Generalize Geology and Geological Section of Tanzania (Semkimwa P. et all, 2005)
Climate
The projects lies at the Coastal region of Tanzania, which due to its high elevation to about 20m AMSL,
remains relatively humid and cool throughout the year. The coastal regions i.e. Pwani and Dar es
Salaam are warm and humid, with temperatures between 23°C to 30°C through most of the year,
dipping just below 25°C in the coolest months. The monthly average temperatures for Kilindoni town
5
are usually between 24.8°C (77°F) for the cooler period and 28.3°C (83°F) for hotter periods. The
average temperature for town of Kilindoni is 26.7°C. These temperatures appear to be similar in all
areas around the island and shall be considered for Mafia District, for the purpose of this report
(Wikipedia).
Rainfall is similar for all the roads in project area, where the rainfall information indicates the average
annual rainfall is 1705mm at Kilindoni town. In general there one major rain season, with most rainfall
coming between March and May. Dry season extends from July to October.
For purposes of pavement design PMDM-1999 divides Tanzania into three environmental zones
namely dry, moderate and wet. Figure below shows climatic pattern of Tanzania regions. It has been
established that the project route falls entirely within the WET climatic zone.
6
SOILS AND MATERIALS INVESTIGATION
General
Materials investigations and characterization was carried out based on the following approach:
Investigations and characterization of alignment/centreline soils along the existing gravel road
for the purpose of carrying out structural pavement design based on traffic loading and
environment as recommended by PMDM-1999 and the Field Testing Manual -2003;
Investigations of existing and potential new borrow areas for the purposes of securing
appropriate construction materials for pavement layers and road embankment mainly for
improved subgrade (capping), subbase and base layer;
Investigations of potential existing and new quarry/stone sites for obtaining appropriate
materials for pavement surfacing and crushed tock for base;
Investigations of potential sand and water sources in order to understand their physical and
chemical suitability for concreting, mortar and paving works;
7
Figure 3- 2: Excavated pits at Chainage 0+250 RHS and 8+250 CENTRE respectively along Kilindoni-
Rasmkumbi road
Figure 3- 3: Excavated pits at Chainage 31+750 CENTRE and 41+750 CENTRE respectively along
Kilindoni-Rasmkumbi road
8
The alignment soils samples collected were taken to the laboratory for different tests. The samples
were tested according to CML-2000 Test methods. The laboratory testing conducted comprised of the
following tests;
The summary of test results for Subgrade alignment are attached and presented as Appendix 2. The
detailed Test results are presented in a separate volume
(i). Field reconnaissance and visual inspection of excavated soils along the centerline
(ii). The laboratory test CBR soaked strength less 3% (<2% in dry climatic zones).
(iii). The Laboratory test PIw>20%
The laboratory weighted Plasticity Index has shown some section to consist of PIw>20%, the list of
chainages is shown on Table 3.1 below.
The field reconnaissance has shown that, the section from km 0+00-28+00 is dominated by brown-
blackish silty SAND soil of non-plastic (NP). Furthermore, the section from 28+000 to 42+000 is
dominated by light brown to blackish silty clay and sands with gravel pockets in some areas. However,
the last 10km is encroaching the sea and the area is dominated mainly by light brown to blackish silty
SAND soil mixed with gravel.
The Analysis of the laboratory results for all sections with PIw>20% has CBR greater than 5% after 4
days soaked. In this regard, the design subgrade CBR=3%. Therefore, the soils for these sections do
not need special investigations. However, special treatment of the subgrade soil should be adopted
according to section 6.25 of PMDM figure 6.3.
9
Table 3- 1: Problem areas along the road section.
Chainage GM LL PL SL CBR Strength AASHTO Class Property
(%)
2+750 0.9 49.1 21.2 14.3 9 A-7-5 Clayey soil
26+500 0.3 45.2 20.4 12.1 6 A-7-5 Clayey soil
28+500 0.5 39.6 11.8 12.1 7 A-6 Clayey soil
28+750 0.3 25.6 8.7 7.1 9 A-6 Clayey soil
29+000 0.4 65.0 25.5 12.9 7 A-7-5 Clayey soil
29+750 0.5 43.6 17.3 12.9 8 A-7-5 Clayey soil
30+000 0.7 31.1 14.5 7.1 A-6 Clayey soil
30+250 0.4 45.2 19.3 12.1 8 A-7-5 Clayey soil
30+500 0.5 47.2 19.2 13.6 7 A-7-5 Clayey soil
30+750 0.5 39.6 11.8 12 A-6 Clayey soil
31+000 0.2 38.2 17.1 10 5 A-6 Clayey soil
31+250 0.4 36.4 15.5 10 7 A-6 Clayey soil
31+500 0.6 27.4 15.5 5.7 6 A-6 Clayey soil
31+750 0.5 43.6 17.3 12.9 A-7-5 Clayey soil
33+000 0.3 36.2 14.0 11.4 5 A-6 Clayey soil
33+250 0.5 40.8 16.2 10.7 10 A-7-5 Clayey soil
33+500 0.6 40.1 17.4 10 5 A-7-5 Clayey soil
33+750 0.2 41.3 19.9 11.4 10 A-7-5 Clayey soil
34+000 0.3 46.3 18.5 13.6 7 A-7-5 Clayey soil
35+750 0.4 52.0 21.5 15.7 6 A-7-5 Clayey soil
36+750 0.7 42.2 17.5 11.4 6 A-7-5 Clayey soil
46+500 0.2 22.5 12.9 5 A-7-5 Clayey soil
Homogenous Sections
Si = Xi − X m + Si−1
where,
Xi= CBR at chainage i
Xm = Mean CBR
Si = Cumulative sum of the deviations from the mean CBR at Chainage i
10
Using the cumulative sums, the extent to which the measured CBR values on sections of road vary
from the mean CBR of the whole road can be determined. Changes in the slope of the line connecting
the cumulative sums will indicate non-homogeneity.
