Project: FADHILI GAS PLANT PROJECT (T-10040)

Level IV - PIPING WORK (SUNGCHANG)

Cut-off date: 30-Aug-19

Unit Discipline % Weight % Progress

PACKAGE 1 PIPING 8.638% 99.61%

UNIT 42 PIPING 8.638% 99.61%

200 PIPING 5.2879% 99.79%

214 PIPING 1.0927% 99.30%

224 PIPING 1.1278% 99.55%

234 PIPING 1.1294% 99.13%

SIGNATURES
Prepared by
Approved by TR Construction Approved by TR Planning
Subcontractor

Name: Leonardo Denia Name: Prabakaran Selvaraj


NAME: Chulsoo Kim
Construction Area Manager Planning Engineer
Project Director
(Area D42)
DATE: 30-Aug-2019 DATE: 30-Aug-2019 DATE: 30-Aug-2019

1 of 23
###
### Project: FADHILI GAS PLANT PROJECT (T-10040)
Level IV - PIPING WORK (SUNGCHANG)
UNIT-200

Cut-off date: 8/30/2019

Punch Listed A
Spool Erection

Supported &

Certificate
(Including
Welding

Valves)

QA/QC
ActivityID Piping Erection Resource Act Progress % QtyDone Weight Budget/Qty

PI.BB 45 35 15 5

1C420PIBB1010 Big Bore Piping A/Equip. Erection - Inlet Facilities 10040.PI.BB.DI 99.95 51709 0.573 51,709.000 100.00 100.00 99.77 99.77 back log progress
Big Bore Piping A/Equip. Erection - Inlet Facilities 42767.75 42,767.750 100.00 100.00 0.00 0.00
Big Bore Piping A/Equip. Erection - Inlet Facilities - Sour gas 8941.25 8,941.250 100.00 100.00 0.00 0.00
51,587.48 51587.48385

Cutting/Bevelin
g & Alignment

Certificate
Welding

QA/QC
ActivityID Piping Prefabrication Resource Act Progress % QtyDone Weight Budget/Qty

PI.PR 35 60 5

1C420PIPR1010 Piping Prefabrication - Inlet Facilities 10040.PI.FB.DI 100.00 98,136.00 0.630 98,136.000 100.00 100.00 100.00
50.66449603 41.50 0

Punch Listed A
Spool Erection

Supported &
(Including

Certificate
Welding

Valves)

QA\QC
ActivityID Piping Erection Resource Act Progress % QtyDone Weight Budget/Qty

PI.RA 45 35 15 5

1C420PIRA1010 Pipe Rack Piping Erection - Inlet Facilities 10040.PI.PR.DI 100.00 67,174.50 0.870 67,174.500 100.00 100.00 99.995 99.995 back log progress
Pipe Rack Piping Erection - Inlet Facilities 48,526.00 48,526.000 100 100.00 62.44064551 62.4406455 99.995
Pipe Rack Piping Erection - Inlet Facilities- sour gas 18,648.50 18,648.500 100 100.00 28.029441685 28.0294417
67,171.14 67171.1413

Punch Listed A
Spool Erection

Supported &
(Including

Certificate
Welding

Valves)

QA\QC
ActivityID Piping Erection Resource Act Progress % QtyDone Weight Budget/Qty

PI.SB 30 50 15 5

1C420PISB1010 Small Bore Piping A/Equip. Erection - Inlet Facilities 10040.PI.SB.DI 99.96 19081.75 1.348 19,081.750 100 100 99.78 99.78 back log progress
19,039.77 19039.7702

Tracer Fixing
ready for HT

Leak Testing
installation

Hidrotest)
(Steam or

Certificate
Tracers

QA\QC
ActivityID Heat / Steam Tracing Piping Resource Act Progress % QtyDone Weight Budget/Qty

PI.ST1 70 15 10 5

1C420PIST1010 Piping Steam Tracing Install. - Inlet Facilities 0.00

Installation/Con

Hydraulic Test
Fabrication &

Condensate
Installation

Certificate
Manifolds

Steam or

nection
Tracing

QA/QC
Line
ActivityID Steam / Condensate Manifolds Stations - Steam Tracing Piping Resource Act Progress % QtyDone Weight Budget/Qty

PI.ST2 25 20 40 10 5

1C420PIST1020 Steam/Condensate Manifolds Stations Install. - Inlet Facilities 0.00

Prefabrication

Certificate
Materials

QA\QC
Supply
ActivityID Piping Support Prefabrication Resource Act Progress % QtyDone Weight Budget/Qty

PI.SU1 35 60 5

1C420PISU1010 Piping Supports Prefabrication - Inlet Facilities 10040.PI.PU.TN 100.00 283.10 0.380 283.100 100.00 100.00 100.00

Installation

Certificate
QA\QC
ActivityID Piping Support Erection Resource Act Progress % QtyDone Weight Budget/Qty

PI.SU2 95 5

1C420PISU1020 Piping Supports Erection - Inlet Facilities 10040.PI.SU.TN 99.78 309.05 0.724 309.737 99.78 99.78
Piping Supports Erection - Inlet Facilities 244.52 244.518 100.00 98.03
Piping Supports Erection - Inlet Facilities - Sourgas 64.53 65.219 98.95 94.35

2 of 23
###
### Project: FADHILI GAS PLANT PROJECT (T-10040)
Level IV - PIPING WORK (SUNGCHANG)
UNIT-200

Cut-off date: 8/30/2019

Painting/Touch

Identification

Certificate
QA/QC
Signs
Fluid
Final

up
ActivityID Piping & Support Finishing Painting (Final Coat & Touch Up) Resource Act Progress % QtyDone Weight Budget/Qty

PA.FP 85 10 5

1C420PAFP1010 Piping Final Coat & Touch-Up Painting - Inlet Facilities 87.87 44788 0.034 126,456.000 99.85 20.00 20.00
12,645.60 44,856.000

Sandblasting &

Coat Painting
Intermediate

Certificate
Primming

QA\QC
ActivityID Piping Primming (Prefabrication) Resource Act Progress % QtyDone Weight Budget/Qty

