SIGNATURES
Prepared by
Approved by TR Construction Approved by TR Planning
Subcontractor
1 of 23
###
### Project: FADHILI GAS PLANT PROJECT (T-10040)
Level IV - PIPING WORK (SUNGCHANG)
UNIT-200
Punch Listed A
Spool Erection
Supported &
Certificate
(Including
Welding
Valves)
QA/QC
ActivityID Piping Erection Resource Act Progress % QtyDone Weight Budget/Qty
PI.BB 45 35 15 5
1C420PIBB1010 Big Bore Piping A/Equip. Erection - Inlet Facilities 10040.PI.BB.DI 99.95 51709 0.573 51,709.000 100.00 100.00 99.77 99.77 back log progress
Big Bore Piping A/Equip. Erection - Inlet Facilities 42767.75 42,767.750 100.00 100.00 0.00 0.00
Big Bore Piping A/Equip. Erection - Inlet Facilities - Sour gas 8941.25 8,941.250 100.00 100.00 0.00 0.00
51,587.48 51587.48385
Cutting/Bevelin
g & Alignment
Certificate
Welding
QA/QC
ActivityID Piping Prefabrication Resource Act Progress % QtyDone Weight Budget/Qty
PI.PR 35 60 5
1C420PIPR1010 Piping Prefabrication - Inlet Facilities 10040.PI.FB.DI 100.00 98,136.00 0.630 98,136.000 100.00 100.00 100.00
50.66449603 41.50 0
Punch Listed A
Spool Erection
Supported &
(Including
Certificate
Welding
Valves)
QA\QC
ActivityID Piping Erection Resource Act Progress % QtyDone Weight Budget/Qty
PI.RA 45 35 15 5
1C420PIRA1010 Pipe Rack Piping Erection - Inlet Facilities 10040.PI.PR.DI 100.00 67,174.50 0.870 67,174.500 100.00 100.00 99.995 99.995 back log progress
Pipe Rack Piping Erection - Inlet Facilities 48,526.00 48,526.000 100 100.00 62.44064551 62.4406455 99.995
Pipe Rack Piping Erection - Inlet Facilities- sour gas 18,648.50 18,648.500 100 100.00 28.029441685 28.0294417
67,171.14 67171.1413
Punch Listed A
Spool Erection
Supported &
(Including
Certificate
Welding
Valves)
QA\QC
ActivityID Piping Erection Resource Act Progress % QtyDone Weight Budget/Qty
PI.SB 30 50 15 5
1C420PISB1010 Small Bore Piping A/Equip. Erection - Inlet Facilities 10040.PI.SB.DI 99.96 19081.75 1.348 19,081.750 100 100 99.78 99.78 back log progress
19,039.77 19039.7702
Tracer Fixing
ready for HT
Leak Testing
installation
Hidrotest)
(Steam or
Certificate
Tracers
QA\QC
ActivityID Heat / Steam Tracing Piping Resource Act Progress % QtyDone Weight Budget/Qty
PI.ST1 70 15 10 5
Installation/Con
Hydraulic Test
Fabrication &
Condensate
Installation
Certificate
Manifolds
Steam or
nection
Tracing
QA/QC
Line
ActivityID Steam / Condensate Manifolds Stations - Steam Tracing Piping Resource Act Progress % QtyDone Weight Budget/Qty
PI.ST2 25 20 40 10 5
Prefabrication
Certificate
Materials
QA\QC
Supply
ActivityID Piping Support Prefabrication Resource Act Progress % QtyDone Weight Budget/Qty
PI.SU1 35 60 5
1C420PISU1010 Piping Supports Prefabrication - Inlet Facilities 10040.PI.PU.TN 100.00 283.10 0.380 283.100 100.00 100.00 100.00
Installation
Certificate
QA\QC
ActivityID Piping Support Erection Resource Act Progress % QtyDone Weight Budget/Qty
PI.SU2 95 5
1C420PISU1020 Piping Supports Erection - Inlet Facilities 10040.PI.SU.TN 99.78 309.05 0.724 309.737 99.78 99.78
