Professional Documents
Culture Documents
The Minutes of the 12th meeting of Grid Coordination Committee held on 27.04.2015 at
11.00hrs. at BTPS is enclosed for ready reference and further necessary action please.
Thanking you,
Yours faithfully
Encl. as above
(P.K. GUPTA)
General Manager (SLDC)
To
01 Sh. J.P.S. Chawla, Chairperson, GCC
Director (Operations), Delhi Transco Ltd, 1st floor, Shakti Sadan Building, Kotla Road,
New Delhi-110002, Office-Phone- 011-23232715, Fax : 23232721
02 Sh. Loveleen Singh, General Manager (Technical) C& MM
Delhi Transco Ltd., RPH Complex, RPH, Delhi
03 Sh. P.K. Gupta, General Manager (SLDC)
SLDC Building, Minto Road, New Delhi-11002
04 Ms. Kiran Saini, G. M. (Planning), Delhi Transco Ltd,
Shakti Deep Building, Jhandewalan, Delhi-110055
05 Sh. Roop Kumar, Executive Director (Technical), DTL,
220kV Parkstreet S/stn Building, Opp. Talkatora Stadium, Near RML Hospital, Park
Street, New Delhi-110001, Office Phone - 011-23366462 Fax: 011-23366160
06 Sh. A.C. Aggarwal, G.M. (Commercial & Regulatory Affairs), Delhi Transco Ltd,
IP Estate Bldg, New Delhi-110002
07 Sh. Mukesh Kumar Sharma, G. M. (Corporate Monitoring & SEM), Delhi Transco
Ltd. Shakti Sadan, New Delhi-110002
1
08 Sh. S.K.Mishra, General Manager (Civil)
Delhi Transco Limited, 220kV Grid S/Stn., Lodhi Road, CGO Complex, New Delhi-03
09 Sh. H. Vyas, G. M. (Project)-I, Delhi Transco Ltd,
Shakti Deep Building, Jhandewalan, Delhi-110055
10 Sh. Prem Parkash, General Manager (Project)-II, Delhi Transco Ltd.
Shakti Deep Building, Jhandewalan, Delhi-110055
11 Sh. S.K. Sharma, General Manager (O&M)-II, DTL,
Shakti Deep Building, Jhandewalan, Delhi-110055
12 Sh. Ved Mitra Chief Engineer, DMRC,
Inderlok Metro Station, Delhi, Ph. 9871165812
13 General Manager (NRLDC),
18-A, SJSS Marg, New Delhi-110016, Office Ph: 011-26537351, Fax:011-26852747
14 Sh. Jagdish Kumar, Director(Tech), IPGCL / PPCL
Himadri Building, Rajghat Power House, New Delhi-110002. Office Phone : 011-
23273544, Fax: 011-23270590
15 Sh. H.K. Chawla, Dy. G.M.(Market Operation), NRLDC
18-A, SJSS Marg, New Delhi-16, Office Phone : 011-26537351, Fax: 011-26852747
16 Sh. A.K. Sharma, Head (O&M), BYPL
Shakti Kiran Building, Karkardooma, Delhi
17 Sh. Mukesh Dadhichi, G.M. (SO), BYPL, Shankar Road, New Delhi
18 Sh. Sunil Kakkar
Head (PMG), BYPL, Shakti Kiran Building, Karkardooma, Delhi
19 Chief Engineer (Transmission System), BBMB
SLDC Complex, Sector-28, Industrial Area Phase-I, Chandigarh.
20 Superintending Engineer (O&M) Circle, BBMB
400kV S/Stn, BBMB Complex, Panipat-132107,Mob.09416017711,Fax .0180-2662992
21 Sh. Sanjay Kumar Banga, Head (PEC, PM&BD), TPDDL
SCADA Building, Near Netaji Place Subash Place Metro Station, Pitampura, Delhi 34
Phone Office: 011- 27468027, Fax: 011-27468023
22 Sh. Ajay Kumar, VP (PMG), BRPL,
Building No 20, Nehru Place, New Delhi–110019. Off. 39996052 Fax: 011- 3999605
23 Sh. D. Sarkar , General Manager,
NTPC, BTPS, New Delhi-110044 Office Phone: 011- 26949523, Fax: 011- 26949532
24 Sh. A.K. Joshi, Chief Engineer (Elect)-II, NDMC
Room No. 1706, 17th Floor, Palika Kendra, Sansad Marg, New Delhi-110001
25 Sh. V.K. Pandey, Chief Engineer (Elec)-I, NDMC
Room No. 1701, 17th Floor, Palika Kendra, Sansad Marg, New Delhi-110001
26 Sh. Mohinder Singh, Executive Director (Tariff), DERC
DERC Viniyamak Bhawan, C-Block, Shivalik, New Delhi-17
27 Sh. U.K. Tyagi, Executive Director (Engineering), DERC
DERC Viniyamak Bhawan, C-Block, Shivalik, New Delhi-17
28 General Manager (Commercial), Aravali Power Company Pvt Ltd. (APCPL)
1st Floor, Pawan Hans Towers C-14, Sec-1, Noida-201301
29 Sh. Bhupender Nath, AGM (Elect). DMRC, Opposite, Frank Anthony Public School,
Lala Lajpat Rai Market, Lajpat Nagar-4, New Delhi
30 General Manager (Commercial), NTPC
2
NCR Headquarters, R&D Building, A8A, Sec.-24, Noida-201301. Fax no.0120-
2410192
31 Sh. Neelesh Gupta
Whole Time Director, Timarpur – Okhla Waste Management Company Ltd
Jindal ITF Center, 28 Shivaji Marg New Delhi-110015, Ph. 45021983, Fax 45021982
32 General Manager, Indira Gandhi Super Thermal Power Station, Jharli, Jhajjar Distt.
Haryana Pin-124141, Fax no. 01251-266202, Ph. 01251-266265
33 CWE (U), MES, MES Palam Road, Delhi Cantt, New Delhi-110010
34 GE (U), Electric Supply, Kotwali Road, Delhi Cantt, Delhi-110010
35 Sh. Surender Babbar, G. M. (Finance-), DTL, Shakti Sadan, New Delhi 110002
36 Dy.G.M.(Fin.)-II, DTL, Rajghat Power House Complex, New Delhi-2
37 DGM (SO), Delhi SLDC
38 DGM (SCADA), Delhi SLDC
39 Sh. Darshan Singh, Manager (SO), SLDC Delhi.
40 Sh. Susheel Gupta, Manager (Energy Accounting), Delhi SLDC
41 Manager (SO)-Shift, Delhi SLDC
42 Ms Mukesh Dagar, Dy. Manager (Finance), SLDC
3
DELHI TRANSCO LTD.
(Regd. Office : Shakti Sadan, Kotla Road, New Delhi 110002)
[Office of Deputy General Manager (System Operation)]
SLDC Building, Minto Road, New Delhi – 110 002
Phone No.23221175, Fax 23221012, 23221059
Subject : Summary Record of discussions held in the 12th Meeting of the Grid
Coordination Committee (GCC) of Delhi, held on 27.04.2015 at 11.00Hrs. at
BTPS
WELCOME
Sh. D. Sarkar, General Manager, BTPS welcomed the delegates for the 12th Grid Coordination
committee meeting. He informed that the BTPS fraternity was highly alighted for getting the
chance of hosting the Grid Coordination Committee meeting which is the apex coordination
forum of Delhi Power Sector. This meeting has attained more importance as was convened just
prior to the onset of summer season and the discussions and decision of the meeting would
definitely help the utilities to meet the challenging task to meet peak demand which is expected
to cross more than 6000MW during the summer season. He mentioned the importance of BTPS
Plant which is still operating satisfactorily the country’s first 210MW unit. He also mentioned
about the islanded operation of the plant for more than seven hours in the event of Grid collapse
on 30.07.2012 and was continuing feeding the essential load of Delhi. He outlined the need of
maintaining the generation at the load centre to the maximum capacity for ensuring reliable
power supply to the Capital. He welcomed Chairperson and requested to start the proceedings
of the meeting.
Sh. J.P.S. Chawla, Director (Operations), DTL, Chairman welcomed all delegates in the
12th Grid Coordination Committee meeting. He expressed his happiness that this meeting is
convened in due course as per the stipulations and hoped that in future also, the meetings would
be convened as stipulated in the relevant rules which is on quarterly basis. He also thanked
BTPS authorities to host the meeting.
He outlined the fact that the meeting is held just before the crucial summer month and he hoped
that all the utilities might have made all arrangements to meet the summer demand which is
expected to cross 6000 MW.
He mentioned about the cash crunch faced by the generating and transmission utilities due to non
payment of dues by some of the utilities. He requested all the utilities to pay at least the current
dues of generating and transmission utilities to avoid the situation of collapse of generating
4
stations on account of non-supply of fuels which has the stringent payment conditions of cash
and carry which generating utilities of Delhi cannot be able to adhere to due to non-payment by
some of the utilities. The maintenance work of transmission utility may also hamper, if
sufficient payments are not realised.
With these remarks he advised the Convener to take up the Agenda. Accordingly, agenda was
taken up, the gist of discussions and decisions are as under:
The minutes of the 11th meeting of GCC held on 29.12.2014 have been circulated vide
letter no. F./DTL/207/14-15/GM(SLDC)/F-3/172 dated 03.03.2015. No comments have
been received.
5
S. Capacity Present Original planning for hot Present Status
N populati reserve
on in
nos.
3 220/66kV, 41 New Tx. is required to be The transformer meant as hot
100MVA purchased The scheme for one reserve available at Patparganj has
Tx 220/66/ 33kV 100MVA Tx as been diverted to replaced the
4 220/33kV, 37 hot reserve has been approved damaged 220/66kV 100MVA Tx-I
100MVA and the same would be placed at Park Street. Procurement of new
Tx, at Patparganj before summer transformer is in progrress and
2014 for hot reserve expected by December 2015.
5 66/11kV 24 The scheme for a 66/11kV Tx DERC has already decided that DTL
20MVA as a hot reserve has been should not invest in building up
Tx approved and transformer is assets to feed 11kV load from
under procurement. 220kV S/Stns.
DTL representative intimated that as
per the directives communicated
vide letter no.F.DTL/
Engg./DERC/2012-13/3496 dated
19.11.2013, Discoms should shift
the 11kV load from DTL
Sub’station. They informed that
sofar, no action has been taken by
the Discoms. They informed that as
per DERC directives, the could not
be able to incur any additional
capital expenditure on thise assets
and without which, the continuity of
supply through these assets would
be impossible. They informed that
the conditions of 11kV panels of 4
sub-stations namely Najafgarh,
Okhla, Gopalpur & Lodhi Road are
in deterioated conditions and
without replacing the same, the
continuity of supply can not be
ensured. The cost of the work would
be about more than Rs. 3 Crores and
hence load should be transferred
immediatley to avoid any
interruption in supply.
DTL representative further informed
that one 11kV breaker of controlling
Rama Park. feeder at Najafgarh was
damaged and they don’t have any
space to replace the same. He
requested BRPL to provide a
breaker to revive the feeder.
6
S. Capaci Present Original Present Status
N ty populatio planning for
n in nos. hot reserve
BRPL representative agreed to consider the same provided
a written / email communicaiton be made by DTL.
Further, Discoms intimated that it is not possible to shift
all load from 11kV system fed from DTL’s sub-stations
provided the estalishment of alternative system.
In the last meeting, Distribution Companies have informed that they have to make
necessary modification in the SCADA system as over drawal and under drawal is now
not linked with frequency. It was also decided that Discoms should keep their drawal as
per the drawal schedule and at the same time, should also consider the drawal of Delhi as
whole from the Grid so as to avoid unnecessary load shedding in case Delhi drawal is less
than the scheduled drawal.
TPDDL informed that the automatic State-Of-The-Art Load Management Scheme as per
the Grid Code provisions applicable from 17.02.2014 is envisaged in the upgradation of
the SCADA system which is expected by 31.03.2016. In the present system, the
provisions linked with frequency are functioning. However, they are observing the load
management as per the Grid Code conditions.
BRPL informed that their system is also being upgraded and ADMS provisions as per the
prevailing Grid Code in the provision could be implemented along with the upgradation
of SCADA system i.e. 31.03.2016.
BYPL informed that their SCADA system has already having the ADMS provisions
except the polarity changes in the 12 Fifteen minutes time blocks. They are trying to
update the software of ADMS linked with overall over drawal of Delhi as a whole to
avoid unnecessary load shedding in any part of Delhi when Delhi (as a State) does not
over draw from the Grid.
7
NDMC informed that the software development in SCADA with reference to ADMS is
assigned to TCS which is expected by 31.03.2016. Further, the system is partly
implemented in some of the feeders.
MES has been exempted from ADMS as per the earlier decisions of GCC considering the
strategic importance load to be catered by the utility beside total consumption of utility is
less than 1% of the Delhi.
BRPL representative suggested that the SCADA staff should also be posted on round the
clock basis in SLDC to address the SCADA related issues on real time basis as at present,
to resolve the SCADA related issues after office hours or holidays, no arrangement is
available in SLDC leading to load shedding due to data related issues.
BYPL representative suggested that real time operator in SLDC should adopt Discom
data for drawal (as available in SLDC through ICCP) in case of SCADA problem of
SLDC system.
GCC advised that a meeting of DTL, SLDC and Discoms be immediately convened
at SLDC to resolve the data integration issues. GCC also advised all stakeholders to
strictly adhere Grid Code provisions to ensure secure and economic operation of the
Grid.
IPGCL/PPCL’s representatives informed that. IPGCL and PPCL used to raise power
supply bills to BRPL and BYPL and got the payment thereof on regular basis till
September, 2010. Thereafter, BRPL and BYPL started defaulting in payments thereby
putting IPGCL and PPCL in financial crunch. In later development BRPL and BYPL
stopped payment to NTPC w.e.f. January, 2014 and in response NTPC issued Power
Regulation Notice to BRPL and BYPL w.e.f. 11.02.2014. BRPL and BYPL filed a Civil
Suit with Hon’ble Supreme Court of India vide Petition No. 104 & 105 of 2014. In the
Petition, IPGCL & PPCL had been made respondents No. 12 & 13 respectively. Hon’ble
Supreme Court further heard the matter on 26.03.2014, 29.04.2014, 06.05.2014. After
last hearing, the Supreme Court of India vide order dt. 07.05.2014 directed the petitioner
i.e. BRPL and BYPL to pay current outstanding dues by 31st May, 2014, failing which
generation and transmission companies including IPGCL and PPCL can regulate power
supply after 31.05.2014. BRPL and BYPL further filed IA Nos 4-5 and IA 3-4 before
vacation bench of the court and matter was heard on 19-05-2014, the court has refused to
give any further direction as prayed by Appellants. BRPL & BYPL further filed various
8
petitions and interim applications on the above subject i.e. vide Civil Appeal No. 8464–
8466 and 8387–8389 of 2014, BRPL & BYPL challenged APTEL Order dt. 23.05.2014
in the matter of IPGCL/PPCL IA No. 286 & 287 of 2014. Further, BRPL & BYPL have
also filed IA No. 06 in matter of CWP 104 of 2014 and IA No. 07 in matter if CWP 105
of 2014 requesting to modify Hon’ble Supreme Court of India Order dt. 26.03.2014,
06.05.2014 & 03.07.2014. The matters were heard in Hon’ble Supreme Court on
08.09.2014, 31.10.2014, 17.11.2014 & 24.11.2014. Hon’ble Court had further hearing in
the matter and issued daily order dt. 27.01.15, 06.02.15, 09.02.15, 18.02.15 & 19.02.15.
Based upon the hearing on 19.02.15, Hon’ble Supreme Court had concluded the hearing
on above matter and the final order is awaited. BYPL is not honoring the order of
Hon’ble Supreme Court of India dt. 26.03.2014 and 03.07.2014. BRPL also started
defaulting in payment since November, 2014, in total disregard to Hon’ble Supreme
Court’s order. Therefore, IPGCL & PPCL filed a contempt petition in Hon’ble Supreme
Court of India on dt. 27.01.2015. The matter was listed for scheduled hearing on
12.03.2015. However, BRPL & BYPL advocates mentioned the matters on 10.03.2015
in the court and accordingly Hon’ble Supreme Court issued amended daily order dt.
10.03.2015 with remarks “list all the civil appeals and contempt petitions after the
pronouncement of the judgment in writ petitions”.
The final order of the Supreme Court of India is still awaited. The status of total current
outstanding bills raised, payment received and balance dues is as under:
IPGCL
BRPL 428.00 244.15 183.84
a)
BYPL 250.68 65.60 185.08
Total (a) 678.68 309.76 368.92
PPCL
BRPL 1013.08 457.94 555.14
b) BYPL 606.95 148.66 458.30
Total (b) 1620.04 606.60 1013.44
Total (a) + (b) 2298.71 916.35 1382.36
9
However, accumulated outstanding since dues including surcharge since default wef
October, 2010 is Rs. 4821.69 crores. They requested the defaulting utilities to pay atleast
the current charges failing which they may not be able to maintain the generation as the
payment for the fuel supply agencies and for other maintenance activities may not be
possible with the current finances.
DTL also informed that despite the Supreme Court’s order, payments are not forthcoming
from BRPL & BYPL. The payment position is as under:
Amount in Rs.
BRPL account of LPSC
10
The DTL representative also informed that if the payments are not made by the
Distribution Companies even the day-to-day maintenance activities may also be get
affected which may result to the maintenance of reliability of power supply. They have
also brought the above before the Supreme Court and even condempt petitions were also
the filed before Supreme Court in the matter of non compliance of orders of the court for
pay the current dues from 1.1.2014.
SLDC representative informed that due to non payment of dues, at present, regulations
are imposed on BRPL and BYPL as under:-
11
With regard to payment dues of NDMC & TPDDL for DTL, the utilities were of the view
that the genuine payments are being made by them. TPDDL further, informed that the
matter is still in the consideration of DERC/APTEL.
GCC requested all utilities to pay the current dues as per the Supreme Court orders
to at-least maintain the power supply in the Capital particularly during the crucial
summer months so that the day-to-day work of transmission & generation utilities
do not affect due to payment crises.
12
Clau RECOMMEND STATUS AS ON DATE
se ATIONS
9.1.2 Philosophy of Powergrid has reviewed the zone-3 settings in coordination with STUs, generators and POSOCO
Zone-3 and put them in order in accordance with load ability. The status of implementation of the above by
trippings to be the States was discussed at the meetings of National Power Committee (NPC) held on 15.04.2013
reviewed to and 16.07.2013 wherein the PGCIL has informed that they have reviewed the zone -3 settings in
avoid coordination with STUs and Gencos in interstate system wherever required in the country.
indiscriminate As far Delhi is concerned, the details have been submitted to PGCIL through NRPC as detailed
and load hereunder :-
encroachment
and faults – Sl Name Voltag Name of Voltage Make of CT Zone-3
Time Frame - N of e transmissio (kV) relay primar setting
immediate o substat level(k n line for y (X)
ion V) MVA Seconda
calculat ry Ohms
ion
Bamnau Ballabhrgarh-
Main-I 1 li 400kV I 380kV Micromho 2000/1 13.9
Main-II 380kV Micromho 2000/1 3.36
Bamnau Ballabhrgarh-
Main-I 2 li 400kV II 380kV Micromho 2000/1 13.9
Main-II 380kV Micromho 2000/1 3.36
Bamnau
Main-I 3 li 400kV Mundka-I 380kV Micromho 2000/1 13.4
Main-II 380kV Micromho 2000/1 2
Bamnau
Main-I 4 li 400kV Mundka-II 380kV Micromho 2000/1 13.4
Main-II 380kV Micromho 2000/1 2
Main-I 5 Mundka 400kV Bamnauli-I 380kV P442 2000/1 10.27
Main-II 380kV D60 2000/1 10.27
Main-I 6 Mundka 400kV Bamnauli-II 380kV P442 2000/1 10.27
Main-II 380kV D60 2000/1 10.27
Main-I 7 Mundka 400kV Bawana-I 380kV P442 2000/1 28.4
Main-II 380kV D60 2000/1 28.4
Main-I 8 Mundka 400kV Bawana-II 380kV P442 2000/1 28.4
Main-II 380kV D60 2000/1 28.4
Main-I 9 Mundka 400kV Jhajjar-I 380kV P442 2000/1 20.14
Main-II 380kV D60 2000/1 20.14
Main-I 10 Mundka 400kV Jhajjar-II 380kV P442 2000/1 20.14
Main-II 380kV D60 2000/1 20.14
Main-I 9 Bawana 400kV Mundka-I 380kV Micromho 2000/1 13.4
Main-II 380kV Micromho 2000/1 2
Main-I 10 Bawana 400kV Mundka-II 380kV Micromho 2000/1 13.4
Main-II 380kV Micromho 2000/1 2
Main-I 11 Bawana 400kV Mandola-I 380kV Micromho 2000/1 11.7
Main-II 380kV Micromho 2000/1 3.12
Main-I 12 Bawana 400kV Mandola-II 380kV Micromho 2000/1 11.7
Main-II 380kV Micromho 2000/1 3.12
13 Bawana 400kV Abdullapur Settings done by PGCIL
14 Bawana 400kV Bahdurgarh Settings done by PGCIL
Hisar (Now
Mahendergar
15 Bawana 400kV h) Settings done by PGCIL
Dipalpur
16 Bawana 400kV Settings done by PGCIL
Note
1) Zone setting for main-I & main-II distance relays to be provided for each line.
2) Voltage kV for MVA calculation may be taken as 380 kV for 400kV lines and 727kV for 765kV
line.
REMARKS
1. MAIN-II PROTECTION OD DTL LINES IN THE DELHI RING MAIN LINES IS IN
BLOCKING SCHEME
2. ZONE 3 IS SET REVERSE LOOKING FOR MICROMHO RELAYS USED AS MAIN-II.
3. CALCULATED MAX LOADING LIMIT IS AS PER THE FORMULA GIVEN IN THE
MINUTES WHERE X IS THE REACTANCE OF LINE
4. THE OTHER END DETAILS IN RESPECT OF JHAJJAR LINE ALSO NEED TO BE
CONFIRMED FROM NTPC/PGCIL/APCL
The Protection Department of DTL intimated that, thus the recommendations stand implemented.
13
Clau RECOMMENDATIONS STATUS AS ON DATE
se
9.1.4 Complete independent audit of time DTL intimated that at all interstate points the time synchronization has
synchronization of DRs, EL and PMs been done. Others will follow. DR is available at all 400kV Grids. ELs for
should be carried out all 220kV S/Stns have been planned. DR is not required at 220kV Sub-
- Time frame – within one month stations as Numerical Relays have this inbuilt feature for which
replacement of all relays with Numerical ones being undertaken.
As far as IPGCL and PPCL systems are concerned, they informed that DR
is available at CCGT Bawana and Pragati. EL is not required at generating
stations as generators have inbuilt features of EL.
IPGCL & PPCL was advised to ensure the time synchronization of DRs.