40
35
30
25
20
CUSUM
15
10
0
0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48 50
-5
-10
-15
Chainage
The design of improved subgrade layers depends on the subgrade CBR design determined in the soil
surveys and assessments of the field data. The representative CBR, i.e. CBR design, which is the 90th
percentile value, would then be calculated as recommended in the PMDM-1999 (Chapter 5,
subsection 5.2.3).
This road is divided into five (5) homogenous sections with different design CBR. Design CBR are
determined as below;
11
(i) Section 1-from Kilindoni (Ch. 0+000 to 12+500)
CBR (%)
8
CBR design 7
6
5% 5
4
3
2
1
0
0 2 4 6 8 10 12 14 16 18 20 22 24 26 28
Tests
CBR design-Section 2
20
90%-ile value 18
d=0.1(n-1) 16
n=36, d= 3.5 14
90%-ile= 6.0 12
CBR (%)
10
8
CBR design
6
6%
4
2
0
0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38
Tests
CBR design-Section 3
20
90%-ile value 18
d=0.1(n-1) 16
n=21, d= 2.0 14
90%-ile=5.0 12
CBR (%)
10
CBR design 8
6
5%
4
2
0
0 2 4 6 8 10 12 14 16 18 20 22 24
Tests
12
(iv) Section 4 (Ch. 40+000-45+500)
CBR (%)
10
8
CBR design
6
6%
4
2
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13
Tests
10
CBR design
6%
5
0
0 1 2 3 4 5
Tests 6 7 8 9 10
3.4.1 Introduction
Mafia Island is characterized mainly by SAND and LOAMY soils, much of Sand soils exposed over beach
extended to inland areas. However, offshore areas are characterized by sedimentary rocks and gravels
which are suitable for construction works. Due to fewer construction projects took place in Mafia, few
borrow pits sources have been established and yet unexploited to their full capacity. However, due to
variation in engineering properties caused by existence of silty SANDS and silty CLAYS, the available
and existing borrow pits sources are few mainly near to or close to the offshore area whereby the
materials are characterized by the formation of sedimentary rocks. These areas include BWENI, JIMBO
KIBAONI and KANGA. The existing pits were found at BWENI, JIMBO and KIBAONI. However, KANGA
Borrow pit was recently identified by TANROADS and has good gravel and stone quarry.
13
3.4.2 Sampling and Testing Method for Borrow pits
The pattern of trial pitting for existing and new pits was decided at randomly order within the selected
locations depending on the topographical features and materials distribution within the source. The
average thicknesses of the material strata of interest (overburden or gravel) were determined from
trial pit profiles. The data obtained from trial pit logs were therefore used to subdivide the borrow
area into segments comprising materials of similar characteristics. At least four (4) bulk samples of
materials were taken from each borrow pit area. The summary of the borrow sources with the
estimated quantities are as shown in Table below. Note that, the Borrow pit Soil Plan is presented in
the Annex 6.
Figure 3- 5: Materials location plan (borrow pits, sandpits, quarry site and water sources) in Mafia.
14
3.4.3 Laboratory Tests and Classification of Borrow pit materials
The samples taken in the listed borrow pits above have been taken to the Laboratory for testing. The
tests conducted to assess their suitability include Grading, Atterberg Limits, Proctor and 4 days soaked
CBR. Borrow pit loggings and detailed laboratory test result have been presented in Appendix 3.
Source: Pavement and Materials Design manual-1999, table 5.5 and table 5.6
15
3.4.5 Cemented Materials
Due to the climatic condition of area, the subbase layers may require being constructed using
cemented materials. The study shows that, the available borrow pits have materials that meet the
requirement for G15, therefore these borrow pit could be utilized for Cemented materials type of
treatment. The laboratory trials tests on Initial lime consumption have been conducted at University
of Dar es Salaam on the respective borrow pits. The test results for ICL for the selected borrow pit
materials is presented below;
16
Quarry Sources
Stone quarry materials is required for production of aggregates for concrete works, production of base
course pavement layers (CRR &CRS) and production of bituminous surfacing pavement layer. Hard
stone samples from Kanga quarry sites were taken for laboratory testing. Following tests were carried
out according to BS 812; BS 812-Part 2;BS 812-Part 111; CML Test No. 2.9, Ref. ASTM C 131-89; CML
Test No. 2.10, Ref. ASTM C 88-90; AASHHTO Designation T 182-84;
Ten Percent Fine Value at dry and wet conditions (TFV dry and TFV wet)
Aggregate Crushing Value (ACV)
Aggregate Impact Value (AIV)
Water Absorption
Sodium Sulphate Soundness (SSS)
Bitumen Affinity
Water Absorption test
Specific gravity
Los Angeles Abrasion test
Aggregates samples were collected from existing Kanga Quarry site in Mafia Island and Lugoba Quarry
in Bagamoyo. Kanga quarry is located at 36.8km from Kilindoni ferry terminal while Lugoba Quarry is
located at 275km from Nyamisati ferry terminal. This means that, the aggregates shall be shipped by
boat from Nyamisati to Kilindoni Port (start of the project) thereafter to the project site. Strength
tests were performed and the results are presented in the table below. The laboratory tests were
attached as Appendix 3 for reference. Not that, the specifications for Aggregates is according to BS
812: 2-1975 test method.
