Professional Documents
Culture Documents
On January 1, 2022, Micho Const Company was contracted to build an office building for Pelo Company for a total
contract price of P12,400,000. Estimated total contract cost are P11,000,000. Costs incurred to date related to the
project are as follows:
Using the POC method, how much is the realized gross profit to be recognized in year 2022?
PROBLEM 2
On January 1, 2022, Aivan Company entered into a contract to construct a building for a customer. Aivan Co
performance obligation will be satisfied over time. The Company uses the input method based on costs to measure
its progress on the contract. The contract price is 10,500,000. Information on the construction is provided below:
Using the cost to cost method, compute for the revenue, contruction costs and gross profits in 2022, 2023, 2024?
Using the cost recovery method, compute for the revenue, contruction costs and gross profits in 2022, 2023, 2024?
PROBLEM 3
In 2022, Fluuuor Builders Inc started on a new project Shell Investa on a P2,000,000 fixed price contract.
Information related to the project shown below:
Using the cost to cost method, compute for the revenue, contruction costs and gross profits in 2022, 2023, 2024?
Using the cost recovery method, compute for the revenue, contruction costs and gross profits in 2022, 2023, 2024?