PPCL / IPGCL informed the following:
1) 1500MW PPS-III Bawana : All the six generating units have least DRs
installed. The process of time synchronization of DRs is under progress by
BHEL. The latest numerical relays are installed on each unit and 400kV
SWYD panels.
ii) 330MW PPS-I, IP Estate: DRs are installed at all the three units of PPS-
I. The DRs are time synchronized with G{S. Further, GT#1 is also having
latest numerical relays and the process of installing of numerical relays on
rest of the units is under progress.
9.2.1 Tightening of Frequency band and be CERC has already issued the amended Grid Code to be implemented from
brought very close to 50Hz. 17.02.2014 in which the allowable frequency band is 49.95Hz to 50.05Hz.
The Deviation Settlement Mechanism has also been introduced according
to the tightening to the frequency band. The main thrust of the amended
Grid Code is the utilities should always stick to its scheduled drawal.
Further, the following are the main issues:-
a) No over drawal by Delhi if frequency is below 49.95Hz.
b) No under drawal by Delhi if the frequency is more than
50.05Hz.
c) Every (12) time blocks the polarity of drawal should change.
14
Clause RECOMMENDATI STATUS AS ON DATE
ONS
The details of the violations for Delhi are as under:-
Duration 17.02.1 12.05.1 23.0 28.07.1 25.08.1 29.09.1 01.1
4 to 4 to 6.14 4 to 4 to 4 to 1.14
11.05.1 22.06.1 to 24.08.1 28.09.1 02.11.1 to
4 4 27.0 4 4 4 30.1
7.14 1.14
Violation of OD – 4 OD – 9 OD OD – 5 OD – 9 OD-4 OD-
drawal limit UD-19 UD-24 –7 UD-19 UD-1 UD-17 2
150MW if freq UD- UD-
>49.7Hz and 30 21
above
Violation of non 405 198 56 116 34 158 135
polarity change
of drawal
It was informed by SLDC that due to shortage of staff, the Discomwise violations could not
be computed. The same would be done as early as possible.
GCC advised all utilities to adhere to the schedules to avoid violations of CERC
regulations and for ensuring secure operation of the Grid.
9.2.2 Review of UI UI regulations have been replaced with DSM Regulations and implemented from 17.02.2014.
mechanism. Frequency The Central Commission has also initiated steps for pressing ancillary services for which a
control through UI drat Ancillary Services Operation Regulations 2015 has been hosted in their website for
maybe faced out in a public comments.
time bound manner
and generation
reserves and ancillary
services may be used
for frequency control
Time frame – 3
months
9.3 All STUs should In Delhi, there are 34 panels of Under Frequency Relays and each panel has 4 numbers of
immediately enable UFR/df/dt Relays. Apart from this, 14 panels of Flat Under Frequency Relays have been
Under Frequency and installed at various Sub-Stations which are the part of Delhi Islanding Scheme and each panel
df/dt under frequency has two relays.
scheme. Central
Commission should The National Power Committee (NPC) in its 2nd meeting held on 16.07.13 has decided to
explore ways and adopt four stages automatic load shedding scheme for NEW Grid. The scheme was decided
means for to be implemented within 3 months i.e. by the end of October 2013. The details are as
implementation of under :-
various regulations
issued under the Scheme for the NEW Grid
Electricity Act 2003. Freq Required Load Relief (MW) (based on max load on feeders)
Any violation of these (Hz) NR WR ER NER Total
regulations can prove 49.2 2160 2060 820 100 5140
to be costly 49.0 2170 2070 830 100 5170
- Time frame - 48.8 2190 2080 830 100 5200
immediate 48.6 2200 2100 840 100 5240
Total 8720 8310 3320 400 20750
15
Clause RECOMMENDATIONS STATUS AS ON DATE
S. State Peak met Load Shedding target for four stages (MW) –
N during 2012- Based on maximum load on the feeders
13 (MW 49.2 49.0 48.8 48.6
1 Chandigarh 340 16 16 16 16
2 Delhi 5642 258 259 262 263
3 Haryana 6725 308 309 312 314
4 HP 1672 77 77 78 78
5 J&K 1817 83 84 84 85
6 Punjab 8751 400 402 406 408
7 Rajasthan 8515 390 392 395 397
8 UP 12048 551 554 559 561
9 Uttrakhand 1674 77 77 78 78
Total 47184 2160 2170 2190 2200
O&M Department of DTL has informed the revised settings for Grid Security and Islanding
for Delhi have been implemented in Delhi as per the advise of NRPC. The details are as
under:-
Frequency set at Load relief in MW
49.2Hz 297
49.0Hz 353
48.8Hz. 428
48.6Hz 1048
Total 2126
df/dt
49.9Hz. with slope 0.1Hz. 261
49.9Hz with slope 0.2Hz 282
49.9Hz with slope 0.3Hz 290
Total df/dt 833
With regard to the suggestion of providing under frequency relay’s at Discoms end, it was
advised that to ensure proper load relief and to avoid confusion in operation of relays in
coordinated ways, the relays be installed in DTL’s Grid S/Stns.
CERC in its order 23.12.2013 has issued notices to the Head of SLDC & MD/CMD of the
STUs to explain why action should not be initiated under section 142 of Indian Electricity Act
2003 (IEC 2003) for non compliance of Grid Code. The relevant portion of the order in
petition no. 221/MP/2012 is reproduced hereunder:
29.We are constrained to remark that we are thoroughly dissatisfied with the defense
mechanism in terms of UFR and df/dt. Hard reality which stares us on the face is that
these have not been provided and maintained as per Regulation 5.2 (n) and 5.4.2 (e) of
the Grid Code by NR constituents. Accordingly, we hereby direct as follows:
(a) Issue notices to the heads of SLDCs and MD/ CMD of the STU of Punjab, Haryana,
Rajasthan, Delhi, Uttar Pradesh, Uttarakhand, Himachal Pradesh, Jammu and Kashmir
and head of Electricity Department, UT of Chandigarh and to explain why action should
not be initiated under Section 142 of the Electricity Act, 2003 for non-compliance of the
Grid Code.
(b)Member Secretary, NRPC to submit the latest status of UFRs and df/dt installations in NR
within 1 month from the issue of this order.
(c) UFRs and df/dt relays also be mapped on the SCADA system of each state so that they can
be monitored from SLDC/NRLDC.
(d)All STUs and SLDCs to map/network the UFR and df/dt on their SCADA system.
Quote
(e)NRLDC to submit the compliance report on the progress of installation of additional UFR
and df/dt relays and quantum of load relief expected during contingency by 31.3.2014.
(f)The staff shall examine the reports of the Member-Secretary, NRPC and NRLDC and shall
submit to the Commission within one month of the receipt of the reports of NRPC and
NRLDC.
With regard to installation of UFR, DTL has complied the directions. As far as integration of
UFR in SCADA system, it would be done by end of January 2015.
SLDC informed that they have integrated the UFR with SCADA system.
16
Clause RECOMMENDATIONS STATUS AS ON DATE
9.4 All out efforts should be made CERC in its order dated 31.12.2012 reiterated the need for compliance by generators and
to implement the provisions of directed as to why they may not be held responsible for non-implementation of RGMO / FGMO
IEGC with regard to Governor mode of operation. A task force has been constituted by CEA under Member (Thermal), CEA
Action - POSOCO to take up to develop a procedure for testing of primary response of Generating units. Activity in
the matter with Central progress.
Commission
- Time frame – 3 months As far Delhi Gencos are concerned, PPCL informed that the generating stations in Delhi mainly
gas based stations are exempted from FGMO/RGMO. They quoted section 5.2(f)(iii) of IEGC
indicating “all other generating units including the pondage upto 3 hours gas turbine /
combined cycle power plants, wind and solar generators, and nuclear power plants are
exempted from operation of RGMO / FGMO till the Commission review the situation.
However, all the 200MW and above thermal machines, should have the RGMO / FGMO.”
In the last meeting, BTPS representative intimated that clause is applicable to the capacity
above 200MW units. As far as BTPS is concerned, the units are fitted with mechanical
governors as BTPS has old LMZ make Russian turbines with no electro hydro governing
system. However to meet the grid code stipulations, 210MW machines would be provided with
RGMO facilities in the proposed R&M activities to be approved by CERC.
BTPS representative informed that they have already filed a Petition in CERC vide Petition
No.MP/65/2014 in the month of September 2014 and admitted by the CERC for exemption till
R&M activities are carried out in the 210MW machines.
BTPS informed that CERC has not yet given the decision on the petition.
9.5.1 POSOCO should take up with CERC vide order dated 22.04.2013 has approved amendment to the detailed procedure for
Central Commission the issue relieving congestion in real time operation under Regulation 4(2) of the Central Electricity
of inconsistency between Regulatory Commission (Measures to relieve congestion in Real Time Operation) Regulation
congestion regulation and 2009. The revised procedure is available in NRLDC’s website homepage.
detailed procedure framed
there under so that congestion
due to forced outage UI can be
handled effectively.
Action : Posoco within one
month
9.6 Outage planning should be in NRPC OCC has already decided all Interstate Transmission Elements shut-down should be
coordinated manner planned and forwarded to RPC by STUs by 8th of every month for the next month. In addition
to above, annual outage plan should also be drawn out. In the 102nd and 103rd NRPC OCC
meetings held on 20.08.2014 and 28.09.2014 respectively, it was further decided that after the
tentative approval of NRPC OCC, the intending utilities should intimate NRLDC regarding
availing of shut-downs before 4th day of actual date of the shut-down.
DTL is adhering the procedure with regard to shutdown of Transmission lines.
9.7 In order to avoid frequent The order for Dynamic Simulation Study and Reactive Power compensation has been placed to
outages / opening of lines CPRI.
under over voltages and also
providing voltage support CPRI has already submitted the report with regard to the Reactive Power compensation. The
under steady state and same is being coordinated with Discoms and DTL for implementation. NRLDC is also being
dynamic conditions, consulted for implementation of CPRI report.
installation of adequate
reactive power compensators It was informed that a training on dynamic stimulation study has already been carried out at
should be planned. CPRI Bangalore. As far as, Reactive Power compensation study is concerned a meeting has
Action : CTU/STUs and CEA already been convened on 18.02.2015 wherein it was decided that the utilities should given
– Time frame 6 months comments as quick as possible.
The comments have been received from BRPL, BYPL and PGCIL. However, TPDDL and
NDMC have yet to submit the comments.
GCC advised Planning Department of DTL to wait for one more week for the comments
failing which CPRI may be requested to go ahead with available data and complete the
study and give the report accordingly.
17
Clause RECOMMENDATIONS STATUS AS ON DATE
9.8 The powers of load dispatch Amended Electricity Bill has been introduced in the Parliament. At present, a
centers, regulatory Standing Committee on Energy is examining the amended bill. The bill is likely to be
commissions related to non come up in monsoon session of Parliament.
compliance to statutory /
regulatory provision including
that for non compliance for
direction for non payment of
UI charges needs review .
Appropriate amendments need
to be carried out in Electricity
Act 2003 after such review.
Action MoP, GoI Time
frame: 6 months.
9.9.1 Regulatory provisions In 79th NRPC’s OCC meeting, NRLDC informed that they have taken up the matter
regarding absorption of with Regional Generators to absorb reactive power as per the capability during high
Reactive Power by generating voltage conditions. They advised SLDCs to do the same. In 84th Operation
units needs to be implemented Coordination Committee meeting of NRPC held on 19.02.2013. It was decided to
: monitor the reactive power generation on real time basis at RLDC / SLDC level
Posoco Time frame : through SCADA. The relevant portion of the MoM is reproduced hereunder :-
immediate
Monitoring of reactive support from generating units.
Representative of NRLDC stated that critical high voltage is being experienced in the
Northern Grid during night off peak hours. Available shunt reactors at the Sub-
stations are being taken into service, power order on HVDC bi-pole is being reduced,
instructions are being given to generators to absorb reactive power to the extent
possible and under exceptional conditions under-loaded/redundant EHV transmission
lines are being manually opened for voltage regulation. Para 13.6 of the revised
Transmission Planning Criteria envisages that during operation, following the
instructions of the System Operator, the
generating units shall operate at leading power factor as per their respective capability
curves. Further as per regulation 5.2 (k) of the Indian Electricity Grid Code, all
generating units shall normally have their automatic voltage regulators (AVR) in
operation. It is proposed that the reactive power absorption/injection by the generating
units may be monitored in the format given under
GENERATOR REACTIVE POWER MONITORING TEMPLATE
Name of the Power Station
Date
Generating Time MW at MVAr Generator Voltage
unit Generato Lead/Lag at transformer at the HV
r Generator Tap Bus
terminals terminals Position
#1 hh.mm
hh.mm
….
#2 hh.mm
hh.mm
….
#3 hh.mm
hh.mm
….
….
SCADA circle of SLDC has already integrated the reactive power position of RPH,
Pragati Stage-I and GT Station. The data integration is in progress in Bawana CCGT
Station which has to be done through SAS by PPCL.
In the last meeting, PPCL intimated that the matter is being persued with Siemens –
the OEM of SAS and GCC advised PPCL to expedite.
PPCL informed that Siemens could not integrate the same so far. However, it is
expected that the issues would be resolved soon.
18
Clause RECOMMENDATIONS STATUS AS ON DATE
9.12 Efforts should be made to design islanding It was informed by representative of DTL that the Islanding Scheme has
scheme based on frequency sensing relays already been commissioned. However, for the healthy operation of the
so that in case of imminent Grid failure, Islanding Scheme, the communication system needs to be strengthened.
electrical island can be formed. These
electrical islands not only help in M/s CPRI was entrusted the job of dynamic simulation study of Delhi
maintaining essential services but would Islanding Scheme. The final report has been submitted by CPRI. Officers
also help in faster restoration of Grid. from DTL had attended the office of M/s CPRI at Bangalore wherein they
Action : CEA, RPCs, CTU, STUs, SLDCs were apprised and explained about the findings about dynamic simulation
and generators Time Frame : six months study of Islanding Scheme.
The copies of the report have been given to Discoms, IPGCL / PPCL,
NTPC and PGCIL for their comments on the outcome of the simulation
study. The comments are awaited.
GCC advised Discoms, PPCL/IPGCL, NTPC and PGCIL to
submitted their comments at the earliest so that a comprehensive
decision can be taken regarding the formation of island.
9.13.1 System Operation needs to be entrusted to Though Delhi SLDC is operated by DTL it has full autonomy with regard
independent system operator. In addition, to grid operation. Further it has separate ARR approved by DERC for
SLDCs should be reinforced for ring fences financial autonomy. Further a committee constituted for creation for SLDC
for ensuring function autonomy. as a separate company has already given its report to State Government.
Action : Govt. of India, time frame : one Decision is likely in line with the decision of Govt. of India on
year Independent System Operator (ISO).
9.13.2 Training and certification of system Discussed in the 1st meeting of the National Power Committee held on
operators need to be given focused 15.04.2013. Maharashtra has already started an incentive scheme for
attention. Sufficient financial incentives System Operators in the State. States were requested to expedite training
need to be given to certified system of system operators and it was recommended that only certified operators
operators so that system operation gets should man the Load Despatch Centers.
recognized as specialized activity.
Action : Govt. of India State Govt. Time As far as Delhi is concerned the officers of SLDC are being sent regularly
frame : 3 months for training to upgrade the knowledge. So far 19 Engineers have obtained
basic certificate and one Engineer got the certification in specialist course
in Regulatory Affairs.
Incentive schemes have been proposed for certified operators which are
under the active consideration of the DTL management.
NPTI and PSTI were also requested to impart training to the Operators of
the Area Control Centres of the Discoms also as decided in the 10 th Grid
Coordination Committee meeting.
It was informed that NPTI has already drawn out four courses for Basic
System Operators for the financial year 2015-16, details of which have
aleady been circulated amongst Distribution Companies.
19
Clause RECOMMENDATIONS STATUS AS ON DATE
9.15.1 Appropriate amendments should be carried GCC advised all utilities that efforts should be made to ensure the data
out in Grid connectivity standards to flow to the control centers w.r.t. new installations as per the relevant
restrain connectivity of a generating station provisions of connectivity conditions of CEA and relevant provisions of
or a transmission element without required IEGC.
communication and telemetry facilities Earlier GCC meeting decided not to issue energization certificate
without data connectivity to SLDC / RLDC. Distribution licenses were
also advised for such actions.
9.15.2 The communication network should be PGCIL have informed that requirement of Fibre Optic link for effective
strengthened by putting fiber optic communication is being worked out by them with STUs through different
communication system. Further, the RPCs and its implementation is being done in a progressive manner. The
communication network should be work of laying Fibre Optic cables in all the regions is being awarded
maintained properly to ensure reliability of progressively from December 2012 and is likely to be completed by the
data at Load Despatch Centers. year end of 2014.
DTL has also given the requisition to PGCIL for laying of 286 Kms of
OPGW for strengthening of communication system across Delhi under the
above contract.
It was informed that PGCIL has already placed orders for additional
OPGW and work would be completed by December 2015.
9.15.3 RTUs and communication equipment It was informed by SLDC that 27 Battery banks for 27 locations are
should have uninterrupted power supply awaited to be supplied by the vender M/s JSK Power. The inspection of
with proper battery backup so that in case of the said banks has been carried out 2 weeks back as per inputs given by
total power failure, supervisory control and Inspection Division.
data acquisition channels do not fail. However, as the work of supply of 27 banks was getting delayed
inordinately, therefore, Hardware division dismantled a 192 cell 200 Ah
hatter banks into 8 banks of 24 cells each and installed at 08 sites namely
400kV Bawana, Gazipur, IP, Wazirabad, Okhla, Kanjhawala, Mehrauli
and Najafgarh.
9.18 There is need to reinforce system study The first meeting of System Study Group has already been conducted on
groups in power sector organizations to 17.04.2015.
analyze the system behavior under different
network status / tripping of lines /outage of
generators. Where these do no exist, these
should be created.
Action by : CEA, STU, CTU
Time frame : one year
9.20 For smooth operation of Grid system, it is CTU have informed that they already have a dedicated independent
absolutely important that all the power communication network in place. Further, they are in the process of
generating and distribution stations are developing a Grid Security Expert System (GSES) at an estimated cost of
connected on a very reliable telecom about Rs.1300 Crore which involves laying of optical fiber network
network. costing about Rs.1100 Crore for reliable communication and control of
i) A proper network may be built under-frequency & df/dt relay based load shedding, etc. System will
up preferably using MPLS include substations of 132kV level and above.
(Multi Protocol Label
Switching) which is simple, cost
effective and reliable. In remote
place where connectivity is a
problem, the stations can use
dedicated fiber cable from the
nearest node.
ii) Since POWER GRID has its
own fiber optic cables,
practically covering all major
nodes and power stations, a
proper communication / IT
network may be built using
dedicated fibres to avoid any
cyber attack on the power
system.
20
NEW ISSUES
3 OPERATIONAL ISSUES
The anticipated power supply position versus the actual position for April & May 2015
has been as under:-
ANTICIAPTED 2400 3000 3500 3400 3700 4200 3550 4300 4700 4650
DEMAND
DEMAND MET 2500 2961 3498 3524 3666 4018 3394 4067 4517 4351
DEVIATION IN -4 1 0 -4 1 4 4 5 4 6
%AGE
May 2015
ANTICIAPTED 4400 4000 4500 4850 4650 4900 4600 4900 5600 5200
DEMAND
4610 4142 4525 5111 5125 5171 4605 4905 5465 5231
DEMAND MET
DEVIATION IN
%AGE 4.77 3.55 0.56 5.38 10.22 5.53 0.11 0.10 -2.41 0.60
It may be noted that during the month of April 2015, the anticipated and actual demand
varies within the range of + or – 5% as per the norms of CEA. However, there are slight
various during the month of May-2015 which is obviously due to weather conditions.