Piping Supports Erection - Inlet Facilities 244.52 244.518 100.00 98.03
Piping Supports Erection - Inlet Facilities - Sourgas 64.53 65.219 98.95 94.35
2 of 23
###
### Project: FADHILI GAS PLANT PROJECT (T-10040)
Level IV - PIPING WORK (SUNGCHANG)
UNIT-200
Painting/Touch
Identification
Certificate
QA/QC
Signs
Fluid
Final
up
ActivityID Piping & Support Finishing Painting (Final Coat & Touch Up) Resource Act Progress % QtyDone Weight Budget/Qty
PA.FP 85 10 5
1C420PAFP1010 Piping Final Coat & Touch-Up Painting - Inlet Facilities 87.87 44788 0.034 126,456.000 99.85 20.00 20.00
12,645.60 44,856.000
Sandblasting &
Coat Painting
Intermediate
Certificate
Primming
QA\QC
ActivityID Piping Primming (Prefabrication) Resource Act Progress % QtyDone Weight Budget/Qty
PA.PP 65 30 5
1C420PAPP1010 Piping SandBl. & Primming - Inlet Facilities 10040.PA.PP.M2 99.93 37,959.55 0.217 38,039.759 100.00 99.79 99.79
38039.76 37959.55 37959.55 38039.7588 37034.9
Sandblasting &
Coat Painting
Intermediate
Certificate
Primming
QA\QC
ActivityID Supports Painting (Prefabrication) Resource Act Progress % QtyDone Weight Budget/Qty
PA.SP 65 30 5
1C420PASP1010 Piping Supports SandBl. & Primming - Inlet Facilities 10040.PA.SU.TN 100.00 275.53 0.014 275.531 100.00 100.00 100.00
Piping Supports SandBl. & Primming - Inlet Facilities 239.93 239.931 100.00 100.00 100.00
Piping Supports SandBl. & Primming - Inlet Facilities - Sour gas 35.51 35.600 100.00 100.00 100.00 35.60 37.4429
259.80 259.80 259.80 259.6 254.505
Hydrotest
Folder
ActivityID Piping (Punch list A/Hydrotest/Flushing/Reinstatement) Resource Act Progress % QtyDone Weight Budget/Qty
PR.HT 20 80
1C420PRHT1010 Piping Hydrotesting - Inlet Facilities 99.66 254149 0.226 255,019.000 99.66 99.66
254149 254149
Flushing /
Blowing
ActivityID Piping (Punch list A/Hydrotest/Flushing/Reinstatement) Resource Act Progress % QtyDone Weight Budget/Qty
PR.FL 100
1C420PRFL1010 Piping Flushing/Blowing - Inlet Facilities 100.00 237807 0.045 237,807.000 100
Reinstatement
Handover HCS
(Remaining)
Punch List B
Certificate
Certificate
QA/QC
ActivityID Piping (Punch list A/Hydrotest/Flushing/Reinstatement) Resource Act Progress % QtyDone Weight Budget/Qty
PR.RE 55 35 5 5
1C420PRRE1010 Piping Reinstatement - Inlet Facilities 100.00 212242 0.181 212,242.000 100.000 100.00 100.000 100.000
Completed
Certificate
QA/QC
ActivityID Resource Act Progress % QtyDone Weight Budget/Qty
PR.PR 95 5
1C420PRPR1030 Walkthrough & NO Exception Items Clearance - Inlet Facilities 91.73 11729 0.044 12,764.000 91.89 88.67
11318
Act Progress Weight
99.79% 5.2879
3 of 23
###
### Project: FADHILI GAS PLANT PROJECT (T-10040)
Level IV - PIPING WORK (SUNGCHANG)
UNIT-214
Punch Listed A
Spool Erection
Supported &
Certificate
(Including
Welding
Valves)
QA/QC
ActivityID Piping Erection Resource Act Progress % QtyDone Weight Budget/Qty
PI.BB 45 35 15 5
1C420PIBB2010 Big Bore Piping A/Equip. Erection - MEG Train 1 10040.PI.BB.DI 99.69 14,456.25 0.215 14,456.250 100.00 100.00 98.47 98.47 back log progress