Table 3- 6: Summary test results for Kanga and Lugoba Quarry sites
TEST DESCRIPTION KANGA LUGOBA REQUIREMENT REMARKS
Specific Gravity 2.52 2.85 Min.2.6 Kanga is Light
Water Absorption 1.94% 0.09% Less than 2% OK
Bitumen Affinity ˃95% >95% Min 95% OK
Aggregate Crushing Value (ACV) 23% 19.3% Max. 30% OK
Ten Percentage Fine Value (TFV)-dry 157kN 216kN Min.110kN OK
Ten Percentage Fine Value (TFV)-wet 132kN 161 Min.75% of Dry OK
Aggregate Impact Value (AIV) 21% 17.6% Max. 30% OK
Sodium Sulphate Soundness (SSS) 0.7% 2.4% Less than 7% OK
17
Both quarry aggregates found to meet the minimum strength, however the Kanga aggregate quarry
has slightly less dense than minimum requirement of aggregates according to BS 812:2-1975 test
method. According to PMDM, the aggregates from Kanga stone Quarry meet the requirements for
construction of base course pavement layer, surfacing and concrete works.
The stone quarry found at Kanga site meets the minimum requirement for aggregates required for
surface dressing for traffic AADT <1000 in which the minimum TFVdry is 120kN (refer table 10.2,
PMDM-1999). However, due to increase of commercial and goods vehicles, the AADT is expected to
grow than current state to more than AADT >1000. Therefore, superior aggregates, i.e. granite is
recommended for surfacing. In this regard, the Lugoba stone quarry has been tested and meet all
requirements for surfacing aggregates for all traffic levels.
Sand Sources
Potential and Existing Sand sources were investigated along the project area. Three (3) sand sources
and sampling were found at Dongo, Kiegeani and Kirongwe. The sources of sand pits were investigated
by sampling and performing sieve analysis to ascertain their suitability for concrete works. Location
of sand pit sources and estimated quantities is presented in the table below.
18
SP03 KIRONGWE 22.00 0.60 LHS 3.0 648,848 296,150 1,058,094
Testing was done at University of Dar es Salaam; Building Materials Laboratory and the following tests
were performed;
Particle Size Distribution(PDS)
Chloride content
Sulfate content
Organic impurities
The grading of these sources were checked to verify the compliance of grading requirements for fine
aggregates according to BS 812-103.1. The graph for sand grading envelopes for each sand pit have
been developed and presented hereunder in the figures below;
19
Figure 3- 10: Grading envelope for Kirongwe sandpit.
The chemical impurities in the sand contents have been checked to enable the consultant decide on
the contamination of the materials in question. The results have indicated that, all sand pits have low
chemical contents for Sulphate (<0.7%) and Chlorides (<0.01%). %. The organic impurities (content) of
the sand samples is to be ≤0.5%. Sand pit loggings together with detailed laboratory test results have
been attached as Appendix 4.
It is concluded that all proposed sand sources were found to meet grading requirement and other
laboratory tests hence suitable for construction works. It has also noted that, the sand in two sand
pits consist of high organic content due to decomposition of plant remains. It is therefore
recommended that these sand pits to be abandoned. It is recommended that, Kiegeni sand pit to be
utilized for concrete works on the construction of proposed road projects. Furthermore, before
extracting sand, 450mm depth overburden should be removed to ensure that the sand is not
contaminated by organic materials.
Water Sources
The water samples have been collected from different source to ensure sufficient water is available
during construction. The water sources include Ndagoni Hippo dam and Ndagoni stream crossing the
culvert along Kilindoni-Rasimkumbi road at Baleni area. Both Dam and the Stream crossings at
20
Ndagoni is perennial and has large quantity of water for construction works, hence the proposed
project.
The chemical tests for the samples have been conducted to ascertain the quality of these proposed
sources. The summary of the test parameters and their quality have presented in the table below. The
detailed test results were attached on Appendix 5.
Parameters Units
Acid content(pH) 6.58 6.81 5.5- 8.5
Chloride(Cl-) mg/L 50.0 10.0 300- 600Mg/l
The results have indicated that, all water sources proposed have slightly acid and with slightly alkaline.
Therefore, the degree of aggressiveness is absolutely low and is suitable for construction works.
Figure 3- 11: Shows water sources at Ndagoni Hippo dam and Ndagoni stream
21
section 7104 shall be complied promptly to verify the quality of the materials brought to site for
construction works.
22
EVALUATION AND PROPOSED USE OF CONSTRUCTION MATERIALS
General
Owing to the design requirements provided for bituminous surfaced roads with possible unbound or
bound pavement layers, the utilization of sources of materials can be recommended as follows:
Surfacing aggregates
The Kanga existing crushing site is definitely suitable in quality and quantity for production of crushed
materials for base course and surfacing aggregates for low traffic volume. However, for high traffic
volume, chippings shall be high strength stone such as granite. In this regard, it is recommended
aggregates from Lugoba for chipping materials.