PA.PP 65 30 5

1C420PAPP1010 Piping SandBl. & Primming - Inlet Facilities 10040.PA.PP.M2 99.93 37,959.55 0.217 38,039.759 100.00 99.79 99.79
38039.76 37959.55 37959.55 38039.7588 37034.9

Sandblasting &

Coat Painting
Intermediate

Certificate
Primming

QA\QC
ActivityID Supports Painting (Prefabrication) Resource Act Progress % QtyDone Weight Budget/Qty

PA.SP 65 30 5

1C420PASP1010 Piping Supports SandBl. & Primming - Inlet Facilities 10040.PA.SU.TN 100.00 275.53 0.014 275.531 100.00 100.00 100.00
Piping Supports SandBl. & Primming - Inlet Facilities 239.93 239.931 100.00 100.00 100.00
Piping Supports SandBl. & Primming - Inlet Facilities - Sour gas 35.51 35.600 100.00 100.00 100.00 35.60 37.4429
259.80 259.80 259.80 259.6 254.505

Hydrotest
Folder
ActivityID Piping (Punch list A/Hydrotest/Flushing/Reinstatement) Resource Act Progress % QtyDone Weight Budget/Qty

PR.HT 20 80

1C420PRHT1010 Piping Hydrotesting - Inlet Facilities 99.66 254149 0.226 255,019.000 99.66 99.66
254149 254149

Flushing /
Blowing
ActivityID Piping (Punch list A/Hydrotest/Flushing/Reinstatement) Resource Act Progress % QtyDone Weight Budget/Qty

PR.FL 100

1C420PRFL1010 Piping Flushing/Blowing - Inlet Facilities 100.00 237807 0.045 237,807.000 100

Reinstatement

Handover HCS
(Remaining)
Punch List B

Certificate

Certificate
QA/QC
ActivityID Piping (Punch list A/Hydrotest/Flushing/Reinstatement) Resource Act Progress % QtyDone Weight Budget/Qty

PR.RE 55 35 5 5

1C420PRRE1010 Piping Reinstatement - Inlet Facilities 100.00 212242 0.181 212,242.000 100.000 100.00 100.000 100.000

Completed

Certificate
QA/QC
ActivityID Resource Act Progress % QtyDone Weight Budget/Qty

PR.PR 95 5

1C420PRPR1030 Walkthrough & NO Exception Items Clearance - Inlet Facilities 91.73 11729 0.044 12,764.000 91.89 88.67
11318
Act Progress Weight
99.79% 5.2879

3 of 23
###
### Project: FADHILI GAS PLANT PROJECT (T-10040)
Level IV - PIPING WORK (SUNGCHANG)
UNIT-214

Cut-off date: 8/30/2019

Punch Listed A
Spool Erection

Supported &

Certificate
(Including
Welding

Valves)

QA/QC
ActivityID Piping Erection Resource Act Progress % QtyDone Weight Budget/Qty

PI.BB 45 35 15 5

1C420PIBB2010 Big Bore Piping A/Equip. Erection - MEG Train 1 10040.PI.BB.DI 99.69 14,456.25 0.215 14,456.250 100.00 100.00 98.47 98.47 back log progress
14,235.07 14,235.07

Cutting/Bevelin
g & Alignment

Certificate
Welding

QA/QC
ActivityID Piping Prefabrication Resource Act Progress % QtyDone Weight Budget/Qty

PI.PR 35 60 5

1C420PIPR2010 Piping Prefabrication - MEG Train 1 10040.PI.FB.DI 100.00 27,755.50 0.147 27,755.500 100.00 100.00 100.00
79.766807794 17.8 60.85 39.15

Punch Listed A
Spool Erection

Supported &
(Including

Certificate
Welding

Valves)

QA\QC
ActivityID Piping Erection Resource Act Progress % QtyDone Weight Budget/Qty

PI.RA 45 35 15 5

1C420PIRA2010 Pipe Rack Piping Erection - MEG Train 1 10040.PI.PR.DI 99.89 3,374.62 0.117 3,378.000 99.9 99.9 99.86 99.86 back log progress
1C420PIRA2010 Laydown 3,378.00
Field 3,373.27 3373.2708

Punch Listed A
Spool Erection

Supported &
(Including

Certificate
Welding

Valves)

QA\QC
ActivityID Piping Erection Resource Act Progress % QtyDone Weight Budget/Qty

PI.SB 30 50 15 5

1C420PISB2010 Small Bore Piping A/Equip. Erection - MEG Train 1 10040.PI.SB.DI 99.95 7,992.00 0.404 7,992.000 100.00 100.00 99.77 99.77 welding done - spool erection must done also
7974 7974

Tracer Fixing
ready for HT

Leak Testing
installation

Hidrotest)
(Steam or

Certificate
Tracers

QA\QC
ActivityID Heat / Steam Tracing Piping Resource Act Progress % QtyDone Weight Budget/Qty

PI.ST1 70 15 10 5

1C420PIST2010 Piping Steam Tracing Install. - MEG Train 1 0.00

Installation/Con

Hydraulic Test
Fabrication &

Condensate
Installation

Certificate
Manifolds

Steam or

nection
Tracing

QA/QC
Line
ActivityID Steam / Condensate Manifolds Stations - Steam Tracing Piping Resource Act Progress % QtyDone Weight Budget/Qty

PI.ST2 25 20 40 10 5

1C420PIST2020 Steam/Condensate Manifolds Stations Install. - MEG Train 1 0.00

Prefabrication

Certificate
Materials

QA\QC
Supply
ActivityID Piping Support Prefabrication Resource Act Progress % QtyDone Weight Budget/Qty

PI.SU1 35 60 5

1C420PISU2010 Piping Supports Prefabrication - MEG Train 1 10040.PI.PU.TN 100.00 46.00 0.029 46.000 100.00 100.00 100

Installation

Certificate
QA\QC
ActivityID Piping Support Erection Resource Act Progress % QtyDone Weight Budget/Qty

PI.SU2 95 5

1C420PISU2020 Piping Supports Erection - MEG Train 1 10040.PI.SU.TN 93.53 48.14 0.055 51.474 93.53 93.53