14,235.07 14,235.07
Cutting/Bevelin
g & Alignment
Certificate
Welding
QA/QC
ActivityID Piping Prefabrication Resource Act Progress % QtyDone Weight Budget/Qty
PI.PR 35 60 5
1C420PIPR2010 Piping Prefabrication - MEG Train 1 10040.PI.FB.DI 100.00 27,755.50 0.147 27,755.500 100.00 100.00 100.00
79.766807794 17.8 60.85 39.15
Punch Listed A
Spool Erection
Supported &
(Including
Certificate
Welding
Valves)
QA\QC
ActivityID Piping Erection Resource Act Progress % QtyDone Weight Budget/Qty
PI.RA 45 35 15 5
1C420PIRA2010 Pipe Rack Piping Erection - MEG Train 1 10040.PI.PR.DI 99.89 3,374.62 0.117 3,378.000 99.9 99.9 99.86 99.86 back log progress
1C420PIRA2010 Laydown 3,378.00
Field 3,373.27 3373.2708
Punch Listed A
Spool Erection
Supported &
(Including
Certificate
Welding
Valves)
QA\QC
ActivityID Piping Erection Resource Act Progress % QtyDone Weight Budget/Qty
PI.SB 30 50 15 5
1C420PISB2010 Small Bore Piping A/Equip. Erection - MEG Train 1 10040.PI.SB.DI 99.95 7,992.00 0.404 7,992.000 100.00 100.00 99.77 99.77 welding done - spool erection must done also
7974 7974
Tracer Fixing
ready for HT
Leak Testing
installation
Hidrotest)
(Steam or
Certificate
Tracers
QA\QC
ActivityID Heat / Steam Tracing Piping Resource Act Progress % QtyDone Weight Budget/Qty
PI.ST1 70 15 10 5
Installation/Con
Hydraulic Test
Fabrication &
Condensate
Installation
Certificate
Manifolds
Steam or
nection
Tracing
QA/QC
Line
ActivityID Steam / Condensate Manifolds Stations - Steam Tracing Piping Resource Act Progress % QtyDone Weight Budget/Qty
PI.ST2 25 20 40 10 5
Prefabrication
Certificate
Materials
QA\QC
Supply
ActivityID Piping Support Prefabrication Resource Act Progress % QtyDone Weight Budget/Qty
PI.SU1 35 60 5
1C420PISU2010 Piping Supports Prefabrication - MEG Train 1 10040.PI.PU.TN 100.00 46.00 0.029 46.000 100.00 100.00 100
Installation
Certificate
QA\QC
ActivityID Piping Support Erection Resource Act Progress % QtyDone Weight Budget/Qty
PI.SU2 95 5
1C420PISU2020 Piping Supports Erection - MEG Train 1 10040.PI.SU.TN 93.53 48.14 0.055 51.474 93.53 93.53
4 of 23
###
### Project: FADHILI GAS PLANT PROJECT (T-10040)
Level IV - PIPING WORK (SUNGCHANG)
UNIT-214
Painting/Touch
Identification
Certificate
QA/QC
Signs
Final
Fluid
up
ActivityID Piping & Support Finishing Painting (Final Coat & Touch Up) Resource Act Progress % QtyDone Weight Budget/Qty
PA.FP 85 10 5
1C420PAFP2010 Piping Final Coat & Touch-Up Painting - MEG Train 1 56.21 902 0.003 - 66.129032258
1,364.000
Sandblasting &
Coat Painting
Intermediate
Certificate
Primming
QA\QC
ActivityID Piping Primming (Prefabrication) Resource Act Progress % QtyDone Weight Budget/Qty
PA.PP 65 30 5
1C420PAPP2010 Piping SandBl. & Primming - MEG Train 1 10040.PA.PP.M2 98.30 3000.99 0.018 3,058.956 98.40 98.10 98.10
3010.08 3000.99 3000.99
3010.080904 2992.156
Sandblasting &
Coat Painting
Intermediate
Certificate
Primming
QA\QC