Subbase Construction
Due to the climatic condition of the area, it is recommended that, the subbase to be constructed with
impermeable layer to restrict movement of water to the subgrade layer. Therefore cemented layer,
CM category is recommended for this purpose.
23
TRAFFIC ANALYSIS AND PAVEMENT DESIGN
Macroeconomic forecasts show a decrease in GDP growth at the national level of about 6.7% in 2018,
down from 7.1% in 2017. According to Economic report, in 2008, M/s Intercontinental Consultants Pvt
prepared a generalized traffic forecast model for TANROADS for use on Tanzania roads. Proposed
passenger and freight growth rates ranged between 6-8% for a 20-year analysis period. Therefore, the
design traffic growth rate is taken as 8%.
24
Generated traffic
This is the vehicular traffic that is expected to use the project road as a result of improvement as a
result of subsequent lowering of user costs. Most of this traffic will come from increased use of the
improved facility from existing base traffic. It is commonly accepted as a good approximation that the
traffic to be generated by the project is primarily linked to the decrease in vehicle operating costs
(VOC).According to Economic Report, short term generated traffic will arise from increased number
of trips of existing operators on reduced surface roughness on upgrading the road. In the medium and
long term there will be increased demand for transport due to increased touristic economic activities
in Mafia District council. Therefore, the generated traffic forecasted due to tourism growth is
considered as 3.4% (economic report) and this will result into the growth of freight vehicles
respectively. Therefore, the adjustment factors for generated traffic is taken as 3.4% for all traffic
categories.
Diverted traffic
This is traffic that is expected to be attracted to the project road after widening and
improvement of intersections. Economic report prevails, due to the nature of the Island, there
is no possibility of vehicles to divert from east to north, hence to the project road. Therefore,
taking into consideration this situation, the diverted traffic is taken as 0% of the total traffic.
5.8.1 Vehicle Equivalent Factors standard axle loading on the project road
Due to unavailable passenger and goods vehicles, the consultant has adopted rigorous
factors obtained from previous nearest project along Dar es Salaam-Kibiti-Lindi -Mingoyo
road (Kurasini station). Therefore, the equivalence factor, VEF is taken as 1.80 for Low
Good vehicles (LGV); 1.80 for Medium Goods Vehicles (MGV), 4.1 for Heavy Goods
25
Vehicles (HGV), 3.73 for Very Heavy Goods Vehicles (VHGV) and 3.9 for buses in all
directions.
It is also estimated that, the Quantity for construction material is 374,000m3 for 52km
will be moved on the road during construction transported with trucks with 15m3
capacity and having equivalence factor of 12.5 when fully loaded.
374,000
Equivalency for this is 15
𝑥12.5 = 311,700
26
Kirongwe
2 Wet TLC1
(Bweni-Kigamboni) 0.56x106
Bweni
3 Wet TLC05
(Rasimkumbi-Kirongwe) 0.35x106
The design of improved sub-grade is referenced on Materials Report section 3.3.2 design CBR
using CUSUM method into homogeneous sections. The overall design CBR is 5%, therefore,
the minimum improved subgrade layer is G7 materials.
27
5.10.2 Low strength Sub- grade Soils.
A problem soil is a soil with low strength and/or exhibit unfavorable characteristics such as
expansiveness. The Soil problem soil is regarded as soil with low strength when subjected to the
following conditions.
(i). Field reconnaissance and visual inspection of excavated soils along the centerline
(ii). The laboratory test CBR soaked strength less 3% (<2% in dry climatic zones).
(iii). The Laboratory test PIw>20%
According to the Materials report, the weighted has occurred from various location, starting r from
chainage 2+750 to 46+500, however these locations are dominated by silt-clayey sand with very good
strength. The minimum CBR strength along the section with PIw>20% is 5%. This indicates that, the
soils consist of silts/sand and soft rocks from sea shores. In this regard, some treatment should be
adopted where the soil conditions are changing.
28
References
i. Baseline Traffic Counts in Tanzania Mainland and Establishing a Comprehensive
TRAFFIC Census Methodology for TANROADS, 2008.