21
Anticipated power supply position for June-2015 to September-2015
AVAILABILITY 1755 1755 1755 1821 1903 1829 1829 1829 1895 1977
SURPLUS (+) /
SHORTAGE (-) 755 510 309 417 357 62 382 84 -22 38
MAY 2015
DEMAND 1849 1667 1823 1971 1941 2059 1897 1976 2288 2178
AVAILABILITY 2030 2030 2030 2113 2162 2105 2105 2105 2188 2237
SURPLUS (+) /
SHORTAGE (-) 181 364 208 142 221 46 208 129 -101 59
JUNE 2015
DEMAND 2327 1983 2235 2488 2416 2314 1979 2274 2449 2420
AVAILABILITY 2180 2180 2180 2312 2329 2180 2180 2180 2312 2329
SURPLUS (+) /
SHORTAGE (-) -147 197 -54 -176 -87 -133 202 -93 -136 -91
JULY 2015
DEMAND 2449 2235 2272 2618 2630 2312 1972 2097 2495 2367
AVAILABILITY 2214 2214 2214 2396 2412 2214 2214 2214 2396 2412
SURPLUS (+) /
SHORTAGE (-) -235 -21 -58 -222 -218 -99 242 117 -99 45
AUG 2015
DEMAND 2229 1928 2066 2282 2315 2229 1928 2058 2268 2323
AVAILABILITY 2181 2181 2181 2363 2379 2181 2181 2181 2363 2379
SURPLUS (+) /
SHORTAGE (-) -49 253 114 81 65 -48 253 123 95 56
SEP 2015
DEMAND
1854 1632 1906 1907 2093 1849 1630 1906 1906 2070
AVAILABILITY 2034 2034 2034 2167 2216 2034 2034 2034 2167 2216
SURPLUS (+) /
SHORTAGE (-) 180 402 128 260 123 185 404 128 261 146
22
BYPL ALL FIGURES IN MW
1st Fortnight 2nd fortnight
MONTH
00-03 03-09 09-12 12-18 18-24 00- 03- 09-12 12-18 18-24
03 09
APRIL 2015
DEMAND 579 720 836 812 895 1022 837 1009 1108 1122
AVAILABILITY 1034 1034 1034 1072 1120 1059 1059 1109 1147 1195
SURPLUS (+) /
SHORTAGE (-) 455 314 198 260 225 37 222 100 39 73
MAY 2015
DEMAND 1069 964 1054 1140 1123 1191 1097 1143 1323 1260
AVAILABILITY 1425 1425 1425 1473 1502 1425 1425 1475 1523 1552
SURPLUS (+) /
SHORTAGE (-) 356 461 371 333 379 235 328 332 200 292
JUNE 2015
DEMAND 1346 1147 1292 1439 1397 1338 1144 1315 1416 1400
AVAILABILITY 1450 1450 1500 1577 1586 1450 1450 1500 1577 1586
SURPLUS (+) /
SHORTAGE (-) 105 304 208 138 189 112 306 185 161 187
JULY 2015
DEMAND 1416 1292 1314 1514 1521 1337 1140 1213 1443 1369
AVAILABILITY 1425 1425 1475 1607 1616 1425 1425 1475 1607 1616
SURPLUS (+) /
SHORTAGE (-) 9 133 162 93 95 88 285 263 164 247
AUG 2015
DEMAND 1289 1115 1195 1320 1339 1289 1115 1190 1312 1344
AVAILABILITY 1377 1377 1427 1559 1568 1425 1425 1475 1607 1616
SURPLUS (+) /
SHORTAGE (-) 88 262 232 239 230 136 310 285 295 272
SEP 2015
DEMAND
1072 944 1102 1103 1210 1069 943 1102 1102 1197
AVAILABILITY 1326 1326 1326 1428 1457 1326 1326 1326 1428 1457
SURPLUS (+) /
SHORTAGE (-) 253 382 223 325 246 256 383 223 326 260
23
TPDDL ALL FIGURES IN MW
1st Fortnight 2nd fortnight
MONTH
00-03 03-09 09-12 12-18 18-24 00- 03- 09-12 12-18 18-24
03 09
APRIL 2015
DEMAND 699 870 1010 981 1081 1235 1011 1219 1339 1355
AVAILABILITY 1408 1408 1408 1454 1512 1408 1408 1408 1454 1512
SURPLUS (+) /
SHORTAGE (-) 710 539 398 474 431 174 397 189 116 157
MAY 2015
DEMAND 1292 1164 1273 1377 1356 1438 1325 1381 1598 1522
AVAILABILITY 1631 1631 1631 1689 1723 1722 1722 1722 1865 1814
SURPLUS (+) /
SHORTAGE (-) 340 467 358 312 367 284 397 342 267 293
JUNE 2015
DEMAND 1625 1385 1561 1738 1687 1616 1382 1588 1710 1690
AVAILABILITY 1727 1649 1649 1886 1853 1673 1595 1595 1912 1879
SURPLUS (+) /
SHORTAGE (-) 102 264 88 148 166 57 213 7 202 188
JULY 2015
DEMAND 1710 1561 1587 1829 1837 1615 1378 1465 1743 1654
AVAILABILITY 1884 1595 1595 2156 2168 1759 1595 1595 1951 1963
SURPLUS (+) /
SHORTAGE (-) 174 34 9 328 331 144 218 130 209 309
AUG 2015
DEMAND 1557 1347 1443 1594 1617 1557 1347 1437 1585 1623
AVAILABILITY 1740 1620 1620 1932 1944 1740 1620 1620 1932 1944
SURPLUS (+) /
SHORTAGE (-) 183 274 177 339 327 183 274 183 348 321
SEP 2015
DEMAND
1295 1140 1332 1332 1462 1292 1139 1332 1332 1446
AVAILABILITY 1902 1777 1777 2059 2094 1777 1777 1777 1934 1969
SURPLUS (+) /
SHORTAGE (-) 607 637 445 727 632 485 638 445 603 523
24
NDMC ALL FIGURES IN MW
1st Fortnight 2nd fortnight
MONTH
00-03 03-09 09-12 12-18 18-24 00- 03- 09-12 12-18 18-24
03 09
APRIL 2015
DEMAND 100 140 180 180 150 150 220 290 300 200
AVAILABILITY 312 312 312 312 312 312 312 312 312 312
SURPLUS (+) /
SHORTAGE (-) 212 172 132 132 162 162 92 22 12 112
MAY 2015
DEMAND 160 170 310 325 200 180 250 360 350 210
AVAILABILITY 344 344 344 344 344 344 344 344 344 344
SURPLUS (+) /
SHORTAGE (-) 184 174 34 19 144 164 94 -16 -6 134
JUNE 2015
DEMAND 170 250 370 390 260 200 260 380 380 250
AVAILABILITY 344 344 344 344 344 344 344 344 344 344
SURPLUS (+) /
SHORTAGE (-) 174 94 -26 -46 84 144 84 -36 -36 94
JULY 2015
DEMAND 190 270 380 390 270 200 270 380 380 270
AVAILABILITY 344 344 344 344 344 344 344 344 344 344
SURPLUS (+) /
SHORTAGE (-) 154 74 -36 -46 74 144 74 -36 -36 74
AUG 2015
DEMAND 190 270 350 360 290 190 270 370 390 270
AVAILABILITY 344 344 344 344 344 344 344 344 344 344
SURPLUS (+) /
SHORTAGE (-) 154 74 -6 -16 54 154 74 -26 -46 74
SEP 2015
DEMAND
150 250 320 320 200 160 250 320 320 250
AVAILABILITY 344 344 344 344 344 344 344 344 344 344
SURPLUS (+) /
SHORTAGE (-) 194 94 24 24 144 184 94 24 24 94
25
MES
APRIL 2015
DEMAND 22 25 28 23 28 26 35 36 36 34
AVAILABILITY 40 40 40 40 40 40 40 40 40 40
SURPLUS (+) /
SHORTAGE (-) 18 15 12 17 12 14 5 4 4 6
MAY 2015
DEMAND 30 35 40 38 30 32 30 40 40 30
AVAILABILITY 53 53 53 53 53 53 53 53 53 53
SURPLUS (+) /
SHORTAGE (-) 23 18 13 15 23 21 23 13 13 23
JUNE 2015
DEMAND 32 35 42 45 40 32 35 43 45 40
AVAILABILITY 53 53 53 53 53 53 53 53 53 53
SURPLUS (+) /
SHORTAGE (-) 21 18 11 8 13 21 18 10 8 13
JULY 2015
DEMAND 35 42 48 50 41 35 40 45 40 40
AVAILABILITY 53 53 53 53 53 53 53 53 53 53
SURPLUS (+) /
SHORTAGE (-) 18 11 5 3 12 18 13 8 13 13
AUG 2015
DEMAND 34 40 45 45 40 35 40 45 45 40
AVAILABILITY 53 53 53 53 53 53 53 53 53 53
SURPLUS (+) /
SHORTAGE (-) 19 13 8 8 13 18 13 8 8 13
SEP 2015
DEMAND
28 35 40 38 35 30 39 40 40 37
AVAILABILITY 53 53 53 53 53 53 53 53 53 53
SURPLUS (+) /
SHORTAGE (-) 25 18 13 15 18 23 14 13 13 16
26
The summer power supply position was reviewed by the Hon’ble Minister of Power,
GNCTD on 16.03.2015. The following was discussed and decided (The latest position is
updated as under):
a) Minister of Power insisted that Discoms should ensure that there is no power cut
during the peak summer months this year on account of scheduling power by the
Discoms. Discoms were asked to certify that they have made adequate
arrangements for Power in summer vis-a-vis the peak power demand in summer
and there will not be any overloading in the peak summer on the transformers and
other associated system like Cable-lines etc. in their area and adequate
arrangements have been made. BYPL and BRPL said that they are ready to certify
the same. TPDDL mentioned that they are maintaining N-I contingency in all their
areas and do not expect any problem during peak summer months. Similarly, DTL
to certify that there will not be any transmission constraints in meeting the summer
peak demand.
[action : Discoms & DTL to certify by 30.03.2015]
The Distribution Companies informed that they have already submitted the details.
DTL’s Planning Department informed that the position would be submitted soon. It was
further informed that with the commissioning of 220kV Mundka – Peera Garhi D/C line,
220kV Patparganj – Gazipur single circuit cable, 220/66kV 160MVA Txs at Wazirabad
and Gazipur, expected commissioning of LILO of 220kV Najafgarh – Kanjhawala Ckt at
Mundka and commissioning of 220kV Wazirpur – Peera Garhi D/C cable during the
summer season, the transmission capability has been improved and no transmission
constraints anticipated in any part of Delhi except South Delhi where constraints are
prevailing. Though orders have been placed for enhancement of transformation capacity
at Masjid Moth, commissioning of additional transformer at Sarita Vihar, the same may
not be matured during summer season considering the delivery period. It was suggested
that all out efforts should be exercised to commission additional transformer at Masjid
Moth by end of June 2015 by shifting the available transformer at Lodhi Road S/Stn.
G.M. (O&M)-II of DTL intimated that Discoms should attend the following constraints
immediately to avoid load shedding in case of any issue at DTL sub-stations:-
i) Four 11kV feeders namely Aali Village, Jaitpur, Saurav Vihar Ckt-I, Saurav Vihar Ckt-II
at Sarita Vihar have no back feed arrangements and hence in case of tripping of any the
four feeders, the area is left with loss of supply till the same is rectified.
ii) 66kV Jafarpur Ckt-I & II has only the feed from Najafgarh. These feeders have no bus
selection at Najafgarh due to space constraints. Therefore, in case of fault at the Grid
S/Stn or shut-down taken for maintenance activities for 66kV Bus, the areas fed from
66kV Jafarpur S/Stn of BRPL is left with load shedding.
27
iii) 66kV Nangloi and Nangloi Water Works feeders emanating from Najafgarh S/Stn have
alternative back feeding arrangements at 66kV level from Mundka S/Stn but the 66kV
supply of Mundka is normally out due to cable faults which is a normal phenomenon of
the circuits.
iv) 12 number of 11kV Feeders from Najafgarh have no back feed arrangements and any
tripping of transformer or feeders, the areas left with no supply. BRPL should shift the
load to the nearby sub-station DJB S/Stn of BRPL established nearby Najafgarh S/Stn.
v) Four numbers of 11kV feeders (Bengali Colony, Vinodpuri, Pappankalan Sec-7 and
NSIT) at Pappankalan-I have no back feeding arrangements at Discoms end.
vi) 66kV radial feeding of GGSU Grid of BRPL from Pappankalan-II has no alternate source.
vii) 33kV India Habitat Center Ckt-I & II is redially fed from 220kV Lodhi Road S/Stn have
not alternate arrangements.
viii) 66kV Sonia Vihar Ckt-I & II and 66kV Shastri Park Ckt-I & II of BYPL are radially fed
from South of Wazirabad. In case of any major fault, break-down at South of Wazirabad,
there is no alternate arrangement to meet the entire load.
ix) Four numbers of 11kV feeders (Ghevra, SOS Bawana, JJ Cluster and ABC Kanjhawala)
from Kanjhawala 220kV S/Stn have no back feed arrangements leaving supply failure in
case of fault at 11kV system at the S/Stn.
x) The 11kV panels of Gopalpur have outlived their useful life. The four feeders (Rainey
Well, Takia Chowk, Shah Alam Bandh, Jagatpur) have no back feed arrangements.
TPDDL informed that at present, part load can be back feeded from these feeders.
However, these feeders would have alternate arrangement for back feeding after the
commissioning of 33kV Dheerpur Grid S/Stn which is expected to be commissioned
during 2016-17 and commissioning of 66kV Burari Grid subsequently.
BYPL informed that with regard to 66kV Sonia Vihar feeders from SOW there are no
other 66kV sources however, some part of load can be shifted through 11kV System.
With regard to 66kV Shastri Park Ckt.I & II from SOW is concerned, there are no other
66kV sources at Shastri Park but some load can be shifted through 33kV System.
28
BRPL provided the back feeding arrangement as under:
b) However, TPDDL insisted that if DTL Sub-station projects at Peera Garhi and DTL
cable projects between Mundka to Peeragarhi, Peeragarhi to Wazipur, LILO at
Mundka – Kanjhawala lines are not completed in time then there may be load
shedding in case of overloading of existing line. MD, DTL informed that all these
projects shall be completed by April end positively.
29
CEO, BYPL said that Gazipur – Noida – Badarpur circuit is very important to meet
any contingency in case of any problem in Maharani Bagh – Gazipur lines.
However, both the circuits of Gazipur – Noida – Badarpur lines are out of order.
MD, DTL informed that they are regularly following up with UPTCL for early
repair of these lines and have also arranged a meeting in Central Electricity
Authority for early revival of the same. CEO, BYPL also raised the issue of
saturation of capacity of the DTL sub-station in Central Delhi and said it may pose
problems in ensuing summer.
CEO, BRPL said that additional transformer at Pappankalan is very important for
them, otherwise, there may be power cut during the summer. MD, DTL informed
that their request for diverting one transformer have not been accepted by Punjab
State Transmission Co. Ltd and a draft letter on behalf of Minister of Power,
GNCTD has been put up. The order of the transformer has already been placed on
BHEL and it is expected by May end.
It was informed that the Power evacuation position of Peeragarhi Substation is very slow
and Discoms were requested to utilize maximum from Peeragarhi to ease loading on
Papankalan-I, Najafgarh etc. As on date, the following feeders are still not energized
from Peeragarhi:
33kV Peera Garhi Ckt-I -BRPL
33kV Peera Garhi Ckt-II -BRPL
33kV Sudershan Park Ckt. -TPDDL
BRPL assured that during the summer maximum 150 MW load would be put on the
substation and requested for additional 100MVA Transformer by 31.03.2016 to ensure
reliability.
TPDDL informed that they have already charged 33kV Rani Bagh feeder (through which
the Peeragarhi substation was test charged). As far as Sudarshan Park is concerned, this
is a deposit work and would be ready by 31.03.2017.
c) The members of Task Group of the Delhi Dialogue Committee (DDC) said that
Discoms should anticipate the worst scenario, make a plan according to that and
provide the same to Power Minister and Power Department by 31.03.2015.
[Action : BYPL, BRPL and TPDDL]
30
d) The members of Task Group of the Delhi Dialogue Committee (DDC) also asked
DTL to put up a note informing about the works which have been done for
strengthening the transmission system and solution for mitigating the crisis in
Central Delhi, since it was highlighted by BSES Yamuna Power Limited that all
sub-stations owned by DTL supplying to Central Delhi are overloaded and does not
have any capacity for augmentation.
[Action : DTL]
DTL intimated that the note would be provided soon.
e) BSES Discoms requested Principal Secretary (Power), to write to Centre for providing
cheaper power from the unallocated power of Central quota to Delhi. Pr. Secretary
(Power) said that a request letter in this regard is being sent.
The members of Task Group of the DDC said that the Reliance Discoms should ensure
that the full entitlement of 426MW from Sasan Plant is provided by their sister concern
Reliance Energy. Since, this was the cheapest source of power, this should be prioritized
even above the unallocated power of Central quota.
[Action : BRPL and BYPL]
It was intimated by Discoms that as per the Tariff Regulations, the Sasan plant has to
attain 85% availability factor to recover the full fixed charges which has already attained.
The details of commissioning of units of Sasan UMPP are as under :
The details of generation of Sasan for the year 2013-14 and 2014-15 are as under:-
31
The tariff of Sasan has been derived through competitive bidding and the rates approved
by CERC vide its order dated 17.10.2007 are as under:-
Contr Commence End Quoted Non Quoted Quoted Quoted Indexed Actual commencement
act ment date Date of Escalable Escalable Non Energy Charges date of contract year
year of Contract Contract Capacity Capacity indexed (Rs/kWh)
Year Year Charges Charges (Rs. / Energy
(Rs/kWh) kWh) Charges
(Rs/kWh)
1 27-Nov- 31-Mar 0.121 0.001 0.575 0.001 31.03.2013
2012
2 1-Apr 31-Mar 0.125 Same as above 0.575 Same as above 01.04.2013-31.03.2014
3 1-Apr 31-Mar 0.163 Same as above 1.148 Same as above 01.04.2014-31.03.2015
4 1-Apr 31-Mar 0.171 Same as above 1.148 Same as above 01.04.2015-31.03.2016
5 1-Apr 31-Mar 0.169 Same as above 1.148 Same as above 01.04.2016-31.03.2017
6 1-Apr 31-Mar 0.169 Same as above 1.148 Same as above 01.04.2017-31.03.2018
7 1-Apr 31-Mar 0.169 Same as above 1.148 Same as above 01.04.2018-31.03.2019
8 1-Apr 31-Mar 0.168 Same as above 1.148 Same as above 01.04.2019-31.03.2020
9 1-Apr 31-Mar 0.167 Same as above 1.148 Same as above 01.04.2020-31.03.2021
10 1-Apr 31-Mar 0.166 Same as above 1.147 Same as above 01.04.2021-31.03.2022
11 1-Apr 31-Mar 0.165 Same as above 1.147 Same as above 01.04.2022-31.03.2023
12 1-Apr 31-Mar 0.164 Same as above 1.147 Same as above 01.04.2023-31.03.2024
13 1-Apr 31-Mar 0.164 Same as above 1.147 Same as above 01.04.2024-31.03.2025
14 1-Apr 31-Mar 0.163 Same as above 1.147 Same as above 01.04.2025-31.03.2026
15 1-Apr 31-Mar 0.162 Same as above 1.146 Same as above 01.04.2026-31.03.2027
16 1-Apr 31-Mar 0.161 Same as above 1.146 Same as above 01.04.2027-31.03.2028
17 1-Apr 31-Mar 0.160 Same as above 1.146 Same as above 01.04.2028-31.03.2029
18 1-Apr 31-Mar 0.160 Same as above 1.146 Same as above 01.04.2029-31.03.2030
19 1-Apr 31-Mar 0.159 Same as above 1.145 Same as above 01.04.2030-31.03.2031
20 1-Apr 31-Mar 0.158 Same as above 1.145 Same as above 01.04.2031-31.03.2032
21 1-Apr 31-Mar 0.157 Same as above 1.145 Same as above 01.04.2032-31.03.2033
22 1-Apr 31-Mar 0.136 Same as above 1.145 Same as above 01.04.2033-31.03.2034
23 1-Apr 31-Mar 0.126 Same as above 1.144 Same as above 01.04.2034-31.03.2035
24 1-Apr 31-Mar 0.126 Same as above 1.144 Same as above 01.04.2035-31.03.2036
25 1-Apr 31-Mar 0.137 Same as above 1.144 Same as above 01.04.2036-31.03.2037
26 1-Apr 25th 0.169 Same as above 1.143 Same as above 01.04.2037-31.03.2038
annivers
ary of
the
schedule
d COD
of the
first unit
32
It was also informed that lots of litigations are going at CERC level / APTEL level.
Some of the details of CERC level litigations are as under:-
33
Petition No. Title of the Petition Present status
relevant documents including the audited capital cost as
on the commercial operation of the respective units and
the last unit of the generating station, (ii) Financing
Agreements including the Order in Petition No.
21/MP/2013 Page 59 of 59 capital cost as per the
Financing Agreement, (iii) documents as sought under
various items allowed under Change in Law, (iv) all
relevant documents with regard to the decision for
utilization of coal from the captive mines in other
projects of the petitioner, (v) the actual quantum of coal
extracted from the mines and the actual quantum of coal
utilized separately for Sasan UMPP, for other projects of
the petitioner and for commercial purposes, if any, (vi)
information regarding coal sought in para 25, 26, 27 and
29 of the order and (vii) any other relevant information.
(e) This information is required to decide the exact
quantum of compensation admissible under “Change in
Law”. (f) The petitioner is entitled to relief under Change
in Law strictly in accordance with Article 13.2(a) of the
PPA. 50. The petitioner had filed IA No.24/2013 for
provisional increase in tariff of Sasan UMPP on account
of Change in Law as per the computation submitted
along with the said IA pending final disposal of the
petition. In view of our decision in this order, the IA has
become infructuous and is accordingly disposed of in
terms of our above directions.
75/MP/2013 Petition under Section The petition was disposed off vide order dated
79 of the Electricity Act, 22.02.2014. The decision is as under:-
2003 read with statutory However the petitioner has not submitted any
framework governing documentary proof of this order which explicitly directs
procurement of power OMCs to raise prices for bulk consumers. It has only
through competitive submitted a Press Release of Indian Oil Corporation one
bidding and Articles of the PSU OMCs intimating the withdrawal of
13.2.(b) of the Power subsidized pricing for bulk consumers. Even if
Purchase Agreement Government of India ordered the PSU OMCs to raise the
dated 07.08.2007 price of diesel for bulk consumers, it is only applicable
executed between Sasan for the specific Oil marketing Companies, and not for the
Power Limited and the other private players or to the market as a whole, as the
Procurers for price of petroleum products are already deregulated vide
compensation due to Gazette Notification dated 28.03.2002. So the argument
Change in Law of the petitioner that charging market determined price
impacting revenues and and withdrawal of subsidy for bulk consumers is a
costs during the change of law event is not tenable. The petitioner must
Operating Period. have been aware of such possibility at the time of bid
submission as decision for phased dismantling of APM,
gradually migrating towards market determined pricing
and specific timeline for it were determined in Gazette
Notification dated 24.11.1997. Hence any relief to the
petitioner will not be admissible under Change of Law.
34
Petition Title of the Petition Present status
No.
85/MP/2013 Consideration of the The petition was disposed off vide order dated 08.08.2014.
declaration of COD Treatment of the power scheduled after 30.3.2013 upto
and scheduling of 15.8.2013 36. As a consequence of the above, the final
Sasan UMPP in terms question which remains to be answered is what treatment
of the judgement should be given to the power scheduled for the period
dated 12.8.2013 in 31.3.2013 to 15.8.2013. Since, we have held that the unit of
Appeal No.149/2013 the generating station has failed to qualify the performance
of Appellate Tribunal test for 95% of the contracted capacity which is a pre-
for Electricity requisite for declaration of the commercial operation in
terms of the provisions of the PPA, the power injected
during this period shall be treated as infirm power. 37.
Learned senior counsel for the petitioner suggested during
the hearing on 27.5.2014 that an independent technical
committee be appointed to look into the aspect of readiness
of unit-3 of the generating station to achieve full load on
31.3.2013. The petitioner in its additional submission filed
vide affidavit dated 27.5.2014 has reiterated the same
suggestion and has submitted that appointing a independent
committee will be in the interest of justice and no prejudice
will be caused to the petitioner. We have considered the
suggestion of the petitioner. In our view, the facts on record
make it crystal clear that the load restriction was only on
27.3.2014 and thereafter, the petitioner had the opportunity
to achieve the full load as its machine repeatedly tripped. In
our view, readiness of the machine is not a relevant factor
for declaration of COD under the PPA unless the machine
actually achieves the 95% of the contracted load as per the
provisions of the PPA. We do not find any requirement to
constitute a committee as suggested by the petitioner in view
of our finding that the unit-3 of the generating station was
unable to achieve its full load on 31.3.2014. The petition is
disposed of in terms of the above.
6/MP/2013 Petition under Section The petition was disposed off vide order dated 31.03.2015.
79 of the Electricity 25. The cutoff date for submission of bid was 21.7.2007. As
Act, 2003 read with per the notification dated 27.7.2003 issued by Government
statutory framework of Madhya Pradesh, the applicable water rate as on the date
governing of submission of the bid was `1.80/M3 . Through the
procurement of power notification issued by Government of Madhya Pradesh dated
through competitive 21.4.2010, the water charges have been revised for the years
bidding and Article starting 1.1.2010, 1.1.2011, 1.1.2012 and 1.1.2013 @`4.00,
13.2(b) of the Power 4.50, 5.00 and 5.10 respectively. The petitioner has claimed
Purchase Agreement the water charges on the basis of the notification dated
dated 7.8.2007 21.4.2010 treating it as “Change in Law”. At this stage, we
executed between have not gone into the aspect whether the notification dated
Sasan Power Limited 10.4.2010 issued by the Government of Madhya Pradesh
and the Procurers for would amount to “Change in Law” and whether the said
compensation due to notification would have the effect on the cost/revenue of the
“Change in Law” petitioner from the business of selling electricity to the
impacting revenues procurers under the terms of the PPA. For taking a view
and costs during the whether increase in water charges should be considered as
Operating Period. “Change in Law”, we direct the petitioner to submit the
following information: (a) Prevailing rates of water charges
in Madhya Pradesh from the year 1995 onwards along with
35
Petition Title of the Present status
No. Petition
the supporting notifications. (b) Water charges assumed and factored
while the quoted bid for the project along with year to year escalation
assumed for the entire bid period. (c) Actual quantum of water required
to generate the contracted capacity of electricity and the basis of
calculation of water consumption. (d) Other bid parameters (final and
operation) assumed in the bid in respect of quoted tariff like cost of
additional water beyond requirement, etc. The petitioner is granted
liberty to approach the Commission along with the above information for
consideration of its claim in terms of the PPA.