ActivityID Supports Painting (Prefabrication) Resource Act Progress % QtyDone Weight Budget/Qty
PA.SP 65 30 5
1C420PASP2010 Piping Supports SandBl. & Primming - MEG Train 1 10040.PA.SU.TN 100.00 44.70 0.001 44.700 100.00 100.00 100.00
44.70 44.70 44.70
45 45
Hydrotest
Folder
ActivityID Piping (Punch list A/Hydrotest/Flushing/Reinstatement) Resource Act Progress % QtyDone Weight Budget/Qty
PR.HT 20 80
1C420PRHT2010 Piping Hydrotesting - MEG Train 1 99.97 54799 0.048 54,816.000 99.97 99.97
54799 54799
Flushing /
Blowing
ActivityID Piping (Punch list A/Hydrotest/Flushing/Reinstatement) Resource Act Progress % QtyDone Weight Budget/Qty
PR.FL 100
1C420PRFL2010 Piping Flushing/Blowing - MEG Train 1 100.00 54521 0.010 54,521.000 100.00
Reinstatement
Handover HCS
(Remaining)
Punch List B
Certificate
Certificate
QA/QC
ActivityID Piping (Punch list A/Hydrotest/Flushing/Reinstatement) Resource Act Progress % QtyDone Weight Budget/Qty
PR.RE 55 35 5 5
1C420PRRE2010 Piping Reinstatement - MEG Train 1 100.00 26171 0.039 26,171.000 100.00 100.00 100.00 100.00
Completed
Certificate
QA/QC
ActivityID Resource Act Progress % QtyDone Weight Budget/Qty
PR.PR 95 5
1C420PRPR2030 Walkthrough & NO Exception Items Clearance - MEG Train 1 79.09 2920 0.007 3,676.000 79.43 72.50
2665
Act Progress Weight
99.30% 1.0927
5 of 23
###
### Project: FADHILI GAS PLANT PROJECT (T-10040)
Level IV - PIPING WORK (SUNGCHANG)
UNIT-224
Punch Listed A
Spool Erection
Supported &
Certificate
(Including
Welding
Valves)
QA/QC
ActivityID Piping Erection Resource Act Progress % QtyDone Weight Budget/Qty
PI.BB 45 35 15 5
1C420PIBB3010 Big Bore Piping A/Equip. Erection - MEG Train 2 10040.PI.BB.DI 100.00 14941.75 0.231 14,941.750 100 100.00 99.99 99.99
14,940.26 14940.2558
Cutting/Bevelin
g & Alignment
Certificate
Welding
QA/QC
ActivityID Piping Prefabrication Resource Act Progress % QtyDone Weight Budget/Qty
PI.PR 35 60 5
1C420PIPR3010 Piping Prefabrication - MEG Train 2 10040.PI.FB.DI 100.00 27,328.50 0.144 27,328.500 100.00 100.00 100.00
77.4474315083 21.00 60 40.00
Punch Listed A
Spool Erection
Supported &
(Including
Certificate
Welding
Valves)
QA\QC
ActivityID Piping Erection Resource Act Progress % QtyDone Weight Budget/Qty
PI.RA 45 35 15 5
1C420PIRA3010 Pipe Rack Piping Erection - MEG Train 2 10040.PI.PR.DI 99.99 3,324.25 0.126 3,324.250 100.00 100.00 99.97 99.97
Laydown
Field 3,323.42 3323.41763
Punch Listed A
Spool Erection
Supported &
(Including
Certificate
Welding
Valves)
QA\QC
ActivityID Piping Erection Resource Act Progress % QtyDone Weight Budget/Qty
PI.SB 30 50 15 5
1C420PISB3010 Small Bore Piping A/Equip. Erection - MEG Train 2 10040.PI.SB.DI 100.00 8,149.25 0.413 8,149.250 100 100 99.99 99.99
8,148.44 8148.43508
Tracer Fixing
ready for HT
Leak Testing
installation
Hidrotest)
(Steam or
Certificate
Tracers
QA\QC
ActivityID Heat / Steam Tracing Piping Resource Act Progress % QtyDone Weight Budget/Qty
PI.ST1 70 15 10 5
Installation/Con
Hydraulic Test
Fabrication &