4 of 23
###
### Project: FADHILI GAS PLANT PROJECT (T-10040)
Level IV - PIPING WORK (SUNGCHANG)
UNIT-214

Cut-off date: 8/30/2019

Painting/Touch

Identification

Certificate
QA/QC
Signs
Final

Fluid
up
ActivityID Piping & Support Finishing Painting (Final Coat & Touch Up) Resource Act Progress % QtyDone Weight Budget/Qty

PA.FP 85 10 5

1C420PAFP2010 Piping Final Coat & Touch-Up Painting - MEG Train 1 56.21 902 0.003 - 66.129032258
1,364.000

Sandblasting &

Coat Painting
Intermediate

Certificate
Primming

QA\QC
ActivityID Piping Primming (Prefabrication) Resource Act Progress % QtyDone Weight Budget/Qty

PA.PP 65 30 5

1C420PAPP2010 Piping SandBl. & Primming - MEG Train 1 10040.PA.PP.M2 98.30 3000.99 0.018 3,058.956 98.40 98.10 98.10
3010.08 3000.99 3000.99
3010.080904 2992.156

Sandblasting &

Coat Painting
Intermediate

Certificate
Primming

QA\QC
ActivityID Supports Painting (Prefabrication) Resource Act Progress % QtyDone Weight Budget/Qty

PA.SP 65 30 5

1C420PASP2010 Piping Supports SandBl. & Primming - MEG Train 1 10040.PA.SU.TN 100.00 44.70 0.001 44.700 100.00 100.00 100.00
44.70 44.70 44.70
45 45

Hydrotest
Folder
ActivityID Piping (Punch list A/Hydrotest/Flushing/Reinstatement) Resource Act Progress % QtyDone Weight Budget/Qty

PR.HT 20 80

1C420PRHT2010 Piping Hydrotesting - MEG Train 1 99.97 54799 0.048 54,816.000 99.97 99.97
54799 54799

Flushing /
Blowing
ActivityID Piping (Punch list A/Hydrotest/Flushing/Reinstatement) Resource Act Progress % QtyDone Weight Budget/Qty

PR.FL 100

1C420PRFL2010 Piping Flushing/Blowing - MEG Train 1 100.00 54521 0.010 54,521.000 100.00

Reinstatement

Handover HCS
(Remaining)
Punch List B

Certificate

Certificate
QA/QC
ActivityID Piping (Punch list A/Hydrotest/Flushing/Reinstatement) Resource Act Progress % QtyDone Weight Budget/Qty

PR.RE 55 35 5 5

1C420PRRE2010 Piping Reinstatement - MEG Train 1 100.00 26171 0.039 26,171.000 100.00 100.00 100.00 100.00

Completed

Certificate
QA/QC
ActivityID Resource Act Progress % QtyDone Weight Budget/Qty

PR.PR 95 5

1C420PRPR2030 Walkthrough & NO Exception Items Clearance - MEG Train 1 79.09 2920 0.007 3,676.000 79.43 72.50
2665
Act Progress Weight
99.30% 1.0927

5 of 23
###
### Project: FADHILI GAS PLANT PROJECT (T-10040)
Level IV - PIPING WORK (SUNGCHANG)
UNIT-224

Cut-off date: 8/30/2019

Punch Listed A
Spool Erection

Supported &

Certificate
(Including
Welding

Valves)

QA/QC
ActivityID Piping Erection Resource Act Progress % QtyDone Weight Budget/Qty

PI.BB 45 35 15 5

1C420PIBB3010 Big Bore Piping A/Equip. Erection - MEG Train 2 10040.PI.BB.DI 100.00 14941.75 0.231 14,941.750 100 100.00 99.99 99.99
14,940.26 14940.2558

Cutting/Bevelin
g & Alignment

Certificate
Welding

QA/QC
ActivityID Piping Prefabrication Resource Act Progress % QtyDone Weight Budget/Qty

PI.PR 35 60 5

1C420PIPR3010 Piping Prefabrication - MEG Train 2 10040.PI.FB.DI 100.00 27,328.50 0.144 27,328.500 100.00 100.00 100.00
77.4474315083 21.00 60 40.00

Punch Listed A
Spool Erection

Supported &
(Including

Certificate
Welding

Valves)

QA\QC
ActivityID Piping Erection Resource Act Progress % QtyDone Weight Budget/Qty

PI.RA 45 35 15 5

1C420PIRA3010 Pipe Rack Piping Erection - MEG Train 2 10040.PI.PR.DI 99.99 3,324.25 0.126 3,324.250 100.00 100.00 99.97 99.97
Laydown
Field 3,323.42 3323.41763

Punch Listed A
Spool Erection

Supported &
(Including

Certificate
Welding

Valves)

QA\QC
ActivityID Piping Erection Resource Act Progress % QtyDone Weight Budget/Qty

PI.SB 30 50 15 5

1C420PISB3010 Small Bore Piping A/Equip. Erection - MEG Train 2 10040.PI.SB.DI 100.00 8,149.25 0.413 8,149.250 100 100 99.99 99.99
8,148.44 8148.43508

Tracer Fixing
ready for HT

Leak Testing
installation

Hidrotest)
(Steam or

Certificate
Tracers

QA\QC
ActivityID Heat / Steam Tracing Piping Resource Act Progress % QtyDone Weight Budget/Qty

PI.ST1 70 15 10 5

1C420PIST3010 Piping Steam Tracing Install. - MEG Train 2 0.00

Installation/Con

Hydraulic Test
Fabrication &

Condensate
Installation

Certificate
Manifolds

Steam or

nection
Tracing

QA/QC
Line
ActivityID Steam / Condensate Manifolds Stations - Steam Tracing Piping Resource Act Progress % QtyDone Weight Budget/Qty

PI.ST2 25 20 40 10 5

1C420PIST3020 Steam/Condensate Manifolds Stations Install. - MEG Train 2 0.00

Prefabrication

Certificate
Materials

QA\QC
Supply
ActivityID Piping Support Prefabrication Resource Act Progress % QtyDone Weight Budget/Qty

PI.SU1 35 60 5

1C420PISU3010 Piping Supports Prefabrication - MEG Train 2 10040.PI.PU.TN 100.00 46.40 0.029 46.400 100.00 100.00 100.00