36
It was further clarified that from 01.04.2015 full contracted capacity (446 MW) power is
being scheduled by Sasan to Delhi.
f) Minister of Power desired that the provisions of PPA be studied for penalizing
Sasan for not generating at its full present available capacity.
[Action : Pr. Secretary (Power)]
g) On the insistence of the Task Group of the DDC, the Reliance Discoms assured that there
would be no default in payment to DVC, SJVNL, NHPC, PGCIL and that there would be
no shortage of power due to regulation.
[Action : BRPL & BYPL]
It was informed that at present, the following regulations are continued in BRPL and
BYPL areas:-
Tanakpur 28/03/2015-24/09/2015 5 3
Chamera -I 28/03/2015-24/09/2015 19 11
Chamera-II 28/03/2015-24/09/2015 18 10
URI 28/03/2015-24/09/2015 23 13
Dhauliganga 28/03/2015-24/09/2015 16 9
Sewa II 28/03/2015-24/09/2015 7 4
Chamera-III 28/03/2015-24/09/2015 13 7
09/05/2015 --continuing 62 25/09/2013- 39
SJVNL TILL DATE
-- 8/10/2013- 102 (withdrawn from
DVC LT3 22.02.2015 01/05/15)
-- 8/10/2013-
DVC LT4 22.02.2015
22/02/2015-30/04/2015 177 22/02/2015- 100 (withdrawn from
DVC LT3 30/04/2015 01/05/15)r
22/02/2015-30/04/2015 22/02/2015-
DVC LT4 30/04/2015
8/10/2013- 119
30/04/2015 (withdrawn from
Mejia 7 01/05/15)
TOTAL 107 120
BRPL and BYPL representatives assured that all out efforts are taken to withdraw the
above regulations and they hoped that the regulations of DVC would be withdrawn from
01.05.2015.(which was subsequently withdrawn from 01.05.2015).
37
GCC noted that power regulations of cheaper sources like hydro during summer
months is not advisable and advised the utilities to make all efforts to withdraw the
regulations and advised to ensure that consumers are not suffered due to load
shedding in peak summer season on account of the regulations.
BRPL & BYPL assured that substation power would be arranged to meet the
requirement during summer season.
To ensure the reliable power supply, various plans have been drawn out by DTL and
Discoms. The details are as under:-
a) Transmission System
38
S. Details of System Reason for Timeline Executi Current status Revised
N. Improvement requirement fixed by ng Timeline
project MoP, GoI Agency
/ DTL
5 Commissioning of --do-- 31.05.13 DTL Substation at Wazir Pur 31.05.15
220kV Peera has been commissioned
Garhi – Wazipur and energized from
D/C cable Shalimar Bagh through
220kV Wazirpur double
circuit cables.
The contract issues with
the vendor namely M/s
Tibbia has been settled
for commissioning of
220kV Peera Garhi –
Wazirpur D/C cable.
Expected by May 2015
6 Commissioning of To reduce loading Before DTL Total length of the 31.10.15
220kV Bawana– of 220kV Rohini-I summer circuit is 6.1Kms. Out
Rohini-II Double S/Stn 2014. of 38 Nos. Of towers,
Ckt line (O/H) 19 towers have been
erected. At 30 locations
foundations have been
cast. Work is likely to
be completed by
October 2015 as shut-
downs are involved in
220kV Bawana –
DSIDC D/C and 220kV
Bawana – Shalimar
Bagh one ckt. And
220kV Bawana –
Rohini one ckt.
7 Commissioning of To reduce the 31.08.14 DMRC Charged on no load on Already
220kV Gazipur – loading of 220kV 31.03.15 at 13:48 hrs. commissio
Patparganj link Wazirabad – Geeta Load was taken on ned
Colony Ckts and to 07.04.15 at 12:56 hrs.
increase the supply
of Patparganj
8 Augmentation of To control the Before DTL Techno Commercial 31.12.15
2X 220/66kV loading of existing summer bids were opened on
100MVA Txs to transformers and to 2014 30.01.2015. since the
160MVA Txs at create reliability of rates quoted by L-1
Pappankalan-I supply bidder are 30.47%
higher, Planning
Department was
requested to revisit the
estimates.
9 LILO of one To provide alternate By end of DTL Tender opened on 31.12.15
circuit of 220kV source at March 30.03.2015. Technical
Bamnauli – Pappankalan-II 2015 evaluation is in process
Najafgarh link at with TEC.
Pappankalan-II
10 LILO of one To provide alternate By end of DTL Tender opened on 31.03.16
circuit of 220kV source at March 30.03.2015. Technical
Bamnauli – Pappankalan-I 2015 evaluation is in process
Naraina Ckt-I at with TEC.
Pappankalan-I
39
S. Details of System Reason for Timeline Executi Current status Revised
N. Improvement requirement fixed by ng Timeline
project MoP, GoI Agency
/ DTL
11 HTLS re- To provide reliable By end of PGCIL Shutdown of Ckt.I has 11.07.15
conductoring of supply at Naraina March been taken on 09.05.15
D/C 220kV and Ridge Valley 2015 for augmentation of
Bamnauli – etc conductors and
Naraina Ckts expected to be
completed by 09.06.15.
the shutdown of the
other ckt would be on
11.06.15 and expected
to be completed by
11.07.15
12 HTLS re- To avoid over- 31.03.15 PGCIL The augmentation of 31.05.15
conductoring of loading of existing ckt.I has already been
D/C 220kV Geeta circuits and to completed on 14.05.15.
Colony – enhance reliability The work on the other
Wazirabad D/C of supply ckt has started on
18.05.2015 and could
be finished by
31.05.15.
13 HTLS re- To avoid over- 31.03.15 PGCIL Material has been 31.03.16
conductoring of loading of existing arranged by PGCIL
D/C 220kV IP circuits and to Possibility of shut-
Power – Sarita enhance reliability down would be
Vihar Ckts of supply explored after the
commissioning of
220kV Wazirabad –
Geeta Colony D/C.
14 LILO of first To avoid over- 31.03.15 DTL Scheme is under 31.03.16
circuit of double loading of existing revision with Planning GCC
circuit of 220kV circuits and to Department for both advised
Pragati – Sarita enhance reliability the circuits(Ckt-I & II) DTL to
Vihar Ckt. at of supply complete
400kV Maharani at least one
Bagh ckt. LILO
by 31.03
.16 to meet
the next
summer
demand.
15 Commissioning of To ensure 31.03.15 PGCIL To be carried out 31.03.16
220kV Harsh maximum PGCIL.
Vihar – evacuation from
Patparganj D/C Harsh Vihar and
ease loading on
Mandola system
16 Augmentation of To ease the loading 31.03.15 PGCIL Work awarded to M/s 31.10.15
2X315MVA ICTs of existing CGL. One 500 MVA
to 2X500MVA transformers and to Tr. has already reached
ICTs at Bamnauli. enhance reliability at site. The shutdown
of supply. of the existing one 315
MVA Tx. would be
taken during the period
25.05.15 to 31.05.15 to
place the 500 MVA Tx.
in its place. The other
Tx. is expected to be
commissioned by
31.10.15
40
S. Details of System Reason for Timeline Executi Current status Revised
N. Improvement requirement fixed by ng Timeline
project MoP, GoI Agency
/ DTL
17 Augmentation of To ease the loading Two ICTs PGCIL Two ICTs are expected Two Tx by
4X315MVA ICTs of existing before by July 2015 and other 31.07.15
to 4X500MVA transformers and to summer two by end of 2015. and other
ICTs at Mandola enhance reliability 2014 and To be executed by two by
(PGCIL S/Stn) of supply. two before PGCIL. Last year, one 31.12.15
summer additional 315MVA Tx
2015 was energized through
common breaker.
However, CEA has not
agreed to charge the
additional tr. Through a
same breaker of other
transformer citing
safety reasons.
18 Augmentation of To ease the loading Before PGCIL The Tx is expected by
4X315MVA ICTs of existing summer December 2015..
to 4X500 MVA transformers and to 2015
ICTs at enhance reliability
Ballabhgarh of supply.
(PGCIL S/Stn)
19 Additional To enhance Before DTL LOI issued to L-1 31.12.15
220/66kV reliability of supply summer bidder, M/s Safety Plus
100MVA Tx at 2015 Power Ltd. on
Sarita Vihar 22.04.2015. LOA under
approval and likely to
be awarded by
14.05.2015.
20 Additional To enhance Before DTL LOA issued to L-1 31.12.15
220/66kV reliability of supply summer bidder M/s Kanohar
160MVA Tx at 2015 Electricals Ltd in Joint
DSIDC Bawana Venture with Jayashree
Electro mech (P) Ltd.
on 20.04.2015.
21 Additional To enhance Before DTL LOA issued to L-1 31.12.15
220/66kV reliability of supply summer bidder M/s Kanohar
160MVA Tx at 2015 Electricals Ltd in Joint
Pappankalan-II Venture with Jayashree
Electro mech (P) Ltd.
on 22.04.2015.
22 Additional To enhance Before DTL LOA issued to L-1 30.09.15
220/66kV reliability of supply summer bidder M/s Kanohar
160MVA Tx at 2015 Electricals Ltd in Joint
Kanjhawala along Venture with Jayashree
with 4 Bays at Electro mech (P) Ltd.
66kV level on 20.04.2015.
41
S. Details of System Reason for Timeline Executi Current status Revised
N. Improvement requirement fixed by ng Timeline
project MoP, GoI Agency
/ DTL
23 Additional To enhance Before DTL The evaluated price of 30.06.15
220/33kV reliability of supply summer L-1 bidder are very high GCC
1000MVA Tx at 2014 in comparison to the advised
Masjid Moth estimated cost. Tender DTL to
Committee explore the
recommended to review possibility
the price estimate. Case of shifting
referred for review of the
cost estimate. transforme
r available
at Lodhi
Road and
commissio
ned the
same by
30.06.15
considerin
g the
criticality.
24 Establishment of To reduce the Aug. 2014 DTL 33kV GIS works 31.12.15
33kV GIS at loading on the completed. 220kV GIS
Lodhi Road with existing work and additional
additional transformers transformer work to be
220/33kV completed by December
100MVA Tx at 2015.
Lodhi Road
42
SN Details of System Improvement project Current status
19 220kV D/C Tuglakabad – Okhla O/H line To be executed by PGCIL
20 220kV D/C Kashmiri Gate – Raj Ghat O/H line To be executed by PGCIL
21 LILO of Geeta Clny – Patparganj O/H line at Rajghat To be executed by PGCIL
22 LILO 220kV D/C Narela – Rohtak Road at SGTN To be executed as TBCB
23 220kV D/C Masjid Moth – Okhla U/G line To be executed by PGCIL
24 PR received. QR for erection and
for manufacturing of line materials,
route map and FQP are awaited
HTLS conductoring D/C Bamnauli-Mehrauli-BTPS
from Planning Deptt. However,
other sections of NIT are under
compilation.
25 PR received. QR is in approval
LILO of D/C U/G Ridge Valley-AIIMS at RKPuram
process.
26 LILO of Najafgarh-Bamnauli D/C O/H at Budella To be executed as TBCB
27 To be executed as TBCB
D/C LILO Maharani Bagh – Sarita Vihar at Jasola
28 LILO of 220kV D/C Narela–Mandola at Hamidpur RFQ under preparation
29 Scheme is under revision by
2nd ckt LILO of Pragati –Sarita at Maharanibagh
Planning Deptt.
30 Project is being executed by
220kV D/C Vasant Kunj – R K Puram U/G line
DMRC.
31 LILO of D/C Gopalpur–SabjiMandi at Chandrawal To be executed as TBCB
32 IP Power to Rajghat Tower route modification The work to be executed by PGCIL
33 QR is under review by Planning
3 nos 220KV GIS bay addition at Kashmiri gate
Deptt.
43
S.
Details of System Improvement project Current status
N.
19 LILO D/C Wazirpur-Peera garhi at Karampura U/G To be executed by PGCIL
20 Karmapura to Rohtak road D/C U/G cable To be executed by PGCIL
21 220kV D/C Karampura – Budella O/H line To be executed by PGCIL
22 220kV D/C Karampura – Subzi Mandi line To be executed by PGCIL
23 220kV D/C Peeragadi – Rohini-II O/H line To be executed by DTL
24 LILO of 220kV D/C Masjid Moth – Maharani Bagh at Nehru
To be executed as TBCB
Place
25 220kV D/C Papankalan-I to Janak Puri To be executed as TBCB
26 LILO of D/C Mehrauli-DIAL O/H line at Rang Puri To be executed as TBCB
27 LILO of D/C Rohini to Budella at Rohini Sector-1 To be executed as TBCB
b) Distribution System
44
MVA Present Status
S Particulars / Name of the Project /
Additi Scheme Status
N Element
on
Strengthening of 33kV Line between Under Execution. Will be
13 0 WIP
AIR Khampur and Tigi Pur Grid completed on 31st Mar.16.
33kV Twin Cable (2 x 3C*400 sqmm) TPDDLwork is ompleted.
Energisation is
14 between 220kV Peera Garhi and Rani 0 Pending at DTL end
pending
Bagh CC Grid
33 /11 kV Rani Bagh CC Grid (2 x
15 20MVA + 2 x 3C*400sq.mm. XLPE 40 Completed
from 220kV Peera Garhi Grid)
66/11 kV Dheerpur Grid ( 2 x 25MVA Submitted for re-approval
DERC Approval
+1* 1000sq.mm. Cable LILO of 66kV
16 50 received in Sep-
line between 220kV Gopal Pur and
2014
Jahangir Puri)
66 / 11 kV Prashant Vihar Grid (2 x 25 Grid charge with LILO of
MVA + 1*1000sq.mm. cable LILO of Work in one circuit. LILO of other
17 50
66kV line between Pitam Pura-1 and progress circuit will be completed
Rohini-3 Grid) on 30th June 2015.
66/11 kV Bawana-1 Grid (2 x 25 MVA + Completed
66kV line from 220kV DSIIDC Bawana
Grid + 66kV line LILO between 220kV
18 50 Completed
Kanjhawla and BCWW Grid + 66kV
LILO between BCWW and Bawana-7
Grid) line twin cable 1C*1000 sqmm
33 /11 kV A-21 Naraina Grid (2 x 18 Completed
MVA + 33kV line LILO between Inder
19 36 Completed
Puri and Rewari Line), line twin cable
3*400 sqmm
66 / 11 kV RG-34 Grid (2 x 25 MVA + Under Execution. Will be
D/C 1C*1000 sq.mm. cable from completed on March 16
DERC Approval
20 proposed 66kV RG-30 Grid + D/C 50
received
1C*1000 sq.mm. cable from proposed
220 kV Rohini-34 Grid)
66 / 11 kV Bawana-1 Ph-2 Grid (2 x 25 Under Tendering
MVA + D/C O/H line LILO between DERC Approval
21 50
220kV DSIIDC Bawana and 66kV received
DSIIDC-2 Narela)
TPDDL 2015-16
45
MVA Present Status
S
Particulars / Name of the Project / Element Addit Scheme Status
N
ion
Under Execution.
Additional 25 MVA PTR-3in 66/11 kV Bhalswa- DERC Approval
4 25 Will be completed
1 received
in July 2015.
Under Execution.
DERC Approval
Additional 25 MVA PTR-3 at 66/11 kV RG 22 Will be completed
5 25 received in Sep-
Grid in July 2015.
2014
Under Execution.
Additional 16 MVA PTR-3 at 33/11 kV GTK DERC Approval Will be completed
6 16
Grid received in June 2015.
46
MVA Present Status
S
Particulars / Name of the Project / Element Addit Scheme Status
N
ion
66 / 11 kV NSC G-8 Grid (2 x 25 MVA + D/C DERC Approval
twin 3*300 sq.mm. cable from proposed 220kV DERC Approval awaited
17 50
NSC-1 Grid + D/C twin 3*300 sq.mm. cable from awaited
66kV NSC G2 G6 Grid-2 )
66 / 11 kV Pooth Khurd-2 Grid (2 x 25 MVA + Payment awaited
D/C twin 3*300 sq.mm. cable from 66kV BCWW from applicant.
DERC Approval
18 Grid + S/C twin 1*1000 sq.mm. cable LILO line 50
awaited
between 66kV Bawana-6 and 66kV Pooth Khurd-
1 Grid)
TPDDL 2016-17
S No Particulars / Name of the Project Scheme Status
Conversion of Sabzi Mandi to SKN CKT to Twin cable (3 x
1 To be submitted to DERC.
400 sqmm)
2 Twin 3*300sqmm S/C 66kV from Mundka to Mangol Puri-1 To be submitted to DERC.
33/11 kV Bhor Garh Grid (2 x 25 MVA + 33kV line LILO
3 between 220kV Subzi Mandi and Shakti Nagar), twin cable 3 x To be submitted to DERC.
400 sqmm
33/11 kV WazirPur-4 Grid (2 x 25 MVA + 33kV line LILO
Will be submitted for
4 between Wazir Pur-1 and Wazir Pur-2 Grid), twin cable 3 x
2017-18
400 sqmm
33/11 kV LRIA Grid (2 x 25 MVA + 33kV line LILO between Will be submitted for
5
Ram Pura and Ashok Vihar Grid), twin cable 3 x 400 sqmm 2017-18
66/11 kV Rohini-6 No-2 Grid (2 x 25 MVA + 66kV line LILO
Will be submitted for
6 between 220kV Rohini and Rohini-6 Grid), twin cable 3 x 300
2017-18
sqmm
66/11 kV Budh Vihar Grid (2 x 25 MVA + 66kV line LILO Will be submitted for
7
between Rohini-2 and Rohini-23 Grid), cable 1C*1000 sqmm 2017-18
33/11 kV NSP Grid (2 x 25 MVA + 33kV line LILO between
Will be submitted for
8 220kV SMB and Wazir Pur-1 Circuit-2), twin cable 3 x 400
2017-18
sqmm
66 / 11 kV NSC G2-G6 Grid-2 (2 x 25 MVA + D/C twin 3*300
sq.mm. cable from proposed 220kV NSC-1 Grid + D/C twin Will be submitted for
9
3*300 sq.mm. cable from 66kV NSC G8 Grid + D/C twin 2017-18
3*300 sq.mm. cable from 66kV NSC G3-G4 Grid)
66 / 11 kV NSC G3-G4 Grid (2 x 25 MVA + D/C twin 3*300
Will be submitted for
10 sq.mm. cable from proposed 220kV NSC-2 Grid + D/C twin
2017-18
3*300 sq.mm. cable from 66kV NSC G2-G6 Grid-2)
Augmentation of 16MVA PTR-1 and 16MVA PTR-2 to
11 To be submitted to DERC.
25MVA each in 33/11kV Trinagar Grid
47
BYPL
2014-15
Capacity DERC
S. Voltage
Scheme Description Addition approval Work Status
No. Level
(MVA) Status
Establishment of New 66/11 kV
1 66/11kV 50 Approved Completed
Grid Sub-Station at Kondli Gharoli
Establishment of New 33/11 kV
2 33/11kV 50 Approved Completed
Grid Sub-Station at DDU Marg
Addition of 25 MVA Power
3 66/11kV Transformer at 66/11 KV East of 25 Approved Completed
Loni Road Grid Sub-station
Addition of 25 MVA Power
4 66/11kV Transformer at 66/11 kV Bhagirathi 25 Approved WIP, April-2015
Grid Sub-station
Addition of 16 MVA Power
5 33/11kV Transformer at 33/11 kV Kanti 16 Approved Completed
Nagar Grid Sub-station
Addition of 16 MVA Power
6 33/11kV Transformer at 33/11 kV CBD-2 16 Approved Completed
Grid Sub-station
Addition of Power Transformer of
7 33/11kV 25 MVA at 33/11 kV Delhi Gate 25 Approved WIP, April-2015
Grid Sub-station
Addition of 20 MVA Power
8 66/11kV Transformer at 66/11 KV GH-1 20 Approved Work held up
Grid Sub-station
Augmentation of Power
Transformer from 16 MVA to 25
9 33/11kV 9 Approved Completed
MVA at 33/11kV CBD-1 Grid Sub-
station
Augmentation of Power
Transformer No.2 from 15 to 25
10 33/11kV 10 Approved Completed
MVA at 33/11kV Shankar Road
Grid Sub-station
Augmentation of 16 MVA Power
Transformer no-3 to 25 MVA at
11 33/11kV 9 Approved Completed
33/11 KV Shankar Road Grid Sub-
station
Augmentation of Power
Transformer No.-2 from 16 MVA to
12 33/11kV 9 Approved Completed
25 MVA at 33/11 KV Preet Vihar
Grid Sub-station
Augmentation of Power transformer
Work In Progress(WIP),
13 33/11kV from 16 MVA to 25 MVA at 33/11 9 Approved
April 2015
KV Kailash Nagar Grid Sub-station
48
S. Capacity DERC
Voltage
No Scheme Description Addition approval Work Status
Level
. (MVA) Status
Augmentation of Power
66/11k Transformer No-1 from 20 MVA
14 12 Approved Deferred
V to 31.5 MVA at 66/11 KV Yamuna
Vihar Grid Sub-station
Augmentation of 66/33kV, 30
MVA Power Transformer with
66/33k
15 66/33kV, 50 MVA Power 20 Approved YTS, June 2015
V
Transformer at Bhagirthi Grid Sub-
station.
Total 305
S. Volta DERC
Source
N ge Scheme Description pproval Work Status
Station
o. Level Status
Providing 66 KV infeed for 66/11
66kV Kondli KV O/D grid S/STN at Kondli
1 66kV Approved Completed
Grid Resettlement colony in Div Mayur
Vihar III
220kV IP Providing 33KV Infeed to DDU
2 33kV Station & Marg Grid Sub-Station by laying of Approved Completed
RPH 2 nos 33KV 3CX400MM2 Cable.
Providing 33 kV feed from
33kV
Shakarpur Grid to Guru Angad
3 33kV Shakarpur Approved Completed
Nagar Grid by laying of 2 nos 33kV,
Grid
3CX400MM2 XLPE cables.
Laying of 66 KV 1CX1000MM2
XLPE cables from Mayur Vihar - I
4 66kV Pragati Power Approved Completed
Grid to 66 KV Common Wealth
Games Village Grid (Akshardham)
Providing additional 33 KV feed to
5 33kV 66kV Ghonda Karawal Nagar Grid substation from Approved WIP, May 2015
Ghonda Grid.