Condensate
Installation
Certificate
Manifolds
Steam or
nection
Tracing
QA/QC
Line
ActivityID Steam / Condensate Manifolds Stations - Steam Tracing Piping Resource Act Progress % QtyDone Weight Budget/Qty
PI.ST2 25 20 40 10 5
Prefabrication
Certificate
Materials
QA\QC
Supply
ActivityID Piping Support Prefabrication Resource Act Progress % QtyDone Weight Budget/Qty
PI.SU1 35 60 5
1C420PISU3010 Piping Supports Prefabrication - MEG Train 2 10040.PI.PU.TN 100.00 46.40 0.029 46.400 100.00 100.00 100.00
Installation
Certificate
QA\QC
ActivityID Piping Support Erection Resource Act Progress % QtyDone Weight Budget/Qty
PI.SU2 95 5
1C420PISU3020 Piping Supports Erection - MEG Train 2 10040.PI.SU.TN 93.98 48.50 0.056 51.609 93.98 93.98
6 of 23
###
### Project: FADHILI GAS PLANT PROJECT (T-10040)
Level IV - PIPING WORK (SUNGCHANG)
UNIT-224
Painting/Touch
Identification
Certificate
QA/QC
Signs
Final
Fluid
up
ActivityID Piping & Support Finishing Painting (Final Coat & Touch Up) Resource Act Progress % QtyDone Weight Budget/Qty
PA.FP 85 10 5
1C420PAFP3010 Piping Final Coat & Touch-Up Painting - MEG Train 2 86.30 17248.44 0.003 23,628.000 99.77 10.00 10.00
14468 14,502.000
Sandblasting &
Coat Painting
Intermediate
Certificate
Primming
QA\QC
ActivityID Piping Primming (Prefabrication) Resource Act Progress % QtyDone Weight Budget/Qty
PA.PP 65 30 5
1C420PAPP3010 Piping SandBl. & Primming - MEG Train 2 10040.PA.PP.M2 99.46 3051.42 0.018 3,099.011 100.00 98.46 98.46
3,099.01 3,051.42 3051.42
3055.02547729 2992.8816442
Sandblasting &
Coat Painting
Intermediate
Certificate
Primming
QA\QC
ActivityID Supports Painting (Prefabrication) Resource Act Progress % QtyDone Weight Budget/Qty
PA.SP 65 30 5
1C420PASP3010 Piping Supports SandBl. & Primming - MEG Train 2 10040.PA.SU.TN 100.00 46.55 0.001 46.554 100.00 100.00 100.00
45.00 46.55 45.00
45 45
Hydrotest
Folder
ActivityID Piping (Punch list A/Hydrotest/Flushing/Reinstatement) Resource Act Progress % QtyDone Weight Budget/Qty
PR.HT 20 80
1C420PRHT3010 Piping Hydrotesting - MEG Train 2 99.99 58411.5 0.050 58,420.000 100.00 99.99
58,420.00 58411.5
Flushing /
Blowing
ActivityID Piping (Punch list A/Hydrotest/Flushing/Reinstatement) Resource Act Progress % QtyDone Weight Budget/Qty
PR.FL 100
1C420PRFL3010 Piping Flushing/Blowing - MEG Train 2 100.00 58307 0.010 58,307.000 100.00
Reinstatement
Handover HCS
(Remaining)
Punch List B
Certificate
Certificate
QA/QC
ActivityID Piping (Punch list A/Hydrotest/Flushing/Reinstatement) Resource Act Progress % QtyDone Weight Budget/Qty
PR.RE 55 35 5 5
1C420PRRE3010 Piping Reinstatement - MEG Train 2 98.61 57972 0.040 57,972.000 99.43 97.62 97.62 97.62
Completed
Certificate
QA/QC
ActivityID Resource Act Progress % QtyDone Weight Budget/Qty
PR.PR 95 5
1C420PRPR3030 Walkthrough & NO Exception Items Clearance - MEG Train 2 91.64 3756 0.007 4,087.000 91.90 86.62
3540
Act Progress Weight
99.55% 1.1278
7 of 23
###
### Project: FADHILI GAS PLANT PROJECT (T-10040)
Level IV - PIPING WORK (SUNGCHANG)