Installation

Certificate
QA\QC
ActivityID Piping Support Erection Resource Act Progress % QtyDone Weight Budget/Qty

PI.SU2 95 5

1C420PISU3020 Piping Supports Erection - MEG Train 2 10040.PI.SU.TN 93.98 48.50 0.056 51.609 93.98 93.98

6 of 23
###
### Project: FADHILI GAS PLANT PROJECT (T-10040)
Level IV - PIPING WORK (SUNGCHANG)
UNIT-224

Cut-off date: 8/30/2019

Painting/Touch

Identification

Certificate
QA/QC
Signs
Final

Fluid
up
ActivityID Piping & Support Finishing Painting (Final Coat & Touch Up) Resource Act Progress % QtyDone Weight Budget/Qty

PA.FP 85 10 5

1C420PAFP3010 Piping Final Coat & Touch-Up Painting - MEG Train 2 86.30 17248.44 0.003 23,628.000 99.77 10.00 10.00
14468 14,502.000

Sandblasting &

Coat Painting
Intermediate

Certificate
Primming

QA\QC
ActivityID Piping Primming (Prefabrication) Resource Act Progress % QtyDone Weight Budget/Qty

PA.PP 65 30 5

1C420PAPP3010 Piping SandBl. & Primming - MEG Train 2 10040.PA.PP.M2 99.46 3051.42 0.018 3,099.011 100.00 98.46 98.46
3,099.01 3,051.42 3051.42
3055.02547729 2992.8816442

Sandblasting &

Coat Painting
Intermediate

Certificate
Primming

QA\QC
ActivityID Supports Painting (Prefabrication) Resource Act Progress % QtyDone Weight Budget/Qty

PA.SP 65 30 5

1C420PASP3010 Piping Supports SandBl. & Primming - MEG Train 2 10040.PA.SU.TN 100.00 46.55 0.001 46.554 100.00 100.00 100.00
45.00 46.55 45.00
45 45

Hydrotest
Folder
ActivityID Piping (Punch list A/Hydrotest/Flushing/Reinstatement) Resource Act Progress % QtyDone Weight Budget/Qty

PR.HT 20 80

1C420PRHT3010 Piping Hydrotesting - MEG Train 2 99.99 58411.5 0.050 58,420.000 100.00 99.99
58,420.00 58411.5

Flushing /
Blowing
ActivityID Piping (Punch list A/Hydrotest/Flushing/Reinstatement) Resource Act Progress % QtyDone Weight Budget/Qty

PR.FL 100

1C420PRFL3010 Piping Flushing/Blowing - MEG Train 2 100.00 58307 0.010 58,307.000 100.00

Reinstatement

Handover HCS
(Remaining)
Punch List B

Certificate

Certificate
QA/QC
ActivityID Piping (Punch list A/Hydrotest/Flushing/Reinstatement) Resource Act Progress % QtyDone Weight Budget/Qty

PR.RE 55 35 5 5

1C420PRRE3010 Piping Reinstatement - MEG Train 2 98.61 57972 0.040 57,972.000 99.43 97.62 97.62 97.62

Completed

Certificate
QA/QC
ActivityID Resource Act Progress % QtyDone Weight Budget/Qty

PR.PR 95 5

1C420PRPR3030 Walkthrough & NO Exception Items Clearance - MEG Train 2 91.64 3756 0.007 4,087.000 91.90 86.62
3540
Act Progress Weight
99.55% 1.1278

7 of 23
###
### Project: FADHILI GAS PLANT PROJECT (T-10040)
Level IV - PIPING WORK (SUNGCHANG)
UNIT-234

Cut-off date: 8/30/2019

Punch Listed A
Spool Erection

Supported &

Certificate
(Including
Welding

Valves)

QA/QC
ActivityID Piping Erection Resource Act Progress % QtyDone Weight Budget/Qty

PI.BB 45 35 15 5

1C420PIBB4010 Big Bore Piping A/Equip. Erection - MEG Train 3 10040.PI.BB.DI 99.85 14,597.25 0.232 14,597.250 100.00 100.00 99.24 99.24 back log progress
14,486.31 14486.3

Cutting/Bevelin
g & Alignment

Certificate
Welding

QA/QC
ActivityID Piping Prefabrication Resource Act Progress % QtyDone Weight Budget/Qty

PI.PR 35 60 5

1C420PIPR4010 Piping Prefabrication - MEG Train 3 10040.PI.FB.DI 100.00 27,115.75 0.144 27,115.750 100.00 100.00 100.00
70.37505785 19.00 55 45.00

Punch Listed A
Spool Erection

Supported &
(Including

Certificate
Welding

Valves)

QA\QC
ActivityID Piping Erection Resource Act Progress % QtyDone Weight Budget/Qty

PI.RA 45 35 15 5

1C420PIRA4010 Pipe Rack Piping Erection - MEG Train 3 10040.PI.PR.DI 99.92 3,421.25 0.127 3,421.250 100 100.00 99.60 99.60 back log progress
Laydown
Field 3,407.57 3407.57
796 796

Punch Listed A
Spool Erection

Supported &
(Including

Certificate
Welding

Valves)

QA\QC
ActivityID Piping Erection Resource Act Progress % QtyDone Weight Budget/Qty

PI.SB 30 50 15 5

1C420PISB4010 Small Bore Piping A/Equip. Erection - MEG Train 3 10040.PI.SB.DI 99.65 8,000.25 0.413 8,000.250 100 100 98.23 98.23 back log progress
7,858.65 7858.65

Tracer Fixing
ready for HT

Leak Testing
installation

Hidrotest)
(Steam or

Certificate
Tracers

QA\QC
ActivityID Heat / Steam Tracing Piping Resource Act Progress % QtyDone Weight Budget/Qty

PI.ST1 70 15 10 5

1C420PIST4010 Piping Steam Tracing Install. - MEG Train 3 0.00

Installation/Con

Hydraulic Test
Fabrication &

Condensate
Installation

Certificate
Manifolds

Steam or

nection
Tracing

QA/QC
Line
ActivityID Steam / Condensate Manifolds Stations - Steam Tracing Piping Resource Act Progress % QtyDone Weight Budget/Qty