Providing Additional 33 KV feed Yet to be
220kV Subji
6 33kV 220kV Subji Mandi Grid to 33/11kV Submitte Scheme not approved
Mandi
B.G Road Grid Sub-Station. d
Providing Additional 33 KV feed Yet to be
220kV RPH
7 33kV 220kV RPH/IP Grid to 33/11kV Submitte Scheme not approved
Grid
Delhi Gate Grid Sub-Station. d
Providing Additional 33 KV feed Yet to be Scheme not approved
220kV RPH
8 33kV 220kV RPH/IP Grid to 33/11kV G.B Submitte
Grid
Pant Grid Sub-Station. d
Providing Additional 33 KV feed Yet to be
220kV
9 33kV 220kV Narayana Grid to 33/11kV Submitte Scheme not approved
Narayana Grid
Prasad Grid Sub-Station. d
Providing Additional 33 KV feed Yet to be
220KV Geeta
10 33kV 220kV Patparganj Grid to 33/11kV Submitte Scheme not approved
Colony Grid
Preet Vihar Grid Sub-Station. d
49
S. Volta DERC Work Status
Source
N ge Scheme Description pproval
Station
o. Level Status
Providing Additional 33 KV feed Yet to be Scheme not approved
220KV Geeta
11 33kV 220kV Patparganj Grid to 33/11kV Submitte
Colony Grid
CBD-1 Grid Sub-Station. d
Providing additional 66 KV feed
Yet to be
220kV Park doble circuit from 220kV Park Scheme not approved
12 66kV Submitte
Street Grid Street Grid to 66/11kV Shastri Park
d
Grid Sub-Station.
50
BYPL 2015-16
Capacity DERC
S.N Voltage Present
Scheme Description addition Approval
o. Level Status
(MVA) Status
Establishment of New 66/11 kV Grid Sub- Yet to
1 66/11kV 50 Approved
Station at Mandoli Jail Complex Start
Establishment of New 33/11 kV Grid Sub- Tender
2 33/11kV 32 Approved
Station Krishna Nagar floated
Establishment of New 33/11 kV Grid Sub- Yet to
3 33/11kV 50 Approved
Station Gangaram Hospital Grid Start
Establishment of New 33/11 kV Grid Sub-
Yet to
4 33/11kV Station at D.B Gupta Road near Naaz 32 Approved
Start
Cinema
WIP,
Addition of Power Transformer of 25
5 66/11kV 25 Approved June
MVA at 66/11 Khichripur Grid Sub-station
2015
Addition of 16 MVA Power Transformer
6 33/11kV at 33/11 KV Motia Khan Grid Sub-station 16 Approved Yet to
with GIS Start
Addition of 31.5 MVA Power Transformer
7 66/11kV 32 Approved Yet to
at 66/11 KV Vivek Vihar Grid Sub-station
Start
Addition of one no 66/33kV, 50 MVA
Power Transformer with associated Yet to
8 66/33kV 50 Approved
equimpents at Shastri park (East) Grid Start
Sub-station.
Augmentation of Power Transformer No-1
Yet to
9 33/11kV from 16 MVA to 25 MVA at 33/11 KV 9 Approved
start
Dwarkapuri Grid Substation
Augmentation of Power Transformer No.1
Yet to
10 33/11kV from 15 to 25 MVA at 33kV BG Road 10 Approved
start
Grid Sub-station
Augmentation of Power Transformer No.- Approved
Yet to
11 33/11kV 2 from 16 MVA to 25 MVA at 33/11 KV 9
start
BG Road grid substation
Augmentation of Power Transformer No.2 Approved
12 33/11kV from 16 MVA to 25 MVA at 33/11 KV 9 Yet to
CBD-1 grid substation start
Augmentation of Power Transformer from
Yet to be Scheme
13 33/11kV 16 MVA to 25 MVA at 33/11 KV Geeta 9
Submitted not
Colony grid substation
approved
Augmentation of Power Transformer No.2
Yet to be Yet to
14 66/11kV from 20 MVA to 31.5 MVA at 66/11 KV 11
Submitted start
Yamuna Vihar grid substation
Augmentation of Power Transformer No-2
Yet to be Scheme
15 33/11kV from 16 MVA to 25 MVA at 33/11 KV 9
Submitted not
Dwarkapuri Grid Substation
approved
Augmentation of Power Transformer from Scheme
Yet to be
16 33/11kV 16 MVA to 25 MVA at Karawal Nagar 9 not
Submitted
33/11 KV Grid Sub-station approved
51
BYPL Additional feeders (2015-16)
DERC
S. Voltage Present
Scheme Description Approval
No. Level Status
Status
Providing 66 KV infeed to newly proposed 66/11 KV
Indoor Grid Substation at Mandoli Jail Complex by
1 66kV Approved YTS
laying 6 nos. 66 KV 1CX1000 sq. mm cable for 400 KV
Harsh vihar Grid.
Laying of 33 KV 3Cx400 sq mm XLPE U/G cable from
Yet to
2 33kV 220KV Geeta Colony Grid to proposed 33kV C Block Approved
start
Krishna Nagar Indoor Grid
Laying of 33 KV 3Cx400 sq mm XLPE U/G cable from
Yet to be Yet to
3 33kV Shastri Park Grid and Shankar Road Grid to proposed
Submitted start
33kV Sir Ganga Ram Hospital Indoor Grid
LILO of 33 KV cable betwwn Motia Khan to Faiz Road
Yet to
4 33kV at newly proposed DB Gupta Road Grid near Naaz Approved
start
Cinema
Laying of one ckt of 33 KV 3Cx400 sq mm XLPE U/G Yet to be Yet to
5 33KV
cable from 220KV Park Street to Naaz Cinema Submitted start
Laying of New feeder from 220 KV Wazirabad(single Yet to be Yet to
5 66kV
circuit) to 66 KV Bhagirathi Grid Submitted start
Laying of new feeder from Rajghat Power House grid to Yet to be Yet to
6 33kV
33 KV I G Stadium. Submitted start
LILO 66kV Cable of Wazirabad- Ghonda circuit at Sonia Yet to be Yet to
7 66kV
Vihar Submitted start
Laying of 33kV New feeder From RPH to 33/11kV Delhi Yet to be Yet to
8 33kV
Gate Grid Sub-Station Submitted start
Providing Additional 33 KV feed 220kV Subji Mandi Yet to be Yet to
9 33kV
Grid to 33/11kV B.G Road Grid Sub-Station. Submitted start
Laying of additional 33kV Feeder from 220kV Naraina Yet to be Yet to
10 33kV
Grid to DMS Grid Substation Submitted start
Providing Additional 33 KV feed 220kV Narayana Grid Yet to be Yet to
11 33kV
to 33/11kV Prasad Grid Sub-Station. Submitted start
Providing additional 66 KV feed doble circuit from
Yet to be Yet to
12 66kV 220kV Park Street Grid to 66/11kV Shastri Park Grid
Submitted start
Sub-Station.
Providing Interconnector between Dwarkapuri to Kanti Yet to be Yet to
13 33kV
Nagar Grid. Submitted start
DERC
S. Present
Category Scheme Description Approval
No. Status
Status
Replacement of Conversion of Ridge valley -Shanker Road Grid Yet to
1 Yet to
Cable Schemes O/H Circuit no -1 Line into Under Ground. Submitted
start
Replacement of Conversion of Ridge valley -Shanker Road Grid Yet to
2 Yet to
Cable Schemes O/H Circuit no -2 Line into Under Ground. Submitted
start
Replacement of Re conductring with AAAC conductor Patparganj Under
3 Yet to
Feeder Schemes Grid Sub-Station to Khichripur Grid Sub-Station Approval
start
52
BYPL Augmentation of switch gears / capacitors (2015-16)
DERC
S. Present
Category Scheme Description approval
No. Status
Status
Provision of LT AC Distribution board at Minto
LTAC DB Under
1 Road Grid , Delhi Gate Grid, Jama maszid Grid, Yet to
Schemes Approval
Prasad Nagar Grid, DMS Grid start
Provision of yard lighting, LT AC distribution
LTAC DB Under
2 board and replacement of outdoor terminal kiosk Yet to
Schemes Approval
at Ghonda Grid. start
Provision of double bus bar system at 33 kV Guru Under
3 Bays Schemes Yet to
Angad Nagar Grid. Approval
start
Conversion Single Bus Bar to double bus bar Under
4 Bays Schemes Yet to
system at 66 kV Dilshad Garden Grid Sub-Station. Approval
start
Provision of double bus bar system at 33 kV Under
5 Bays Schemes Yet to
Seelampur Grid Sub-Station Approval
start
Replacement of 81 nos of 33KV Current
Under
6 CTs Schemes Transformers & 36 no of 66 KV Current Yet to
Approval
Transformers at Various Grid in BYPL. start
Replacement of 36 no of Potential Transformers at Under
7 PTs Schemes Yet to
various Grid in BYPL Approval
start
Replacement of 50V Battery bank and Battery
Battery
chargers at various 33 KV & 66KV Grid Sub- Under
8 Charger/Battery Yet to
Station in central circle ( 5 nos -50V & 1 no.- Approval
bank Schemes start
220V)
Installation of Digital RTCC Panels in BYPL Grid Under
9 RTCC Schemes Yet to
Sub-Station. Approval
start
Fire Alarm Installation of Fire Alarm System in BYPL Grid Under
10 Yet to
Schemes Sub-Station. Approval
start
C&R Panel Replacement of Old Control and Relay Panel at Under
11 Yet to
Schemes various Grids in BYPL Approval
start
Capacitor bank Installation of 11KV, 5.4 MVAR Capacitor Bank Under
12 Yet to
Schemes at 33 KV Town Hall Grid. Approval
start
Capacitor bank Installation of 11KV, 5.4 MVAR Capacitor Bank Under
13 Yet to
Schemes at 33 KV Shankar Road Grid. Approval
start
Capacitor bank Installation of 11KV, 5.4 MVAR Capacitor Bank Under
14 Yet to
Schemes at 33 KV Dwarkapuri Grid. Approval
start
Capacitor bank Installation of 11KV, 5.4 MVAR Capacitor Bank Under
15 Yet to
Schemes at 66KV Mayur Vihar-2 Grid. Approval
start
53
DERC Present
S.
Category Scheme Description approval Status
No.
Status
Capacitor bank Installation of 11KV, 5.4 MVAR Capacitor Bank Under
16 Yet to
Schemes at 33KV Preet Vihar Grid. Approval
start
Isolator Replacement of 57 nos of Isolator's at various Under
17 Yet to
Schemes 33KV grid in BYPL Approval
start
Capacitor bank Installation of 11KV, 5.4 MVAR Capacitor Bank Under
18 Yet to
Schemes at 33 KV DMS Grid. Approval
start
Capacitor bank Installation of 11KV, 5.4 MVAR Capacitor Bank Under Yet to
19
Schemes at 33 KV Anand Parvat Grid. Approval start
Capacitor bank Installation of 11KV, 5.4 MVAR Capacitor Bank Under Yet to
20
Schemes at 33 KV Jama Masjid Grid. Approval start
Capacitor bank Installation of 11KV, 5.4 MVAR Capacitor Bank Under
21 Yet to
Schemes at 33 KV Minto Road Grid. Approval
start
Capacitor bank Installation of 11KV, 5.4 MVAR Capacitor Bank Under
22 Yet to
Schemes at 33 KV B.G. Road Grid. Approval
start
Capacitor bank Installation of 11KV, 5.4 MVAR Capacitor Bank Under
23 Yet to
Schemes at 33 KV G.B Pant Grid. Approval
start
Capacitor bank Installation of 11KV, 5.4 MVAR Capacitor Bank Under
24 Yet to
Schemes at Shastri Park(Central Circle) Grid. Approval
start
BRPL 2014-15
DERC
S.
Type of Scheme Description approval Present Status
No.
Status
New Grid With
1 DJB Najafgarh Approved Completed
Infeed
Civil work
New Grid With
2 G-4 Dwarka Approved completed, electrical
Infeed
work in progress
Additional Power Addition of 66/11 kV, 25 MVA
3 Approved Completed
Transformer PTR at Okhla Ph- 1
Additional Power Addition of 66/11 kV , 16 MVA
4 Approved Completed
Transformer PTR at Shivalik
Additional Power Addition of 66/11 kV, 25 MVA
5 Approved Completed
Transformer PTR at Sarita Vihar
Additional Power Addition of 66/11 kV, 25 MVA
6 Approved Completed
Transformer PTR at Bijwasan
Additional Power Addition of 66/11 kV, 20 MVA
7 Approved Completed
Transformer PTR at at G-2 Pappankalan
Additional Power Addition of 66/11 kV, 25 MVA
8 Approved Target : June 2015
Transformer PTR at VSNL
Additional Power Addition of 66/11 kV, 25 MVA
9 Approved Completed
Transformer PTR at Bodella – 1
54
DERC
S.
Type of Scheme Description approval Present Status
No.
Status
Additional Power Addition of 66/33 kV, 24/30 MVA Not
10 Completed
Transformer PTR at Nangloi Approved
Additional Power Addition of 66/11 kV, 25 MVA
11 Submitted Work in progress
Transformer PTR at G-6 Dwarka
Augmentation of Augmentation of 66/11 kV, 2 X 16
12 Power MVA PTRs to 2x25 MVA PTRs Approved Completed
Transformer at Tughlakabad
Augmentation of Augmentation of 66/11 kV, 1 X 16
13 Power MVA PTR to 1x25 MVA PTR at Approved Completed
Transformer Okhla Ph- II
Augmentation of Augmentation of 66/11 kV, 1 X 16
14 Power MVA PTR to 1x25 MVA PTR at Approved Completed
Transformer Lajpat Nagar
Augmentation of Augmentation of 66/11 kV, 1 X 16
15 Power MVA PTR to 1x25 MVA PTR at Approved Completed
Transformer Defence Colony
Augmentation of Augmentation of 66/11 kV, 1 X 16
16 Power MVA PTR to 1x25 MVA PTR at Approved Completed
Transformer Nizamuddin
33 kV line from JNU to Vasant
17 New Feeder Approved Completed
Vihar
33 kV line from AIIMS Trauma
18 New Feeder Approved Completed
Center to Bhikaji Cama Place
LILO of 33 kV Paschimpuri-
19 New Feeder Vishal circuit at 33 kV bus of 220 Approved Completed
kV Peeragarhi
LILO of 33 kV Paschimpuri-
20 New Feeder Madipur circuit at 33 kV bus of Approved Work in progress
220 kV Peeragarhi
LILO of 33 kV Udyog Nagar - A-
21 New Feeder 4 Paschim Vihar circuit at 33 kV Approved Work in progress
bus of 220 kV Peeragarhi
2015-16
New Grid With 66/11 kV Grid Substation at Work in progress.
1 Approved
Infeed Mundka Target: July 2015
New Grid With 66/11 kV Grid Substation at G-7
2 Approved Target : March 2016
Infeed Dwarka
New Grid With 66/11 kV Grid Substation at Work in progress
3 Approved
Infeed Vasant Kunj Institutional Area Target : March 2016
New Grid With 66/11 kV Grid Substation at West Horticulture issues
4 Approved
Infeed of JNU are being resolved
New Grid With 66/11 kV Grid Substation at Work in progress.
5 Approved
Infeed Meethapur Target: March 2016
33/11 kV Grid Substation at A-43
New Grid With Work in progress.
6 Mayapuri + Infeed from 220 kV Approved
Infeed Target: March 2016
Naraina
New Grid With 66/11 kV Grid Substation at To be
7 Target : March 2016
Infeed Fatehpur Beri Approved
55
DERC
S.
Type of Scheme Description approval Present Status
No.
Status
Laying of 2 Nos. 33kV
3x400sq.mm. XLPE Cable from
8 New Feeder Approved Work in progress
proposed 220/33kV AIIMS
Trauma Centre to IIT Grid s/stn.
Laying of 33 kV double circuit
comprising 2x3Cx400 sq.mm
To be
9 New Feeder XLPE Cables from Paschim Work to be taken up
Approved
Vihar/Chaukhandi to DC
Janakpuri
Additional Additional Power Transformer at To be Scheme under
10
Transformer Kilokari submitted revision.
Laying of One 33 kV Circuit each
to Defence Colony, Lajpat To be Bay to be allotted by
11 New Feeder
Nagar, NDSE and Hudco from submitted DTL
AIIMS Trauma Centre
Additional Additional Power Transformer at To be
12 Work to be taken up
Transformer A-4 Paschim Vihar submitted
2016-17
New Grid With
1 33/11 kV Grid Substation at Okhla Phase 3 Approved
Infeed
New Grid With
2 66/11 kV Grid Substation at Jasola Media Centre Approved
Infeed
New Grid With 33/11 kV Grid Substation at Court Complex
3 Approved
Infeed Saket
Additional Power
4 Additional Power Transformer at Malviya Nagar Approved
Transformer
Additional Power
5 Additional Power Transformer at Andheria Bagh Approved
Transformer
Additional Power
6 Additional Power Transformer at C-DOT Not approved
Transformer
Laying of 12 Nos. D/C 1x630sq.mm. XLPE U/G
7 New Feeder Cable from 220kV s/stn. Sarita Vihar to LILO Approved
66kV tower opp. Asia Pacific Inst. Jasola.
Laying of 2Nos. 33kV XLPE Cable of Size
3X400Sq.mm. Between I.P. Stn. (Bay No.7) to
8 New Feeder 33kV Exhibition-I Grid S/Stn. and balance from Approved
1No. 33k 3CX400Sq.mm.(Existing) Railway
Work shop to Exhibition-I S/Stn
SLDC informed that on the advise of Govt. of NCT of Delhi, a meeting of Delhi Power
Procurement Group (DPPG) members, DTL and SLDC was held in the Conference Hall
of SLDC to discuss and decide about the issue of surrender of power from various
sources beyond 31.03.2015. The minutes of the meeting is appended as Annexure. The
gist of broad discussions and decisions are explained as under:-
56
a) RPH Station
The State Government was requested to close down RPH Plant forever from 01.10.2015
considering the age of the plant, environmental conditions and cost of the generation
which is about Rs. 5.75 per unit.
b) Pragati Stage-I
Full generation of Pragati Stage-1 be maintained during summer months and from
October to March, the entire gas allocation of Pragati Station be diverted to Bawana for
better utilization. After the commissioning of 400kV RPH System, the entire station may
be closed down if the generating company could not assure cheap gas to run the plant.
c) IPGCL’s GT Station
The Government may take a call of closure of the station considering black start facility
available with the station.
d) BTPS
The State Govt may consider to request the Central govt. to decommission Stage-1units
(95MW capacity of each three units) from October 2015. 210MW units be closed down
after the commissioning of 400kV ISTS Tuglakabad.
The State Government was also requested to request NTPC not to infuse additional funds
for renovation and modernization of Stage-II units whose expenditure was expected to Rs.
741 Crores as approved by CERC in its order dated 12.05.2011 in Petition No. 324/2009
as the overall cost of the power from the station is nearly Rs. 6/unit.
e) Rithala Station
Rithala Station was commissioned in the year 2011. Since last two years, there was no
generation due to non availability of gas. The fixed cost of the station is Rs. 90 Crores
per annum as per the tariff petition filed before DERC.
TPDDL was requested to decommission the plant immediately to ease the burden of
fixed charges on consumers without any generation.
f) Interstate Generation
i) The entire allocation of Delhi from Anta, Auriya and Dadri Gas Stations to be reallocated
to needy states forever from October 2015.
ii) 125MW (NDMC share) of Dadri (Thermal)-I be reallocated to needy states from October
to March.
iii) 400MW (share of TPDDL and BRPL) from Dadri Thermal Stage-II be reallocated to
needy states from October to March.
57
iv) All the Distribution Companies should make sufficient arrangements of power to meet
the demand in the event of reallocation of power as mentioned above to avoid any load
shedding in Delhi.
v) SLDC was advised to intimate the above decisions to the State Govt.
G.M. (Commercial), NTPC was of the view that the factual position has not been
considered while making the suggestions and the suggestions of the forum are also not
legally tenable. He was also of the view that the issue tantamount to review of PPAs and
hence not in the purview of the discussions in GCC which is evident from the ‘Functions
and Responsibility of GCC assigned to it by Delhi Grid Code in Regulation No.6.2.2 as
under:-
(c) review of the DGC, in accordance with the provisions of the Act
and these Regulations;
As such, he was of the view that the item put forth for discussion should be withdrawn.
Delhi Gencos representatives expressed the same view. They were of the view that while
making the suggestions by the forum to the State Government, the legal and commercial
aspects contained in the Power Purchase Agreements were totally ignored and Gencos
were also not associated with the discussions. They also requested for withdrawal of the
item from the agenda.
DTL representatives were also of the view that SLDC was advised by the State
Government to assess the demand – supply position in consultation with Discoms and
DTL and furnish the comments on reallocation of power from various generating stations
beyond 31.03.2015. Accordingly, they have done the exercise by convening a meeting
58
on 27.03.2015 and the Minutes of the Meeting have been circulated and posted in the
website of SLDC. As such, there was no need to put the item as an agenda for discussion
in this meeting.
BRPL, BYPL and TPDDL representatives objected the views of NTPC, Delhi Gencos
and DTL. They were of the view that the recommendations have wide impact not only in
the power purchase cost but also in the electrical network and hence it should be
discussed in this apex forum which consists of Gencos, DTL, SLDC, DMRC, NRLDC
etc. BYPL representative was further of the view that if such vital aspects are not
included for discussions, the outstanding payment issue should also not be figured in the
agenda as the issues are commercial issues between two parties and not general in nature.
Concluding the discussions on the jurisdictional issue, the Chair opined that the
issue affects the overall power sector of Delhi including all stakeholders viz Gencos,
Transco, Discoms and System Operation. As such, he advised all Stakeholders to
provide their comments on the issue which would be placed before the State
Government.
The representatives of Delhi Gencos were of the view that while making the suggestions
by the Forum consisting of DTL, SLDC and DPPG to the State Government for closing
down all the plants – RPH, GTPS, PPS 1, BTPS stage I and also BTPS stage 2 only on
the basis of cost of generation, the legal and commercial aspects contained in the Power
Purchase Agreements were totally ignored. Review of PPAs and shutting down of power
stations is not being the subject matter of SLDC, and DISCOMs . As far as cost is
concerned, it is as per the tariff orders issued by the respective electricity regulatory
commissions. Further, decisions taken by the Delhi Power Purchase Group to
recommend the State Govt for closure of load centre based generation at RPH, GT and
PPS 1 is not legally tenable as the PPAs have no exit clause and the units are supposed to
be in operation for their entire life of the plant.
Even basic concepts of power allocations, purpose of embedded generation of Delhi at
load centre for energy security of the capital city has not been considered.
As far as cost is concerned, it is as per the tariff order issued by DERC / CERC. The
performance parameters of the stations had been made stricter and the norms of the
quantity of fuel and auxiliary power consumption are same for all the power stations
within the state and outside Delhi state, since the regulated regime came into existence in
2005-06, with no relaxations to Delhi generation utilities. Cost of generation of load
centre coal station located at a distance of 1000 KM or more from coal mines and Gas
based CCGTs cannot be compared simply with the pithead coal based / hydro power
transmitted from long distance incurring transmission losses and transmission charges
along with the associated energy insecurity.