UNIT-234
Punch Listed A
Spool Erection
Supported &
Certificate
(Including
Welding
Valves)
QA/QC
ActivityID Piping Erection Resource Act Progress % QtyDone Weight Budget/Qty
PI.BB 45 35 15 5
1C420PIBB4010 Big Bore Piping A/Equip. Erection - MEG Train 3 10040.PI.BB.DI 99.85 14,597.25 0.232 14,597.250 100.00 100.00 99.24 99.24 back log progress
14,486.31 14486.3
Cutting/Bevelin
g & Alignment
Certificate
Welding
QA/QC
ActivityID Piping Prefabrication Resource Act Progress % QtyDone Weight Budget/Qty
PI.PR 35 60 5
1C420PIPR4010 Piping Prefabrication - MEG Train 3 10040.PI.FB.DI 100.00 27,115.75 0.144 27,115.750 100.00 100.00 100.00
70.37505785 19.00 55 45.00
Punch Listed A
Spool Erection
Supported &
(Including
Certificate
Welding
Valves)
QA\QC
ActivityID Piping Erection Resource Act Progress % QtyDone Weight Budget/Qty
PI.RA 45 35 15 5
1C420PIRA4010 Pipe Rack Piping Erection - MEG Train 3 10040.PI.PR.DI 99.92 3,421.25 0.127 3,421.250 100 100.00 99.60 99.60 back log progress
Laydown
Field 3,407.57 3407.57
796 796
Punch Listed A
Spool Erection
Supported &
(Including
Certificate
Welding
Valves)
QA\QC
ActivityID Piping Erection Resource Act Progress % QtyDone Weight Budget/Qty
PI.SB 30 50 15 5
1C420PISB4010 Small Bore Piping A/Equip. Erection - MEG Train 3 10040.PI.SB.DI 99.65 8,000.25 0.413 8,000.250 100 100 98.23 98.23 back log progress
7,858.65 7858.65
Tracer Fixing
ready for HT
Leak Testing
installation
Hidrotest)
(Steam or
Certificate
Tracers
QA\QC
ActivityID Heat / Steam Tracing Piping Resource Act Progress % QtyDone Weight Budget/Qty
PI.ST1 70 15 10 5
Installation/Con
Hydraulic Test
Fabrication &
Condensate
Installation
Certificate
Manifolds
Steam or
nection
Tracing
QA/QC
Line
ActivityID Steam / Condensate Manifolds Stations - Steam Tracing Piping Resource Act Progress % QtyDone Weight Budget/Qty
PI.ST2 25 20 40 10 5
Prefabrication
Certificate
Materials
QA\QC
Supply
ActivityID Piping Support Prefabrication Resource Act Progress % QtyDone Weight Budget/Qty
PI.SU1 35 60 5
1C420PISU4010 Piping Supports Prefabrication - MEG Train 3 10040.PI.PU.TN 100.00 46.00 0.029 46.000 100.00 100.00 100.00
Installation
Certificate
QA\QC
ActivityID Piping Support Erection Resource Act Progress % QtyDone Weight Budget/Qty
PI.SU2 95 5
1C420PISU4020 Piping Supports Erection - MEG Train 3 10040.PI.SU.TN 93.72 48.26 0.056 51.492 93.72 93.72
8 of 23
###
### Project: FADHILI GAS PLANT PROJECT (T-10040)
Level IV - PIPING WORK (SUNGCHANG)
UNIT-234
Painting/Touch
Identification
Certificate
QA/QC
Signs
Fluid
Final
up
ActivityID Piping & Support Finishing Painting (Final Coat & Touch Up) Resource Act Progress % QtyDone Weight Budget/Qty
PA.FP 85 10 5
1C420PAFP4010 Piping Final Coat & Touch-Up Painting - MEG Train 3 36.24 1858.6776 0.003 - 42.64
4,359.000
Sandblasting &
Coat Painting
Intermediate
Certificate
Primming
QA\QC
ActivityID Piping Primming (Prefabrication) Resource Act Progress % QtyDone Weight Budget/Qty