PI.ST2 25 20 40 10 5

1C420PIST4020 Steam/Condensate Manifolds Stations Install. - MEG Train 3 0.00

Prefabrication

Certificate
Materials

QA\QC
Supply
ActivityID Piping Support Prefabrication Resource Act Progress % QtyDone Weight Budget/Qty

PI.SU1 35 60 5

1C420PISU4010 Piping Supports Prefabrication - MEG Train 3 10040.PI.PU.TN 100.00 46.00 0.029 46.000 100.00 100.00 100.00

Installation

Certificate
QA\QC
ActivityID Piping Support Erection Resource Act Progress % QtyDone Weight Budget/Qty

PI.SU2 95 5

1C420PISU4020 Piping Supports Erection - MEG Train 3 10040.PI.SU.TN 93.72 48.26 0.056 51.492 93.72 93.72

8 of 23
###
### Project: FADHILI GAS PLANT PROJECT (T-10040)
Level IV - PIPING WORK (SUNGCHANG)
UNIT-234

Cut-off date: 8/30/2019

Painting/Touch

Identification

Certificate
QA/QC
Signs
Fluid
Final

up
ActivityID Piping & Support Finishing Painting (Final Coat & Touch Up) Resource Act Progress % QtyDone Weight Budget/Qty

PA.FP 85 10 5

1C420PAFP4010 Piping Final Coat & Touch-Up Painting - MEG Train 3 36.24 1858.6776 0.003 - 42.64
4,359.000

Sandblasting &

Coat Painting
Intermediate

Certificate
Primming

QA\QC
ActivityID Piping Primming (Prefabrication) Resource Act Progress % QtyDone Weight Budget/Qty

PA.PP 65 30 5

1C420PAPP4010 Piping SandBl. & Primming - MEG Train 3 10040.PA.PP.M2 100.00 3037.11 0.018 2,986.409 100.00 100.00 100.00
2,986.41 3,037.11 2986.41
2986.408903 2931.0774829

Sandblasting &

Coat Painting
Intermediate

Certificate
Primming

QA\QC
ActivityID Supports Painting (Prefabrication) Resource Act Progress % QtyDone Weight Budget/Qty

PA.SP 65 30 5

1C420PASP4010 Piping Supports SandBl. & Primming - MEG Train 3 10040.PA.SU.TN 100.00 44.10 0.001 44.100 100.00 100.00 100.00
44.10 44.10 44.10
44.1 44.1

Hydrotest
Folder
ActivityID Piping (Punch list A/Hydrotest/Flushing/Reinstatement) Resource Act Progress % QtyDone Weight Budget/Qty

PR.HT 20 80

1C420PRHT4010 Piping Hydrotesting - MEG Train 3 100.00 52637 0.050 52,637.000 100.00 100.00
52637

Flushing /
Blowing
ActivityID Piping (Punch list A/Hydrotest/Flushing/Reinstatement) Resource Act Progress % QtyDone Weight Budget/Qty

PR.FL 100

1C420PRFL4010 Piping Flushing/Blowing - MEG Train 3 100.00 52363 0.010 52,363.000 100.00

Reinstatement

Handover HCS
(Remaining)
Punch List B

Certificate

Certificate
QA/QC
ActivityID Piping (Punch list A/Hydrotest/Flushing/Reinstatement) Resource Act Progress % QtyDone Weight Budget/Qty

PR.RE 55 35 5 5

1C420PRRE4010 Piping Reinstatement - MEG Train 3 100.00 21763 0.040 21,763.000 100.00 100.00 100.00 100.00

Completed

Certificate
QA/QC
ActivityID Resource Act Progress % QtyDone Weight Budget/Qty

PR.PR 95 5

1C420PRPR4030 Walkthrough & NO Exception Items Clearance - MEG Train 3 65.70 2270 0.007 3,454.000 65.72 65.23
2253
Act Progress Weight
99.13% 1.1294

9 of 23
PROJECT No. : T-10040
PROJECT TITLE : FADHILI GAS PLANT PROJECT
CLIENT : SAUDI ARAMCO
LOCALIZATION : FADHILI, SAUDI ARABIA
CUT-OFF DATE : 30-Aug-19

HOLD by TR Subcontractor
TOTAL WORK
DISCIPLINE/UNIT TOTAL SCOPE TOTAL IFC TOTAL DONE (Engineering / Construction Restriction REMARKS
FRONT
Procurement) Sequence
10040 - Piping - Prefabrication Dia Inches (10040.PI.FB.DI)
200 98,136 98,136 98,136 0 ###

214 27,756 27,756 27,756 0 ###

224 27,329 27,329 27,329 0 ###

234 27,116 27,116 27,116 0 ###

TOTAL 180,336 180,336 180,336 0 0 0 ###

10040 - Piping - Rack Erection Dia Inches (10040.PI.PR.DI)


200 48,526 48,526 48,526 0 Engineering Hold (0") 0 ###

200 sourgas 18,649 18,649 18,649 Engineering Hold (0") 0

214 3,378 3,378 3,375 0 1 Engineering Hold (0") 3 ###

224 3,324 3,324 3,324 0 Engineering Hold (0") 0 ###

234 3,421 3,421 3,421 0 0 Engineering Hold (0") 0 ###


TOTAL 77,298 77,298 77,295 0 1 0 3 ###

10040 - Piping - Big Bore Erection (Around Equipment) Dia Inches (10040.PI.BB.DI)
200 42,768 42,768 42,768 Engineering Hold (0") 0 ###
200 sourgas 8,941 8,941 8,941 Engineering Hold (0") 0
214 14,456 14,456 14,456 0 Engineering Hold (0") 0 ###
224 14,942 14,942 14,942 Engineering Hold (0") 0 ###
234 14,597 14,597 14,597 0 Engineering Hold (0") 0 ###
TOTAL 95,704 95,704 95,704 0 0 0 0 ###

10040 - Piping - Small Bore Erection (Around Equipment) Dia Inches (10040.PI.SB.DI)
200 19,082 19,082 19,082 0 Engineering Hold (0") 0 ###
214 7,992 8,023 7,992 0 25 Engineering Hold (0") 6 ###
224 8,149 8,149 8,149 Engineering Hold (0") 0 ###
234 8,000 8,000 8,000 60 Engineering Hold (0") 181 ###
TOTAL 43,223 43,254 43,223 0 85 0 187 ###

SIGNATURES

WorkFront Definition:
Approved by PD (SUNG) Approved by CM (TR)
WorkFront= Quantiy IFC 100% Constructible. Considering material available and without holds and construction interferences, in accumulated basis and
not considering a time period.

