Professional Documents
Culture Documents
engineering’
1
‘Constructing a universal passion for
engineering’
E-mail: admin@uniengineers.com.au
2
‘Constructing a universal passion for
engineering’
1. Executive Summary
The Northern Connector is a solution to the increasing population growth in Adelaide.
It will be a section of the North-South corridor, a multi-laned motorway that extends
from Gawler to old Noarlunga. This project provides the missing link between the
Port Expressway, South Rd Super way and recent duplication of the Southern
Expressway. It is part of the 30-year plan for Greater Adelaide and will significantly
increase travel time and ease traffic congestion in the Northern suburbs. The existing
and forecasted traffic volumes, civil engineering options, safety and sustainability
have been the key points in the design of the Northern connector.
In the completion of a feasibility study, recommendations were made for the best
detailed design elements. This included practical and economical structural solutions,
such as Super T Beams in bridge construction, finding the preferred road alignment,
considered environmental features and industrial (and business) benefits. There will
be a swale along the road that will return water back into the local creeks and rivers,
and a detailed Environmental Management Plan that will protect the surrounding areas
rich ecosystem during all phases of construction and road use.
Inclusive within this document are a number of other files that have been produced for
the detailed design. This includes a detailed construction methodology (where
applicable) that demonstrates the steps that need to be taken in the building stage.
And a costings section, that has a break-down of materials and quantities needed for
the detailed design stage. There are two separate documents that are also included in
the detailed design:
3
‘Constructing a universal passion for
engineering’
The total cost of the proposed design will be $93 085 000. A costings summary and
employee consulting fees can be found in Appendix A1 and A2.
4
‘Constructing a universal passion for
engineering’
Table of Contents
1. Executive Summary................................................................................................ 3
1.1. Project Background .......................................................................................... 18
1.2. Introduction ...................................................................................................... 19
1.3. Project Funding ................................................................................................. 20
1.4. Project Goals and Objectives ............................................................................ 20
1.5. Further Reflection ............................................................................................. 22
1.6. Design Requirements ........................................................................................ 23
2. Transport Department ......................................................................................... 25
2.1. Road location .................................................................................................... 25
2.1.1. Local centre median widening for bridges ................................ 26
2.2. Radius and Superelevation of Horizontal Curvatures (corners) ....................... 27
2.3. Intelligent Transport Systems (ITS) ................................................................. 30
2.3.1. Variable Message Signs (VMS) ................................................ 30
2.3.2. Variable Speed Limit (VSL) ..................................................... 32
2.3.3. GE1-14 direction gantry ............................................................ 34
2.3.4. ITS Costing ................................................................................ 34
2.4. Signage ............................................................................................................. 34
2.4.1. Regulatory signs ........................................................................ 34
2.4.2. Warning signs ............................................................................ 34
2.4.3. Guide signs ................................................................................ 35
2.4.4. Speed limit signs........................................................................ 35
2.4.5. Other road signs in the project .................................................. 36
2.4.6. Emergency stopping Lane only ................................................. 38
2.5. Emergency Crossovers ..................................................................................... 39
2.6. Total cost of static road-side signs ................................................................... 40
2.7. Safety Phones ................................................................................................... 40
2.8. Lane markings .................................................................................................. 41
2.9. Proposed Interchange Globe Derby Drive ....................................................... 41
3. Geotechnical .......................................................................................................... 43
3.1. Introduction ...................................................................................................... 43
3.1.1. Bore Log Analysis ..................................................................... 44
3.1.2. Explanation of Geological Profile: ............................................ 45
5
‘Constructing a universal passion for
engineering’
6
‘Constructing a universal passion for
engineering’
7
‘Constructing a universal passion for
engineering’
8
‘Constructing a universal passion for
engineering’
9
‘Constructing a universal passion for
engineering’
10
‘Constructing a universal passion for
engineering’
11
‘Constructing a universal passion for
engineering’
List of Figures
12
‘Constructing a universal passion for
engineering’
13
‘Constructing a universal passion for
engineering’
14
‘Constructing a universal passion for
engineering’
15
‘Constructing a universal passion for
engineering’
List of Tables
16
‘Constructing a universal passion for
engineering’
17
‘Constructing a universal passion for
engineering’
This ultimately will increase the traffic volume in existing routes connecting the
northern and southern regions of Adelaide. Apart from the consequences that will be
brought up by the population increase in northern and southern region of Adelaide; the
other reason for the need of new road is to provide solutions to the congestion that are
experienced by the freight vehicles moving between Adelaide’s Northern and North-
Western industrial regions and within Adelaide’s Northern region. If not addressed
appropriately, existing routes such as Port River Expressway and Port Wakefield Road
connecting the above mentioned regions will become a ‘red spot’ in traffic
engineering jargon due to congestion.
The new 15.6 kilometre northern connector road connecting north-south regions of
Adelaide is a multi-million dollar project and the Government of South Australia will
be seeking Commonwealth funding to carry out the construction of this road.
The Northern Connector would specifically link the South Rd Superway with the
Northern Expressway to create a north-south freight route on parallel with existing
Port Wakefield Rd on its western side.
18
‘Constructing a universal passion for
engineering’
1.2. Introduction
This reports details the technical and design requirements for the Northern Connector
Stage 1.
Universal Engineers have built on the findings and recommendations from the
feasibility study to complete a comprehensive detailed design report. This report has
been as inclusive as possible within the specified timeframe. The outcome of this
design is a forward thinking traffic solution that will successfully connect the people
and businesses of Adelaide.
The departments utilised in detailed design were based on the project’s needs. These
included:
- Transport
- Geotechnical
- Water
- Structural
- Urban Design
- Environmental
- Project Management
Transport developed a superior road alignment; this ensures that the Northern
Connector will have minimal impact on housing and industries. The signage,
intelligent transport systems and lane marking has been detailed in the report.
The structural design team determined the most practical and economical bridge
design in the feasibility stage. This has been designed for in the detailed design, and
consists of three lanes of traffic travelling in different directions.
Urban design has taken into consideration the traditional custodians, the Kaurna
community, and have management plan if artefacts are found during construction.
Traffic noise will be alleviated with the use of noise barriers, and a shared path has
also been designed. Environmental produced an extensive
19
‘Constructing a universal passion for
engineering’
Environmental Management Plan that has provided a framework and guidance for the
project. The plan will ensure that throughout construction and the projects life all
environmental impacts are minimised or eliminated.
A superior quality management system report has ensured that the detailed design
stage has been kept on track. This has consisted of weekly meetings, timelines and
deadlines being met and design issues being dealt with effectively.
The Federal Government is funding the project in order to create a freight network
which easily links all around Australia; the State Government is funding this project in
order to fulfil the 30 year plan for South Australia and the plan for greater Adelaide.
The areas that future possible funding opportunities may come from are listed below:
• Local Government
• Private Sector
• Ensure the National Network Transport Link (South Road) fulfils its role in
accordance with both State and National plans, and as a freight link as outlined in the
30-Year Plan for Greater Adelaide
20
‘Constructing a universal passion for
engineering’
• Provide an integrated solution that directly and indirectly enhances transport system
safety for all road users (including motorists, public transport, pedestrians and
cyclists)
• Develop a corridor wide solution that makes the best use of both new and existing
transport network infrastructure, and is integrated with the broader multi-modal
transport network of Greater Adelaide
• Develop a sustainable solution that provides the optimal balance between economic,
social and environmental outcomes.
The objectives for this detailed design remain the same as they have been
throughout this project:
• To protect and provide freight priority consistent with a National Network Transport
Link between the Northern Expressway and Southern Expressway and commercial
centres consistent with Adelaide’s 30-Year Plan
• To improve travel time, reliability and vehicle operating costs in Adelaide’s north-
south corridor
• To minimise greenhouse gas emissions and improve air quality within the South
Road corridor
• To provide the best possible solutions that reduce, if at all, potential environmental
impacts that could occur.
21
‘Constructing a universal passion for
engineering’
22
‘Constructing a universal passion for
engineering’
23
‘Constructing a universal passion for
engineering’
24
‘Constructing a universal passion for
engineering’
2. Transport Department
2.1. Road location
The Road is broken into 17 segments of varying length, each of these segments is
given a specified GPS start location and finish location. The GPS coordinate describes
the position of the exact centreline of the dual carriageway which is 16.825 metres
from either edge of the pavement (except at bridges), directly under the middle of the
concrete barrier. These segments are defined in Table 1 and shown in drawing T-012
and T-013 through T-013C.
Table 1 - Road Segment Location
2. R 700 and R 1000 refer to the radius of the corner, refer to section 2.2 for details, and also note the development lengths
will overrun into the previous and following segments
25
‘Constructing a universal passion for
engineering’
26
‘Constructing a universal passion for
engineering’
The maximum superelevation for the horizontal curves is emax= 6% (Table 7.7,
AustRoads Guide to Road Design Part 3: Geometric Design).
Therefore, the maximum superelevation is given in mm.
The side friction for the Northern Connector is going be f = 0.11 (Table 7.4,
AustRoads Guide to Road Design Part 3: Geometric Design). Using the maximum
superelevation and the side friction factor, the minimum radiuses for the curves will
be Rmin = 667m (Table 7.5, AustRoads Guide to Road Design Part 3: Geometric
Design). Using this as the minimum, the two radii’s for the curves will be;
27
‘Constructing a universal passion for
engineering’
These two radii’s were chosen for ease of design, requirements of client and for the
space available for the alignment of the road, Error! Reference source not found.
xplains how these radii are used.
(Commentary 18. C2, AustRoads Guide to Road Design Part 3: Geometric Design)
28
‘Constructing a universal passion for
engineering’
R = 700m
R = 1000m
The superelevation development length adopted will be 130m for both curvatures of
radiuses 700m and 1000m. (Table C19.1 & C19.2, Austroads Guide to Road Design
Part 3: Geometric Design). The first 91m of the superelevation development length
will be the straight leading up to the curve, with the remaining 39m located on the
curve itself before reaching the required superelevation for the duration of the
horizontal curvatures. The same distances in the same sections will be applied when
returning from the required superelevation to the normal cross fall. Drawings T-006
through T-008 show a cross section of the curves at the maximum superelevation
point.
29
‘Constructing a universal passion for
engineering’
Refer to drawings T-01 through to T-01-D for locations of all the intelligent transport
systems (ITS) along the alignment designed by Universal Engineers.
There will be one VMS system located 1000 metres after the Port River Expressway
interchange and a further two proposed VMS located 1000 metres either direction of
the proposed interchange at Globe Derby Drive, this distance will give motorists
ample warning and time to read the message presented. The VMS will have the
following message priorities listed in Figure 1.
The VMS will be permanent and installed behind crash barriers on the verge of the
roadway with displays on both sides of the frame to enable motorists travelling from
either direction to read and understand the message being displayed, refer to drawing
T-05. All messages will be conveyed in two frames of the VMS, as this ensures that
all road users will be able to view and comprehend the message in the time it takes for
them in their vehicle to approach and pass the VMS.
30
‘Constructing a universal passion for
engineering’
As each message can only be displayed in a maximum of two frames, each message
must be able to be understood in one frame, in the event that a road user only sees one
frame of the message. Figure 2 depicts the use of messages on a permanent VMS with
two frames and each frame being understood without the other.
As the Northern Connector (South) is a 110km/hr roadway, the two frame message is
to be restricted to 3 lines of 18 characters with no single word greater than 15
characters.
Error! Reference source not found. below lists existing messages available for the
ermanent VMS located on the Northern Connector (South) and correct times they can
be displayed to road users.
31
‘Constructing a universal passion for
engineering’
32
‘Constructing a universal passion for
engineering’
The VSL signs, selected are able to display to any speed and conform to all required
Australian Standards shown in Table 2.
Figure 4 shows a VSL in use, the features include High brightness LED display, local
and remote (optional) programming, long life cycle, impact resistant polycarbonate
screen and facility key switch for road workers/police/emergency services. The added
option of having all the variable speed limit signs to be solar powered will be taken for
the Northern Connector. Refer to drawing T-003 for details regarding the designed
overhead VSL gantry for the Northern Connector.