PA.PP 65 30 5
1C420PAPP4010 Piping SandBl. & Primming - MEG Train 3 10040.PA.PP.M2 100.00 3037.11 0.018 2,986.409 100.00 100.00 100.00
2,986.41 3,037.11 2986.41
2986.408903 2931.0774829
Sandblasting &
Coat Painting
Intermediate
Certificate
Primming
QA\QC
ActivityID Supports Painting (Prefabrication) Resource Act Progress % QtyDone Weight Budget/Qty
PA.SP 65 30 5
1C420PASP4010 Piping Supports SandBl. & Primming - MEG Train 3 10040.PA.SU.TN 100.00 44.10 0.001 44.100 100.00 100.00 100.00
44.10 44.10 44.10
44.1 44.1
Hydrotest
Folder
ActivityID Piping (Punch list A/Hydrotest/Flushing/Reinstatement) Resource Act Progress % QtyDone Weight Budget/Qty
PR.HT 20 80
1C420PRHT4010 Piping Hydrotesting - MEG Train 3 100.00 52637 0.050 52,637.000 100.00 100.00
52637
Flushing /
Blowing
ActivityID Piping (Punch list A/Hydrotest/Flushing/Reinstatement) Resource Act Progress % QtyDone Weight Budget/Qty
PR.FL 100
1C420PRFL4010 Piping Flushing/Blowing - MEG Train 3 100.00 52363 0.010 52,363.000 100.00
Reinstatement
Handover HCS
(Remaining)
Punch List B
Certificate
Certificate
QA/QC
ActivityID Piping (Punch list A/Hydrotest/Flushing/Reinstatement) Resource Act Progress % QtyDone Weight Budget/Qty
PR.RE 55 35 5 5
1C420PRRE4010 Piping Reinstatement - MEG Train 3 100.00 21763 0.040 21,763.000 100.00 100.00 100.00 100.00
Completed
Certificate
QA/QC
ActivityID Resource Act Progress % QtyDone Weight Budget/Qty
PR.PR 95 5
1C420PRPR4030 Walkthrough & NO Exception Items Clearance - MEG Train 3 65.70 2270 0.007 3,454.000 65.72 65.23
2253
Act Progress Weight
99.13% 1.1294
9 of 23
PROJECT No. : T-10040
PROJECT TITLE : FADHILI GAS PLANT PROJECT
CLIENT : SAUDI ARAMCO
LOCALIZATION : FADHILI, SAUDI ARABIA
CUT-OFF DATE : 30-Aug-19
HOLD by TR Subcontractor
TOTAL WORK
DISCIPLINE/UNIT TOTAL SCOPE TOTAL IFC TOTAL DONE (Engineering / Construction Restriction REMARKS
FRONT
Procurement) Sequence
10040 - Piping - Prefabrication Dia Inches (10040.PI.FB.DI)
200 98,136 98,136 98,136 0 ###
10040 - Piping - Big Bore Erection (Around Equipment) Dia Inches (10040.PI.BB.DI)
200 42,768 42,768 42,768 Engineering Hold (0") 0 ###
200 sourgas 8,941 8,941 8,941 Engineering Hold (0") 0
214 14,456 14,456 14,456 0 Engineering Hold (0") 0 ###
224 14,942 14,942 14,942 Engineering Hold (0") 0 ###
234 14,597 14,597 14,597 0 Engineering Hold (0") 0 ###
TOTAL 95,704 95,704 95,704 0 0 0 0 ###
10040 - Piping - Small Bore Erection (Around Equipment) Dia Inches (10040.PI.SB.DI)
200 19,082 19,082 19,082 0 Engineering Hold (0") 0 ###
214 7,992 8,023 7,992 0 25 Engineering Hold (0") 6 ###
224 8,149 8,149 8,149 Engineering Hold (0") 0 ###
234 8,000 8,000 8,000 60 Engineering Hold (0") 181 ###
TOTAL 43,223 43,254 43,223 0 85 0 187 ###
SIGNATURES
WorkFront Definition:
Approved by PD (SUNG) Approved by CM (TR)
WorkFront= Quantiy IFC 100% Constructible. Considering material available and without holds and construction interferences, in accumulated basis and
not considering a time period.