Total Done (TR):


Equivalent quantity by progress
Total IFC (TR):
PROJECT No. : T-10040
PROJECT TITLE : FADHILI GAS PLANT PROJECT
CLIENT : SAUDI ARAMCO
LOCALIZATION : FADHILI, SAUDI ARABIA
CUT-OFF DATE : 30-Aug-19

HOLD by TR Subcontractor
TOTAL WORK
DISCIPLINE/UNIT TOTAL SCOPE TOTAL IFC TOTAL DONE (Engineering / Construction Restriction REMARKS
FRONT
Procurement) Sequence
CUT-OFF DATE : 30-Aug-19 CUT-OFF DATE : 30-Aug-19
Done by TR Engineering department
PROJECT No. : T-10040
PROJECT TITLE : FADHILI GAS PLANT PROJECT
CLIENT : SAUDI ARAMCO
LOCALIZATION : FADHILI, SAUDI ARABIA
CUT-OFF DATE : 30-Aug-19

HOLD by TR Subcontractor
TOTAL WORK
DISCIPLINE/UNIT TOTAL SCOPE TOTAL IFC TOTAL DONE (Engineering / Construction Restriction REMARKS
FRONT
Procurement) Sequence

10040 - Piping - Piping Painting (10040.PA.PP.M2)


200 38,040 37,960 37,960 0 ###
214 3,059 3,001 3,001 0 ###
224 3,099 3,051 3,051 0 0 ###
234 2,986 3,037 3,037 0 ###
TOTAL 47,184 47,049 47,049 0 0 0 0 ###

10040 - Piping - Piping Supports Prefabrication (10040.PI.PU.TN)


200 283 283 283 0 ###
214 46 46 46 0 ###
224 46 46 46 0 ###
234 46 46 46 0 ###
TOTAL 422 422 422 0 0 0 ###

10040 - Piping - Piping Supports Painting (10040.PA.SU.TN)


200 239.93 240 240 0 ###
200 sourgas 35.60 36 36 0
214 45 45 45 0 ###
224 47 47 47 0 ###
234 44 44 44 0 ###
TOTAL 411 411 410.80 0 0 0 0 ###

10040 - Piping - Piping Supports Erection (10040.PI.SU.TN)


200 245 245 245 0 ###
200 sourgas 65 65 65 1
214 51 52 48 4 ###
224 52 52 49 4 ###
234 51 52 48 4 ###
TOTAL 464 466 454 0 0 0 12 ###

10040 - Piping - Piping Hydrotesting


200 255,019 255,230 254,149 1,081 ###
214 54,816 54,816 54,799 17 ###
224 58,420 58,420 58,412 9 ###
234 52,637 52,637 52,637 0 ###
TOTAL 420,892 421,103 419,997 0 0 0 1,107 ###

SIGNATURES

WorkFront Definition:
Approved by PD (SUNG) Approved by CM (TR)
WorkFront= Quantiy IFC 100% Constructible. Considering material available and without holds and construction interferences, in accumulated basis and
not considering a time period.
Total Done (TR):
Equivalent quantity by progress
PROJECT No. : T-10040
PROJECT TITLE : FADHILI GAS PLANT PROJECT
CLIENT : SAUDI ARAMCO
LOCALIZATION : FADHILI, SAUDI ARABIA
CUT-OFF DATE : 30-Aug-19

HOLD by TR Subcontractor
TOTAL WORK
DISCIPLINE/UNIT TOTAL SCOPE TOTAL IFC TOTAL DONE (Engineering / Construction Restriction REMARKS
FRONT
Procurement) Sequence
Total IFC (TR):
CUT-OFF DATE : 30-Aug-19 CUT-OFF DATE : 30-Aug-19
Done by TR Engineering department
Prefab
Actid Unit ResID BaseLine Budget DISPATCHED / IFC
1C420PIPR1010 200 10040.PI.FB.DI Early MC March 95648 95648
1C420PIPR2010 214 10040.PI.FB.DI Early MC March 27755.5 27755.5
1C420PIPR3010 224 10040.PI.FB.DI Early MC March 27328.5 27328.5
1C420PIPR4010 234 10040.PI.FB.DI Early MC March 27115.75 27115.75
Sour gas
Actid Unit ResID BaseLine Budget DISPATCHED / IFC
1C420PIPR1010 200 10040.PI.FB.DI Early MC March 2488 2488

Bigbore
Actid Unit ResID BORE BaseLine Budget
1C420PIBB1010 200 10040.PI.BB.DI Big Bore Early MC March 19 TR 42767.75
1C420PIBB2010 214 10040.PI.BB.DI Big Bore Early MC March 19 TR 14456.25
1C420PIBB3010 224 10040.PI.BB.DI Big Bore Early MC March 19 TR 14941.75
1C420PIBB4010 234 10040.PI.BB.DI Big Bore Early MC March 19 TR 14597.25
Sour gas
Actid Unit ResID BORE BaseLine PCS Budget
1C420PIBB1010 200 10040.PI.BB.DI Big Bore Early MC March 19 TR 8941.25

Actid Unit ResID BORE BaseLine Budget


1C420PISB1010 200 10040.PI.SB.DI Small Bore Early MC March 19 TR 19081.75
1C420PISB2010 214 10040.PI.SB.DI Small Bore Early MC March 19 TR 7992
1C420PISB3010 224 10040.PI.SB.DI Small Bore Early MC March 19 TR 8149
1C420PISB4010 234 10040.PI.SB.DI Small Bore Early MC March 19 TR 8000.25

