Professional Documents
Culture Documents
materials as significant in relation to the expected total contract costs. Moreover, ABC
Co. retains control over the unused materials because it can use them in a contract
with another customer. The contract price is ₱20M. How much is the revenue
recognized in 20x1?
a. 7,600,000
b. 12,000,000
c. 8,200,000
d. 11,600,000
5. On January 1, 20x1, ABC Co. entered into a contract with a customer for the
construction of a building. The contract price is ₱1,000,000. The following are the
transactions during 20x1:
● At contract inception, the customer makes an advance payment of ₱100,000 as
facilitation fee.
● ABC Co. incurs total contract costs of ₱300,000 during the period.
● The estimated costs to complete as of year-end amounts to ₱500,000.
● ABC Co. collects the billing, net of 10% retention by the customer to be used to
rectify any unsatisfactory work determined at the completion of the contract.
How much is the gross profit earned from the contract in 20x1?
a. 75,000
b. 82,000
c. 375,000
d. 482,000
Use the following information for the next three cases (three questions per case):
In 20x1, ABC Co. enters into a construction contract with a customer. The contract price
is ₱10,000,000. Information on the contract follows:
20x1 20x2 20x3
Costs incurred to date 2,400,000 4,500,000 6,000,000
Estimated costs to complete 3,600,000 1,500,000 -
Case #1:
At contract inception, ABC Co. assesses its performance obligations in the contract and
concludes that it has a single performance obligation that is satisfied over time. ABC Co.
determines that the measure of progress that best depicts its performance on the contract
is the “cost-to-cost” method.
6. How much is the revenue recognized in 20x1?
a. 4,200,000
b. 4,000,000
c. 2,800,000
d. 3,500,000
7. How much is the cost of construction recognized as expense in 20x2?
a. 2,100,000
b. 2,400,000
c. 3,800,000
d. 1,500,000
8. How much is the gross profit recognized in 20x3?
a. 1,000,000
Page | 3
b. 1,500,000
c. 2,100,000
d. 2,800,000
Case #2:
At contract inception, ABC Co. assesses its performance obligations in the contract and
concludes that it has a single performance obligation that is satisfied over time. However,
ABC Co. determines that the outcome of the performance obligation cannot be reasonably
measured but expects to recover the contract costs incurred.
9. How much is the revenue recognized in 20x1?
a. 4,200,000
b. 4,000,000
c. 2,400,000
d. 0
10. How much is the cost of construction recognized as expense in 20x2?
a. 2,100,000
b. 2,400,000
c. 3,800,000
d. 0
11. How much is the gross profit recognized in 20x3?
a. 5,500,000
b. 1,500,000
c. 4,000,000
d. 2,100,000
Case #3:
At contract inception, ABC Co. assesses its performance obligations in the contract and
concludes that it has a single performance obligation.
In its determination of the satisfaction of the performance obligation, ABC Co. identifies
that, during the construction period, ABC Co. retains control over the asset created in the
contract. This precludes the customer from simultaneously receiving and consuming the
benefits provided by ABC Co.’s performance as ABC Co. performs. Moreover, the asset
created in the contract has an alternative use to ABC Co. because, in case the contract is
cancelled, ABC Co. retains ownership over any asset created and can direct that asset for
another use without significant modification or cost. Accordingly, ABC Co. concludes that
the performance obligation is satisfied at a point in time.
ABC Co. determines the point in time when the performance obligation is satisfied using
the principles in PFRS 15 and concludes that the performance obligation is satisfied only
when the construction is completed and the control over the promised good is transferred
to the customer.
12. How much is the revenue recognized in 20x1?
a. 4,200,000
b. 4,000,000
c. 2,400,000
d. 0
Page | 4
Use the following information for the next two cases (18 and 19)
SOLUTION Construction Co. entered into a fixed price contract for the construction of a
building for PROBLEM, Inc. SOLUTION determines the stage of completion of construction
contracts using the “cost-to-cost” method.
The estimated total costs of the contract are as follows:
Estimated costs of design and technical
assistance that are directly related to the contract 800,000
Estimated costs of design and technical
assistance that are not directly related to a
specific contract (properly allocated) 200,000
Estimated costs of materials to be used in the
construction 22,000,000
Estimated costs of construction labor 11,200,000
Estimated costs of rectification and guarantee
work, including expected warranty costs 1,200,000
Estimated administrative costs expected to be
reimbursed in accordance with contractual
agreement 520,000
Estimated insurance costs during construction 80,000
Estimated construction overheads 4,000,000
Estimated marketing costs for selling
condominium units 400,000
Estimated total contract costs 40,400,000
The following were the actual costs incurred by SOLUTION during the first year of the
construction:
Costs of design and technical assistance
that are directly related to the contract 400,000
Costs of design and technical assistance
that are not directly related to a specific
contract (properly allocated) 100,000
Costs of materials used in the construction 12,000,000
Costs of construction labor 6,000,000
Administrative costs expected to be
reimbursed in accordance with contractual
agreement. 880,000
Administrative costs not expected to be
reimbursed 120,000
Research and development costs for which
reimbursement is not specified in the
contract 6,800,000
Insurance costs during construction 60,000
Construction overheads 960,000
Marketing costs 800,000
Total costs incurred to date 28,120,000
18. What is the total cost incurred to date?
a. 21,320,000b. 28,000,000 c. 20,000,000d. 20,400,000
Page | 6
19. What is the percentage of completion of the contract as of the end of the first year?
a. 42% b. 45% c. 50% d. 51%
Use the following information for the next six cases (20-25):
As of 2 February 2020, approximately 14,642 cases have been confirmed infected for novel
coronavirus of which 14,462 cases are from Mainland China. Wuhan, China was totally
locked down and the Government of China started building an emergency specialty field
hospital called “Huoshenshan Hospital” from 23 January 2020 to 2 February 2020 and
operation scheduled to start by 3 February 2020. The Philippine’ government was
mesmerized by the fast construction of the said hospital for only just 10 days to complete.
The Philippine’ government started to build a 2-storey public hospital to treat coronavirus
as the outbreak is expected to last for four years. Chongchingchong Construction was
hired to finish the construction in 2022. Chongchingchong Construction has consistently
used the percentage-of-completion method of accounting for construction-type contracts.
During 2020, Chongchingchong Construction started work on a P100,000,000 fixed-price
construction contract that will be completed in 2022. Chongchingchong accounting
records disclosed the following:
December 31
2020 2021
Cumulative contract costs incurred P 30,900,000 P 64,080,000
Estimated total cost at completion 61,800,000 80,100,000
20. What is the percentage of completion as of 2020?
a. 45%
b. 37%
c. 52%
d. 50%
21. What is the gross profit/loss for the year 2020?
a. Php 34.351 Million
b. Php 30.520 Million
c. Php 34.550 Million
d. Php 19.100 Million
22. What is the contract cost incurred for 2021?
a. Php 33.18 Million
b. Php 64.08 Million
c. Php 80.10 Million
d. Php 18.30 Million
23. What is the percentage completed for 2021?
a. 55.15%
b. 30%
c. 32%
d. 23.13%
24. The revenue recognized to date in 2021?
a. Php 33.00 Million
b. Php 83.79 Million
c. Php 30.00 Million
d. Php 80.00 Million
Page | 7
25. What is the revenue recognized for the year 2021?
a. Php 30.00 Million
b. Php 31.79 Million
c. Php 81.80 Million
d. Php 83.79 Million
“Come to Me, all you who labor and are heavy laden, and I will give you rest.” (Matthew
11:28)
- END -
SOLUTIONS:
1. B
2. D
3. Solution:
The total costs incurred to date are computed as follows:
Costs of materials used in construction 12,000,000
Site labor costs 4,000,000
Site supervision costs 800,000
Depreciation of equipment used in construction 480,000
Costs of moving plant, equipment and materials to and
from the contract site 160,000
Costs of hiring plant and equipment 560,000
Total costs incurred to date 18,000,000
The percentage of completion as of the end of the first year is computed as follows:
Percentage of completion = Total costs incurred to date
Estimated total contract costs
Percentage of completion = 18,000,000 ÷ 40,000,000
Percentage of completion = 4 5%
4. Solution:
Percentage of completion = (6M – 2M – 200K) ÷ 10M
Percentage of completion = (3.8M ÷ 10M) = 38%
38% x 20M = 7.6M
5. A Solution:
Total contract price 1,000,000
(a) Costs incurred to date 300,000
Estimated costs to complete 500,000
(b) Estimated total contract costs 800,000
Expected gross profit from contract 200,000
Multiply by: Percentage of completion (a) ÷ (b) 37.50%
Gross profit earned to date 75,000
Less: Gross profit earned in previous years -
Gross profit for the year 75,000
Page | 8
the costs of construction are computed as “costs incurred to date” minus “costs incurred in
prior years: 20x2: (4.5M – 2.4M = 2.1M) and 20x3: (6M – 4.5M = 1.5M).
12. D (see solutions below)
13. D (see solutions below)
Page | 9
14. C
Solutions:
20x1 20x2 20x3
Contract revenue to date (a) - - 10,000,000
Contract revenue in prior years - - -
- -
Contract revenue for the year 10,000,000
- -
Cost of construction (b) (6,000,000)
Profit (loss) for the year - - 4,000,000
(a) No revenue is recognized during the construction period because the performance