33
‘Constructing a universal passion for
engineering’
2.4. Signage
Road signs play an important role in guiding road users in the safe and efficient
movement of traffic. The road signs will lose effectiveness if used very frequently
and unnecessarily, therefore accurate placement and type of road signs is very
important. The Australian Standards specify in detail the different type of
requirements for the permanent road signs, temporary road sign and the pavement
markings.
34
‘Constructing a universal passion for
engineering’
35
‘Constructing a universal passion for
engineering’
The sign shown above in Figure 5 is the no turn sign which used at intersections
where vehicles are prohibited from making turns of any description. The size of the
sign is 450 X 600 (mm) according to standard shown. In this project, the sign will be
used to help control the traffic when vehicle is moving with high speed.
There are many different types of direction signs used to help control the traffic, the
signs shown above are just a sample of direction signs which direct road user to their
termination. On the signs, it presents arrows of the direction to the destination, name
of the destination such as City, and the distance to termination with unit of kilometres.
The photograph is taken by the team and dimension for the signs are from AS1743-
2001.
The sign shown in Figure 7 above is warning road users that bicycle, animals and
pedestrians are prohibited beyond this sign. The location of the prohibition sign (R6-
13) is displayed on drawing T-009 and written in
37
‘Constructing a universal passion for
engineering’
Table 4. The size of the sign is 1200 X 1500 mm and present as black letter and white
background according to AS 1743-2001.
38
‘Constructing a universal passion for
engineering’
Table 4 below details the location of each sign on the expressway also shown on
drawing T-009
Emergency Crossover and No U Location along road (metres from road start of
Turn Sign road segment 1)
1 600 m
2 1100 m
3 2700 m
4 3700 m
5 4200 m
6 4700 m
39
‘Constructing a universal passion for
engineering’
40
‘Constructing a universal passion for
engineering’
41
‘Constructing a universal passion for
engineering’
A further two mounted gantry VMS AD302, will be placed 1000 metres in either
direction of the proposed interchange. Two GE1-14 signs will be placed 300 metres
from the interchange. A list of costing of the proposed ITS is presented in Table 8.
Variable Speed
AD307 4 $28,000.00 Limit Sign
Gantry Mounted
LED Variable
AD302 2 $260,000.00 Message Sign
Lane Direction
GE1-14 Sign 2 $110,000.00 Overhead Gantry
Total $398,000.00
Please note these prices are subject to change in the future, further costing is required
when the need arises for the interchange.
42
‘Constructing a universal passion for
engineering’
3. Geotechnical
3.1. Introduction
Geotechnical engineering is an essential aspect in the design and construction of
expressway and the bridge in the Northern Connector project. Understanding the soil
profile and its characteristics and behaviour is very necessary to calculate the possible
settlement in the soil due to the future construction.
The bore logs of the soil near the alignment of Northern Connector produced by
Aurecon on their geotechnical report provided by DPTI showed that the project extent
includes the expansive soft soils in the soil profile. The structures constructed in the
soft soils should be given higher care in order to prevent any differential settlements
that can result in failure of the structures.
The geotechnical engineers in Universal Engineers have thoroughly studied the soil
profile based on the bore logs as well as the geotechnical report 1 and 2 provided by
Aurecon.
Geotechnical engineers have also considered the future possibility of a sea level rise.
A prospective wall design has been provided to mitigate the possible flood situation
that may be caused by the rise in sea level in future.
The soil profile is investigated to provide in-detail information for the soil
consolidation as well as calculating the bearing capacity of the soil. The ground
exposure condition will help to determine the steel or concrete piles required to
support the bridges as well as the time required for soil settlement
43
‘Constructing a universal passion for
engineering’
The road alignment has slightly changed from the one proposed as a concept design
during the tender stage. Due to this, the bore log data that was produced by Aurecon
differs in locality. The most critical and the deepest bore log was BH 129 and this has
been taken as soil sample for the project (Refer to Section 1.5.2 for more information) .
This bore log represents the soil profile throughout the project layout. To simplify the
soil profile, the layers with similar characteristics were put into the same category and
the layer that had negligible thickness was combined with the representative layer
above or below it.
As per the BH129, a simplified geological soil profile has been drafted as below:
44
‘Constructing a universal passion for
engineering’
The soil profile (Error! Reference source not found.0) is drawn to the scale of 1:100.
The generalized layers of the soil and types including the depth have been clearly
shown in the legend in the profile. From the bore hole data, it is shown that the soil at
depth 0-2.7m has been classified as Fill Sandy Clay, although there were 0.5m of core
losses in 0-0.5m and 2-2.5m length of the bore log. Sand occasionally does not stick to
the bore, this results in the small loss of sand data. This sandy clay was brown in
colour with low to medium plasticity and medium to fine grain size.
At the depth of 2.7m-4.2m, the soil sample is clayey silt, dark grey to black in colour
and increases moisture content with the increase in depth. Similarly, the bore log was
differentiated into various soil types and related with their properties in the
geotechnical model in Table 9.In accordance with the geological profile and
AUSTROADS Bridge Design Code, a geotechnical model has been drafted. The
property of the soil profile plays a critical role in calculating the strength of the soil.
Cu Unit soil
Depth Soil type Consistency/Density Φ’ C' (kPa)
(kPa) density (γ)
Fill Sandy
0-2.7 L 108 29 5 18.75
Clay
2.7-4.2 Clayer Silt F 180 21 2.5 19.5
Silty Sandy
4.2-5.4 VS/F 192 21 2.5 20
Clay
5.4-11.5 Sandy Clay VST 100 _ _ 20.5
11.5- Slity Sandy
VST/L 192 21 2.5 19.5
12.4 Clay
12.4-
Sand ST _ 35 5 21
13.5
14-14.4 Sand L _ 35 5 21
14.4- Silty Sandy
H/VST 192 21 2.5 19.5
18.0 Clay
18.5-
Sandy Clay VS/MD 100 _ _ 20.5
19.5
45
‘Constructing a universal passion for
engineering’
A simplified geotechnical soil model was drafted as shown in Table 9. The value for
the internal angle of friction (Φ) and unit weight of the soil (γ) were obtained from the
consolidated un-drained strength (Cu) for soil layers was calculated using the formula
shown below and average value was taken for each layers.
Cu= 6N
Respectively, cohesion (c’) was obtained from “Table D4, Soil Classification” from
AUSTROADS Bridge Design Code and average value for each layer of soil was
recorded.
46
‘Constructing a universal passion for
engineering’
3.2. Consolidation
Project Title North-South Corridor – Northern Connector, Stage 1
(South) –
Detailed Design
Subject: Soil Consolidation
Job Number: G-001 Contract: Geotechnical
Date: 10-05-2015 Prepared: H Kandel
Sheet: 1 of 9 Checked: B Dhamala
Client: DPTI Approved: R Beardwell
In order to simplify the consolidating soil layer, the soil profile has been generalized
into two different layers by assuming the soil layer with similar properties as a single
soil layer. For the second layer of the soil profile, the unit weight has been considered
as 20kN/m3 as it is the average value for those combined soil profile. The total vertical
stress due to the soil layer has been calculated.
47
‘Constructing a universal passion for
engineering’
The consolidation layer generally consists of sandy-silty clayey layers for which the
typical moisture content value is 0.44 (terra GIS, 2007)
Void ratio at the end of odometer test for saturated soil (Das, Ch3)
48
‘Constructing a universal passion for
engineering’
49
‘Constructing a universal passion for
engineering’
ei 1 ei e
e H
1 e H
The table below shows the settlement that occurs at the end of each stage and stress
gained by the soil.
50
‘Constructing a universal passion for
engineering’
Compression-Recompression Curve
stress (kPa)
0.00 100.00 200.00 300.00 400.00 500.00
0.000
Compression-recompression Curve
0.050
cumulative strain
0.100
0.150
0.200
0.250
The graph below shows the compression and expansion of soil before and after the
release of stress. The curved section of the compression-recompression line is the
region of normal consolidation and the linear section is the region of over
consolidation. The
51
‘Constructing a universal passion for
engineering’
52
‘Constructing a universal passion for
engineering’
As the ground water table is at 1m, it is assumed that the soil after consolidation
would become a saturated soil and the total stress would be equal to the effective
stress.
Since there is a ground water table as below as at 1m depth, the soil is saturated.
Therefore effective stress is equal to vertical stress due to soil.
= 224 kPa
The compressibility index of the soil tells about how much the soil could be
compressed. The higher value of compressibility index indicates that the soil contains
large voids and moisture content and is highly compressible. This value can be
obtained from the graph of ‘e vs stress’ by finding the slope of compression curve in
the region of normal consolidation.
53
‘Constructing a universal passion for
engineering’
1.29 1.15
Cc 0.398
log( 450 / 200)
Similar to the compressibility index, swelling index explains the expansive nature of
soil. The swelling occurs when the stress over the soil is released after compression.
The slope of the swelling curve in the above graph of ‘e vs stress’ gives the value of
the swelling index.
1.185 1.14
Cs 0.0272
log( 450 / 10)
The stress increment on soil causes settlement. With the addition of surcharge loading,
the stress increases on soil. The increment of stress was applied in different stages and
the corresponding height change (settlements) were calculated as demonstrated below.
54
‘Constructing a universal passion for
engineering’
(kPa)
Stage 4 (139-147.5) 0.001011 8.5 8.8
Stage 5 (147.5-224) 0.000277 76.5 8.8
Stage 5:
Total settlement:
H H1 H 2 0.076 0.186 0.262 m 262 mm
C v t 50
T50 2
H dr
T50 0.197
55
‘Constructing a universal passion for
engineering’
Need values for 90% settlement time (t90) and the height of water drainage layer (Hdr)
Since, most of the stress increment (78-163) kPa lies in stage 4. Following
conclusions can be made to find the values of Cv.
-1.0
-1.1
4th stage (97.5-147.5kPa)
Total Height change, mm
-1.2
-1.3
-1.4
-1.5
-1.6
-1.7
-1.8
-1.9
-2.0
0.0 5.0 1 10.0 15.0 20.0 25.0 30.0 35.0 40.0
.
(time, min)
9
56
‘Constructing a universal passion for
engineering’
t 90 1.9
t90 3.61
Hence, the time required for 90% settlement of the soil sample in the laboratory
environment is 3.61 minutes.
H o 19.25 mm
H ave 18.76 mm
18.76
H dr 9.38 mm (Double drainage layer)
2
0.848 9.38 2
2
T H
Cv 90 dr 20.66 mm 2 / min 10.71 m 2 / year
t 90 3.61
H o 8.8 mm
Therefore the time needed for 50% settlement of the soil is 4 months. As the
consolidation varies negative logarithmically with time, for full consolidation, the full
consolidation is expected to occur in 12 month time.
57
‘Constructing a universal passion for
engineering’
For the calculation of the bearing capacity the below equation was used.
In this case the r and i values are not applicable and can be cancelled out resulting in
the following, slightly more simplified, equation.
This calculation is completed twice, once to find the drained solution and again to find
the undrained solution, after which the more critical value is used as the ultimate
bearing capacity.
From the Geological Profile the following values for the soil layer were taken to be
used within the calculation.
Throughout the calculation of the drained solution and the different factors, the c’
value was used as c (c = 5kPa) and was used as the value. The bearing
capacity factor equations can be found below.
58
‘Constructing a universal passion for
engineering’
Using the values from the geological profile, the value was calculated to be
16.4kN, the value was found to be 27.9kN and the value was determined to be
13.6kN.
The shape factors were calculated based of a square footing 3mx3m (i.e. B = L = 3m).
The shape factor equations can be found below.
Using the above equations, was found to be 1.6, was found to be 1.6 and was
found to be 0.6.
The depth factors were calculated based on a depth of 0.6m using the below depth
factor equations as .
Using the above equations, was found to be 1.06 and was found to be 1.42.
After inputting all of these values into the simplified bearing capacity equation the
ultimate bearing capacity for the drained analysis was calculated to be 779kPa.
Throughout the calculation of the undrained solution and the different factors, the
value was used as c (c = 108kPa) and was used as the value. For the case
where , the value is 1kN, the value is 5.14kN and is 0kN.
Using the same formulas for the shape factors as in the drained solution, was found
to be 1.2, was found to be 1 and was found to be 0.6.