29
APPENDICES
30
IN-SITU SOIL SAMPLING AND MATERIAL INVESTIGATION SUMMARY
ROAD SECTION: KILINDONI- RASMKUMBI
ROAD LENGTH: 52.3 Km
Date: 4th -9th March 2019
CHAINAGE SAMPLE DEPTH LEGEND DESCRIPTION PHOTO
(km + m) NO. (mm)
0+000 LHS 1
light brown coarse gravel silty sand soil
300
G15
700
0+250 RHS 2
blackish silty sand topsoil
200
1000
0+500 CENTRE 3
light brown silty sand soil
350
1000
0+750 LHS 4
light brown silty sand soil
400
1000
1+00 RHS 5
blackish soil sand coarse gravel
300
whitish bolded gravel silty sand soil
450
1000
1+250 CENTRE 6
blackish soil sand/coarse gravel
400
1000
1+500 LHS 7
light brown silty sand soil,coarse gravel
400
1200
900
1000
2+250 LHS 10
blackish silty sand soil
200
1000
2+500 RHS 11
300 blackish soil sand
1000
2+750 CENTRE 12 150 blackish soil
brownish silty soil sand
300
1000
3+000 LHS 13
light brown soil (imported)
300
1000
1000
3+500 CENTRE 15 100 blackish sand soil
1000
3+750 LHS 16
G15
300
1000
4+00 RHS 17
blackish silty sand soil
300
1000
4+250 CENTRE 18 100 blackish soil
blackish silty sand soil
300
1000
4+500 LHS 19
light brown soil sand
200
brownish sand
1000
4+750 RHS 20
300 light brown imported soil sand gravely
white sand
1000
5+000 CENTRE 21 100 blackish soil
1000
5+250 LHS 22
light brown soil sand imported
300
blackish silty soil sand
450
1000
600
1000
5+750 CENTRE 24
light brown silty sand soil coarse gravel
400
1000
1000
6+250 RHS 26
light brown silty sand soil
350
1000
6+500 CENTRE 27 100 light brown soil
1000
6+750 LHS 28
light brown coarse gravel soil
300
800
darkish silty sand soil
1000
1000
7+250 CENTRE 30
light brown soil sand (imported)
200
1000
7+500 LHS 31
blackish silty sand soil
300
1000
7+750 RHS 32
light brown coarse gravel soil
300
1000
8+000 LHS 33
light brown silty sand soil
300
1000
8+250 CENTRE 34
reddish silty sand soil
200
1000
9+000 RHS 37
1000
9+250 CENTRE 38
light brown coarse gravel soil
150
1000
9+500 LHS 39
blackish soil sand
150
1000
9+750 CENTRE 40
800
light brown silty sand soil
1000
1000
10+250 CENTRE 42
1000
10+500 LHS 43
blackish soil sand
200
1000
10+750 CENTRE 44
ligth brown silty sand soil
200
1000
11+000 LHS 45
blackish silty sand soil
300
1000
11+250 CENTRE 46
1000
11+500 LHS 47
blackish soil
200
1000
11+750 CENTRE 48
light brown soil sand coarse gravel
300
1000
12+000 RHS 49
blackish soil
150
1000
12+250 CENTRE 50
1000
12+500 LHS 51
blackish silty sand sol
300
1000
12+750 CENTRE
light brown soil sand coarse gravel
300
52
1000
13+000 RHS 53
blackish silty soil sand
200
1000
13+250 CENTRE 54
light brown soil sand
350
1000
13+500 LHS 55
blackish soil sand
150
1000
13+750 CENTRE 56
light brown coarse gravel soil
350
1000
14+000 RHS 57
1000
14+250 CENTRE 58
light brown gravelly soil
350
1000
14+500 LHS 59
blackish soil
150
1000
14+750 CENTRE 60
light brown soil sand coarse gravel
400
1000
15+000 RHS 61
light brown soil sand
250
1000
15+250 CENTRE 62
light brown soil sand
300
1000
15+500 LHS 63 100 blackish soil
1000
15+750 CENTRE 64
light brown silty soil sand
300
1000
16+000 RHS 65
blackish silty sand soil
300
1000
16+250 LHS 66
300 light brown silty sand soil
1000
16+500 CENTRE 67
1000
1000
17+000 CENTRE 69
blackish soil
200
1000
17+250 LHS 70
light brown soil sand
200
1000
17+500 CENTRE 71
light brown silty sand soil
200
1000
17+750 LHS 72 100 brownish soil
1000
18+000 CENTRE 73
blackish silty sand soil
300
1000
18+250 RHS 74
light brown sand soil
300
1000
18+500 CNTRE 75
blackish silty sand soil
400
1000
18+750 RHS 76
light brown soil gravelly
400
1000
19+000 CENTRE 77
1000
19+250 LHS 78
G15
300
1000
19+500 CENTRE 79
blackish soil
150
1000
19+750 RHS 80
light brown soil coarse gravel
200
1000
20+000 CENTRE 81
light brown soil coarse gravel
200
blackish soil
400
1000
1000
20+500 CENTRE 83
light brown gravelly soil
200
1000
20+750 RHS 84 100 light brown soil sand
1000
21+000 CENTRE 85
1000
21+250 LHS 86
brownish silty clayish soil sand
200
1000
21+500 CENTRE 87
light brown clayish soil sand
300
1000
21+750 RHS 88
blackish silty sand soil
200
1000
1000
22+250 LHS 90
light brown silty sand soil
250
1000
22+500 CENTRE 91
blackish soil
200
1000
1000
23+000 CENTRE 93
1000
23+250 LHS 94
1000
23+500 LHS 95
light brown coarse graavel soil
300
1000
23+750 CENTRE 96
blackish soil sand
200
1000
24+000 RHS 97
brownish silty sand soil
300
1000
24+250 CENTRE 98