59
They also drawn attention on the Director (Operations), DTL’ view recorded in the
minutes of the meeting dated 27.03.2015 wherein the need of embedded generation was
emphasized. They cited the relevant portion of the minutes as under:-
They were also of the view that the observation of DISCOMs stated in the minutes that
possibility of grid failure being remote and hence the shutting down of embedded
generation will not have any effect is technically incorrect and the basic intent of
planning of embedded power generation at load centre in the state gets defeated.
Therefore, stability of supply in the National Capital should be given priority rather than
only commercial aspect to reduce the power purchase cost. As such; the proposal of
closure of load centre power stations is not in the public interest.
In this regard they requested to consider the observations of CEA in their letter dated
25.03.2015 emphasizing need of embedded generation in Delhi for energy security.
DTL representative intimated that Grid authorities like CEA etc has also emphasized the
need of enhancement of load centre based generation for successful operation of Delhi
Islanding Scheme devised to safely island Delhi system in the event of Grid collapse as
occurred on 30/31.07.2012. He has given the details of CEA communication dated
25.3.15 in this regard as under:-
This has the reference to the email received from G.M. DTL of dated 12th March on the
above subject. We have gone through the text of the DTL report, wherein it has been
mentioned that the islanding scheme for Delhi network is frequency measurement based.
If the load is well within the on line generating capacity of the system, then the frequency
can be maintained at 50 Hz. Similarly, if the actual generation is less than the load, then
the frequency drops and settles below 50Hz. At the time, major disturbance in the
Northern Grid, when grid frequency reaches 47.9Hz, the interstate feeders will be opened
thereby leaving the Delhi embedded generation, Dadri and Jhajjar generation balancing
Delhi network load and if the available embedded generation in Delhi is sufficient then
there will be less possibility of load shedding and survival of post islanding.
It has been indicated that for meeting the Delhi peak load requirement of 6200MW, the
available generation in Delhi totalling 4135MW at the time of Islanding will be from
following plants :-
60
Dadri : 1700MW
Pragati + IPGT : 500MW
Bawana CCGT : 685MW
BTPS : 500MW
But the generation from BTPS, Bawana CCGT (limited gas available), Jhajjar and Pragati
GT remain below above level due to non-scheduling there generation by the Delhi
Discoms because of high cost and cheaper power is available from other outside sources.
At the time of islanding these outside generation will also cut off leading to additional
load shedding for controlling the frequency.
During the major grid disturbance, the necessary condition for survival of Delhi network
without any load shedding is that the available generation should exceed the prevailing
loads. But since Delhi network is already deficit by around 220MW so far survival of
Delhi network with minimum load shedding or no load shedding, it is essential that total
embedded generation in Delhi is more than Delhi load. The embedded generation in
Delhi network can be established by:
With these above projects around 2200MW power would still needs to be added to secure
Delhi system after Islanding without any load shedding under the existing load condition.
This would ensure the generation availability matching the Delhi network load thereby
maintaining the power system integrity and keeping the frequency above 49.2Hz thus
restricting the load shedding during major grid disturbance.
The above observation of DTL is correct and CEA is also in agreement with the views of
DTL. Without adequate embedded generation within Delhi system is indicated above, it
would be absolutely impossible to create an islanding system for Delhi system without
doing any load shedding.
61
i) Badarpur station was owned by Govt. of India and operated by NTPC till
31.3.2006. 100% of power from Badarpur has been allocated to Delhi. The
Station was transferred to NTPC on 1.4.2006 by Govt. of India.
ii) Dadri Stage –I and Dadri Stage –II have since inception been planned and
implemented by NTPC primarily as generating stations dedicated for Delhi
based on requisition of Delhi Govt. 90% of power from Dadri stage-I and 75%
power from Dadri stage-II have been allocated to Delhi. Knowing well that coal
for these stations will be sourced from mines from around 1200-1300 kms away,
thereby, incurring additional transportation cost over and above the coal cost at pit
head, Delhi Govt wanted NTPC to set up these stations. About 40% of fuel cost
of these stations is attributable to transportation cost, which Delhi Government
and Delhi Transco Ltd were fully aware of at the time of entering into the PPA.
These PPAs were reassigned to Delhi Discoms from 01.04.2007 as per order of
DERC.
iii) Badarpur, Dadri-I and Dadri-II have been envisaged as Load Centre stations to
enhance stability of Grid. These stations have helped Delhi all these years in
making electricity available to Delhi consumers. Even today they play important
role in Delhi Grid Stability as evident from the fact that Delhi SLDC has all along
been insisting for enhanced level of generation from these power stations.
iv) This is further substantiated vide Delhi SLDC submission dtd. 28.5.2014 in
DERC in petition no. 10/2014.
Quote
As far as BTPS is concerned, the Requisition should not be less than 80% ex bus
capacity of running machines --------
At the present condition, SLDC has confirmed that during summer season, full
generation at BTPS, IPGCL GT & RPH and Pragati Stage-I is required to be
delivered during peak demand which is expected to cross 6000 MW this year in
hassle free manner. One Caution should also be taken that in no power system,
the local generation can completely be eliminated if stability is required.
Unquote
v) Investment decisions for Dadri-I & Dadri-II were taken by NTPC for entire life
of the station based on comfort given by Delhi Govt./ Power Purchase Agreement
signed by Delhi Transco Ltd to take power from these stations for entire life of
the stations. Accordingly, Investments once made are to be serviced during the
life of the plants and not open to review in between. This is fundamental to any
Long Term PPA. These PPAs were reassigned to Delhi Discoms from
01.04.2007 as per order of DERC.
vi) The risk of price of fuel increasing or the reward of fuel price reducing or
remaining constant is necessarily on the Procurers and the fuel cost in all PPAs
which are based on cost plus basis and tariff being determined under section 62 of
the Electricity Act is a pass through. If otherwise there cannot be any long term
62
planning and implementation of PPA particularly at the time when the above
mentioned stations were established
vii) Due to low availability of APM gas, NTPC gas station are getting APM upto
around 40% PLF and Discoms are scheduling upto generation available on APM.
Discoms are not scheduling generation available on RLNG due to high variable
cost. The low schedule in effect is increasing per unit fixed charges. It may be
appreciated that allocation of Gas to NTPC and pricing of APM gas are governed
by GOI. During the period of low gas / RLNG prices, beneficiaries including
Delhi had no complaint while availing power from these projects. Just because the
APM gas / RLNG prices have become costlier Delhi Discoms can not take a stand
that they want to move out of the PPA leaving the NTPC to bear the stranded cost
of these projects.
ix) NTPC wish to place the following legal aspects in regard to the Power Purchase
Agreement existing between NTPC and the Delhi Distribution Companies/
Licensees in regard to the generation and sale of electricity from various
Generating Stations of NTPC including the Badarpur Thermal Power Station
acquired by NTPC from the Government of India and also the Gas Power Stations
of NTPC, namely, Anta Auraiya, Dadri Gas as well as Dadri Thermal Power
Station:
(a) There exist a duly concluded, binding and enforceable agreement with clear
obligation on the part of the Distribution Companies/Licensees to purchase power
from the above Generating Stations and pay for the tariff, namely, the capacity
charges, variable charges and all other applicable charges and the cost as provided
in the Power Purchase Agreements and as per the Tariff Regulations of the
Central Commission and Tariff Orders passed by the Central Commission. This
obligation of Delhi Distribution Companies/Licensees cannot be unilaterally
varied either by the Distribution Companies/Licensees or by the Delhi Transco
Limited or Delhi SLDC or even by the government of NCT of Delhi;
(b) The obligation specified in the Power Purchase Agreement include taking the
power scheduled by giving requisite dispatch instructions and if the Procurer do
not schedule the power, to pay for the capacity and other charges applicable
notwithstanding that the actual power is not taken;
(c) It is the Government of India which has allocated the power from various
Generating Stations of NTPC to Delhi on a Long Term basis. It is for the
Government of India to change the allocation to any other Procurer on a Long
Term basis either wholly or partly for the capacity allocated to Delhi. Till such
time the Government of India allocates on a Long Term basis, such capacity now
63
with Delhi, Delhi Distribution Companies/Licensees shall continue to be liable
under the Power Purchase Agreement. Such an obligation cannot be unilaterally
terminated as recorded in the Minutes of the Meeting dated 27th March 2015 or
otherwise;
(d) The Delhi Distribution Companies/Licensees are bound to service the cost and
expenses in regard to various Generating Stations of NTPC including renovation
and modernisation as per the Orders passed by the Central Commission from time
to time. It is not open to the Delhi Distribution Companies/Licensees to
unilaterally and selectively decide to service only some of the Generating Stations
and not to service others.
(e) The Central Commission and the Hon’ble Appellate Tribunal have consistently
held that the Procurers shall be bound to service the capital cost and other fixed
charges of NTPC, notwithstanding that the Procurer do not schedule the power
from any of the generating station. It is reiterated that the Procurers have a
binding obligation to pay for the capacity charges and fixed charges
notwithstanding that they may not schedule the power on any day or during some
months of the relevant tariff year.
It was also informed that the above facts have been placed before the State Government
vide their letter no.01:CD:152 dated 20.04.2015 addressed to the Principal Secretary
(Power), Govt. of NCT of Delhi.
Discoms representatives reiterated their stand that that considering the massive
corrective steps taken by all utilities after the 30th and 31st July 2012 Grid Disturbances
occurred in country and considering the much improved stability of power system, the
possibility of occurrences of such Grid disturbances for which Islanding Schemes are
devised, are remote. As such, to take care of such remote chances of Grid eventualities, it
is not proper to force the Distribution utilities to utilize such costlier generation thereby
burdening the consumers. They also informed that most of the plants in Delhi have
already out lived their useful lives. As such they have every rights to exit the PPAs on
commercial and operational grounds after the life span of the plants. They have indicated
the details of the plants who have out lived their useful lives as under:
64
Name of Unit Capacity Date of Age as on Remarks
the plant no. in MW commissioning/ date (in
CoD years)
RPH 1 67.5 May 1990 25 DERC Generation Tariff
2 67.5 June 1990 25 Regulations notified on 2.12.2011
Total 135 Regulations A.2 DEFINITIONS
GT 1 30 17.7.1986 29 AND INTERPRETATIONS 2.1(ii)
2 30 20.6.1986 29 USEFUL LIFE in relation to
3 30 11.8.1986 28 caoal/gas based thermal generating
4 30 3.9.1986 28 station from CoD shall be 25 years.
5 30 11.11.1986 28
6 30 20.11.1986 28
STG 1 30 2.4.1996 19
STG2 30 12.8.1997 17
STG3 30 27.12.1996 19
Total 270
Pragati 1 104 May 2002 13
stage 1 2 104 November 2002 12
STG 122 March 2003 12
Total 330
BTPS 1 95 26.7.1973 42 The useful life is defined in
2 95 5.8.1974 40 Regulation 3 (67) of CERC tariff
3 95 29.3.1975 40 regulations notified on 12.3.14 for
4 210 2.12.1978 37 the period 2014-19 as Coal/ Lignite
5 210 25.12.1981 34 based thermal generating stations
Total 705 shall be 25 years from CoD.
It was further clarified by Discoms that reallocation of power from center sector stations
has been a regular feature particularly during lean period November to March. TPDDL
informed that their allocation from Dadri Stage-I is still reallocated to Bihar from
September 2014 and will continue till 31 st August 2015. There allocation from Dadri
Stage-II is also remained reallocated during November 2014 to March 2015. As such
NTPC’s contention in Dadri Stage-I & II is not tenable. Further, they requested to
reallocate the entire share of Anta, Auriaya & Dadri Gas stations from October, 2015
forever.
TPDDL representative further added about the status of their Rithala Gas Station that
Scheme for utilization of Gas Based Power Generation Capacity” issued by Ministry
of Power vide Office Memorandum dated 27th Mar 2015 envisages supply of imported
spot RLNG “e bid RLNG” to stranded gas based plants as well as plants receiving
domestic gas upto target PLF of 25% to 30% during the year 2015-16 and 2016-17. The
scheme has provisions for reviving the operations of 14000 MW of stranded gas based
assets and TPDDL Rithala Plant is eligible for support under the scheme. The details of
the scheme were shared with all stakeholders by Ministry of Power through a discussion
forum organized on 31st March 2015 at Scope Complex, NTPC and comments were also
invited from stakeholders. The scheme envisages a cut from all stakeholders to ensure
that stranded assets are given a chance of revival. The support under this scheme shall be
for a period of 2 years during which MoP shall be taking concrete steps to make gas
available to power plant to run at their partial / full capabilities. TPDDL has already
responded to the Ministry of Power on the same expressing its intent to revive the Rithala
65
Plant under the scheme and is awaiting further details of the scheme and the response
from MoP on the same. The issues raised before the Govt. of India, Ministry of Power are
as under:-
a) Tata Power Delhi Distribution Limited had set up a 94.8 MW Gas Based Generation
Plant at Delhi in Oct 2010. The Plant was set up with the objective of having captive,
load center (in Delhi) power generation for enhancing reliability, meeting the supply
deficits and ensure islanding capabilities in case of Grid Distress/ collapse, an
eventuality, which had happened many times in the past and which reoccurred on
30/31.07.2012. Further, it was also important in view of the upcoming Commonwealth
Games which were to be held in Delhi in 2010. Considering the importance of the Plant,
it was allocated 0.4 MMSCMD gas from the KG D6 basin by the Ministry of Petroleum
and Natural Gas. The plant has been in operation since Oct 2010 to Feb 2013 to the
extent of availability of KG D6 basin gas.
b) Supply to Gas Based Plants from KG D6 basin was curtailed since 1st March 2013 as per
Gas Utilization Policy of Govt. of India which allocates higher priority to LPG and
Fertilizers, consequently the Plant has not been in operation since Mar 2013, except for
one day in June 2013 wherein it was operated on Spot Gas to provide power when severe
storm disrupted the partial power supply to Delhi from other sources. While adequate
Spot Gas tie up exists for the Plant, the same is currently not being dispatched on account
of high costs associated with Spot RLNG.
c) The Scheme issued by Ministry of Power has provided us with some hope of sustaining
the operations of the Plant during the Financial Year 2015-16 and 2016-17 during which
more concrete steps could be taken to make gas available from other sources to operate
the stranded assets to their full capabilities. TPDDL has gone through the scheme in
detail and also attended the discussion on 31st March 2015 where this scheme was
elaborately presented for the benefit of stakeholders.
d) TPDDL like to make certain submissions regarding the scheme and especially for
operationalizing our plant in the capital city of Delhi.
e) Considering that the plants shall operate at 30% PLF, we believe that the plants shall
experience high Station Heat Rates which shall increase the cost of Generation and the
cap of Rs. 6.44/ unit ( Rs. 5.50/ unit net purchase price + Rs. 0.94/unit support from
PSDF) is inadequate to support the generation costs + O&M Costs and Debt Servicing of
plants. We would like to understand the Genesis, costs of RLNG and SHR considered by
MoP to arrive at the base figures in the scheme. This shall help us to provide more
elaborate views.
f) The Scheme envisages that the risk of dispatch is to be borne by the Developers and that
plants operating under this scheme shall not be considered as “Must Run Plants” by
concerned Load Despatch Centers. We believe that this is a huge risk to be borne
considering that today power is available in short term markets at an average rate of Rs.
66
3-4/unit and that conventional plants operating today on coal would have a much lower
cost that is Rs. 5.50/unit. Under these conditions, until the Plants are declared as Must
Run, there shall be no buyers for the expensive power. As all stakeholders are taking
some cuts in the scheme including foregoing of entire RoE by developers, we believe that
utilities must also be made to participate in the scheme to purchase power from these
plants. Alternatively, a risk sharing mechanism for non dispatch should be worked out to
insulate the developers from “Take or Pay” obligations under the scheme.
g) There should be some additional dispensation for plants like that of TPDDL ours
operating in the capital of the country and instrumental in providing relief in case of Grid
distress/ emergencies.
h) TPDDL shall await for the sharing of Genesis for the Target Price and Support Price in
the scheme, we have worked out the total costs for operating our plant at the Target PL
taking some assumptions on the gas price , waiver of CST/VAT etc and cuts in marketing
margin and transmission tariff by GAIL.
i) As per the computations as detailed below, the landed costs for Discoms while operating
at a PLF of 30% shall be Rs. 9.59/unit.
Price under Normal Price under
Circumstances proposed scheme
Gas Supply Rate MMBTU 1 1
USD
Spot Gas Rate /MMBTU 10.32 10.32
USD to INR 60 60
Gas Supply Rate 619.2 619.2 619.2 619.2
Marketing Margin 10.21 10.21 2.55 2.55
Transportation 71.18 71.18 35.59 35.59
Service Tax 12% 8.5416 0
ECS on Service Tax 2% 0.170832 0
SECes on Service Tax 1% 0.085416 0
AR/ VAT Payale 5% 35.46939 0
744.8572 657.3425
Kcal kcal 252000 252000
Rithala - Expected SHR (GCV) at 30% PLF kcal/kwh 2700 2700
Units Generated Gross 93.3 93.3
Units Generated Net (considering 6% Aux) 87.7 87.7
VC Rs./unit 8.49 7.49
Fixed Costs Rs. Crs 49.05
FC Rs./unit 2.1
Total Cost Rs./unit 9.59
Gas Price Payable by Discoms Rs./unit 5.5
Additional support required Rs./unit 4.09
67
*Assumptions
1. Taxes/ CSAT/ VAT waive off by State Govt.
2. Gail shall take a cut of 50% on transmission tariff and 75% on Marketing Margin
j) As such, it is requested to review the Target Price and Ceiling Support Price under the
scheme. We would also request that some additional time be provided for
operationalizing the scheme in order to provide adequate time for a) Obtaining approval
from Regulatory Commission for supply power to Discoms at the rates mentioned in the
scheme and b) for State Govts to provide relevant waiver.
In view of the above, TPDDL requested for modification of Minutes of the meeting on
27.03.2015 through a Corrigendum indicating the change in circumstances which has
brought about the possibility of operating the plant immediately and continue doing so till
the end of its useful life. They also informed that that surplus power in Delhi scenario is
not attributed to Rithala plant's operations in any manner which was the focus point of
discussions in the meeting and hence requested for amendment of Minutes and
Corrigendum be issued to reflect the true state of affairs for clear records.
SLDC representative stated that the issue of surrender of power from various sources has
already been under the consideration of DERC vide petition no.23/2015 filed by BRPL
and 24/2015 filed by BYPL and petition no.11/2014 filed by TPDDL
PPCL in connection with their upcoming Bamnauli CCGT Station has converted the
overhead portions of all 400kV transmission lines emanating from 400kV Bamnauli
S/Stn to cable and commissioned as under
Unfortunately out of 4 cables circuits, 3 cables are out. PPCL provided the revival status
as under:-
68
S. Name of the Cable portion Present status Remarks Plan to revive the ckt in
commissioned
N Circuit original cable system
on
1 400kV Bamnauli 27.12.2013 Cable portion is Expected to be restored
– Jhatikara Ckt-I at 19.21hrs. out from 16.03.15 in 2nd week of May
at 19.43hrs. 2015.
2 400kV Bamnauli 19.42hrs. Cable portion is The ckt is on Material required
– Jhatikara Ckt-II on out from ERS w.e.f. expected in mid June
27.12.2013 11.06.2014 at 19.16hrs. on 2015. Job is expected
19.42hrs. 12.08.2014. to completed by July
2015 end
3 400kV Bamnauli 06.04.2014 Ckt. is in operation
– Ballabhgarh at 21.07hrs.
Ckt-I
4 400kV Bamnauli 06.04.2014 Cable portion is The ckt is on Expected by 1st week
–Ballabhgarh at 21.07hrs. out from ERS w.e.f. of June 2015
Ckt-II 01.01.2015 at 18.53hrs. on
17.01hrs. 17.01.15
SLDC representative presented the importance of revival of the circuits on the original
system as at present, two circuits are on ERS and causing Delhi 400kV Ring System
more vulnerable due to which the entire Northern Grid System’s stability is also affected.
Summer is approaching fast as such apart from picking up of load, the possibility of
storms can also not be ruled out. As such, the circuits which are on ERS (one of which is
in operation since last one year) are required to be restored immediately on normal
system for ensuring safety and security of the Grid. Load is also restricted to half of the
capacity in ERS system due to which load regulation also becomes tedious as load flows
on the circuits depends upon system parameters which are not under the control of system
operators. He has also cited 2-3 examples of tripping of the existing circuits in which
Grid also escaped narrowly from total collapse of Delhi system along with Punjab,
Haryana, Himachal etc.
PPCL representative informed that they are vigoursly following up with their OEM.
On a query of any study carried out on the failure of cables as two circuits failed while
normalising the system after taking the shut-down (400kV Bamnauli – Jhatikara Ckt-II
on 11.06.2014 at 19.42hrs. and 400kV Bamnauli –Ballabhgarh Ckt-II on 01.01.2015 at
17.01hrs). The other circuit i.e. 400kV Bamnauli – Jhatikara Ckt-I cable end box
damaged on running conditions on 16.03.2015 at 19.43hrs., GM (O&M)-I, DTL
intimated that as per Indian Electric Act, CEA is the competent authority to carry out the
study and suggest remedial measures. It was also informed that LS Cable has assigned
the task of the study of cable failures to M/s KEEMA considering the specialty of the
system of 400kV overhead cum underground terminations. We have to wait till the final
report comes.
GCC advised PPCL to vigorously monitor and ensure the restoration of the system
on original scheme for ensuring stability of the Grid.
69
3.5 CAPACITOR INSTALLATION PLAN
The utilities updated the position of additional capacitors in the last meeting as under:-
Utility Planning for Installed so Position informed in 10th GCC Status as on date
installation of far in meeting
additional MVAR
capacity in
MVAR (HT
level)
2013-14
70
Utility Planning for Installe Position informed in 10th Status as on date
installation of d so far GCC meeting
additional capacity in
in MVAR (HT MVAR
level)
2013-14
BYPL 108 5.4 Approval for 32.4MVAr 10.8MVAr capacity has been added up at 66kV
has already been accorded New Kondli S/Stn at 11kV side.
by DERC. 5.4MVAR The following plan has already been drawn out to
added at Jama Masjid commission by March 2015
S/stn on 12.06.12. S S/Stn Capacity at 11kV in
N MVAR
1 DDU Marg 10.8--commissioned
2 Kanti Nagar 5.4-Commissioned
3 Khichripur 5.4
4 CBD-II 5.4-Commisioned
5 Delhi Gate 5.4
6 GH-1 5.4
7 Bhagirathi 5.4
Total 43.2
MES -- -- The installed capacity
21.1MVAR is sufficient to
meet the load of MES.
However for voltage
regulation they have
planned additional
capacity at LT level for
2013-14.