59
‘Constructing a universal passion for
engineering’
Using the same formulas for the depth factors as in the drained solution was found
to be 1 and remains equal to 1. However, due to being equal to 0° throughout the
undrained analysis is used to calculate and was calculated
to be 1.07.
After inputting all of these values into the simplified bearing capacity equation the
ultimate bearing capacity for the undrained analysis was calculated to be 706kPa
which is the more critical of the two calculated bearing capacities and therefore the
one to be used to determine the value.
After determining the ultimate bearing capacity, the safe or allowable bearing capacity
can be calculated.
Therefore, the max bearing capacity that this proposed footing can safely apply
to the soil is 247kPa over a 3x3m area.
60
‘Constructing a universal passion for
engineering’
= 16.4kN
Shape Factors
= 1.6
Depth Factors
61
‘Constructing a universal passion for
engineering’
= 779kPa
62
‘Constructing a universal passion for
engineering’
Shape Factors
=1
Depth Factors
= 718kPa
63
‘Constructing a universal passion for
engineering’
Therefore,
64
‘Constructing a universal passion for
engineering’
Using the data provided by DPTI in the nearby roads such as Port Wakefield Road
and Salisbury Highway
Where:
AADT = Average Annual Daily Traffic count, from the provided traffic data.
= 64 900
= 0.5
65
‘Constructing a universal passion for
engineering’
NHVAG =
= 2.66
CGF = Cumulative Growth Factor, to allow for traffic growth over the life of the road.
= 30
66
‘Constructing a universal passion for
engineering’
= 79.6 106
DESA (Design traffic in Equivalent Standard Axles) is required for the subgrade
design.
= 71.66 106
67
‘Constructing a universal passion for
engineering’
Also, the table 2.1 from the Guide to Pavement Technology states the use of AC 10 or
AC 14mm as the wearing surface of the pavement. In this project, AC 14mm has been
used as the open graded wearing course.
68
‘Constructing a universal passion for
engineering’
69
‘Constructing a universal passion for
engineering’
The pavement type was chosen as Open Graded Asphalt pavement containing
unbound granular pavement/cemented soil layer as recommended in the feasibility
study and agreed by the client in the presentation.
To calculate the appropriate thickness of the pavement, the CIRCLY was set to the
required DESA value and the desired pavement type was selected.
70
‘Constructing a universal passion for
engineering’
After several initial trails for the thickness of the pavement, the final thickness of
40mm, 50mm, 80mm and 250mm were found to be adequate for Asphalt wearing
course, intermediate course, Asphalt base course and unbound granular base course
respectively. Calculate Damage Factors (CDF) need to be less than 1 as output from
CIRCLY to accomplish an adequate design for the pavement.
The strength of the unbound granular base course was set as 850 MPa. The CBR for
the existing soil is calibrated as 7 in majority and 28 for minority of the project land.
71
‘Constructing a universal passion for
engineering’
After the consolidation, it is expected to increase. Hence CBR of 8% has been adopted
for all the locations for the calculations. As CDFs for all the material was less than 1,
the design is adequate for the number of traffic predicted for the expressway.
Below is the output that was generated by Circly in regards to road pavement design.
-------------------------------------------
-------------------------------------------
72
‘Constructing a universal passion for
engineering’
-------------------------------------------
73
‘Constructing a universal passion for
engineering’
The final pavement design for Northern Connector as calculated by CIRCLY has been
tabulated below:
AC 14 40 mm
AC 20 50+100 mm
Total 440 mm
74
‘Constructing a universal passion for
engineering’
AC 14 1 x 40 mm 40 mm
AC 20 3 x 50 mm 150 mm
75
‘Constructing a universal passion for
engineering’
The shared use paths along the corridor are designed for 2.5m wide. Taking into
consideration the safety of the pedestrian and the cyclists, the wearing surface is
designed as sprayed treatment. According to DPTI Bikeway Pavement Guidelines
(Table 11.2), the minimum design for sprayed seal granular bikeway and moderate
strength soil strength (CBR≥5%) without traffic is 10/5 double seal (as the wearing
surface) and 100mm PM3/20 as the base course. This type of surface is selected as
referred by the urban design team to aesthetic reason of the surrounding as well as for
the economical prospective.
76
‘Constructing a universal passion for
engineering’
The natural topography of the project area along the proposed alignment typically
ranges between 0 to +2 m of the Australian Height Datum (AHD). Due to the earlier
mentioned sea level rise the road will need to be raised 3m in order to ensure that the
road doesn’t get flooded. This means that the whole project will mostly only require
fill to be completed. As such the only excavations that will be done within the project
will be due to footings, foundations and pipe work.
The construction of the embankments will be done using the select earth fill so that
the properties of the soil are good to have a stable slope. According to AS 4678-2002,
only the selected cohesion less granular fill can be placed in a controlled manner. As
the use of plastic cohesive fills such as clay can cause problems like shrink, swell and
soft soil during and after the construction, the fill soil has been chosen as per the
standard’s table D4 as:
Weak weathered rock, gravel and recycled concrete: c'=20 kPa and f'=40o
77
‘Constructing a universal passion for
engineering’
Hence, geotechnical engineers suggested using the batter slope of 10:1. A slope
stability test was conducted for the embankments for the designed slope using the
software called Galena. The embankment is designed symmetrical in both sides for
better aesthetic purpose as well as ease of design. The restraints were applied on both
sides to determine the most critical failure surface.
The soil properties for the layers used in Galena are listed as follows:
Weak weathered rock, gravel and recycled concrete: (g) = 23 kN/m3 c'=20 kPa &
f'=40o
Existing soil after consolidation: Unit Weight (g) = 18.95kN/m3 c'=10 kPa and f'=35o
78
‘Constructing a universal passion for
engineering’
79
‘Constructing a universal passion for
engineering’
The detailed output of slope stability from Galena has been attached in the appendices.
80
‘Constructing a universal passion for
engineering’
From this figure it can be seen that when the thickness of the road pavement is
considered the average cross-sectional area of the road profile is approximately 176m2.
This means that in order to construct the whole 6330 meter section of road, and ensure
that it is not susceptible to flooding due to rising sea levels; approximately 1.1 million
cubic meters of fill will be needed for the project.
81
‘Constructing a universal passion for
engineering’
Since the construction requires multiple contractors with their own specialties, each of
the contractors are responsible for determining their own construction method, overall
scheduling and timing. However, a frequent and enough inter contractor
communication is required for the effective and simultaneous proceedings.
The tasks, without which other tasks cannot proceed forward or proceed with less
efficiency, shall be staged out to be completed at earlier time. And the tasks which
could only proceed with the help of former one, will be put to start at later time. The
staging shall be prepared so that there won’t be any gap or delay between the
consecutive tasks. In this way, each of the construction phases will be staged out to
occur sequentially, however, some works could be undertaken during and before the
completion of other phases or both at simultaneous time.
Site visit
Fencing of construction site to prevent public access and secure a site
Appropriate signage display for wearing protective equipment such as hard hats,
steel toe shoes and high visibility vest at site entrance will be installed
Supply water for construction, caravans and portable toilets and rest rooms
Removal or proper mitigation of any trees that may have to be avoided if found
lying on the designed alignment
Since this stage is a long process, the completion of the project on time depends
heavily on the results of this stage. Stripping of topsoil is done up to 150mm and the
top soil is stockpiled on site, which will be re-spread after the completion of project
over the project site. The stockpile will be regularly sprayed to prevent the dust being
eroded.
82
‘Constructing a universal passion for
engineering’
The ground treatment to improve the quality of the soil in the area will be done by
filling the site with the select fill and extra surcharge if required. The select fill used as
surcharge can further be used for the construction of embankment in later stages. The
time required for this stage is at least 18 months including the time to deposit the
surcharges, consolidation and removal of extra surcharge at the end.
Various construction vehicles and equipment used for this stage are graders, trucks,
excavators, Bobcat, forklifts, Loader Bucket, etc.
Topsoil containing surface soils which have sufficient humus to support plant
growth shall be removed.
The natural ground surface should be cleared of all artificial debris and
vegetation, either growing or in decay. It is advisable to take advantage of the tensile
reinforcement provided by a root system if the embankment is constructed over very
soft subsoil.
Fill material should be placed systematically and in uniform layers to the
correct width and side slope in order to facilitate control. Care is needed to make sure
the edges are compacted well.
3.10.4. Phase 4: Pavement construction
Compaction of the sub base granular materials with optimum moisture content
of 98%, each layer not more than 125mm at a time.
Proof role the compacted layer with the water truck and verified by Project
Manager
Paving of asphalt overlays will be conducted using two asphalt batching plant.
Sufficient raw materials will be stockpiled on the site to ensure that the plants are
running efficiently.
The thickness of the pavement layer has to be verified either by the site
engineer or supervisor
Various construction vehicles and equipment used for this stage are graders,
trucks, Bobcat, asphalt pavers and rollers.
3.10.5. Phase 5: Disestablish site
Once the project is completed, the site will be disestablished involving the
clean up as well as removal of equipment, fences and plants.
Various construction vehicles and equipment used for this stage are excavators,
trucks, cranes, dozers and rollers.
83
‘Constructing a universal passion for
engineering’
84
‘Constructing a universal passion for
engineering’
3.11. Costing
As can be seen in Error! Reference source not found. the estimated amounts of
aterials required over the project can be seen in the third column, while the cost of the
material is in the fourth column. The prices used within the cost column are estimates
taken from the Australian Construction Handbook, (Rawlinson, 2014).
Vol./m
Weight
of Total Volume Cost/
Material Cost ($)
road (m3) ($/tonne)
(tonne)
(m3)
Fill 176.14 1114995 2675988 22 58871736
AC 14 1.35 8520.2 20448.5 180 3680726
AC 20 5.05 31950.8 76681.9 180 13802746
Granular
8.41 53251.3 127803 20 2556062
850MPa
Total
78911270
Cost
85
‘Constructing a universal passion for
engineering’
86
‘Constructing a universal passion for
engineering’
The total cost of the geotechnical section of the project came out to be $ 81,793,396
However, it must be noted that this cost is based on estimated material requirements
and the final cost could either be higher or lower depending on changes to these
amounts.
87
‘Constructing a universal passion for
engineering’
4. Stormwater Design
This open channel/swale system will run parallel with the connector on both sides; it
will be 4.5m wide in total and will have a maximum depth of 0.2m. Where the swale
is within 20m of the bridges, the cross section will be altered such that the overall
width is 3.7m. The reason for the change in cross section is to incorporate steeper side
slopes such that the swale does not overflow when coping with the excess stormwater
runoff from the bridges.
88
‘Constructing a universal passion for
engineering’
For our open channel swale design we must consider the following:
89
‘Constructing a universal passion for
engineering’
4.2.1. Assumptions
There are a number of different types of flow and given that our design is an open
channel, the flow will be naturally occurring dynamic flow. This type of flow is hard
to analyse and model and as a result we must make some assumptions in order to
design the open channel:
90
‘Constructing a universal passion for
engineering’
subject to; an open channel was selected as a solution to this as it is a low maintenance,
environmentally friendly, highly effective and simple design. The open channel will
be include vegetation, it will act as a filtration device that will treat the water before it
flows back into the adjacent creeks thus reducing environmental impact from the busy
road on the local flora and fauna.
91
‘Constructing a universal passion for
engineering’
Catchment Area:
Fraction impervious:
50 years
6 minutes 144mm/hr
92
‘Constructing a universal passion for
engineering’
(interpolated)
We can now determine the slope by checking the velocity of the desired slopes and
ensuring it is not greater than .
93
‘Constructing a universal passion for
engineering’
Adopted slope
Manning’s
Side slopes
Area
Wetted perimeter
Hydraulic radius
94
‘Constructing a universal passion for
engineering’
Velocity capacity (5 year ARI)
Wetted area
Wetted perimeter
Hydraulic radius
Therefore our channel is more than capable of handling the stormwater runoff
from the road and the design is conservative in order to accommodate for future
flooding.
The stormwater that is collected from the bridge will be collected into the open
channel that was previously designed. This channel will then disperse all water into
95
‘Constructing a universal passion for
engineering’
the creek which the bridge spans across. It will be ejected into the creek via the open
channel, we will not utilise any pipelines to perform this function. This option is the
most environmentally friendly as the channel is vegetated with grass.