blackish silty sand soil
300
1000
1000
25+250 CENTRE 102
light brown silty sand soil
200
1000
1000
1000
26+000 RHS 105
blackish soil
300
1000
1000
1000
26+750 CENTRE 108
light brownish silty soil sand
300
1000
1000
1000
28+250 CENTRE 114
light brown soil sand
300
1000
1000
1000
29+000 RHS 117
light brown clay soil
150
1000
1000
1000
29+750 CENTRE 120
1000
1000
yellowish soil
1000
30+500 LHS 123
blackish clayish soil
300
1000
1000
1000
31+250 CENTRE 126
yellowish soil
200
1000
1000
1000
32+000 RHS 129
blackish silty sand soil
200
1000
1000
1000
32+750 CENTRE 132
silty clay sand soil
250
1000
1000
1000
33+500 LHS 135
blackish soil
300
1000
1000
1000
34+250 CENTRE 138
1000
700
soft rock
1000
1000
35+000 RHS 141
blackish silty sand soil
200
700
boulders
1000
boulders
1000
rock boulders
1000
35+750 CENTRE 144
blackish silty sand soil
300
1000
1000
350
soft rock
1000
36+500 LHS 147
blackish silty sand soil
300
1000
1000
1000
37+250 CENTRE 150
blackish silty sand soil
250
1000
1000
1000
38+000 RHS 153
blackish silty clay soil
200
1000
1000
1000
38+750 CENTRE 156
light brown coarse gravel soil
200
1000
1000
1000
39+500 LHS 159
blackish soil
300
1000
1000
1000
40+250 CENTRE 161-B
light brown soil sand
200
1000
1000
1000
41+000 RHS 164
blackish silty sand soil
350
1000
1000
1000
41+750 CENTRE 167-A
light brown silty sand soil
200
1000
brownish soil
1000
1000
42+500 LHS 169
light brown silty sand soil
250
1000
1000
1000
43+250 CENTRE 172
blackish soil sand
250
1000
1000
1000
44+000 RHS 175
blackish silty soil
250
1000
1000
1000
44+750 CENTRE 178
blackish silty sand soil
200
1000
1000
45+500 LHS 181
blackish silty sand soil
350
1000
1000
350
1000
46+250 CENTRE 184
light brown soil, course gravel
300
rock
1000
1000
bouldered rock
1000
47+000 RHS 187
1000
400
rock
1000
700
rock
1000
47+750 CENTRE 190 100 blackish soil/topsoil
1000
rock
1000
48+250CENTRE 192
1000
48+500 LHS 193 100 light brown brown soil with coarse gravel
rock
1000
rock
1000
rock
1000
49+250 CENTRE 196
brownish gravel with soil
200
rock
1000
49+500LHS 197
light brown soil with gravel
200
rock
1000
49+750CENTRE 198
blackish silty sand soil
200
1000
light brown soil with coarse grvel
1000
400
rock
1000
Appendix 2: Detailed laboratory test results for subgrade soils
alignment
31
Appendix3: Borrow pit loggings and detailed laboratory test results
32
BORROW PIT NAME DEPTH(mm) LEGEND DESCRIPTION PHOTO
1. KANGA
blackish silty sand soil
200
1500
2. BWENI
light brown soil sand
300
1700
3. JIMBO
light brown silty clayish sand soil
250
1800
4. KIBAONI
light brown soil sand
300
1600
6.3.2 Detailed Laboratory test results
33
Appendix 4: Sand pit loggings and detailed laboratory test results
34
SAND PIT NAME DEPTH(mm) LEGEND DESCRIPTION PHOTO
1. DONGO (existing sandpit)
blackish silty sand soil
150
1700
2. KIEGEANI(existing sandpit)
light brown silty sand soil
200
whitish sand
2000
2
3. KIRONGWE(existing sandpit)
blackish silty sand soil
200
whitish sand
2500
3
6.4.2 Laboratory test results
35
UNIVERSITY OF DAR ES SALAAM DEPARTMENT OF STRUCTURAL AND CONSTR. ENG.
P.O.Box 35131 Tel 2410500/9 Ext. 2861
-~
~-
-~~~~
STRUCTURES AND BUILDING MATERIALS LABORATORY
TEST REPORT
LIMIT OF CLAY & SILT CONTENT (SAND) =< 3'}'o (TZS 58 Part 2:1980)
LIMIT OF CHLORIDE CONTENT =< 0.01 '}'o (BS 58 EN 12620: 2002+AL:2008) __ ..~..,-·:::-· ..•
LIMIT OF SULFATE CONTENT= < 0 . 2'}/o (BS EN 12620:2002 + AL:2008) .~·"~';,~~--~~·fl~ti~"~;,~~ri;~,?~~)'~
:\ . :i: (.~b·
;/.-§' •'·'I'·'·.f·E~/',}.'' '\
/ ·~ ~ ~
•.. 'f'<. v~ · - ·.:· • \\
'/) "'· ...
.........-
UNIVERSITY OF DAR ES SALAAM
DEPARTMENT OF STRUCTURAL & CONSTRUCTION ENGINEERING
[I]
Tel 2410500 /9 Ext. 2861 Telegram Univeng
Direct line 2410500 DarEs Salaam
Our reference SCE 2019 Fax 2410114
Your reference E-mail head ste @ce.udsm.ac.tz
TEST RESULTS
SIEVE ANALYSIS BS 882
zone 2 sieve curve for sand and grdlng limits for zone 2
lower limit zone 3 pper/Limit ZONE Sand
0.08 1 . 100
_,
.-- ......
0 0 90
0.15 0 10 3 .>
.!!
.t:
60
70
60
I
_,_ ..,..
en 50
"0
,,
0 .3 8 30 25 :5
40
30
_A' _/
en ..;';/
20
0.6 33 59 57 ."'
c:
'iii
c.
10
0
~
1.18 55 90 91 ;!. 0.075 0.15 0.3 0.6 1.18 2.36 4.75 9.5 19 37.5
s/slze
2 .36 75 100 100
4.75 90 100 100 I -- - - u p per limit zone 2 --Sand I
9 .5 100 100 100
19 100 100 100
37.5 100 100 100
...... ,,
Date ........ I/t/.?.::17.
.... .. ......... ...
