Professional Documents
Culture Documents
Construction contract - a contract specifically negotiated for the construction of an asset or a combination
of assets that are closely interrelated or interdependent in terms of their design, technology and function
or their ultimate purpose or use.
Fixed price contract - a construction contract in which the contractor agrees to a fixed contract price, or
a fixed rate per unit of output, which in some cases is subject to cost escalation clauses.
Cost plus contract - a construction contract in which the contractor is reimbursed for allowable or
otherwise defined costs, plus a percentage of these costs or a fixed fee.
Contract revenue - includes (a) Initial amount of revenue agreed in the contract; and (b) Variations in
contract work, claims and incentive payments: to the extent that it is probable that they will result in
revenue; and they are capable of being reliably measured.
(a) It is probable that the customer will approve the variation/amount of revenue arising from variation
and (b) the amount of revenue can be measured reliably
(a) Negotiations have reached the advanced stage and it is probable that the customer will accept the
claim and (b) the amount probable to be accepted by the customer can be measured reliably
(a) The contract is sufficiently advanced that it is probable that the specified performance standards will
be met or exceeded and (b) the amount of incentive payments can be measured reliably
Contract costs - are (a) Costs specifically related to the contract; (b) general costs attributable to the
contract; and (c) such other costs specifically chargeable to the customer under the terms of the contract
(administrative costs, development costs etc.)
The above stated costs will be reduced any incidental income such as from sale of surplus materials,
wastes etc.
Costs that may be attributable to contract activity in general and can be allocated to specific
contracts include:
a) insurance;
b) costs of design and technical assistance that are not directly related to a specific contract; and
c) construction overheads
A. Percentage of Completion (POC) Method - When the outcome of a construction contract can be
estimated reliably, contract revenue and contract costs associated with the construction contract
shall be recognized as revenue and expenses respectively by reference to the stage of completion
of the contract activity at the end of the reporting period.
Note: Progress payments and advances received from customers often do not reflect the work
performed.
B. Cost Recovery Method – This method is used when the outcome of a contract can’t be estimated
reliably then:
a. Revenue shall be recognized to the extent of contract costs incurred that is probable will be
recoverable; and
b. Contract costs shall be recognized as an expense (costs of construction) in the period in which
they are incurred.
ABC Construction Co. entered into a fixed price contract for the construction of a private road for XYZ, Inc.
ABC determines the stage of completion of construction contracts using the "cost to cost" method. The
estimated total contract cost is P10M. The following were the actual costs incurred by ABC during the first
year of the construction:
ABC Construction Co. entered into a fixed price contract for the construction of a building for XYZ, Inc.
ABC determines the stage of completion of construction contracts using the "cost to cost" method.
The following were the actual costs incurred by ABC during the first year of the construction:
Costs of design and technical assistance that are directly related to the contract 100,000
Costs of design and technical assistance that are not directly related to the specific
contract (properly allocated) 25,000
Requirement: Compute for the POC of the contract as of the end of the first year. 50%
Illustration 3. Percentage of completion (POC) - Estimated cost to complete
ABC Construction Co. entered into a contract for the construction of a flyover for XYZ, Inc in 2021.
Information on costs is as follows:
2021 2022
Cost incurred to date 400,000 1,500,000
Estimated cost to complete 1,600,000 375,000
Requirement: Compute for the POC of the contract as of December 31, 2021 and 2022. 20% and 80%
ABC Co. is contracted to construct an amusement park for XYZ, Inc. ABC subcontracted a large portion of
the contract. ABC uses the efforts-expended method in determining the stage of completion of the
contract. Information on efforts expended on the contract is shown below:
2021 2022
Total direct labors hours to date 400 1,500
Estimated direct labors hours to complete 1,600 375
Requirement: Compute for the POC of the contract as of December 31, 2021 and 2022. 20% and 80%
ABC Construction Co. entered into a fixed price contract for the construction of a gymnasium for XYZ, Inc.
The contract price is P9M. Construction was started in 2021 and was completed early in 2023. The
following transactions occurred during the construction period.
2021
2022
e. Incurred total contract costs of P3,540,000.
f. Billed XYZ for 30% of the contract price.
g. Collected 90% of the progress billings after 10% retention by XYZ
h. Estimated costs to complete as of December 31, 2022 are P700,000
2023
i. Incurred total contract costs of P500,000.
j. Billed XYZ for the remaining 20% of the contract price. All receivables from XYZ were collected.
k. The construction contract was completed and ownership over the completed gymnasium was
transferred to XYZ, Inc.
Requirements:
a. Compute for the gross profit to be recognized in each year. 840K, 960K, 400K
b. Compute for the contract revenue to be recognized in each year. 3.6M, 4.5M, 900K
Illustration 6. ZERO PROFIT METHOD - Journal Entries
On January 1, 2021, ABC Construction Co. entered into a fixed price contract for the construction of a
specialized equipment for XYZ, Inc. The contract price is P9M. Construction was started in 2021 and was
completed early in 2023. The following transactions occurred during the construction period.
2021
a. Incurred total contract costs of P2,760,000
b. Billed XYZ for 50% of the contract price.
c. Collected 90% of the progress billing; 10% was retained by XYZ to be reverted to ABC upon completion
of the contract. The amount retained shall be used to rectify any unsatisfactory work to be determined
at the completion of the contract.
d. The outcome of the contract cannot be estimated reliably.
2022
e. Incurred total contract costs of P3,540,000.
f. Billed XYZ for 30% of the contract price.
g. Collected 90% of the progress billings after 10% retention by XYZ .
h. The outcome of the contract cannot be estimated reliably.
2023
i. Incurred total contract costs of P500,000.
j. Billed XYZ for the remaining 20% of the contract price. All receivables from XYZ were collected.
k. The construction contract was completed and ownership over the completed gymnasium was
transferred to XYZ, Inc.
Requirements:
a. Compute for the gross profit to be recognized in each year. ZERO, ZERO, 2.2M
b. Compute for the contract revenue to be recognized in each year. 2760K, 3540K, 2.7M
In 2021, ABC Co. started work on a P10M fixed price contract. All costs incurred are expected to be
recoverable. Information on the construction as of year-end is shown below:
Requirement: Compute the profit and loss to be recognized by ABC in 2021. 1.8M LOSS
Requirement:
a. Compute the profit and loss to be recognized in each year under POC method. 50K, (150K), 150K
b. Compute for the contract revenue to be recognized in each year. 250K, 500K, 250K
c. Compute for the gross amounts of due from (due to) customers for contract work in each year. (100K),
25K, ZERO
d. Compute the profit and loss to be recognized in each year under Zero profit method. ZERO, (100K),
150K