Actid Unit ResID LOCATION BaseLine Budget


1C420PIRA1010 200 10040.PI.PR.DI Rack Erection Early MC March 19 TR 48526
1C420PIRA2010 214 10040.PI.PR.DI Rack Erection Early MC March 19 TR 3378
1C420PIRA3010 224 10040.PI.PR.DI Rack Erection Early MC March 19 TR 3324.25
1C420PIRA4010 234 10040.PI.PR.DI Rack Erection Early MC March 19 TR 3421.25

Actid Unit ResID LOCATION BaseLine Budget


1C420PIRA1010 200 10040.PI.PR.DI Rack Erection Early MC March 19 TR 18648.5

Actid Unit ResID BaseLine PCS Budget DISPATCHED / IFC


1C420PAPP1010 200 10040.PA.PP.M2 Early MC March 38039.7587665779 37921.7330335681
1C420PAPP2010 214 10040.PA.PP.M2 Early MC March 3058.95605521838 3058.95605521838
1C420PAPP3010 224 10040.PA.PP.M2 Early MC March 3099.01132102407 3051.4159041662
1C420PAPP4010 234 10040.PA.PP.M2 Early MC March 3032.74855421084 3037.11442795771

Actid Unit ResID BaseLine PCS Budget DISPATCHED / IFC


1C420PAPP1010 200 10040.PA.PP.M2 Early MC March 8592.65955478916 8355.94282557801
support prefab
Actid Unit ResID BaseLine PCS Budget DISPATCHED / IFC
1C420PISU1010 200 10040.PI.PU.TN Early MC March 244.22 244.22
1C420PISU2010 214 10040.PI.PU.TN Early MC March 46 46
1C420PISU3010 224 10040.PI.PU.TN Early MC March 48.44 48.44
1C420PISU4010 234 10040.PI.PU.TN Early MC March 46 46

Sour gas
Actid Unit ResID BaseLine PCS Budget DISPATCHED / IFC
1C420PISU1010 200 10040.PI.PU.TN Early MC March 64.6979631730235 64.6979631730235

Actid Unit ResID BaseLine PCS Budget DISPATCHED / IFC


1C420PASP1010 200 10040.PA.SU.TN Early MC March 239.931166067547 239.931166067547
1C420PASP2010 214 10040.PA.SU.TN Early MC March 44.7 44.7
1C420PASP3010 224 10040.PA.SU.TN Early MC March 46.5536621866516 46.5536621866516
1C420PASP4010 234 10040.PA.SU.TN Early MC March 44.1 44.1
Sour gas
Actid Unit ResID BaseLine PCS Budget DISPATCHED / IFC
1C420PASP1010 200 10040.PA.SU.TN Early MC March 35.600 35.6

Actid Unit ResID BaseLine PCS Budget DISPATCHED / IFC


1C420PISU1020 200 10040.PI.SU.TN Early MC March 244.517957748823 244.517957748823
1C420PISU2020 214 10040.PI.SU.TN Early MC March 51.4736060724314 51.4736060724314
1C420PISU3020 224 10040.PI.SU.TN Early MC March 51.6093848134308 51.6093848134308
1C420PISU4020 234 10040.PI.SU.TN Early MC March 51.4918806714411 51.4918806714411
sourgas
Actid Unit ResID BaseLine PCS Budget DISPATCHED / IFC
1C420PISU1020 200 10040.PI.SU.TN Early MC March 65.2186065058915 65.2186065058915

Actid Unit ActivityName Area SubC PCS Budget


1C420PRHT1010 200 Piping Hydrotesting42 SUNG 255019
1C420PRHT2010 214 Piping Hydrotesting42 SUNG 54816
1C420PRHT3010 224 Piping Hydrotesting42 SUNG 58420
1C420PRHT4010 234 Piping Hydrotesting42 SUNG 52637

1C420PRFL1010 200 Piping Flushing - Inlet Facilities 237807


1C420PRFL2010 214 Piping Flushing - MEG Train 1 54521
1C420PRFL3010 224 Piping Flushing - MEG Train 2 58307
1C420PRFL4010 234 Piping Flushing - MEG Train 3 52363

1C420PRRE1010 200 Piping Reinstatement - Inlet Facilities 212242


1C420PRRE2010 214 Piping Reinstatement - MEG Train 1 26171
1C420PRRE3010 224 Piping Reinstatement - MEG Train 2 57972
1C420PRRE4010 234 Piping Reinstatement - MEG Train 3 21763
Prefab+Sour gas
PROGRESS % CUMM. Progress Actid
1 95648 1C420PIPR1010
1 27755.5 1C420PIPR2010
1 27328.5 1C420PIPR3010
1 27115.75 1C420PIPR4010

PROGRESS % CUMM. Progress


0.1694938347 2488

DISPATCHED / IPROGRESS % CUMM. Progress INCHES Actid


42767.75 0.99820 42767.75 1C420PIBB1010
14456.25 0.99320 14456.25 1C420PIBB2010
14941.75 1.00000 14941.75 1C420PIBB3010
14597.25 0.99918 14597.25 As per PCA 1C420PIBB4010

DISPATCHED / IPROGRESS % CUMM. Progress INCHES


8941.25 1 8941.25 0

DISPATCHED / IPROGRESS % CUMM. Progress INCHES Actid


19081.75 0.999580926937231 19081.75 1C420PISB1010
7992 0.996136108687523 7992 1C420PISB2010
8149 1 8149 1C420PISB3010
8000.25 1.00003125 8000.25 1C420PISB4010

DISPATCHED / IPROGRESS % CUMM. Progress INCHES Actid


48526 1 48526 1C420PIRA1010
3378 1 3378 1C420PIRA2010
3324.25 1.00015043249342 3324.25 1C420PIRA3010
3421.25 1 3421.25 1C420PIRA4010

DISPATCHED / IPROGRESS % CUMM. Progress INCHES


18648.5 0.990861029196886 18648.5

PROGRESS % CUMM Progress LM CUMM Progress M2 Actid


0.9978913664 55306.6941267957 37959.5468537972 1C420PAPP1010
0.9810497996 10728.9057129523 3000.98822493696 1C420PAPP2010
0.9846417415 10849.6526790166 3051.4159041662 1C420PAPP3010
1.001439577 10851.8500904095 3037.11442795771 1C420PAPP4010