The side slopes of the open channel will be slightly increased within close proximity
(20m) to the bridges. This slope increase will cater for any additional water that this
section of the channel has to cope with. The adjusted cross section will have side
slopes of 1:8 and hence we must recalculate to ensure the velocity is still within our
acceptable range and does not exceed 0.5m/s.
96
‘Constructing a universal passion for
engineering’
Velocity capacity (5 year ARI)
Wetted area
Wetted perimeter
Hydraulic radius
Therefore this swale design is satisfactory given the velocity of the flow is less than
97
‘Constructing a universal passion for
engineering’
The construction cost for swales depends on the surface area/width, type of vegetation
and the gradient of the area. The essential unit rate construction for a nominal 3 metre
wide swale is summarised in Table 1.
98
‘Constructing a universal passion for
engineering’
The maintenance objectives for a vegetated swale system include retaining the
hydraulic and pollutant removal efficiency of the channel, and maintaining a dense,
healthy vegetation cover. The table (2) below describe the cost of the maintenance for
the Northern Connector Swale Design.
Swale size
Component Estimate 0.2m deep, 0.5m Comments
Cost bottom, 3m top width
Mow 2-3 times per
Mowing 264.6
year
Grass Maintenance
General grass care 297 area is top width +
99
‘Constructing a universal passion for
engineering’
Maintenance should include frequent inspection during the first few months to ensure
vegetative cover is establishing well. Once established, continue to inspect biannually
for signs of erosion. Weed control and periodic mowing of grass swales (typically
biannually), with grass never cut shorter than the design flow depth, are recommended.
Cuttings should be removed from the channel and disposed in a local composting
facility. Similarly, vegetated swales should be pruned and harvested in place of
mowing. Before winter and after major storm events, debris and blockages should be
cleared. The vegetation cover should be thick and reseeded as necessary. Swales will
be inspected regularly for pest intrusion such as mosquitoes.
4.4.2.1. Vegetation
50mm to 40mm turf grass vegetation is required to cover the entire width of the swale
in order to have a water quality filtering function, rather than simply a conveyance or
infiltration function. For this swale design, a fine, close growing, water resistant grass
is selected to increase the surface area of the vegetation exposed to the runoff and
thereby improve effectiveness of the system. The dense form and height of the turf
grass will provide an aesthetically pleasing landscape feature.
The proposed stormwater system strictly adheres to the Water Sensitive Urban Design
requirements. With the introduction of swale systems, any collected water is
redistributed into the natural water systems via our channels besides the bridges. The
swales will be comprised of grass that will act as a filtration system such that the
stormwater runoff has minimal impact on the Little Para River and the Dry Creek
River.
100
‘Constructing a universal passion for
engineering’
Figure 26: Global Mean Sea Level Rise (Baseline 1961-1990, WMO standard)
101
‘Constructing a universal passion for
engineering’
102
‘Constructing a universal passion for
engineering’
5. Structural Design
5.1. Introduction
There are currently no major bridge structures allowing transit over the two waterways
within the Northern Connector development area. These waterways, Little Para River
and Dry Creek, have spans of 40m and 120m respectively. The locations of water
courses and the corresponding bridges can be seen in Figure 28. In order to maintain
a constant traffic flow over these water bodies it is essential to design and construct
bridge structures to carry three lanes of traffic in each direction.
The design and construction of these bridges is the main structural component of the
Northern Connector Project, which includes computer analysis, hand calculations,
construction procedure and relevant safety procedures during the construction phase.
103
‘Constructing a universal passion for
engineering’
Final costing’s of the structural component having also been considered, utilizing
subcontractors and material property guides.
SpaceGass is a proven and reliable structural analysis tool (SpaceGass 2015). The
primary use of SpaceGass in this design was to model the main superstructure of the
bridge including girders and deck and use simulations to apply combination load cases.
By using SpassGass and RAPT an accurate, efficient and thorough evaluation has
been achieved that satisfies the design brief in quality and aesthetics.
The following sections and subsections provide an in-depth discussion into the design
and detail of the bridges. For ease of installation and simplicity of design the bridges
have been designed and analysed in 20m sections, which can then be connected in
series to achieve the desired span of the bridges. Many other aspects have been
considered and will be further detailed throughout this report.
104
‘Constructing a universal passion for
engineering’
Wind load is an important consideration in bridge design due to the surface area of the
superstructure and the significant exposure. Both Little Para River and Dry Creek
bridges have very high wind exposure due to limited obstacles in the surrounding area.
The bridges are located on very flat terrain with few surrounding trees and no tall
buildings, allowing the bridges to receive the full impact of the wind pressure. Two
key wind loads have been considered in the following calculations including vertical
and transverse loads. Vertical load or uplift acts upward on the underside of the
girders, perpendicular to the horizontal decking slab and creates a bending moment on
the superstructure opposite to that created by the dead loads and traffic loads. The
transverse wind load acts perpendicular to the side of the bridge and creates bending
moment on the columns and bridge girders.
The wind loading calculations have complied with the Australian standards and
consider a wind speed ARI of 2000 years as specified in AS5100.2: 2004, clause
16.2.2. The design wind speed has been found by considering the maximum wind
speed applied to the bridge from wind speeds specific for the Adelaide area for each
cardinal direction. The wind speeds have been factored by values specific to the
conditions associated with the bridge locations and dimensions and loads have been
calculated for force analysis on the bridge superstructure.
105
‘Constructing a universal passion for
engineering’
Where:
VR (Regional gust wind speed) = 48m/s from table 3.1, region A1 (1170.2:
2004) for 2000 year ARI as stated by section 16.2.2 in (AS5100.2: 2004)
Md (Wind direction multiplier) for the 8 cardinal directions from table 3.2 for
region A1
Table 22: Wind Direction Multipliers
Direction Multiplier
N 0.90
NE 0.80
E 0.80
SE 0.80
S 0.85
SW 0.95
W 1.00
NW 0.95
Mzcat (Terrain/height multiplier) = 0.99 from table 4.1 (1170.2: 2004) for
terrain category 1 with a height (z) of less than 3m
106
‘Constructing a universal passion for
engineering’
Where,
u (Design wind speed for ultimate limit states). The bridge runs 20 degrees
East of true North longitudinally. Hence interpolation between North-West and West,
and South-East and East is required to calculate transverse direction. Linear
interpolation is used to calculate required direction:
107
‘Constructing a universal passion for
engineering’
t (Area from the critical span of bridge) = depth x length = 1.1 × 20.0 = 22 2
108
‘Constructing a universal passion for
engineering’
109
‘Constructing a universal passion for
engineering’
The ultimate traffic loads considered to be acting on the bridge consisted of three class
M1600 vehicles travelling simultaneously across the bridge. Class M1600 is specified
in the Australian standards (AS5100.2-2004, CL 6.2.3) as moving traffic loads
produced by truck actions. By utilising the SpaceGass software traffic library, the
analysis of the worst case combination for traffic loading was achieved. The M1600
truck configuration data found in the SpaceGass library provided dimensions and
loads generated by each axle. In Figure 29 below extracted from SpaceGass,
illustrates the dimensions of the vehicle. The spacing between the individual wheels
horizontally is 1.25m. The spacing between the sets of axles is 3.75m, 6.25m and 5m
from front to back respectively.
The vehicle library in SpaceGass also provided isolated wheel loading transferred to the
bridge from each vehicle. Figure 30 below extracted from SpaceGass illustrates the force
exerted by each wheel.
60 kN
110
‘Constructing a universal passion for
engineering’
To generate the worst case loading combinations for the bridge, dynamic loads
produced from moving vehicles were analysed. Through utilising the SpaceGass
moving loads function, it was possible to generate the simulation of three concurrent
moving vehicles. In Figure 31 below, is extracted information from SpaceGass
illustrates the simulation of the vehicle tires moving from right to left across the
bridge.
When analysing the dynamic loads it was essential to consider the effects of three
vehicles moving across the bridge. The bridge standards (AS5100.2-2004) require the
consideration of the accompanying lane factor when calculating the worst case load
combination. In accordance with AS5100.2-2004 (table 6.6) the three lane
accompanying factors are 1.0, 0.8, and 0.4 respectively. The specified values were
inputted as Figure 31: Dynamic Loads
the dynamic
load factors in
SpaceGass.
111
‘Constructing a universal passion for
engineering’
considering road surface irregularities. This value can then be applied in the worst
case load combination; this is calculated below in traffic loads below (ST002).
(AS5100 Cl 6.7.1)
Therefore the dynamic load allowance of 1.35 can be utilised in finding the worst case
loading combinations.
112
‘Constructing a universal passion for
engineering’
113
‘Constructing a universal passion for
engineering’
Therefore:
114
‘Constructing a universal passion for
engineering’
115
‘Constructing a universal passion for
engineering’
116
‘Constructing a universal passion for
engineering’
117
‘Constructing a universal passion for
engineering’
118
‘Constructing a universal passion for
engineering’
119
‘Constructing a universal passion for
engineering’
They are found in the Z-axis moment and Y-axis shear columns and as visible the
maximum positive and negative values have been labelled. The rendered images assist
in giving a visual representation of what the output files are linked to and what has
been tested in Space Gass to get these results.
120
‘Constructing a universal passion for
engineering’
121
‘Constructing a universal passion for
engineering’
122
‘Constructing a universal passion for
engineering’
123
‘Constructing a universal passion for
engineering’
124
‘Constructing a universal passion for
engineering’
125
‘Constructing a universal passion for
engineering’
126
‘Constructing a universal passion for
engineering’
127
‘Constructing a universal passion for
engineering’
128
‘Constructing a universal passion for
engineering’
The Slab is modelled as 1m width strips and therefore has a Load Width (LW) =1m.
129
‘Constructing a universal passion for
engineering’
130
‘Constructing a universal passion for
engineering’
f’cf=0.6(f’c)0.5
=0.6(40)0.5
=3.79MPa
131
‘Constructing a universal passion for
engineering’
Muo.min=1.2[Z(f’cf+ )+Pe]
=1.2[6.67x106(3.79+0)+0]
=30.4kNm
Ast.min=0.0025 bd
=0.0025*1000*154
=385mm2
Z= 0.925d
=0.925(154)
=142.45mm
Muo=Ast *fsy * Z
Ast=Muo/ (fsy * Z)
=43.4x106/(500 * 142.45)
=609.34 mm2
T=Ast*fsy
=629*500
=314.5 kN
C=T=0.85*f’c* ϒ*ku*b*d
132
‘Constructing a universal passion for
engineering’
ku
133
‘Constructing a universal passion for
engineering’
Muo = T*Zu
=T(d-0.5(ku* ϒ*d))
=314.5x103(154-0.5(0.08*0.77*154))
=46.9 kNm
φMuo = 0.8(46.9)
=37.52 kNm > M* ok
Z=0.925d
=0.925(154)
=142.45mm
T=Ast*fsy
=440*500
=220 kN
C=T=0.85*f’c* ϒ*ku*b*d
134
‘Constructing a universal passion for
engineering’
ku =
135
‘Constructing a universal passion for
engineering’
φMuo = 0.8(33.2)
=26.56 kNm > M* ok
V* =11.829kN
Vuc=(1.59)(1)(1)(1000)(154)(3.42)(629/(1000*154))1/3
= 133.9kN
0.5φVuc=0.5*0.7(133.9)=46.8 kN > V*
therefore no shear ligatures required
136
‘Constructing a universal passion for
engineering’
5.6.3.2.1. Positive:
n= Es/Ec
=200/32.8
=6.1
137
‘Constructing a universal passion for
engineering’
Icr =
= 4.5x107mm4
σst1 = My/Icr
=
= 9.02 MPa<295MPa
138
‘Constructing a universal passion for
engineering’
σst2 = My/Icr
=
= 9.33 MPa<295MPa
5.6.3.2.2. Negative:
N = Es/Ec
=200/32.8
=6.1
Icr =
= 6.04x107mm4
σst1 = My/Icr
= 1.1 MPa<295MPa
139
‘Constructing a universal passion for
engineering’
σst2 = My/Icr
=
= 1.55 MPa<295MPa
140
‘Constructing a universal passion for
engineering’
Lsy.t =
Lsy.c = (0.125fsy-22)db
= (0.125(500)-22)(12)
= 486mm = 500mm
141
‘Constructing a universal passion for
engineering’
f’c = 65MPa
142
‘Constructing a universal passion for
engineering’
A = 507600 mm2
Iy = 1.38x1011 mm4
Iz = 6.65x1010 mm4
Zz t= 1.26x108mm3
Zzb = 1.4x108mm3
Cb = Iz/Zzb
= 6.65x1010/1.4x108
= 475mm
Ct = Iz/Zzt
= 6.65x1010/1.26x108
143
‘Constructing a universal passion for
engineering’
e = Cd-dc
= 475-80
= 395mm
A = 907600 mm2
Iy = 3.96x1011 mm4
Iz = 1.55x1011 mm4
Zz t= 3.45x108mm3
Zzb = 2.07x108mm3
Cb = Iz/Zzb
= 1.55 x 1011/2.07 x 108
= 748.8 mm
Ct = Iz/Zzt
= 1.55x1011/3.45x108
= 449.3 mm
e = Cd-dc
= 748.8-80
= 668.8mm
An initial ductility value (ku) value is taken, ku ranges from 0.15-0.25. Therefore ku =
0.20 and the following steps are used to determine if this choice is sufficient.