Signature ~., .,
UNIVERSITY OF DAR ES SALAAM
DEPARTMENT OF STRUCTURAL & CONSTRUCTION ENGINEERING
[I]
Tel 2410500 /9 Ext. 2861 Telegram Univeng
Direct line 2410500 Dar Es Salaam
Our reference SCE 2019 Fax 2410114
Your reference E-mail head ste @ce.udsm.ac.tz
TEST RESULTS
SIEVE ANALYSIS BS 882
zone 2 sieve curve for sand and grdlng limits for zone 2
lower limit zone 3 pper/limit ZONE Sand
~~f
1.18
I :1 I 1'!1 11111 11 1
55 90 85 ,'t 0.075 0.15 0.3 0.6 1.18
s/slze
2.36 4.75 9.5 19 37.5
2.36 75 100 98
4 . 75 90 100 100 I -- - - upper limit zone 2 - - Sand I
·-·· ·-...
9.5 100 100 100 -
19 100 100 100
37.5 100 100 100
~ ·~ "' j_ll.fiO~.i\'U"' -G· t.\f\1'tn•-~· · .., .,
,·c.o ~
. iiD\14 •i . .·.'
5/<J/.?:!.:.J'J........
Date .........
. ~;;., :.:;
;c:- '
.
S1gnature HOL!........ .. .... .. ............ .. ...........,.,~ ·:'"
' 1tt.
..; ....
., .h .,..,..,
"! -~ .:;,11/f.;tsn-.- Ol- ;;~~~:-~. -·
. . ~~·~:.,~ ==..---:-~
UNIVERSITY OF DAR ES SALAAM
DEPARTMENT OF STRUCTURAL & CONSTRUCTION ENGINEERING
~
Tel 2410500 /9 Ext. 2861 Telegram Univeng
Direct line 2410500 Dar Es Salaam
Our reference SCE 2019 Fax 2410114
Your reference E-mail head ste @ce.udsm.ac.tz
TEST RESULTS
SIEVE ANALYSIS BS 882
zone 2 sieve curve for sand and grdlng limits for zone 2
~·
lower limit zone 3 pper/Limit ZONE Sand
Hl liHtfr
0.08 0 0 0
0.15 0 10 1
0.3 8 30 7
0.6 33 59 28 'iii
:::
10
0
c.
1.18 55 90 85 ~ 0.075 0.15 0.3 0.6 1. 18 2.36 4.75 9. 5 19 37.5
s/slze
2.36 75 100 98
100 100 -- --upper limit zone 2 --Sand I
4.75 90
9.5 100 100 100 . ~·~ -
.. . ,.....c-·.-..
~ -.
,_. .c ~)\/\11\~~ ·~1 ·~!1N;n~\j,~':~~.
19 100 100 100 /".;'<> ~ ..\r.. "1:5ll r1G IJfi· ,:· ' 'lt~ -,
~ ~·<- c"~·
··~\. ..,. ·L·r• d• ·,
l ~"'-
. >.,'!.! '1'<.7', ..•
37.5 100 100 100 ·'? "' , ·\
" ---~., ~.r·.~~r~~ ~~,·l.\\
-< :Z I ;
:n:
..., ..
J..fct./..?:PJ..i. . . ..
Date ............ ..
.','
AGGREGATE IMPACT VALUE
Material: Aggregate
Source
I
.,.No.
Date: 9/4/2019
Tested By: Yohane Lusega
Checked By: Marco M.Bisake
Approved By: Rachel Henry
Test 1 Test 2
WeiQht of dry sample (g) 350 .0 356.0
WeiQht retained on 2.36 mm sieve (Q) 277 .0 282 .0
Weight pasing 2.36 mm sieve (g) 73 .0 74 .0
Difference A- (b+c) I Nil Nil
Aggregate Impact value (%) 20.9 20 .8
Remarks
Laborato
!.. ~
. ' .,
I. .J.
Material: Aggregate
Sample No:
Date: 9/4/2019
ested By: Yohane Lusega
Checked By: Marco M.Bisake
Approved By: Rachel Hen
Trial 1 Trial 2
Weight of dry sample (g) 2629 2710
Weight retained on 2.36 mm sieve (g) 2015 2075
Weight pasing 2.36 mm sieve (g) 614 635
Difference A- (b+c) Nil Nil
Aggregate Crushing value (%) 23.4 23.4
Remarks
Highway Laboratory
r "''l'-'~'
. .J'tv ..
.,
'1
. ., ::
~
!·lc;·i·: ~l- ~tC:·::,1~ . :·t i·.:.' ~ . ··-;~J !.:r~~tor:v
':·· . .,. .,,., ......... , .~ -. ,,_.,, ·· ··~:,. · '] .,. ~..'1!''~1 ;;:;r., ·
tu . \\ .. J.1..~·· .. : :•.. ·'·:··• ~t.J l .:·:...... ,: \.\..t: .. ~.;........ t ... r- •·0
11
t.) ~:-~.\'\/f, .\"~~~-~~.'/ ;; f. t .... ,..'·. ~~/)··· ~...:·;J.a.'itHl
E 0. Btm :i::J D 1
Da!i'~es~r.;alaa.m ·· Tai11.ania
LOS ANGELES ABRASION TEST
CML TEST NO. 2.9, Ref. ASTM C 131-89
Test Results
~ -
JJ.l'l.CIU.GJl
• i X.Ji;.,-
JL.t6., '-·r~
•. ,.. . . ~; ~; •• · ' , , ·
....... . . . ... _ \
COARSE AGGREGATES
According to BS 812 Part 2
TEST RESULTS
Test 1 Test 2
Bulk Specific Gravity saturated surface dry basis B/(B-C) 2.590 2.546
Highway Laboratory
I~·
~{1,.''; .-l>
'',-··;
u.• ,~ .-··. .·...· ·J. '
.. .. i.' ... . ~ ·
·, · ' .,1_,•o.