PROGRESS % CUMM Progress LM CUMM Progress M2


2.117341E-05 0.038 0.181935913754692
PROGRESS % Progress Tons Actid
1.0002451062 244.22 1C420PISU1010
0.9957 46 1C420PISU2010
1.0000045416 48.44 1C420PISU3010
0.9957 46 1C420PISU4010

PROGRESS % Progress Tons


1 64.6979631730235

PROGRESS % Progress Tons Actid


1 239.931166067547 1C420PASP1010
1 44.7 1C420PASP2010
1 46.5536621866516 1C420PASP3010
0.9977324263 44.1 1C420PASP4010

PROGRESS % Progress Tons


0.9975000604 35.5110021493193

PROGRESS % Progress Tons Actid


1.0018098626 244.517957748823 1C420PISU1020
0.9352944366 48.1429773904698 1C420PISU2020
0.9397650614 48.5006966875257 1C420PISU3020
0.9371603695 48.2561499186677 1C420PISU4020

PROGRESS % Progress Tons


0.9894882719 64.5330462500923

PROGRESS % TESTED TP WEEK TESTED TP TESTED INCHES Actid


0.058062735 1093 0 254149 1C420PRHT1010
0.0008512856 601 0 54799 1C420PRHT2010
0.0004871938 609 0 58411.5 1C420PRHT3010
0.0008541645 545 0 52637 1C420PRHT4010

237807 1C420PRFL1010
54521 1C420PRFL2010
58307 1C420PRFL3010
52363 1C420PRFL4010

212242 1C420PRRE1010
26171 1C420PRRE2010
57972 1C420PRRE3010
21763 1C420PRRE4010

As per the Actual


Done In the site
Unit ResID Budget DISPATCHED / IFC CUMM. Progress
200 10040.PI.FB.DI Prefab 98136 98136 98136
214 10040.PI.FB.DI Prefab 27755.5 27755.5 27755.5
224 10040.PI.FB.DI Prefab 27328.5 27328.5 27328.5
234 10040.PI.FB.DI Prefab 27115.75 27115.75 27115.75
180335.75 180335.75 180335.75

Unit ResID BORE Budget DISPATCHED / IFC CUMM. Progress INCHES


200 10040.PI.BB.DI Big Bore 51709 51709 51709
214 10040.PI.BB.DI Big Bore 14456.25 14456.25 14456.25
224 10040.PI.BB.DI Big Bore 14941.75 14941.75 14941.75
234 10040.PI.BB.DI Big Bore 14597.25 14597.25 14597.25

Unit ResID BORE Budget DISPATCHED / IFC CUMM. Progress INCHES


200 10040.PI.SB.DI Small Bore 19081.75 19081.75 19081.75
214 10040.PI.SB.DI Small Bore 7992 7992 7992
224 10040.PI.SB.DI Small Bore 8149.25 8149.25 8149.25
234 10040.PI.SB.DI Small Bore 8000.25 8000.25 8000.25

Unit ResID LOCATION Budget DISPATCHED / IFC CUMM. Progress


200 10040.PI.PR.DI Rack Erection 67174.5 67174.5 67174.5
214 10040.PI.PR.DI Rack Erection 3378 3378 3378
224 10040.PI.PR.DI Rack Erection 3324.25 3324.25 3324.25
234 10040.PI.PR.DI Rack Erection 3421.25 3421.25 3421.25

Unit ResID BaseLine PCS BudgetDISPATCHED / IFC CUMM Progress M2


200 10040.PA.PP.M2 Painting 38039.759 37921.7330335681 37959.5468537972
214 10040.PA.PP.M2 Painting 3058.9561 3058.95605521838 3000.98822493696
224 10040.PA.PP.M2 Painting 3099.0113 3051.4159041662 3051.4159041662
234 10040.PA.PP.M2 Painting 3032.7486 3037.11442795771 3037.11442795771
47230.475 47049.0654108581
Unit ResID BaseLine PCS BudgetDISPATCHED / IFC Progress Tons
200 10040.PI.PU.TN Support Prefab 283.1 283.1 283.1
214 10040.PI.PU.TN Support Prefab 46 46 46
224 10040.PI.PU.TN Support Prefab 46.4 46.4 46.4
234 10040.PI.PU.TN Support Prefab 46 46 46
421.500 421.500

Unit ResID BaseLine PCS BudgetDISPATCHED / IFC Progress Tons


200 10040.PA.SU.TN Support painting 275.53117 275.531166067547 275.442168216866
214 10040.PA.SU.TN Support painting 44.7 44.7 44.7
224 10040.PA.SU.TN Support painting 46.553662 46.5536621866516 46.5536621866516
234 10040.PA.SU.TN Support painting 44.1 44.1 44.1
410.88483 410.795830403518

Unit ResID BaseLine PCS BudgetDISPATCHED / IFC Progress Tons


200 10040.PI.SU.TN Support erection 309.73656 309.736564254714 309.051003998915
214 10040.PI.SU.TN Support erection 51.473606 51.4736060724314 48.1429773904698
224 10040.PI.SU.TN Support erection 51.609385 51.6093848134308 48.5006966875257
234 10040.PI.SU.TN Support erection 51.491881 51.4918806714411 48.2561499186677
464.31144 453.950827995578

Unit ActivityName PCS Budget TESTED INCHES


200 Piping Hydrotesting - Inlet Facilities 255019 254149
214 Piping Hydrotesting - MEG Train 1 54816 54799
224 Piping Hydrotesting - MEG Train 2 58420 58411.5
234 Piping Hydrotesting - MEG Train 3 52637 52637
420892 419996.5
200 Piping Flushing - Inlet Facilities 237807 237807
214 Piping Flushing - MEG Train 1 54521 54521
224 Piping Flushing - MEG Train 2 58307 58307
234 Piping Flushing - MEG Train 3 52363 52363

200 Piping Reinstatement - Inlet Facilities 212242 212242


214 Piping Reinstatement - MEG Train 1 26171 26171
224 Piping Reinstatement - MEG Train 2 57972 57972
234 Piping Reinstatement - MEG Train 3 21763 21763
Progress INCHES
0
0
0
0

Progress INCHES
0
0
0
0

0
0
0
0

Progress M2