144
‘Constructing a universal passion for
engineering’
b = 2500mm
φ = 0.8
f’c = 65 MPa
d = D-dc
=1200-80
=1120mm
145
‘Constructing a universal passion for
engineering’
n=1
Zzt = 1.23x108 mm3
Ag = 507600 mm2
e = 395 mm
M*G = 1220.895 kNm [Self-Weight Bending
Moment]
Top fibre stress: f’ci = 52MPa
σtop = 0.6(f’ci)0.5
= 0.6(52)0.5
= 4.33 MPa
Pi<4508.1 kN
146
‘Constructing a universal passion for
engineering’
σbottom = 0.6(f’c)0.5
= 0.6(65)0.5
= 4.84 MPa
Pi<2677.9 kN
Under the fill service load, the Effective Prestress Pe applies, Assume 20 percent deferred
losses, so n=0.8.
Pe = 0.8Pi
= 0.8(2677.9)
= 2142.32 kN
147
‘Constructing a universal passion for
engineering’
5.8.1.2.1. At transfer
At transfer the beam carries it’s self-weight only.
148
‘Constructing a universal passion for
engineering’
Pij = 2677.9/0.943
= 2839.8 kN
Limiting the stress in the strands to 80 percent of their breaking load, the needed
breaking capacity of the tendon is:
149
‘Constructing a universal passion for
engineering’
Ppu = 2839.8/0.8
= 3549.8 kN
Therefore the number of 15.2mm diameter strands is: Assume that 7-wire ordinary is
used
Ppu/MBL = 3549.8/250
= 14 [Super T standards: strands placed 50x50mm pitch]
fpb = MBL/Anominal
= 250x103/143
= 1748MPa
Apt = 14*143=2002mm2
find k1:
fpy/fpb = 1482/1748
= 0.85 < 0.9, k1=0.4
150
‘Constructing a universal passion for
engineering’
σpu = 1748(1-(0.4*0.019)/0.67)
= 1728.17 MPa
M*/φ = 2923.238/0.8
= 3654> Mpu therefore no tensile reinforcement is needed for strength
Vu c = Vt+Pv
151
‘Constructing a universal passion for
engineering’
=317.6 kN
= -17.76 MPa
Q = (852*200)(748.8-75)
= 114.8x106mm3
bv = 852-0.5(7*50)
=677mm [Super T standards: strands placed 50x50mm pitch]
Vt = 3032.4 kN
Vuc = 3032.4+317.6
= 3350 kN
152
‘Constructing a universal passion for
engineering’
Ф*0.5*Vuc = 0.7(0.5)(3350)
=1172.5 kN >V*
Therefore ok for shear, no shear ligatures required for strength.
Vuc = Vt+Pv
=317.6 kN
= -4.7 MPa
153
‘Constructing a universal passion for
engineering’
Q=
= 481.3 x 106mm3
bv = 852-0.5(7*50)
= 677mm [Super T standards: strands placed 50x50mm pitch]
Vt = 438.7kN
Ф*0.5*Vuc = 0.7(0.5)(756.3)
= 264.7 kN <V*
Therefore shear ligatures needed for strength
154
‘Constructing a universal passion for
engineering’
When choosing the spacing of the ligatures, take the minimum of 0.75D or 500mm.
5.8.4. Deflection:
155
‘Constructing a universal passion for
engineering’
h = e = 668.8mm
Ag = 907600mm2
I = 1.55x1011
Pe = 0.8*14*212 = 2374.4kN
= 11.41mm (upwards)
156
‘Constructing a universal passion for
engineering’
DL+0.7LL = (5*UDLserv*L4)/(384*Ec*I)
= (5*69.74*200004)/(384*37400*1.55*1011)
= 25.1mm downward
st = p+ DL+LL
= -11.41 + 25.1
= 13.7mm < L/800 = 25mm [span to
deflection ratio]
therefore ok for deflection
157
‘Constructing a universal passion for
engineering’
158
‘Constructing a universal passion for
engineering’
Therefore
159
‘Constructing a universal passion for
engineering’
Therefore
Hence the minimum reinforcement required for the headstock is 1391 mm2
160
‘Constructing a universal passion for
engineering’
Therefore:
161
‘Constructing a universal passion for
engineering’
162
‘Constructing a universal passion for
engineering’
Therefore:
163
‘Constructing a universal passion for
engineering’
Therefore:
164
‘Constructing a universal passion for
engineering’
165
‘Constructing a universal passion for
engineering’
Therefore:
166
‘Constructing a universal passion for
engineering’
167
‘Constructing a universal passion for
engineering’
Therefore:
168
‘Constructing a universal passion for
engineering’
Through rearranging:
169
‘Constructing a universal passion for
engineering’
5.10. Column
The following section includes the design and calculation process for the bridge
columns. Column design is based on the RAPT software output, which includes the
calculated bending moment and shear forces. The column reinforcement has also been
provided by the RAPT output. The reinforcement layout provided presented variables
for the first design check using hand calculations.
The capacity of the column was determined using hand calculations using the
reinforcement and dimensions provided from RAPT and were compared with the
ultimate loads provided by the SpaceGass analysis. As conservative techniques are
used in hand calculations due to simplification of the member behaviour the column
capacity was expected to be greater using hand calculations compared with the RAPT
results. The following section includes the column design with bending moment and
shear force capacities.
170
‘Constructing a universal passion for
engineering’
171
‘Constructing a universal passion for
engineering’
172
‘Constructing a universal passion for
engineering’
The Muo has been calculated from RAPT is 159kN < 196.35kN, therefore Muo is
acceptable in this case.
The Nub has been calculated from RAPT is 2152kN < 3210kN, therefore Nub is
acceptable in this case.
173
‘Constructing a universal passion for
engineering’
eccentricity,
The Mub has been calculated from RAPT is 414kN<677.31kN, therefore Mub is
acceptable in this case.
At ku = 1
T=0
H = 285.5mm
V = 200mm
Mu = 6340.5*0.0855 = 542kNm
The Mu has been calculated from RAPT is 234kN < 542kN, therefore Mu is
acceptable in this case.
174
‘Constructing a universal passion for
engineering’
The Nuo has been calculated from RAPT is 5610kN < 9400kN, therefore Nuo is
acceptable in this case.
5.10.1.4. Ligature calculation
175
‘Constructing a universal passion for
engineering’
5.11. Summary
Table 26: RAPT Vs Hand Calculations
10000
9000
8000
7000
SHEAR FORCE
6000
5000
hand calculation
4000 RAPT
3000
2000
1000
0
0 100 200 300 400 500 600 700 800
BENDING MOMENT
176
‘Constructing a universal passion for
engineering’
When the results from the hand calculations are compared with the RAPT output for
bending moment and shear force capacities (Figure 52), the hand calculation results
are shown to be greater than RAPT output. Therefore using 4N24 reinforcement in
500mm x 500mm concrete column is acceptable in this case (refer to figure 7). In
addition, N10 ligatures will be used at 360mm spacing (refer to ligature calculations).
This reinforcement and ligature design has been applied to all bridge columns due to
consistent loads from all bridge spans being 20m.
177
‘Constructing a universal passion for
engineering’
The footing design is a critical element of the bridge superstructure. The footing
supports the entire structure including the piers, girders and bridge deck and must
transmit all construction and operational loads to the ground including significant
forces created by large freight vehicles. The footing supports the superstructure
including piers, girders and decking, therefore the maximum combination of
downward forces must be considered. The footing is also in contact with the
underlying soil and is subject to an upwards force created by the soil bearing pressure.
80 footing pads must be constructed as foundations for the 80 piers for the two bridges.
56 footing pads are required for the 120m Dry Creek bridge and 24 footings pads are
required for the 40m Little Para River bridge (see drawings: 120m bridge (ST002) and
40m long section (ST003)).
The site surface soil in the areas surrounding the bridges is described as stiff clay with
a normal range of allowable bearing capacity of 200-400kPa. (Foster, Et Al. 2007) The
geotechnical analysis performed by Universal Engineers has studied the soil at the
locations subjected to the footing loading and provided a critical allowable bearing
capacity of 247kPa. This critical bearing capacity has been used across all footing pad
locations for a conservative design approach.
Known variables:
178
‘Constructing a universal passion for
engineering’
179
‘Constructing a universal passion for
engineering’
180
‘Constructing a universal passion for
engineering’
181
‘Constructing a universal passion for
engineering’
182
‘Constructing a universal passion for
engineering’
For the final footing design with detailed dimensions see drawing:
‘Pier Footing Design’ No. ST009 and ST010
183
‘Constructing a universal passion for
engineering’
5.13. Exclusion
The inclusion of sound barriers was a late modification to the initial scope of design
and has been excluded from the presented design. The advanced stage of design at the
time of the addition, made the budget and deadline for the design infeasible. The
addition of sound barriers also posed logistical problems with future access for
maintenance. Future investigation into the operational traffic noise levels should be
performed to ensure noise guidelines are not breached. If sound barriers are proven
necessary, the conservative bridge design implemented will allow provision for extra
dead loads and live loads associated with the sound barriers but Universal Engineers
will not take responsibility of any additional expenses in modifications to the
superstructure if required.
184
‘Constructing a universal passion for
engineering’
For approval of a construction method that has minor modification to the provided
method or entails a significantly different sequence of works, the contractor must
develop a detailed construction methodology. The construction methodology must
include detailed calculations and drawings and is to be provided to the consulting
engineer for review.
185
‘Constructing a universal passion for
engineering’
top of each pier. The launching skid uses a steel truss design to minimise deflection
but the contractor can gain approval of an alternative method by submission of design
to the consulting engineer.
The spans launched are assumed to have all concrete forms complete and no
further dead or live loads added during movement across piers.
The loads created from the movement of the girder spans across the piers are
assumed to be less than the ultimate design loads during service and therefore the
girder, pier and footing designs are assumed to be sufficient to withstand the imposed
forces during erection.
1. Construct site access roads to withstand loads specified in the logistics section.
Access road construction to consider future use as maintenance road.
5.14.3. Construction Sequence for 120m span bridge at Dry Creek location
Figure 55: Stage 1 construction element set-out for 120m span bridge
186
‘Constructing a universal passion for
engineering’
5.14.3.1. Stage 1
1. Perform rough grade work and prepare site to the requirements of constructing
piers 1, 2, 3, 4, 5, 6 and 7. The site preparation works are to be within the guidelines
of the environmental management plan and any other special considerations outlined
in the design brief.
Note: The contractor must install temporary drainage and erosion control devices
immediately following rough grade work.
3. Drill pile shafts for piers 1, 2, 3, 4, 5, 6 and 7 install reinforcement and place
concrete (see proposed drill pile method).
9. Improve access roads used for pier construction for permeant access for future
maintenance of superstructure.
187
‘Constructing a universal passion for
engineering’
1. Using temporary casing and slurry, drill shaft to a depth of 12m to ensure stiff
clay is reached.
2. Fix permanent casing in place at bottom of hole and remove overburden within
casing.