Total 473.6 97.56
As follow up action, a meeting was held in the SLDC on 18.02.2015 wherein the
representatives of Discoms, PGCIL etc attended. The gist of the decisions are as under:-
1 It was agreed that all Discoms would submit their observations after detailed study of
CPRI report by 28.02.2015 which would be forwarded to CPRI for their comments.
Planning Department would arrange CPRI participation in the next meeting.
2 Since regional capacitor study for 2015-16 is already under way by NRLDC, Delhi
SLDC should involve in study by providing requisite data.
In the last meeting, the representative of the Planning Deptt. of DTL informed that by
2015-16 the outlet from the 400kV ISTS at Inderlok (earlier Karampura) to 220kV
Rohtak Road S/Stn. is proposed to be established. As such, the proposal of LILO of
71
220kV Wazirpur - Peeragarhi (one circuit) at Rohtak Road is dropped. BBMB was to be
approached for re-conductoring of existing 220kV Narela - Rohtak Road D/C Line with
HTLS conductors.
DTL was advised by GCC to expedite the HTLS re-conductoring of 220kV Narela-
Rohtak Road D/C Line for reliability of supply, it was also emphasized the timely
completion of proposed 220kV outlet from the upcoming ISTS from Inderlok to Rohtak
Road.
DTL’s Planning Department representative reported that the 400kV Karam Pura
substation may be functional only by the end of 2017. BBMB would soon be approached
for LILO of one of the 220kV circuits between Wazirpur & Peeragarhi at Rohtak Road
substation to facilitate the augmentation of the conductors of 220kV Rohtak Road-Narela
double circuit line.
It was informed by DMRC that following shut-downs are required for DMRC works:-
i) 400kV Dadri – Ballabhgarh D/C line for 30 days in connection with the work of
line-8 (Janakpuri – Botanical Garden, Noida). Entire Maharani Bagh S/Stn would
be left without 400kV infeed during the shut-down period.
ii) 400kV Mundka – Bawana Ckt-I & II for Phase-III expansion of DMRC. The
shut-down is required for about 30 days.
DMRC representative informed that they could not wait upto October as the DMRC work
would be remained hurdled if the shut-downs are not allowed before that for which the
contracts are likely to be finalized with Powergrid soon. He also assured the service of
line through ERS during shut-down period.
GCC advised that the shut-downs cannot be allowed during the peak summer
season at least during the period May 2015 to August 2015 even with ERS as the
transmission circuits through ERS reduces the transmission capacity. DMRC was
accordingly advised.
3.8 NON USAGE OF BAYS ALLOTTD TO VARIOUS UTILITIES FROM DTL SUB-
STATIONS.
The details of plans to utilize the unutilized bays of recently commissioned sub-stations
given by the utilities are as under:-
72
S Name of Details of non utilization of bays
N. 400/220k Voltag Name of bay Name of the Original Present status
V S/Stns. e level utility to allocation
whom the date
bay is
allocated
1 220kV 33kV 1. Race Course NDMC 19.11.09 1.80% work has been completed. Work is
Trauma held up due to non availability of cables
Centre which is being arranged on priority basis.
Expected by June 2015.
2 220kV 66kV 1 RG-30-I TPDDL 31.05.12 Scheme has been approved by DERC in
Rohini-II November 2014. It is a deposit work of
2 RG-30-II DDA. Demand note has been raised to
DDA. DDA has yet to deposit the amount.
Total = 2 Bays First TPDDL would connect both bay of
Rohini-2 to RG-34 Grid and then TPDDL
will LILO at RG-30.
73
S Name of Details of non utilization of bays
N. 400/220k Voltag Name of bay Name of the Original Present status
V S/Stns. e level utility to allocation
whom the date
bay is
allocated
5 400kV 66kV 1.66kV Mundka BRPL 19.11.09 1&2. 66kV Mundka Grid is under
Mundka Ckt-I construction and expected to be
2.66kV Mundka commissioned by May 2015. Circuit -1 &
Ckt-II
Circuit – 2 shall be laid by May 2015.
3.66kV Bakar 3&4.
wala ckt-I Bakkarwala grid shall be a deposit work of
4.66kV Bakar DDA. Construction of Grid has not been
wala ckt-II taken up as development in the area is slow
and hence the load requirement has not come
up.
5.66kV Paschim
5. Scheme for 66 kV circuit was dropped as
Vihar
the route length of the circuit is approx.. 18
Total = 5 Bays Km, which is considered to be non-
maintainable.
This bay is being planned to utilise for
upcoming Grid at Dichaun Kalan, for which
the scheme is under approval by DERC.
1.66kV TPDDL 19.11.09 1 Being the less priority item as Mangolpuri
Mangolpuri-II S/Stn. has Sufficient in feed capacity the
scheme has been shifted for 2016-17 Capex
schemes.
2.66kV Kirari For 2&3 the Sub-stn is envisaged in 2015-16
Sultan Puri Ckt.-I and by the time the Ckt would be readied.
3.66kV Kirari The matter has been taken up with Delhi
Sultan Puri Ckt.-II Govt for allocation of land for establishment
Total = 3 Bays of 66kV Grid S/Stn. As on date, land has
not been allocated by Delhi Govt.
6 400kV 66kV 2 bays - DMRC DMRC 12.04.10 DMRC for Phase-III expansion and expected
Harsh by December 2015
Vihar
7 220kV 220/33 1 Rani Bagh Ckt TPDDL 12.04.10 1 The S/Stn and both the cables have been
Peeragar kV charged. About 12-15 MW load is taken at
hi Ranibagh CC Ckt
2 Sudarshan Park S/Stn is ready and load is
2 Sudarshan Park
met through 33kV Sudarshan Park-Rohtak
Road Ckt. However 33kV Sudarshan Park-
Pira garhiRohtak Ckt would be ready by the
end of Dec-15.
Total = 2 Bays Paschimpuri & Vishal circuits have been
1 Paschimpuri commissioned.
Ckt-I • Other cable works are completed
2 Paschimpuri BRPL energisation pending.
Ckt-II • Peeragarhi – I & II shall be taken up with
3 Vishal Ckt construction of 33kV Peeragarhi grid at the
4 Madipur Ckt same plot by BRPL
5 Udyog Nagar
Ckt
6 A-4 Paschim
Vihar Ckt
7 Peeragarhi Ckt-I
8 Peeragarhi Ckt-
II
Total = 8 Bays
74
3.9 LONG OUTAGE OF ELEMENTS OF DELHI POWER SYSTEM
75
Sr. Name of feeder Name Date of Time Reasons
No. of outage of
Utility outage
16 33KV SCHOOL LANE NDMC 14.12.14 -- FAULTY CABLE HAS BEEN REPAIRED BUT
– VIDHUT BHAWAN NOT ENERGIZED AS 33KV PANEL
CKT REPLACEMENT WORK IS UNDER PROGRESS
AT 66KV SCHOOL LANE S/STN. EXPECTED BY
MARCH 2015 END.
17 66KV DMRC 17.05.13 13.55 CABLE DAMAGED DUE TO FIRE. CIVIL
PAPPANKALAN-I – WORKS FOR NALAH CROSSING IN PROGRESS.
DMRC CKT-II ENERGIZED ON 23.06.2015.
18 33KV VSNL – NEHRU BRPL 02.07.14 03.01 ENERGIZED ON 07.06.2015.
PLACE CKT
19 33KV RIDGE VALLEY BRPL 08.02.15 10.30 `Y’PHASE CABLE AND CIRCUIT BREAKER
– KHAIBAR LAINE FAULTY AT RIDGE VALLEY. EXPECTED BY END
CKT-I OF JULY 2015.
20 66/33KV 50MVA PR. BRPL 01.03.15 08.35 CHARGED.
TR.-I AT RIDGE
VALLEY
21 33/11KV 16MVA PR BRPL 19.03.15 18.47 TRANSFORMER CHARGED.
TR-III AT JAMIA
22 66KV – BRPL 01.02.15 02.17 READY FOR CHARGING.
PAPPANKALAN-I –
BODELLA-I CKT.
23 66/33KV 50MVA PR. BRPL 01.03.15 08.25 CHARGED.
TR.-I AT NANGLOI
24 66/11KV 20MVA PR. BRPL 08.04.15 12.25 CHARGED
TR.-III AT HARI
NAGAR
25 33KV NANGLOI – BRPL 08.04.15 16.30 CHARGED.
UDYOG NAGAR CKT-
II
26 11KV I/C-II AT BRPL 09.04.15 21.45 CHARGED.
UDYOG NAGAR
27 66KV G-V – DJB CKT- BRPL 15.04.15 08.25 `Y’PHASE CABLE FAULTY
II
28 66KV GT – BYPL 03.01.15 14:00 CHARGED.
AKSHARDHAM CKT
29 66KV HARSH VIHAR – BYPL 29.03.15 20.43 CHARGED.
GONDA CKT-II
30 66KV PATPARGANJ BYPL 05.03.15 16.18 `R’PHASE CABLE FAULTY. CABLE IS BEING RE-
INDL AREA – ROUTED. EXPECTED BY 30.07.2015.
KHICHRIPUR CKT-II
31 33KV BYPL 18.04.15 01.47 CHARGED.
KARKARDOOMA –
KANTI NAGAR KT-II
32 33KV GONDA – BYPL 18.04.15 04.02 CHARGED.
SEELAMPUR – T-OFF
DWARKAPUR CKT
33 33KV TRAUMA NDMC 06.04.15 CHARGED.
CENTER – NETAJI
NAGAR CKT
Since, summer has already set in, utilities were advised to rectify the faults and
normalize the system.
76
They further requested for feasibility and connectivity of 220kV BTPS- Noida feeder
with Grid be evaluated and action plan be communicated to them.
SLDC representative informed that generally 220kV BTPS System is connected through
220kV Bus coupler at Mehrauli substation with Bamnauli system in addition to 220kV
BTPS-Ballabhgarh double circuit line. The Bus coupler at Mehrauli gets opened only on
exceptional cases which would be intimated to BTPS as and when it is done. At present,
220kV BTPS-Noida-Gazipur Circuit is not in service since 17.09.14 due to cable faults.
The cable portion of the circuit is being replaced due to repeated faults. The circuit is
suspected by 30.06.2015. It was also informed that at present Patparganj load is also fed
through 220kV Maharani Bagh - Gazipur - Patparganj route. There is no additional
power available at Gazipur through 220kV Mahrani Bagh - Gazipur circuits to feed
BTPS also, however, it was assured that in case of emergency Gazipur supply can be
extended up to BTPS through 220kV Maharani Bagh – Gazipur – Noida - BTPS circuit.
In case of emergency, BTPS can avail load on the circuit (220kV Gazipur – Noida -
BTPS) with prior permission of SLDC.
4 COMMERCIAL ISSUES.
SLDC representative informed that BRPL, BYPL & MES are the continuous defaulters.
In the last meeting, BRPL and BYPL representatives informed that due to financial
crunch, they could not be able to pay the dues and assured that once they could muster
additional financial resources through loans, they could be able to pay the dues.
77
In the last meeting, MES representative had informed that they would release the dues
immediately but so far it has not happened.
But these utilities continue to default. It was presented by SLDC the week-wise position
of DSM for 2014-2015 and 2015-2016 as under:
78
S. Week no. Duration
no. Amount in Rs. Crores
2014-15 From To
30 30 20/10/2014 26/10/2014 0.4597902
31 31 27/10/2014 2/11/2014 -1.7537914
32 32 3/11/2014 9/11/2014 -0.2123042
33 33 10/11/2014 16/11/2014 -1.1821023
34 34 17/11/2014 23/11/2014 -0.7680342
35 35 24/11/2014 30/11/2014 -0.8298829
36 36 1/12/2014 7/12/2014 -0.4023797
37 37 8/2/2014 14/12/2014 1.8894140
38 38 15/12/2014 21/12/2014 2.2332053
39 39 22/12/2014 28/12/2014 -2.4704799
40 40 29/12/2014 4/1/2015 -0.5742381
41 41 5/1/2015 11/1/2015 0.8565598
42 42 12/1/2015 18/1/2015 0.8065306
43 43 19/1/2015 25/1/2015 0.5163913
44 44 26/1/2015 1/2/2015 -1.9890079
45 45 2/2/2015 8/2/2015 -1.6105399
46 46 9/2/2015 15/2/2015 -0.5804885
47 47 16/2/2015 22/2/2015 0.7861643
48 48 23/2/2015 1/3/2015 0.0546574
49 49 2/3/2015 8/3/2015 1.8452603
50 50 9/3/2015 15/3/2015 1.6199507
51 51 16/3/2015 22/3/2015 4.0999856
52 52 23/3/2015 29/3/2015 2.135334
Total -21.3085815
Total 10.7725161
79
It was evident from the above that during the year 2014-2015 out of 52 weeks, 18 weeks
Delhi is payable whereas during the year 2015-16 so far out of 9 weeks, Delhi is payable
in 7 weeks. It was also explained that as per the DSM regulations, the payable utility has
to pay the amount within 10 days of issue of the accounts by NRPC. It was feared that
without inflow in the account, the available amount in the pool balance which is about
350 Crores available with SLDC would be exhausted soon as Delhi SLDC has to pay to
the regional pool within 10 days of the issue of the accounts to avoid the legal wrangles
for non payment of the dues. As such, SLDC requested all defaulting utilities to pay the
dues immediately.
It was further informed that DERC in its order dated 29.12.2014 had directed SLDC to
take appropriate action to recover dues from BRPL.
SLDC representative informed that as decided in the last GCC meeting, the detailed
calculation of interest for 2013-14 has been forwarded to all stakeholders to check the
same and for the purpose of adjustment and payment. The reconciliation exercise would
have been completed by 31.01.2015 but so far only TPDDL has done their reconciliation
and the available payment has been released to them. The other utilities have not
responded so far. The details of interest payment due as per SLDC computation upto
Week-52/2014-15 are as under:
UTILITY AMOUNT IN RUPEES CRORES
RECEIVABLE (+) / PAYABLE (-) BY THE UTILITIES
TPDDL -1.1203548
BRPL 35.1101915
BYPL -19.9609235
NDMC -4.9652248
MES -1.2727742
IPGCL -0.4651370
PPCL -1.3062075
BTPS 1.0411129
TOTAL 7.0606826
It was also explained that the interest available has been proportionately proposed to be
disbursed / adjusted as shown in the last column of the table above.
GCC expressed displeasure for delay in reconciliation. It was further decided that
the final chances may be given for reconciliation be given upto 1100 hrs on
29.04.2015 failing which the computation of SLDC be treated as final and no request
for reconciliation beyond that be accepted. The payment proposed by SLDC for
disbursement/adjustment in respect of interest of 2013-14 be done accordingly. It
was also advised that final chance be given for clearance of dues of defaulting
utilities (15 days) after that necessary legal proceedings be initiated for recovery of
dues.
80
4.2 HIGH COST OF BTPS AND DADRI (THERMAL)-II STATION (agenda by
BRPL)
BRPL informed that on the analysis of details provided by BTPS and Dadri (Th)-II under
form-15A of CERC Regulations along with the monthly bills, it has been observed that
there are large variation on month to month basis on following accounts
GCV received at BTPS plant is on higher side from Oct-14 onwards as shown below:-
particulars Unit Apr- May- Jun- Jul- Aug- Sep- Oct- Nov- Dec-
14 14 14 14 14 14 14 14 14
GCV billed by CIL Kcal/Kg 3742 3733 3678 3498 3446 3402 5166 5218 5372
GCV (As received at Kcal/Kg 3401 3378 3347 3203 3139 3096 3133 3207 3251
plant)
GCV (Gap from % 10 11 10 9 10 10 65 63 65
`Billed’ to
‘Received’)
They request to provide the justification and supporting documents in large variation in
a) Coal rate from Rs. 4196/MT to Rs. 5024/MT for BTPS and Rs.5058 to Rs.
5126/MT for Dadri-II
b) GCV billed by CIL varies from 3402 to 5372 Kcal/Kg for BTPS
c) GCV billed by CIL for Dadri-II not provided.
They also requested to take necessary steps to minimize the gap in GCV from `Billed’ to
Às received’.
They were of the view that these parameters are the back bone of merit order despatch
principle and post facto variations defeat very essence of merit order despatch. A
proactive approach on continuous basis from NTPC is requested for ensuring reduction of
Discoms power purchase cost thereby leading to reduction in consumer tariff.
81
NTPC representative intimated that they have been giving all details along with the bills
as mandated by Tariff Regulations. He has further offered for any detailed discussions
with the beneficiaries to clear the doubts in this regard. He cited relevant explanations
given by CERC in Explanatory Memorandum-Draft Terms and Conditions for
Tariff Regulations 2014-19 (Page-179 of Clause 15.5.11) to deal fuel shortages.
15.5.11 With regards to scheduling of power in case of fuel shortages the Commission is of the
view that securing fuel is prime responsibility of generator and in case of non
fulfillment of supply of committed quantity of coal the generator is free to procure
either e-auction coal or imported coal and schedule power on the basis of the same. If
the generator is not able to schedule power due to fuel shortage the same shall be
considered as loss in availability of the unit or station as the case may be.
He informed that NTPC follows the above principle in letter & spirit.
(b) The respondents are not providing the details and break-up of the fuels in
compliance with Regulation 30 (7) of the Central Electricity Regulatory
Commission (Terms and Condi tons of Tariff) Regulations, 2014 (2014 Tariff
Regulations);
(c) Delhi Electricity Regulatory Commission (DERC) vide order dated 14.11.2014
disallowed Power Purchase Cost Adjustment Charges (PPAC) on the ground that
complete information regarding pricing of fuel and billing of power generated at
their stations had not been furnished;
(d) The respondents should justify any drastic difference between cost of coal
mentioned in the website of Coal India Ltd. for the grade of coal as received/as
fired by the generating station and that claimed by the generating companies as
provided in Form 15 of Tariff Regulations.
82
(e) The respondents should not be permitted to recover the fuel cost without
furnishing adequate details which entitle the petitioner to recover such cost in the
form of PPAC from its consumers. At present, the petitioner is making continuous
payments to the generating companies for the energy received but the fuel
surcharge is not being allowed by DERC.
(f) DVC has refused to provide copy of the power bills for the last quarter despite
reminders.
(g) As per Section 39 of the Specific Relief Act, 1963, a mandatory injunction must be
granted directing the generating stations to recover energy charge only when the
same is supported by details as per the Regulations. All the requirements for
grant of mandatory injunction under Section 39 have been satisfied.
(a) The attempt made by the petitioner purporting to act as per the directions given
by the Delhi Electricity Regulatory Commission and seeking particulars, is
contrary to the scheme and provisions of the Act. The generating tariff of the
respondents is regulated by the Central Commission in terms of Section 79 (1) of
the Act. In terms of Rule 8 of the Electricity Rules, 2005, the tariff determined by
the Central Commission for generating companies is binding and cannot be
reopened either directly or indirectly at the instance of any of the State Electricity
Regulatory Commission.
(b) (b) NTPC has already furnished to the petitioner the information in respect of all
NTPC stations regarding the fuel cost details for the period April 2014 to October
2014 as per the provisions of Tariff Regulations.
(c) NTPC has given the requisite documents, namely GCV of coal on ‘as received
basis’ as per the 2014 Tariff Regulations and details of the actual amount paid to
the coal companies for the quantum of coal purchased on monthly basis.
(d) The aspect on the grade slippage from the time of loading till the measurement on
‘as received basis’ has been a subject matter of representation to the Govt. of
India and the proceedings before the Competition Commission of India. There is
no option to proceed on the basis that there is a grade slippage in regard to the
GCV measured at the time of loading and measured at the time on ‘as received
basis’ till an acceptable and satisfactory resolution.
3. Due to paucity of time, learned counsel for the parties could not complete their
arguments.
83
It was also informed that the RoP of 27.022015 has not been uploaded in CERC website.
After discussions GCC decided that the matter may mutually be resolved by BRPL
& NTPC. GCC also noted that the CERC is already considering such issues.
BRPL informed that IPGCL vide their letter dated 03.03.2015 has raised the claim of
minimum off take charge of Rs. 91.02 Crores against the pay for `not taken liability due
to less scheduling of generation in the GTPS’. The generation position of GTPS in the
year 2014 and 2015 are as under:-
IPGCL has further informed in the communication that due to the less scheduling by
SLDC / Discoms, the RLNG consumption was less than the contract. According to GSA
Clause-14/1, GTPS have to consume 90% of the allocated quantity of gas otherwise the
Take or Pay clause is applicable. During the contract year 2014, total annual take for pay
deficiency in respect of GTPS worked out to be 4553705MMBTU and the pay for not
taken liability of 434.76 Crores. GAIL has demanded a sum of Rs. 91.02 Crores against
the pay for if not taken liability in line with the Clause-14.1(c) of the GSA. The ‘’pay for
if not taken liability’’ is to be borne by Discoms.
BRPL is further of the view that as per the IEGC provisions, scheduling has to be done
on merit order despatch principle by SLDC. Since the per unit variable cost of the gas
based power station has increased significantly, these plants have moved towards less
priority on MoD list leading less scheduling. Since the information pertaining to gas
allocation, actual gas consumption and impact of take or pay is known only by Gencos
not either by SLDC or Discoms. As such, IPGC/ PPCL should provide the prudent plant
with cost benefit analysis in day ahead/ week ahead / monthly format to SLDC as well as
Discoms in view of FSA / GSA / Take or Pay / ECR for cost effective scheduling from
these plants.
SLDC informed that they have expressed their views in the letter dated 16.03.2015 that it
is the responsibility of the generating companies to impress upon their beneficiaries for
optimum scheduling considering all aspects such as MGO penalties etc.
The issue was discussed in the Delhi OCC meeting held on 24.03.2015, the decision of
which is appended hereunder:-
84
“GTPS and PPCL received very less schedule from SLDC / Discoms in comparison of
DC of GTPS and PPCL. As per the Long Term RLNG Gas Sale Agreement with M/s
GAIL, GTPS and PPCL has to consumer 90% of allocated quantity of gases otherwise
take or pay clause shall be applicable. However, during the current financial year, for
PPCL utilization of allocated gas is in the range of 65-75% which implies PPCL is liable
to pay MGO (Minimum Guarantted Off take of gas) charges to M/s GAIL as the
utilization of the gas is less than 90% as per the agreement. Similarly, GTPS was
demanded Rs. 91.02 Crores by M/s GAIL against the `Pay for if not taken liability’.
GTPS informed that `Pay for if not taken liability has to be bear by Discoms’
Further, GTPS and PPCL requested SLDC to increase the generation schedule so that
their consumption of allocated quantity of gas by M/s GAIL shall be 90% and avoid any
penalty.
Members from GTPS (IPGCL) and PPCL did not attend the meeting for deliberation on
the same. However, OCC advised Discoms to take up with GENCOs regarding
scheduling”.
IPGCL/PPCL representative informed that they have vigorously following up with gas
supply authorities to withdraw the claim. They hoped that they will succeed the same,
however, they cautioned that in case it is not withdrawn as per the PPA conditions the
beneficiaries are required to bear the same. They also agreed to provide the MGO
quantum on quarterly basis and would intimate optimum scheduling to avert the penalty
clause in future.