r.>ept. ornau£110l.~,.~: r. ;.. {:. ;.:.\-.. ~.):i:.jc' .:. \..:.~!;. ;
,l
UniVCl'Sit~}' vf:_:;,:;J-·C':>;;r~l2.".:.m
P. 0. B<'"- 35131
Dar-es·sa}aa111" -ranzanla
SOUNDNESS OF AGGREGATE BY USE OF SODIUM SULPHATE
Consultancy Service of Feasibility Study, Environmental and Social Impact Assessment, Detailed
Project: Engineering Design and Preparation of Tender Documents for the Upgrading of Kilindoni-
Rasimkumbi road (52.3 Km) to Bitumen Standard
Material: Aggregate
Source:
Sample No:
Date: 9/4/2019
Tested By: Yohana J. Lusega -
Checked By: Marco M.Bisake
Approved By: Rachel Henry
(..c...~.
. ,. .· ·'"
·
..... .. : ,:!U
f)ept. Of Trnl~T<::rt..:. : .: 1.'. '.i ~ . '::, . " ..
Univers.H:t of:i_u·-:::.:;-~ .~' __ :~_, ,
P. 0 . Bo3c35 13-].
Dar-es..saJ.a.am ·• T'.wzania
TEN PERCENT FINES VALUE
Material: Aggregates
IS:ornnl<> No:
9/4/2019
Marco M.Bisake
Rachel Henry
TEST RESULTS
Remarks
I ucJft~:\:,
!l.l u~..wl ......i.,)·"••"-·;. 1
r)ept
, • ~.u...-...~t:J • .11. .. -:~·~_:-"' •- ·" ~:- ''"·"!'nic··~!
...... ~vL.I..v- ..~ .. - a:.t ED•'
·w
Umvers1ty m J..!.::.r~cs~s~~hnm
P. 0 . Box35131
Dar-es~salaam ~ Tanzania
TEN PERCENT FINES VALUE
Material: Aggregates
3/12/2018
TEST RESULTS
Remarks
f)'ept
~.
or•p ..,..,, ~., ... ,...·: ... I,:, I '-. , •. .,.·z-,-!"'' 1 E···
.~~ a.~.:.... ..t·"'~-H...... lr..l~.... ~~· ... ·... ...... ~ .•.n\.-\..... t l . '••-~ . ~\
# ,.. ~
( .~(;.
!)e,.;.t c:.
. . ...._,. , !'.:~~ .......ij 2...~~
Oui·.-.;.d.:. .. '.. .. .. , . J.:a::-:::1
p 0 . n::l:.tJU5l3 1
D<1r-es~saiaam ~ Th.uz..arua
Appendix 5: Water sources- Detailed laboratory test results
36
UNIVERSITY OF DARES SALAAM DEPARTMENT OF STRUCTURAL &
CONSTR ENGINEERING
A
CLIENT: MHANDISI CONSULTING ENGINEERS CO.LTD
TEST RESULTS :
NDAGONI BRIDGE WANGONI HIPPO DAM
Acid content (pH) 6.58 6.81
Chloride (cn mg/1 50.0 10.0
Sulfate (S0 42+) mg/1 35.6 12.0
Magnesium(Mq 2+) mg/1 1.02 11.3
Ammonium (NH4+) mg/1 110 20
E/Conductivity_ - -- - - ---
50.2 81 -- - - --- -- - -
The values set by DIN 4030 for various attack are listed below.
.. /i
,:l·t' J/ i"\..1'' u -~ . - :i ..
I• X,\. I , j>\ ol\ " ' ' . ~ • _./
•,•.:t.fli',•?C•~' 0~_.;:;:
\- ._.~,,'(~.:,.··
"'"~~~~;(,;!'~;;::.. ;
Appendix 6: Laboratory test results- Initial Consumption of Lime
37
Appendix 7: Borrow pit Soil Plan
38
Consultancy services for Feasibility Study, Environment & Social Impact Assessment,
Detailed Engineering design and Preparation of Tender Documents for the Upgrading of
Kilindoni-Rasmkumbi road (52.3Km) to Bitumen standards
Classification(PMDM Class)
TP No. 2 G15
KILINDONI
1 Estimated area;
129,418m2
302,904m3
2 Coordinates: 7 46’ 8’ S
JIMBO BP 39 51’ 18’’ E
to RASMKUMBI
Location: 30+500 km
1800m offset
LHS
TP No.
Test PI GM OMC MDD 95%-
1
Pit (%) CBR
G7
TP No. 2 Estimated area; 103,678m2
KILINDONI
Estimated exploitable quantity;
214,387m3
3 Coordinates: 7 41’ 36’’ S
39 52’ 28’’ E
Location: 43+500 km
250m offset
RHS
to RASMKUMBI Test PI GM OMC MDD 95%-
Pit (%) CBR
BWENI
1 16 2.2 9.2 1900 15
BP TP No. 1
2 16 2.2 6.9 1800 14
km
Ch. 43+500
Classification(PMDM Class)
0.25km
offset Excavated G7 & G15
Estimated area;
TP No. 2 112,639m2
KILINDONI
Estimated exploitable quantity;
250,015m3
G7 & G15
658,975m3