188
‘Constructing a universal passion for
engineering’
5.14.3.2. Stage 2
1. Excavate launching pit
Note: The contractor must install temporary drainage and erosion control devices
immediately following excavation. The contractor must also coordinate with the
subcontractors for the storage of materials for girder construction.
2. Install permanent bearing systems and temporary roller bearings and erection
frames on piers 1 to 7.
Figure 56: Stage 3 construction element set-out for 120m span bridge
5.14.3.3. Stage 3
1. Build the reaction foundation at the Northern end of the launching pit.
Figure 57: Stage 4 construction element set-out for 120m span bridge
189
‘Constructing a universal passion for
engineering’
5.14.3.4. Stage 4
1. Launch girders using span by span succession.
Note: Girder launching is only to be performed one span at a time to limit the time the
free cantilever is suspended. After each successive span is launched, the span is
lowered onto the permanent bearings but not fixed.
Figure 58: Stage 5 construction element set-out for 120m span bridge
5.14.3.5. Stage 5
1. As the launching skid crosses the final span, the skid is dis-assembled in
sections.
2. When spans are in final position, the girder load is transferred from the
temporary roller bearings to the permanent bearings.
3. Restore the launching pit to previous grade through backfill.
4. Build abutments 1 and 2.
5. Install stormwater drainage system.
6. Erect the guard rails.
7. Hand over to road surface contractor to install pavement on bridge to required
surface grade59:
Figure and connect
Stage to existing
1 construction road surface
element on 40m
set-out for either sidebridge
span of the abutments.
190
‘Constructing a universal passion for
engineering’
5.14.4. Construction Sequence for 40m span bridge at Little Para River
location
5.14.4.1. Stage 1
1. Perform rough grade work and prepare site to the requirements of constructing
piers 1, 2 and 3. The site preparation works are to be within the guidelines of the
environmental management plan and any other special considerations outlined in the
design brief.
Note: The contractor must install temporary drainage and erosion control devices
immediately following rough grade work.
3. Drill pile shafts for piers 1, 2 and 3 install reinforcement and place concrete
(see proposed drill pile method)
4. Construct footings for piers 1, 2 and 3. Form footing, install reinforcement and
place concrete as specified in structural drawings.
5. Construct Piers 1, 2 and 3. Form pier, install reinforcement and place concrete
as specified in structural drawings.
191
‘Constructing a universal passion for
engineering’
9. Improve access roads used for pier construction for permeant access for future
maintenance of superstructure.
Proposed drilled pile method: See 120m span bridge method for details
5.14.4.2. Stage 2
1. Excavate launching pit
Note: The contractor must install temporary drainage and erosion control devices
immediately following excavation. The contractor must also coordinate with the
subcontractors for the storage of materials for girder construction.
2. Install permanent bearing systems and temporary roller bearings and erection
frames on piers 1 to 3.
Figure 60: Stage 3 construction element set-out for 40m span bridge
5.14.4.3. Stage 3
1. Build the reaction foundation at the Southern end of the launching pit.
192
‘Constructing a universal passion for
engineering’
Figure 61: Stage 4 construction element set-out for 40m span bridge
5.14.4.4. Stage 4
1. Launch girders using span by span succession.
Note: Girder launching is only to be performed one span at a time to limit the
time the free cantilever is suspended. After each successive span is launched, the span
is lowered onto the permanent bearings but not fixed.
Figure 62: Stage 5 construction element set-out for 40m span bridge
5.14.4.5. Stage 5
1. As the launching skid crosses the final span, the skid is dis-assembled in
sections.
2. When spans are in final position, the girder load is transferred from the
temporary roller bearings to the permanent bearings.
193
‘Constructing a universal passion for
engineering’
194
‘Constructing a universal passion for
engineering’
5.15. Logistics
The scope of the key structural design is for two bridges that provide creek crossings
where the designed road alignment intersects. The two bridges for design include a
girder bridge over Dry Creek which has a span of 120m and a girder bridge over Little
Para River which spans 40m.
The construction site of each bridge requires preparation to ensure the key functional
elements such as the site office, storage areas, delivery areas and access roads are
adequate for the operational phase and to meet the environmental management plan
guidelines. This design has several recommendations for site logistics that align with
guidelines and have be deemed feasible for a safe construction phase. In Figure 63 and
Figure 64 shown, the recommended logistics plans for each bridge construction site.
The Figure 63 shows the access roads for the Dry Creek bridge construction site. The
access roads align with pre-existing maintenance roads created for access to the salt
fields and for local services. The main public roads that link to the access roads are
Globe Derby Road and Whites Road to the North and the Princess Highway to the
South. The Figure 64 shows the access roads to the Little Parra River construction site.
Again these access roads have been located to align with pre-existing service roads.
The public roads that link to Little Para River site are Hodgson Road to the North and
Whites Road to the South. The contractor can modify the recommended site logistics
plan but approval must be sought. The approval must include drawings of the
proposed site layout for the client to review to check compliance with the
environmental management plan.
195
‘Constructing a universal passion for
engineering’
196
‘Constructing a universal passion for
engineering’
The design calls for 2 bridges to be constructed, one bridge spanning 120m over North
Arm Creek and a second bridge spanning 40m over Dry Creek. The traffic lane
requirements are 3 North bound and 3 South bound lanes. To accommodate the traffic
requirements, each bridge will be broken down into 2 major segments, each
supporting 3 lanes of traffic, with each bridge 15m wide. Both bridges are planned on
a straight section of road which simplifies the design and construction process. As the
road elevation has been designed for 3m above surface level for flood mitigation, the
clearance achieved by the bridge continuing at this elevation is sufficient for future
creek level rises and no modification to the vertical alignment was needed. The main
structural elements of the bridges are girders which have a super tee design. The super
tees are reinforced concrete structures utilising post-stressing technology. For each
15m wide section, 6 super tees are used and this design has enabled the bridge depth
to be minimised. For both the 120m and 40m spanning bridges, piers have been
designed at 20m centres, giving a design span of 20m for design calculations.
5.15.1.1. Materials
The construction of both bridges requires a variety of construction materials, primarily
concrete, steel, and formwork. To facilitate the coordination of material storage,
accurate design information for the key bridge elements which incorporate a
significant volume of required materials has been supplied. The volumes and
dimensions of materials along with the schedule of construction works should be used
to determine delivery schedules for materials to site to assist in efficient use of
available storage space. The contractor is recommended to only have materials
delivered to site on an as need basis.
5.15.1.2. Storage
The site logistics plan provided shows a recommended area for storage facility
erection. The contractor must coordinate the storage of all materials, tools, equipment
and plant within designated storage areas. Plant requires special consideration for
197
‘Constructing a universal passion for
engineering’
storage location due to heightened safety risk and soil bearing capacity. The
contractor must determine the storage space required and develop a material storage
and delivery plan for approval which includes layout drawings of major plant and a
risk assessment. The contractor must adhere to the environmental management plan
when preparing site for storage and implement controls to prevent environmental
degradation during construction.
198
‘Constructing a universal passion for
engineering’
Figure 65: Incremental launching jack operation sequence (Source: AASHTO 2007)
199
‘Constructing a universal passion for
engineering’
The specialty equipment required including jacking frames and temporary roller
bearings must be sourced by the contractor from specialty providers that sell or lease
the high capacity jacks and roller bearings. The capacity of the equipment must be
chosen to lift and move each span, without additional dead load or live load (loads are
available in the design calculation section).
The incremental launching method has both advantages and disadvantageous over
conventional construction techniques. Disadvantages include longer construction
durations and an increased cost due to longer durations and requirements for specialty
equipment, planning strategies and technical expertise. The advantages, leading to
incremental launching being chosen as the design method include, a minimised
disturbance to the sensitive surrounding environment, a smaller and more
concentrated assembly area and enhanced worker safety due to an increased scope of
work performed at ground level and not high elevations as with conventional
techniques.
200
‘Constructing a universal passion for
engineering’
Table 27: Technical data for mobile crane LTM 1030-2.1 (Sourced from Liebherr 2015)
201
‘Constructing a universal passion for
engineering’
The lifting radius and associated lifting capacity of the LTM 1030-2.1 is shown in (Figure
66: Technical data for mobile crane LTM 1030-2.1 (Sourced from Liebherr 2015). The
maximum lifting capacity of 35 tons is only achieved at a height of 8m and a radius of 3m. If
the contractor choses this recommended mobile crane, a lifting plan must be made available
for review, along with a detailed list of significant lifts, including load, dimensions and
slinging details. If the chosen crane set-out requires a lifting radius and lifting height that
surpasses the allowable crane capacities the contractor will need to coordinate the hire of a
larger item and an investigation and report must be performed for site access road capacity
and safety.
202
‘Constructing a universal passion for
engineering’
This design does not include provisions for the foundation slab to support the mobile
crane during operation. The contractor will be responsible for sub-contacting the
temporary footing design and construction when planning of the cranes position is
finalised. The operation of
the crane must not proceed without risk assessment approval and a qualified crane
operator, certified slinger and supervisor present.
The contractor should only have plant delivered to site on an as need basis to facilitate
with efficient storage and worker safety.
203
‘Constructing a universal passion for
engineering’
During the construction process of the bridge there are some safety factors would need
to be considered. The safety considerations include the risk management, WHS
training, and emergency management.
There are two bridges that have been designed in this project. Both bridges pass over a
watercourse and therefore consideration must be given to the risk of working at
heights and the risk of falling into the body of water. Due to the presence of water on
the worksite, the risk of injury from electrical equipment is also heightened. Risk
assessments for works adjacent to water should be conducted prior to commencement
of operations. A safe work method statement should be produced that outlines the
controls to be used to minimise any identified risks.
There are many heavy machines, such as mobile cranes that are required in the
construction process. The site should be clear and access for large machines
delineated to ensure isolation from workers is achieved. When machines are in
operation an essential worker or spotter must always be present to identify any
ongoing hazards arising as work progresses.
204
‘Constructing a universal passion for
engineering’
Anyone who is working on the construction site should have completed the
construction “White Card” training before they start work. Any personnel operating
machinery such as cranes must have conducted the relevant training and hold the
required license.
205
‘Constructing a universal passion for
engineering’
The concrete being used for this design contains Portland cement which makes the concrete
highly alkaline with pH values normally above 12.5 (Malik 2013, p.4). There are many ways
the acid can attack concrete and to varying severity. As shown in Figure 67 Stages of
Attack (Malik 2013, p.9)it is dependent on the pH of the acid as to how much it affects the
concrete. The pH levels for the area are 8.46 meaning that the cement is susceptible to acid
attacks in this location. It is suggested that an Acid Resistant Epoxy Binder be used as it will
provide the affected portions of the concrete, especially the submerged portions like the
columns and footings with additional protection.
A suggested product for this could be EPIREZ Acid Resistant Epoxy Binder (133AR) as it is
well suited for many conditions including this and will not wash away or affect the local flora
and fauna through harmful chemical exposure (EPIREZ 2015). This product can be applied
over the footings and columns adding an extra layer that will protect them and can be re-
applied when it is washed or worn away (EPIREZ 2015).
206
‘Constructing a universal passion for
engineering’
5.16. Costing
The cost for construction of the designed bridges has been estimated in detail in with a
summary of costs provided in Table 28. The overall cost has been displayed by construction
phase with prices shown for each major element for activities within each phase. The total
cost for the 120m spanning Dry Creek Creek bridge is $2 191 553 with the total cost of the
40m spanning Little Para River bridge being $999 318. Overall the structural component of
the Northern Connector is $3190871 for two bridges. The costing estimation provided is
based on prices sourced from (Rawlinsons 2015) and Bianco Precast construction (2015).
The prices estimated are subject to change through location and supplier price variation,
activity duration changes and construction methodology modifications.