Convener GCC requested MES to host next meeting of GCC which is likely to be held
during last week of August 2015 or 1st week of September 2015. MEs representative
informed that they would taken up the matter with concerned authorities in their
organization and would be informed accordingly.
Chairperson, GCC thanked all the participants for lively discussions. He expressed
sincere thanks to BTPS authorities for the excellent arrangements made to conduct the
meeting. Convener, GCC also expressed sincere thanks on behalf of GCC to BTPS
authorities for making excellent arrangements for the meeting. G.M. BTPS reciprocated
the thanks.
85
ANNEXUE-1
S.No. Name of the Officer Designation Company Phone No. E-Mail Address
1. Sh. J P S Chawla Dir.(Oprs.) – In DTL 011-23232715 dir.opr@dtl.gov.in
Chair
2. Sh.Roop Kumar ED(T) DTL 9999533629 roopkumar2008@gmail.com
3. Sh.Harjiwan Vyas GM (O&M)-II DTL 9999533631 harjiwan.vyas@gmail.com
4. Sh.Prem Prakash GM(O&m)-I DTL 9999533630 premnimbekar@yahoo.com
5. Sh.P.K. Gupta GM(T) SLDC DTL 9999533626 psdpvr 2012@gmail.com
6. Sh.S.K. Mishra GM(CIVIL) DTL 9999533510 skmishra@dtl.gov.in
7. Sh. S.K. Sharma DGM (P/M) DTL 9999533640 dgmprotection@gmail.com
8. Sh. K.M. Lal DGM(T) Plg. DTL 9999533660 kmlal@dtl.gov.in
9. Sh.A.K. Rathore DGM(T)P-II DTL 9999533669 ashokkurathore@yahoo.com
10. Sh.Hitesh Kumar MGR.Prot-III DTL 9999533662 Hiteshkumar.dtl@gmail.com
11. Sh.Darshan Singh MGR(T) SO SLDC/DTL 9999533837 darshansingh.dtl@gmail.com
12. Sh.Sarada Prasanna MGR.(Plg.) DTL 9999533939 sproutray@gmail.com
Routray
13. Sh.Pradeep Katiyar MGR(T)SO DTL 9999533676 pradeepkatiyar03@yahoo.co.in
86
S.No. Name of the Officer Designation Company Phone No. E-Mail Address
31. Sh.Shobit Dhar Sr. Manager BRPL shobit.dhar@relianceada.com
32. Sh.Sunil Barnwal Sr. Manager BRPL 9350261886 sunil.barnwal@relianceada.com
33. Sh.Sanjay Srivastav AVP BRPL 9312147045 sanjay.srivastav@relianceada.co
m
34. Sh.Satinder Singh Sondhi Ad. VP BRPL 9312147009 satindersondhi@relianceada.co
m
35. Sh.Ashis Kumar Dutta DGM TPDDL 9871798566 ashis.dutta@tatapower-ddl.com
87
ANNEXURE-2
Minutes of meeting held on 27.03.2015 at Conference Hall, SLDC to discuss the issues with
regard to reallocation of surplus power available from various sources beyond 31.03.2015 is
enclosed for ready reference and further necessary action please.
Thanking you,
Yours faithfully
Encl. as above
(V. VENUGOPAL)
Dy. General Manager (SO)
To :-
Sh. P.K. Gupta, G.M. (SLDC)
Ms. Kiran Saini, G.M. (C&RA), DTL, Chairperson, DPPG
Sh. Sanjay Banga, Sr. G.M. TPDDL
Sh. Ashish Dutta, Head(PMG), TPDDL
Sh. Sunil Kakkar, Head (PMG), BTPL
Sh. Sanjay Srivastava, Head (PMG), BRPL
Sh. Sachin Bardan, CWE (U), MES
Sh. D.P. Singh, XEN (Power), NDMC
Copy for favour of kind information to:-
1. Principal Secretary (Power), Govt. of NCT of Delhi,
2. Secretary, DERC, Viniyamak Bhawan, C-Block, Shivalik, New Delhi-110017
3. Managing Director, DTL
4. Chairperson, NDMC, Palika Kendra, Sansad Marg, New Delhi
5. Member Secretary, NRPC, Katwaria Sarai, New Delhi-110016
6. Director (Operations), NTPC, Scope Complex, 7 Institutional Area, Lodhi Road, New
Delhi-110003
7. Managing Director, IPGCL/PPCL, Himadri, Rajghat Power House, New Delhi-02
88
8. Director (Operations), DTL
9. Director (Tech), IPGC / PPCL
10. CEO, BSES Rajdhani Power Ltd, BSES Bhawan, Nehru Place, New Delhi-110019
11. CEO, BYPL, Shakti Kiran Building, Karkardooma, New Delhi-92
12. CEO, TPDDL, 33kV Grid S/Stn, Hudson Lane, Kingsway Camp, Delhi-110009
13. Chief Engineer, Delhi Zone,(CEDZ), MES Palam Road, Delhi Cantt, New Delhi-10
14. G.M. (BTPS)
15. Addl. Secretary (Power), Govt. of NCT of Delhi, Delhi Secretariat, New Delhi
89
DELHI TRANSCO LTD.
(Regd. Office : Shakti Sadan, Kotla Road, New Delhi 110002)
[Office of Deputy General Manager (System Operation)]
SLDC Building, Minto Road, New Delhi – 110 002
Phone No.23221175, Fax 23221012, 23221059
A meeting was convened in the Conference Room of SLDC at 12.00hrs. on 27.03.2015 on the
issue of the communication dated 25.03.2015 received from Govt. of NCT of Delhi with regard
to reallocation of power from various generating stations. The text of the communication is as
under:-
“
To
The General Manager (SLDC)
Delhi Transco Ltd
SLDC Building, Minto Road
Delhi
I am directed to inform you that a meeting was held in the chamber of Hon’ble Minister of Power,
GNCTD on 10.03.2015 at 6.00PM wherein it has been decided that Department of Power, GNCTD shall
submit a detailed proposal by 31.03.2015 after consulting the DTL and Discoms to the Ministry of Power,
Govt. of India clearly specifying the timelines by which the power from NTPC Badarpur Plant can be
surrendered and Rajghat Plant can be shut-down so that gas allocation of the same can be re-allocated to
the Bawana Power Plant
It is requested to assess the demand & supply position in consultation with DISCOMs and furnish your
comments on the reallocation of power from various Central Sector Generating Stations beyond
31.03.2015 to this office within two days positively for further necessary action.
Sd
(Alka Sharma)
(Dy Secretary (Power) ”
Copy to :
1 MD, DTL
2 CEO, TPDDL
3 CEO, BRPL
4 CEO, BYPL
90
-2-
The meeting was attended by members of Delhi Power Procurement Group (DPPG) and SLDC.
Director (Operations), DTL chaired the meeting. The list of the participants is appended
hereunder:-
91
--3--
Gist of discussions and decisions are as under:-
It was intimated by SLDC that during this summer, the closing of RPH Plant would
create transmission constraints to meet the peak demand of more than 6000MW.
However considering the commissioning of 220kV Patparganj – Gazipur 1000mm2 cable
and the possibility of re-conductoring of 220kV Wazirabad – Geeta Colony D/C line to
high capacity conductors, the closure of RPH units won’t cause any constraints. As such,
in System Operation point of view, RPH plant can be closed down immediately after
summer 2015 i.e. after 30.09.2015. The average cost of the generation is as under:-
Sept2014 Oct 2014 Nov Dec 2014 Jan 2015 Feb Total 2014-15
2014 2015 (Total cost fixed
and variable)
The environmental issues are also being encountered for running the units. The units
have also outlived their useful life as Unit-1 (67.5MW capacity) was commissioned in the
year May 1990 (67.5MW capacity) and Unit-2 was commissioned during January 1990
as the normal life of the plant is 25 years. Due to aging of the plant, the efficiency of the
plant has also come down. During last summer season, the plant could not deliver 60%
of the capacity as detailed hereunder:-
Month Plant availability in %age Scheduled PLF in %age
April 2014 82.09 37.04
May 2014 72.13 62.98
June 2014 76.39 74.70
July 2014 57.79 57.79
August 2004 55.00 46.47
Sept 2014 51.94 51.94
April to Sep 2014 65.82 55.13
92
--4--
It was also pointed out that as per the ARR filed by IPGCL for the year 2015-16, they
have claimed the fixed cost of Rs. 175.13 Crores per annum with an estimated variable
cost of Rs. 3.51 / unit (further subject to fuel price adjustment on month-to-month basis)
making the composite cost of Rs. 5.76/unit.
All beneficiaries of RPH requested the State Govt. to close down RPH Plant forever
so that fixed charges liability along with variable charges can be get rid off as the
transmission constraints would be eased after the commissioning of 220kV Patpar
Ganj–Gazipur link and re-conductoring of 220kV Wazirabad–Geeta Colony line.
SLDC informed that from the System Studies, it is evident that due to the inadequate
transmission system, during summer months both the units of the station are required till
the establishment of 400kV Inter State Transmission System (ISTS) at RPH. However,
during the period of October to March, the entire station can be closed down and divert
the gas to Bawana CCGT to efficiently utilize its capacity being the high efficient
machines.
Sept2014 Oct 2014 Nov Dec 2014 Jan Feb Total 2014-15
2014 2015 2015 (Total cost fixed
and variable)
It was also pointed out that in the ARR filed by PPCL for the year 2015-16, they have
claimed the fixed cost of Rs. 238.76 Crores per annum which is Rs. 25 Crores more than
the present level with an estimated variable cost of Rs. 4.36/unit (further subject to fuel
price adjustment on month-to-month basis) making the composite cost of Rs. 5.36/unit.
93
--5--
The plant has so far not completed its useful life as the normal life of Gas Turbine Plant
is 15 years.
Considering the overall system, the Forum was of the view that full generation of
Pragati Stage-I be maintained during summer months and the gas allocation of
entire station be diverted to Bawana CCGT during the period October to March till
the ISTS is commissioned at RPH as the Bawana CCGT generation cost is cheaper
than Pragati Stage-I being high efficient plant as under:-
After the commissioning of 400kV ISTS at RPH with outlets at RPH, the entire
Pragati Stage-I station may be closed down if the generating company could not
assure the cheap gas to run the plant, to get rid off the fixed charges liabilities for
non utilization period.
94
--6--
c) Closure of IPGCL’s GT Station
Distribution utilities intimated that the cost of GT Station of IPGCL is very high (about
Rs. 5.50/-) as evident hereunder:-
They further requested the closure of the station immediately. They also informed that
the plant has already completed its useful life as evident from the date of commissioning
of units :
GT-1 30 17.06.1986
GT-2 30 20.06.1986
GT-3 30 11.08.1986
GT-4 30 03.09.1986
GT-5 30 11.11.1986
GT-6 30 20.11.1986
STG-1 30 24.04.1996
STG-2 30 12.08.1997
STG-3 30 27.12.1996
95
--7--
SLDC informed that this is the only station having Black Start facility and hence two
block of GT i.e. 150MW during summer months April to October and one block (75MW)
during November to March be made available. Balance gas be diverted to Bawana
CCGT.
Discoms were of the view that there is no technical constraint in closing down if not now
but definitely after September 2015. Black Start is a very rare incident and for that
purpose running the plant throughout the year and burden the consumer is neither
justified and nor desirable. In case, it is required to be in operation for ensuring black
start facility, only one block i.e. two GTs and one STG is sufficient. Rest two blocks
should be closed down forever from October 2015 and gas allocation should be diverted
to Bawana CCGT.
It was also pointed out that as per ARR filed by IPGCL for the year 2015-16, they have
claimed the fixed cost of Rs. 198.24 Crores per annum with an estimated variable cost of
Rs.3.73 / unit (further subject to fuel price adjustment on month-to-month basis) making
the composite cost of Rs. 4.81/unit.
The Forum was of the view that the decision of closing of GT Station be left to State
Government considering the black start facility available and the overall interest of
the consumers.
This plant is one of costliest sources. Moreover, plant has outlived its life and age of the
units is 30-40 years. Out of five units of BTPS, 3X95 units are very old and highly
inefficient. The cost of the generation is as under:-
96
--8--
The life of the station has already exhausted as evident from date of commissioning of
units:-
1 95 26.07.1973
2 95 05.08.1974
3 95 29.03.1975
4 210 02.12.1978
5 210 25.12.1981
All the Discoms including NDMC and MES is of the view that BTPS should be closed
from October 2015 considering its very high cost and already completed its useful life.
Further, it was informed that BTPS is going for Renovation and Mordernization activities
at the cost of around at Rs. 741/- Crores as per the CERC order dated 12.05.2011 in
petition no.324/2009 which will further enhance the cost of generation at BTPS. As per
the order, it was suggested that both the units of 210MW machines would be renovated
for extension of its life by 20 years more. It was also suggested in the tariff of BTPS
issued by CERC that 95MW units should be phased out and the minimum capital should
be infused for ensuring their operation till the units are fully phased out. Discoms
requested that Delhi Govt. should take immediate steps to stop such R&M activities to
reduce the burden on consumers.
SLDC intimated that at present, the closing of BTPS during summer season would
severely affect the power supply as the import source at BTPS apart from the generation
is 220kV Ballabhgarh – BTPS Double Circuit line owned by BBMB. The lines are quite
old and restricted capacity is 150MW each. In the present conditions, even with full
generation during peak summer, the lines are getting loaded beyond 150MW capacity
and in case of closure, the loading on the circuits would cross more than 450MW each
which would not survive the system. The transmission system can be improved only
after commissioning of 400kV Tuglakabad System which is being established under Inter
State Transmission System (ISTS) and commissioning of 220kV outlet from the station.
As such, during summer months, particularly May to September, full generation i.e.
600MW is required to be ensured. From the past experience, it is evident whenever any
machine at BTPS of 210MW capacity goes under shut-down, load shedding was
inevitable during summer months. As such, for system stability point of view, the plant
should run till the commissioning of 400kV ISTS at Tuglakabad which is expected by
March 2017 as per the present indications.
97
-9-
The beneficiary Discoms further insisted that if not possible to close entire plant, at least
all 3X95MW units should be closed permanently after September 2015.
Director (Operations), DTL cautioned that even at present, only 20-30% internal
generation (load centre based) is available in Delhi and any further reduction in
generation at load centres, the reliability of power supply would definitely affected. He
also cautioned that the operation of much publicized Delhi Islanding Scheme which was
devised to safely island Delhi Power System from the Grid in the case of Grid eventuality
would be affected severely in case of closing down of all such load centre based
generation.
All figures in MW
Details Apr-14 May-14 Jun-14 Jul-14 Aug-14 Sep-14
Peak Demand met 4418 5338 5533 5925 5507 4882
Shedding at the time of 0 20 155 81 82
0
Peak Demand
Date 30.04.14 30.05.14 19.06.14 15.07.14 27.08.14 18.09.14
Time (HRs) 16:32:00 15:41:31 14:46:07 15:20:20 22:49:14 22:53:58
Generation within Delhi
RPH 52 89 93 102 47 82
Gas Turbine 136 121 166 176 141 149
Pragati-I 84 129 273 277 287 265
Bawana CCGT 216 -3 456 266 611 289
BTPS 241 517 400 573 292 312
Rithala 0 0 0 0 0 0
Timarpur Okhla Waste 14 16 16 12 10
12
Management
Total generation within 743 869 1404 1406 1388
1109
Delhi
Drawal from the Grid 3675 4469 4129 4519 4119 3773
Scheduled Drawal from 3437 4283 4170 4360 4009
3612
the Grid
Over drawal (+) / Under 238 186 -41 159 110
161
Drawal (-)
Generation in %age 16.82 16.28 25.38 23.73 25.20
within Delhi w.r.t. Peak 22.72
demand met
98
-10-
The representatives of the Distribution utilities opined that considering the massive
corrective steps taken by all utilities after the 30th and 31st July 2012 Grid Disturbances
occurred in country and considering the much improved stability of power system, the
possibility of occurrences of such Grid disturbances for which Islanding Schemes are
devised, are remote. As such, to take care of such remote chances of Grid eventualities, it
is not proper to force the Distribution utilities to utilize such costlier generation thereby
burdening the consumers.
CWE(U), MES emphasized that PGCIL which is implementing ISTS at RPH and
Tuglakabad and DTL who is the implementing agency for associated downstream
transmission system should be made responsible to implement the respective systems as
per stipulated time or should be pressurized to be implemented before time as is being
done in case of Military System to get rid off the costly generation.
It was also emphasized that the reallocation of capacity of 3X95MW units of BTPS i.e.
285MW out of 705MW total installed capacity may be persued with Central Government
after September 2015. 285MW capacity allocation was made to Madhya Pradesh from
01.10.14 to 31.03.15 by the Central Government. However, on the request of Madhya
Pradesh, the Central Govt. restored the allocation back to Delhi from 26.12.2014. Such
allocation would always beneficial as the benefit of generation at load centre can be
availed by Delhi. If the plant can not be closed down
99
-11-
now, the Central Govt. may be persuaded to allocate the 285MW capacity to needy
states from 01.10.2015 forever.
Considering the overall views, the Forum decided to recommend the State Govt to
take up the matter with NTPC to avoid infusion of additional funds for R&M
activities for already outlived inefficient plant. It was also decided to request the
State Govt to impress upon the Central Govt. to reallocate 285MW capacity as was
done during the period 01.10.2014 to 25.12.2014, for forever. The reallocation of
power would not only reduce the fixed cost liability but also would not create system
constraints as the plant would actually in operation. If that possibility does not
succeed, it would have no option but to close the 3X95MW units during October to
March till the commissioning of ISTS and associated transmission system at
Tuglakabad. The possibility of decommissioning of 95MW capacity after 30.09.2015
should also be studied considering overall system improvement works being
undertaken by DTL.
Due to non availability of Gas since last two years, the station is not in operation.
TPDDL representative informed that neither the tariff nor the PPA has been approved by
DERC although petition in this matter has been submitted in DERC in 2009.
It was further informed that even during operation of the plant, full cost was not allowed
in the ARR of TPDDL but on the contrary during the time of over drawl, pooled purchase
cost was allowed whereas during under drawal, UI cost was allowed. It was also clarified
that they have claimed the fixed charges of Rs. 96 Crores per annum but still pending in
DERC. SLDC informed the generation details of Rithala plant as under:-
100
--12--
Considering the overall situation of gas in the country and to avoid the burdening
the fixed charges, through it is not approved, but still the claim is alive, the Forum
advised TPDDL to de-commission the plant immediately.
i) On the recommendations of Delhi Power Procurement Group, one of the costliest sources
namely Aravali Jhajjar allocation to Delhi i.e. 693MW capacity has been reallocated to
needy states upto 31.03.2016.
ii) From 756MW capacity allocation of Delhi out of 840MW installed capacity of Dadri
(Thermal) Stage-I, 180MW (TPDDL share) has been reallocated to Bihar during the
period from 10.09.2014 to 31.08.2015.
iii) 260MW capacity allocation of Dadri (Thermal)-II, (100MW share of TPDDL and
161MW share of BRPL out of 735MW capacity) out of total 980MW capacity of the
station has been reallocated to Bihar from 14.11.2014 to 31.03.2015.
iv) There is no technical constraint in surrendering of any the share of Central Sector
Generation Stations outside Delhi.
v) The costlier source of thermal and gas generation should be surrendered during the period
October to March every year to get rid off fixed and variable charges liabilities. The
details of costlier gas and thermal stations (more than Rs. 4 above) are as under:-
Name of the Capacity Capacity Fixed Fixed Variable Total in
station of the allocation charges in charges Charges Ps/Unit
station in to Delhi Rs. Crores in in
MW in MW per annum Ps/Unit Ps/Unit
vi) To meet the shortfall, which may occur in maximum 12 hours in a day may be met from
day ahead purchases from Power Exchanges depending upon the requirement.
101
--13--
vii) As per the Market Monitoring Cell Report available in the website of CERC, the power
market rate in the exchange during the April 2014 to December 2014 was as under:-
From the above, it would be prudent to purchase power from market for shortage period
which is not more than 12 hours during winter month rather than keeping the allocation
forcing the purchase on round the clock basis upto technical minimum level of 70% of
the capacity.
Views of different Discoms regarding reallocation of power from various stations were as
under:-
i) BRPL, BYPL and TPDDL who have the shares from Dadri Gas, Anta Gas and Auriya
Gas have proposed reallocation of their entire allocation from these stations from October
2015 permanently due to the fact that these stations generates 40% of its capacity due to
non availability of gas and Discoms have to bear 100% fixed cost of these stations
thereby burdening of consumers.
ii) NDMC which is having allocation from Dadri (Thermal) Stage-I unit has expressed their
desire to surrender NDMC’s share during October to March.
iii) BRPL proposed to surrender 200MW from Dadri (Thermal)-II but desire to keep its full
share from Dadri (Thermal)-I considering the shortages during October to March. Further
they expressed that the rate of day ahead of bilateral power during peak hours is more
than the total cost of power from the station as evident from the above table.
iv) TPDDL also proposed to surrender 200MW from Dadri (Thermal)-II but desire to keep
its full share from Dadri (Thermal)-I considering the shortages during October to March
due to reasons mentioned above.
v) BYPL does not intend to surrender any power from Dadri (Thermal)-I & II due to
ongoing regulations of power from DVC, SJVN etc.
102
--14--
In case of above proposals are materialized, the power position supply position for
October 2015 – March 2016 is likely to be as under:-
All figures in MW
October November December
Sources
Off Peak Peak Off Peak Peak Off Peak Peak
Demand (2014-15) 3200 4570 1800 3408 1800 4271
Expected Demand 2015-16 3350 4800 1850 4000 1850 4100
Availability within Delhi
RPH 0 0 0 0 0 0
GT 75 75 75 75 75 75
Pragati 0 0 0 0 0 0
Bawana 300 300 300 300 300 300
BTPS 350 350 350 350 350 350
TOWMCL 8 8 8 8 8 8
Total 733 733 733 733 733 733
Central Sector 1939 2239 1739 2239 1739 2239
Sasan 360 360 360 360 360 360
Bilateral
DVC 300 300 300 300 300 300
Maithon 280 280 280 280 280 280
CLP Jhajjar 120 120 120 120 120 120
Total bilateral (DVC, Maithon, CLP
Jhajjar) 700 700 700 700 700 700
Total Availability 3732 4032 3532 4032 3532 4032
Balance to be purchased -382 768 -1682 -32 -1682 68
103
--15--
Note :
i) The entire allocation of Delhi from Anta, Auriya and Dadri Gas Stations to be
reallocated to needy states forever from October 2015.
ii) 125MW (NDMC share) of Dadri (Thermal)-I be reallocated to needy states from
October to March.
iii) 400MW (share of TPDDL and BRPL) from Dadri Thermal Stage-II be reallocated
to needy states from October to March.
iv) All the Distribution Companies should make sufficient arrangements of power to
meet the demand in the event of reallocation of power as mentioned above to avoid
any load shedding in Delhi.
v) SLDC was advised to intimate the above decisions to the State Govt.
104