Professional Documents
Culture Documents
LECTURE DRILLS
Theories.
3. Which of the followings costs shall be excluded in the contract costs of construction contract?
a. Costs that relate directly to the specific contract.
b. Costs that are directly attributable to contract activity in general and can be allocated to the
contract.
c. Such other costs are specifically chargeable to the customer under the terms of the contract.
d. Selling/marketing costs such as advertisement expense or commission of real estate agents or
brokers.
4. The following costs shall be capitalized as part of construction in progress or contract costs, except
a. Site labor cost and supervision cost and costs of hiring and moving of plant and equipment to
and from the contract site.
b. Systematically, rationally and consistently allocated construction overheads and borrowing
costs.
c. Costs that are specifically chargeable to the customer under the terms of the contract may
include some general administration costs and development costs for which reimbursement is
specified in the terms of the contract.
d. General and research and developments costs for which reimbursement is not specified in the
contract.
Page 1 of 4
Problems.
Problem 1
In 2023, CM Builders agreed to construct a commercial building at a price of P1,000,000. CM Builders
uses the percentage of completion method of recognizing revenue on long term construction projects.
The data relating to the projects from 2023 to 2025 are as follows:
2. What is the balance of construction in progress net of contract billings account of CM Builders on
December 31, 2024?
a. 350,000
b. 300,000
c. 550,000
d. 380,000
3. Assuming the company uses the zero profit method of recognizing revenue from the project, what
is the balance of the construction in progress account net of contract billings as of December 31,
2024?
a. 200,000
b. 250,000
c. 350,000
d. 300,000
Problem 2
She Construction Co. entered into a fixed price contract for the construction of a private road for He Inc.
She determines the stage of completion of construction contracts using the “cost to cost” method. The
estimated total contract cost is P10,000,000. The following were the actual costs incurred by She during
the first year of the construction:
Page 2 of 4
Depreciation of equipment used in construction 120,000
Depreciation of idle construction equipment not used in the contract 60,000
Costs of moving plant, equipment and materials to and from the contract site 40,000
Costs of hiring plant and equipment 140,000
Compute for the percentage of completion of the contract as of the end of the first year.
Problem 3
A contract to construct a building is entered into by Ward Construction Company. The contract price is
P10,000,000. Ward consistently using the percentage of completion method in estimating the profit on
its project. The construction began in 2023 and the following costs were incurred throughout the
completion:
2023 2024 2025
Costs incurred 2,800,000 2,825,000 3,375,000
Estimated costs at completion 7,000,000 9,000,000 9,000,000
Problem 4
On July 1, 2023, Behalf Construction Corporation contracted to build an office building for Bewhole Inc.
for a total contract price of P975,000.
2023 2024 2025
Contract cost incurred to date 75,000 600,000 1,050,000
Estimated cost to complete 675,000 400,000 -
Billings to Bewhole Inc. 150,000 550,000 275,000
1. Under the percentage of completion method, how much is the Construction in Progress at
December 31, 2024?
a. 650,000
b. 575000
c. 672,500
d. 597,500
2. Under the zero profit method, how much is the Construction in Progress, net of Progress Billings at
December 31, 2024?
a. (125,000)
b. 125,000
c. 50,000
d. (50,000)
3. Under the percentage of completion method, how much is the realized gross profit (loss) at
December 31, 2025?
a. (75,000)
b. (100,000)
c. (50,000)
Page 3 of 4
d. (72,500)
Problem 5
On January 1, 2023, AA Construction Corporation began constructing P2,100,000 contract. The entity
used the percentage of completion method. For the year ended December 31, 2024, AA Construction
billed its client an additional 55% of the contract price.
2023 2024 2025
Construction in progress 441,000 ? ?
Estimated costs to complete ? ? -
Costs incurred 425,250 969,000 675,750
Excess of CIP over billings (84,000) (330,750) -
END
Page 4 of 4