Item Cost
Little Para River $2191553
Dry Creek bridge (40m) $999318
Total bridge construction $3190871
207
‘Constructing a universal passion for
engineering’
Table 29: Cost breakdown of North Arm Creek and Dry Creek bridge construction
208
‘Constructing a universal passion for
engineering’
209
‘Constructing a universal passion for
engineering’
210
‘Constructing a universal passion for
engineering’
211
‘Constructing a universal passion for
engineering’
212
‘Constructing a universal passion for
engineering’
213
‘Constructing a universal passion for
engineering’
frame
Excavator (KOMASTSU
1 125/hr 5000
HB215)
Build reaction Drill Rig 1 150/hr 6000
foundation for 5 40 Labourer 1 62/hr 2480
launching pit Steel 0.1t 2110/t 211
Vibrator 1 40/day 200
Concrete 9cum 256/cum 2304
Mobile crane 1 170/hr 6800
Assemble launching
5 40 Labourer 2 62/hr 4960
skid
Launching skid 1 20000 20000
Full bridge span
Casting and super tee All materials and labour 480m of super
30 240 850/m 408000
launching construction - Cast included tees
segments 1-2 in launching pit
launch segment 1-2 30 240 Jacking frame 1 800/day 24000
Mobile crane 1 170/hr 2720
Disassemble skid 2 16
Labourer 2 62/hr 1984
Bulldozer (John Deere
Backfill launching 1 150/hr 3600
Post 3 24 650J LT)
pit
launching Labourer 2 62/hr 2976
works Concrete 300cum 256/cum 76800
Build abutments 12 96
Labourer 3 62/hr 17856
Guardrails 160 195/m 31200
Install guardrails 3 24
Labourer 2 62/hr 2976
TOTAL 999318
214
‘Constructing a universal passion for
engineering’
215
‘Constructing a universal passion for
engineering’
6. Environmental
6.1. Purpose of the Environmental Management Plan
The Environmental Management Plan (EMP) attached will provide guidance and
framework for the project. The EMP will help with planning for the construction
phase, allowing practical environmental management and ensuring that all
environmental impacts involved in the project life are minimised or eliminated.
3. To minimise or remove all environmental impacts that arise from the project,
whether on the work area or the surrounding environment
4. To provide, and adhere to the most effective environmental management
practises through efficient use of planning, continuous monitoring and improvement
5. Identification and control of potential environmental hazards and incidents by
using the management procedures defined in this document
6. Providing proper procedures and training to the taskforce to ensure that proper
handling of potentially hazardous substances is carried out
7. Provide proper training and safety inductions for all employees and
subcontractors
8. Define the monitoring and auditing procedures which will be used to ensure
that the required environmental outcomes are achieved, highlighting responsibilities of
employees to ensure that the EMP is continually improving
9. Introduce complaint and reporting records to respond to and manage complaint
incidents
216
‘Constructing a universal passion for
engineering’
Air quality and emissions need to be closely monitored in order to keep the project on
track and at the same time to ensure any possible contaminations are minimized. To
preserve air quality and reduce the air pollution/gas emission, the schedule for the air
quality inspection will be prepared and completed by the Environmental team day by
day.
Dust emission during construction can cause health problems and reduce the visibility
and therefore safety. The critical areas, such as residential areas will be given priority
to avoid any problem which may arise.
Although the effectiveness of the project and the key benefit of stake holder is the
main priority, this management plan also will provide a safe working environment to
the company employees and contractors on site.
Any comment or recommendations from other parties will be considered and any
changes or action will be carried out as soon as possible to ensure that contaminations
are minimized.
217
‘Constructing a universal passion for
engineering’
6.5. Flora
6.5.1. Existing Biodiversity
The ‘Project Impact Report: Technical report No. 3, (2011)’ prepared by the
Department for Transport, Energy and Infrastructure (DTEI), provides an
understanding of the complexity of the area. It describes the existing area as primarily
under the control of the Parham Association (DTEI), this entails the area consisting of
a variety of tidal flats, dunes swamps and sandy beaches, all of which are protected by
a gently sloped plain. The sloped plain consists of mangroves, chenopod shrubland of
samphire and abundance of Coast Daisy Bush, Coast Beard Heath and Coastal Wattle,
these are all supported by grey non-cracking plastic clays, grey duplex soils, whitish
sands, grey calcareous loams, and greyish calcareous sands (Laut et al 1977). It also
describes the area as having 46.5% of the native vegetation cleared since European
settlement, the area is considered to have moderate native coverage, however
compared to most similar areas in South Australia, it is considered high. An estimated
1,698 ha of land (DEH 2002) is protected within the Port Gawler Conservation Park,
the Fort Glanville Conservation Park and the Torrens Island Conservation Park. It is
estimated that in these areas, 53.5% of vegetation is native (DEH 2002) the areas
vegetation distribution is demonstrated in Appendix F.1 (DTEI). In the area, eleven
vegetation associations were identified, six of which were considered to be native,
these included:
218
‘Constructing a universal passion for
engineering’
The project would heavily impact the area, as both native and non-native flora would
need to be removed, this however is the preferred route for the project as discussed in
the feasibility stage. The area has been heavily developed since European settlement,
this at least allows the project to contribute to existing infrastructure. Vegetation
clearance will lead to permanent modification of the landscape, the mangrove habitat
is also likely to suffer from this. Near the Bolivar Wastewater Treatment Plant, some
trees have been able to reach the classification of ‘significant,’ in relevance to the
Development Act 1993. This marks the vitality of such trees to the local ecosystem
since the implementation of the planting programme 10 years ago, removal of such
trees will incur an increased remediation ratio.
The Southern section of the connector approximately 27.5ha of native vegetation, the
rest of the area for the development will cover already developed land (such as at
Globe Derby Drive) and land that is essentially barren, such as the salt crystallisation
fields and paddocks. While clearing native vegetation the Native Vegetation Act 1991
must be consulted. Removal of significant trees would incur remediation or the
incurrence of a levy in accordance to the Development Act 1993.
The project could produce the following risks to the local ecosystem:
21. Removal of native flora, this can include mangroves, samphire and cotton bush
(detailed in appendix F.1).
22. Introduction of pollutants and foreign flora species.
219
‘Constructing a universal passion for
engineering’
23. Separation of the ecosystems, as they are divided on either side of the
connector.
24. Diversion of waterways, consequently erosion, loss of sea grass and salinity
changes may result.
25. The removal of some trees from the Bolivar plantation.
Vegetation is to be removed in accordance to the Department of planning, Transport
and Infrastructure Vegetation Removal Policy 2011. A replantation area at the Bolivar
Wastewater Treatment Plant, remediation is desirable and will follow the replacement
rates, following the Native Vegetation Act 1991. For all vegetation that cannot be
replanted, a levy is to incur, this will be detailed in the costing section of the EMP.
6.5.3. Mitigation
During construction no flora in the area is unnecessarily removed, the effects are to be
minimised and the correct procedures are to be followed.
26. The clear designation of the construction site and marking of all native flora
and significant trees (Development Act 1993).
27. Reducing vehicle access areas and worker walkways, as to minimise the spread
of weeds and pollutants.
28. Removing all dirt and debris from all earth moving equipment.
29. Chemical spills are to be contained and remedied.
30. All incoming equipment is to be inspected for evidence of foreign plant life.
31. All waste products are to be removed from the site.
32. Not allowing the removal of canoe or ‘scarred’ trees, or any other flora relevant
to indigenous culture, following regulations of the Aboriginal Heritage Act 1988.
33. Constant communication with the National Vegetation Council, to ensure
compliance of new site developments in relation to the National Vegetation Act 1991.
34. Removal policies are to be accordance to the Department of planning,
Transport and Infrastructure Vegetation Removal Policy 2011.
35. Ensuring remediation practices as defined by the Development Act 1993 are
maintained.
36. Maintaining vegetation in close proximity to the road, in compliance to Section
220
‘Constructing a universal passion for
engineering’
26A of the Highways Act 1926 and the Local Government Act 1999.
37. Modify procedures if they interfere with the local environment in an unforseen
adverse manner.
6.6. Fauna
6.6.1. Existing Biodiversity
Over 2008-2009 the Environment and Biodiversity Services (EBS) conduced fauna
surveys of the approximate site area. The surveys included the identification and
population documentation of avifauna (birds), herptofauna (amphibians and reptiles)
and fish. It should be noted that according to the Northern Connector Technical
Report- Fauna, compiled by the DTEI, that the surveys were a significant distance
from the site as the sites location has changed compared to the intended route in 2009.
The full summation of the survey is available in the EMP. Data compiled in the
Northern Connector Technical Report- Fauna (DTEI), is also used throughout this
discussion.
The EBS survey found that in the site area approximately 128 species of avifauna
inhabit the region, both in fresh and saline water conditions.
38. Barker Wetlands North, which hosted 29 freshwater species and 32 saline
species.
39. Magazine Creek Wetlands, which hosted 28 aquatic and 13 terrestrial species.
40. Barker Inlet Wetlands South, which hosted 32 aquatic species.
41. Range Wetlands, which hosted 15 aquatic and 11 terrestrial species.
42. Supratidal samphire shrubland, which hosted 8 species in total, 5 were
terrestrial.
43. North Arm Creek, which hosted 14 aquatic and 12 terrestrial species.
44. Greenfields Wetlands, which hosted a total of 45 species.
45. Bolivar Wastewater Plant, hosted 59 species in total.
The Barker Wetlands was noted to have a total of approximately 5,000 birds in
between 2009 and 2011. While the Bolivar Wastewater Plant had an estimated 9,000
birds. The salt flats however had almost no birds present, this is assumed to be due to
its hyper saline conditions.
221
‘Constructing a universal passion for
engineering’
6.6.2. Mammals
In the EBS surveying area, sixteen mammal species were identified. Ten of which are
native, these mainly consist of varieties of bats and possums. There however is a
minimal population of mammals the area due to the locations heavily developed
landscape. Appendix 1 shows the compiled data from the survey (DTEI). Dolphin
presence is included in the ‘fish’ section following.
The EBS survey identified a total of 34 reptile and five frog species in the area. The
reptile presence during construction is expected as due to several species accustom to
such an environment, the others however are expected to vacate to more desirable
conditions. An abundance of reptiles is also expected to be in the wooded areas of the
site. The amphibious species are expected to adapt to the changing site, inhabiting
drains and waterways. It is also expected that the occurrence of amphibian presence
will change seasonally.
6.6.4. Fish
Under this category is the inclusion of dolphins, although they are technically
mammals. The Port Adelaide River also harbours the Adelaide Dolphin Sanctuary,
which is thought to have 30 Indo-Pacific Bottlenose Dolphins (Tusiops Aduncus)
permanently residing in the area, with another 300 dolphins visiting the sanctuary. The
dolphin’s habitat requires the upkeep of seagrass, mangroves and tidal creeks. It is
vital that the sanctuary remains unhindered by the development.
The most vulnerable locations are the Greenfields Wetlands (Stages 1 and 3), the
Barker Inlet Wetlands, Chapman Creek and the Little Para River Woodlands (DETI).
It is of concern that with construction there will be a loss of habitat; there is likely to
be contaminants entering the habitats; new runoff may cause erosion; fauna may
become disturbed by the increased noise levels and increased human activity; vehicle
strike will cause loss of fauna; and the introduction of weeds to the area, by foreign
soils entering the site. All of these could cause fragmentation in the current ecosystem,
effectively forcing fauna out or genetically isolating populations. The primary area of
concern is the North Arm Creek, where the connector will connect to the Salisbury
Highway, this area hosts roosting areas, some fish species and a comfortable
222
‘Constructing a universal passion for
engineering’
6.6.6. Mitigation
The majority of the development passes through the salt crystallisation fields, which
are essentially barren, this reduces the concern for the developments construction. As
time progresses the fauna in the area should continue to be studied, any indications of
adverse impacts on the varieties and populations of species should be combatted.
Removal of avifauna habitats should be conducted in the winter months of the year,
this will avoid disturbance of migratory bird species and this also will not interfere
with breeding cycles. The construction of artificial wetlands is also recommended, this
will encourage the return of local fauna to the area, hopefully even improving the
regional fauna habitat. Additionally the removal of mangroves and seagrass should be
negated by implementing artificial sanctuary sites to replicate lost areas. These should
be committed to year’s prior development, due to the long periods taken for the
artificial sites to become sufficient habitats. During operation the implementation of
artificial habitats (marine and terrestrial) are expected to compensate for losses in the
development area.
In order to minimise the construction impact on the fauna in the area the following
steps should be followed:
223
‘Constructing a universal passion for
engineering’
further losses.
6.7. Noise
Noise pollution is a form of sound that is generally considered to annoy, distract or
harm other people. The source of noise pollution is generally found to be caused by
machinery, transportation and traffic, construction sounds or live music. High noise
levels have been found to contribute to negative negatively to cardiovascular effects,
cause rises in blood pressure, increase stress and can lead to permanent hearing loss.