HOLD by TR Subcontractor
TOTAL WORK
DISCIPLINE/UNIT TOTAL SCOPE TOTAL IFC TOTAL DONE (Engineering / Construction Restriction REMARKS
FRONT
Procurement) Sequence
CUT-OFF DATE : 30-Aug-19 CUT-OFF DATE : 30-Aug-19
Done by TR Engineering department
PROJECT No. : T-10040
PROJECT TITLE : FADHILI GAS PLANT PROJECT
CLIENT : SAUDI ARAMCO
LOCALIZATION : FADHILI, SAUDI ARABIA
CUT-OFF DATE : 30-Aug-19
HOLD by TR Subcontractor
TOTAL WORK
DISCIPLINE/UNIT TOTAL SCOPE TOTAL IFC TOTAL DONE (Engineering / Construction Restriction REMARKS
FRONT
Procurement) Sequence
SIGNATURES
WorkFront Definition:
Approved by PD (SUNG) Approved by CM (TR)
WorkFront= Quantiy IFC 100% Constructible. Considering material available and without holds and construction interferences, in accumulated basis and
not considering a time period.
Total Done (TR):
Equivalent quantity by progress
PROJECT No. : T-10040
PROJECT TITLE : FADHILI GAS PLANT PROJECT
CLIENT : SAUDI ARAMCO
LOCALIZATION : FADHILI, SAUDI ARABIA
CUT-OFF DATE : 30-Aug-19
HOLD by TR Subcontractor
TOTAL WORK
DISCIPLINE/UNIT TOTAL SCOPE TOTAL IFC TOTAL DONE (Engineering / Construction Restriction REMARKS
FRONT
Procurement) Sequence
Total IFC (TR):
CUT-OFF DATE : 30-Aug-19 CUT-OFF DATE : 30-Aug-19
Done by TR Engineering department
Prefab
Actid Unit ResID BaseLine Budget DISPATCHED / IFC
1C420PIPR1010 200 10040.PI.FB.DI Early MC March 95648 95648
1C420PIPR2010 214 10040.PI.FB.DI Early MC March 27755.5 27755.5
1C420PIPR3010 224 10040.PI.FB.DI Early MC March 27328.5 27328.5
1C420PIPR4010 234 10040.PI.FB.DI Early MC March 27115.75 27115.75
Sour gas
Actid Unit ResID BaseLine Budget DISPATCHED / IFC
1C420PIPR1010 200 10040.PI.FB.DI Early MC March 2488 2488
Bigbore
Actid Unit ResID BORE BaseLine Budget
1C420PIBB1010 200 10040.PI.BB.DI Big Bore Early MC March 19 TR 42767.75
1C420PIBB2010 214 10040.PI.BB.DI Big Bore Early MC March 19 TR 14456.25
1C420PIBB3010 224 10040.PI.BB.DI Big Bore Early MC March 19 TR 14941.75
1C420PIBB4010 234 10040.PI.BB.DI Big Bore Early MC March 19 TR 14597.25
Sour gas
Actid Unit ResID BORE BaseLine PCS Budget
1C420PIBB1010 200 10040.PI.BB.DI Big Bore Early MC March 19 TR 8941.25
Sour gas
Actid Unit ResID BaseLine PCS Budget DISPATCHED / IFC
1C420PISU1010 200 10040.PI.PU.TN Early MC March 64.6979631730235 64.6979631730235
237807 1C420PRFL1010
54521 1C420PRFL2010
58307 1C420PRFL3010
52363 1C420PRFL4010
212242 1C420PRRE1010
26171 1C420PRRE2010
57972 1C420PRRE3010
21763 1C420PRRE4010
Progress INCHES
0
0
0
0
0
0
0
0
Progress M2