Professional Documents
Culture Documents
Elmer Construction uses the percentage-of-completion method for long-term construction contracts.
A specific job was begun in 2020 and completed 2022. The contract price was 14,000,000 and cost
information as of each year-end is given as follows:
1. Assuming Elmer correctly recorded gross profit in 2020, how much gross profit should the
company record in 2021?
a. 200,000
b. 1,600,000
c. 3,000,000
d. 3,200,000
On July 1, 2020, NORTH CONSTRUCTION CORPORATION contracted to build office building for
SM Inc, for a total contract price of P 2,950,000. Estimated total contract cost is P 2,600,000. Cost
incurred to date related to the project are as follows
2. Using the percentage of completion method, what is the realized gross profit to be
recognized for 2020?
A. P 125,195 C. P 111,055
B. P 104,335 D. P 134,610
(Construction contract - Percentage of Completion Method)
On January 1, 2020, Solid Company accepted a long-term construction project for an initial contract
price of P1,000,000 to be completed on June 30, 2022. On January 1, 2021, the contract price was
increased to P1,500,000 by reason of change in the design of the project. The outcome of the
construction contract can be estimated reliably. The project was completed on December 31, 2022
which resulted to penalty amounting to P200,000. The entity provided the following data concerning
the direct costs related to the said project for 2020 and 2021:
2020 2021
3. What is the construction revenue for the year ended December 31, 2020?
a. 340,000
b. 400,000
c. 440,000
d. 360,000
4. What is the realized gross profit for the year ended December 31, 2021?
a. 200,000
b. 80,000
c. 180,000
d. 100,000
a. 1,200,000
b. 1,020,000
c. 1,120,000
d. 900,000
On January 1, 2020, Hardrock Company started the construction of a building at a fixed contract
price of P1,000,000. On the same date, the customer paid a mobilization fee equal to 5% of contract
price that will be deductible from the first billing. The outcome of construction contract cannot be
estimated reliably
During 2020, the entity billed the customer equivalent to 30% of the contract price. During 2021, the
entity billed again the customer amounting to 20% of the contract price. During 2022, the entity
billed again the customer amounting to 40% of the contract price. The remaining billing was made at
the year of completion of the project.
The entity made collection from the customer at the end of 2020, 2021 and 2022, in the amount of
P120,000, P450,000 and P180,000, respectively. The entity provided the following data concerning
the direct costs related to the said project:
Page 2 of 6
6. What is the realized gross profit for the year ended December 31, 2021?
a. 50,000
b. 200,000
c. 150,000
d. 0
7. What is the excess of construction in progress over progress billings or excess of progress billings
over construction in progress on December 31, 2022?
a. 150,000
b. 100,000
c. 120,000
d. 50,000
9. In its December 31, 2020 Statement of Financial Position, the company would report:
a. The current asset, costs and profits in excess of billings (gross amount due from customer),
50,000
b. The current liability, billings in excess of cost and profits (gross amount due to customers),
50,000
c. The current asset, contract amount in excess of billings, 1,250,000
d. The current asset, deferred profit of 290,000
10. In its December 31, 2021 Statement of Financial Position, the company would report:
a. The current asset, cost and profits in excess of billings (gross amount due from customers),
190,000
b. The current liability, billings in excess of costs and profits (gross amount due to customer),
190,000
c. The current asset, contract amount in excess of billings, of 690,000
d. The current asset, deferred profit of 130,000
11. In its December 31, 2022 Statement of Financial Position, the company would report in relation
to the Construction in Progress and Contract Billings account:
Page 3 of 6
Theory
3. Which of the following costs shall not form part of contract costs of long-term construction
contract?
4. Which of the following costs shall form part of contract costs of long-term construction contract?
a. General administration costs for which reimbursement is not specified in the contract
b. Selling costs such as broker’s commission
c. Research and development costs for which reimbursement is not specified in the contract
d. Construction overheads including costs such as the preparation and processing of
construction personnel payroll
a. The proportion that contract costs incurred for work performed to date bear to the estimated
total contract costs
b. Survey of work to be performed
c. Completion of physical proportion of the contract work
d. Progress payments and advances received from customers
7. Which statement is true when the outcome of construction contract cannot be estimated reliably?
a. Revenue shall be recognized only to the extent of contract costs incurred that is probable will
be recoverable
b. Contract costs shall be recognized as an expense in the period when incurred
c. An expected loss on the construction contract shall be recognized as an expense immediately
d. All of the statements are true
8. An entity shall disclose all of the following in relation to a construction contract, except
Page 4 of 6
c. Advances received in cash, analyzed according to each material contract
d. Total amount of contract revenue to be recognized in the period
10. In selecting an accounting method for a long-term construction contract, the principal factor to be
considered should be
11. In accounting for a long-term construction contract using the percentage of completion method,
the amount of income recognized in any year would be added to
a. Deferred revenue
b. Progress billings on contracts
c. Construction in progress
d. Property, plant and equipment
12. When it is probable that total contract costs on a fixed price contract will exceed the total
revenue, the expected loss should be
13. In accounting for a long-term construction contract using the percentage of completion method,
the progress billings on contracts account is a
14. Which of the following projects undertaken by an entity should be accounted for as a construction
contract?
15. A construction entity signed a contract to build a theatre over a period of two years and with this
contract also signed a maintenance contract for five years. Both contracts are negotiated as a single
package and closely related to each other. The two contracts should be
Page 5 of 6
16. All of the following could be valid reasons why the expected revenue from a fixed price
construction contract should be increased from the original price, except
a. The total costs in the contract have increased and the contract includes cost escalation clause
b. The contractor has incurred additional costs due to errors made by the employees
c. The contractor has agreed variations to the contract with the client
d. The contractor would receive an incentive payment if work continues ahead of schedule and
it is probable that specified performance standards are met or exceeded
17. The percentage of completion method must be used when certain conditions exist. Which of the
following is not one of the conditions?
18. If an entity cannot estimate reliably the outcome of a construction contract, revenue shall be
recognized
19. How should earned but unbilled revenue on a long-term construction contract be disclosed if the
percentage of completion method is used?
20. How should the balances of progress billings and construction in progress be reported prior to the
completion of a long-term construction contract?
Page 6 of 6