The noise issues identified for this project will be as a result of construction noise.
Universal Engineers take responsibility to overcome this problem and will comply
with the required legislative requirements and policies
Post construction the noise pollution will come from traffic noise. Sound barriers are
being designed which will reduce the effect of traffic noise on future residents.
Both of these time periods may have critical effects on the bird sanctuary in the area,
causing interruptions to sleep and mating rituals.
224
‘Constructing a universal passion for
engineering’
6.8. Vibration
Vibration disruptions from construction activities may have a detrimental effect on
local residents and wildlife. The effect of vibration may cause disturbances to building
occupants and could negatively impact building structures.
Residents and buildings within 75m of construction work may perceive vibration
effects due to pile drivers, bulldozers, hydraulic rock breakers and vibratory rollers.
Adaption of low vibration construction processes will be used where possible with
limitations of activities that will produce high vibration levels. Monitoring will be
undertaken to ensure that vibration levels are kept to a minimum and guideline levels
are not exceeded.
Furthermore, it is the responsibility of the contractors to ensure there are proper guides
on the existing bore quality, quantity and drawdown if there is groundwater
construction. It is compulsory for the contractor to consult and seek approval from
DEWNR regarding the extraction rates, licensing requirements, contamination
prevention measures and conditions of extraction for sourcing construction water from
underground water sources if applicable.
6.9.1. Objectives
225
‘Constructing a universal passion for
engineering’
6.10.1. Considerations
69. Excavation
70. Asphalt laying
71. Wood
72. Concrete
73. Metal
74. Management of materials
226
‘Constructing a universal passion for
engineering’
Excavation
Excavated material will be reused as fill for the embankment or other DPTI projects if
it is deemed suitable by the geotechnical team. If the excavated material is found to
be of insufficient quality it will fall under the contaminated soils category.
Asphalt
Asphalt waste will be separated into clean and unclean Asphalt to be transported and
disposed of by RESOURCECO.
Wood
Concrete
Concrete waste should be negligible throughout the project since there are no existing
structures that require demolition. The only source of concrete waste will be excess
from new constructions ie. Bridges, culverts and barriers, this can be kept to a
minimum by taking care during construction and accurately estimating the amount of
material required.
Concrete waste will be separated into clean and unclean concrete to be transported and
disposed of by RESOURCECO.
Metal
227
‘Constructing a universal passion for
engineering’
Metal used throughout the project can generally be reused such as metal drums,
frames, hoardings etc., therefore there is unlikely to be any significant metal waste.
However if any metal waste is generated it will be separated from other materials and
taken to an appropriate recycling facility.
For Vegetation waste, the indigenous plants that must be removed for construction
purposes will be replanted in surrounding wetland. Replanting will contribute to
decreasing the contaminated soil production and help purify the surface water lending
to protection of groundwater sources. General cleared vegetation will be mulched and
recycled for new plant communities created for off-set purposes.
General waste includes: plastics, cardboard, food packaging, food waste, glass and
small items of metal and wood. The procedure for the disposal of these waste
materials shall be as follows.
75. Bins shall be provided to separate waste into recyclable and non-recyclable
items, and will be located at site offices and lunch rooms.
76. Glass, Plastic and paper/cardboard will have separate bins.
77. Clear signage will show the recycling procedure.
78. Non-recyclable items will have a separate bin.
79. Waste will be frequently removed to the appropriate recycling or licensed
landfill facility.
6.10.7. Hazardous Waste
All hazardous waste will be handled based on material safety data sheets provided and
disposed of according to all relevant legislation. Efficient removal from site will be
enforced, with materials being transported to a suitable facility under the appropriate
legislation.
80. Paints
81. Chemicals
82. Fuels
83. Oil/lubricants
228
‘Constructing a universal passion for
engineering’
Acid sulphate soils are naturally occurring waterlogged soils that contain pyrite or
other iron sulphide minerals. Usually this type of soil is found in low lying coastal
areas but can also be found adjacent to some wetlands or near salt lakes. Within the
Northern Connector project area, land has been previously used for salt crystallization.
These soils are harmless if they are not disturbed but if they have been exposed to air
by drainage or excavation, it will react with oxygen and form sulphuric acid or
sulphate minerals. Due to this, structural damage can occur due to formation of rust
which will reduce strength and ductility of the structure. (From Environmental Impact
Statement)
6.10.10. Mitigation
Several key strategies will be followed to minimise the impact of acid sulphate soils,
they are listed in order of preference.
90. Avoidance – the first priority is to reduce the amount of disturbance to the soils
wherever possible, unnecessary or excessive excavation should be strategically
avoided through careful planning and supervision throughout excavation.
91. Neutralisation – this involves neutralising the acidity of the soil through the use
229
‘Constructing a universal passion for
engineering’
of agricultural lime with not less than 95% fine grained carbonate. Treatment stations
will be set up to process and treat the contaminated soil by spreading the acid sulphate
soils in thin layers and spraying the agricultural lime then using mixing machines to
amalgamate the neutralising agent.
92. Storage – neutralisation is a time consuming and costly process so a secondary
option is available for the management of the acid sulphate soils. Strategic reburial of
the contaminated soil is a cost effective method that still minimises the impact of acid
sulphate soils. The contaminated soil can be placed under a permanent water table
before oxidisation occurs, preventing acid formation. Careful planning will be
undertaken when choosing the reburial location, and to reduce the amount of storage
and transportation for the soils to reduce the risk of oxidisation.
6.10.11. Spills during construction
To prevent spills of hazardous materials or liquids that may occur during the project
and lead to contamination of soil the following strategies will be implemented:
93. Inspection – designated personnel will be responsible for the daily inspection
of all hazardous materials on site to ensure proper handling and storage.
94. Maintenance – Storage of hazardous materials will be properly maintained by
users, as well as machinery equipment.
95. Designated refuelling areas – specific areas will be provided for the purpose of
refuelling vehicles and machinery.
96. Fuel and chemical storage areas - specific areas will be provided for the
purpose of storing fuels and hazardous chemicals.
97. Containment and remediation – if spills do occur, immediate action will be
taken according to the hazardous waste guidelines.
6.11. Fire
Universal Engineer’s have a legal obligation under the Workplace health and Safety
Act 1995 to ensure the health and safety of employees and anyone else involved in the
project. This involves ensuring that fire systems are provide onsite and properly
maintained, and proper training and site inductions are undertaken to ensure anyone
involved in this project is fully aware of their fire safety responsibilities. Fire is
identified as a considerable risk in any construction type. This Fire Management Plan
has been prepared to ease the process and appropriately manage the risk.
Fires can occur at any time, especially in hot/summer condition and it is very
important to avoid the threat of a fire and to mitigate any possibility of damage of the
230
‘Constructing a universal passion for
engineering’
98. To ensure an extensive fire risk management process is applied across the
involved area to ensure high level of safety.
99. To make sure that any problems related to fire that arise are instantly and
effectively contained and resolved.
100. To ensure that the company complies with all the regulation and legislation in
relation to fire safety.
101. Aim to provide appropriate training and site induction on fire safety to the
employees and contractor.
102. To avoid fire from occurring in any situation during the construction stage.
103. To limit the loss and damage of property and infrastructure.
104. To prevent or reduce impact of fire on critical environmental.
105. Reduce the incidence of late dry season fires, which are more damaging to
vegetation than early dry season fires
106. Protect archaeological and art sites from damage or destruction from fire.
231
‘Constructing a universal passion for
engineering’
232
‘Constructing a universal passion for
engineering’
233
‘Constructing a universal passion for
engineering’
The North-south corridor project will be constructed on the land of the Kaurna
community. These people are the original inhabitants and occupied this region
between 24,000 and 7,500 years ago. The Kaurna region is now known as the
Adelaide Plains region and is shown in Figure 68.
(Wikimedia 2000)
To acknowledge the traditional custodians of the land, informational signs about the
Kaurna community history will be created to highlight the cultural and indigenous
heritage of the site. A Statement of Acknowledgement by the Kaurna Elders can be
found in Appendix F.1. The statements will be included on all information signs and
these signs will be designed with help from a local elder allocated by the Kaurna
Elders Assembly.
234
‘Constructing a universal passion for
engineering’
Aboriginal sites, objects and human remains (including burials) (Cultural Heritage
Guidelines, Lance 1991, p. 5).
Aboriginal sites, objects and human remains must not be damaged or disturbed during
this project without the authority from the Minister for Aboriginal Affairs under
Section 23 of the Aboriginal Heritage Act, 1988.
Detailed are some examples of what may be discovered throughout the North-south
corridor project:
235
‘Constructing a universal passion for
engineering’
STOP WORK
Call 08 8226 8930
Yes No
236
‘Constructing a universal passion for
engineering’
The CLG will include ten members from the local community. These members will
represent local residents, businesses, council members, community/environmental
groups, and local government.
Any issues or concerns about this project will be discussed by the CLG and the project
team will be informed to help minimise any impacts of the project to the local
community and road users.
A community newsletter has been created to outline the information about the project
to keep to community updated. This newsletter can be found in Appendix G.3.
Meetings are to be held throughout the construction period to provide a forum for the
CLG to raise any issues or concerns from the local residents and business owners. The
project team will be present at all of these meetings to receive feedback from the
community provided to the CLG. These meeting dates are shown in Table 30.
237
‘Constructing a universal passion for
engineering’
The meeting agenda and minutes will be documented at every meeting and posted to
the project website and Facebook page.
A series of street corner meeting will be held to allow to community to express any
concerns to the CLG that can be brought up at the CLG meeting with the project team.
These meetings will be held on Wednesday between 2.00pm – 6.30pm at the
following locations:
124. Wednesday 8 July 2015 – Globe Derby Dr / Trotter Dr, Globe Derby Park
125. Wednesday 5 August 2015 – South Tce / Raffery St, Dry Creek
126. Wednesday 2 September 2015 – Kidman Rd / Vater St, Cavan
127. Wednesday 7 October 2015 – Magazine Rd, Dry Creek
238
‘Constructing a universal passion for
engineering’
The development area is situated approximately 12km north of the CBD in Adelaide’s
northern metropolitan area and the involves three council areas; City of Playford, City
of Salisbury and City of Port Adelaide Enfield. The project will pass through the
suburbs of Virginia, Waterloo Corner, St Kilda, Bolivar, Globe Derby Park, Dry
Creek, Wingfield and Gillman. The project has been divided into three sections for
better planning, design and assessment but the main focus of this detailed design is on
the southern section. This section, a part of the 30 year greater plan, will incorporate
potential mixed used development land (see Figure 70).
Figure 70 - Project Area for Potential Urban Design (Google Maps 2015)
239
‘Constructing a universal passion for
engineering’
128. 30-year Plan for Greater Adelaide highlighted the design area to have the
potential for residential and commercial growth (DPLG 2010).
129. Port Adelaide Enfield (City) Development Plan, consolidated on the 23rd of
September 2010 (DPTI 2011), proposes the zone to be a multifunctional polis.
130. South Australia’s Strategic Plan (Government of South Australia 2007a)
131. Housing and Employment Land Supply Program (Government of South
Australia 2007a)
132. Strategic Infrastructure Plan for South Australia (Government of South
Australia 2005/06-2014/15)
133. Development of Horticulture Industries on the Adelaide Plains- A Blueprint for
2030
134. The Playford Community Plan (City of Playford)
135. Salisbury City Plan 2020 (City of Salisbury)
136. Port Adelaide Enfield City Plan 2010-2016, including vision for 2020 (City of
Port Adelaide Enfield)
137. Heritage SA
138. Planning SA
139. Transport SA
240
‘Constructing a universal passion for
engineering’
The salt crystallisation ponds will be a major land area for future residential and
commercial development. The alignment of the North-South Connector travels
through the middle of the development area and each side of the development area
will be connected via overpasses and turnoff lanes from the North-South Connector.
The development area is located in the City of Salisbury and is bordering the City of
Port Adelaide Enfield with the Barker Inlet Wetlands. Following the Salisbury City
Plan 2020, there are potential development strategy outcomes for residential and
commercial development in the surrounding areas, see Figure 71.
241
‘Constructing a universal passion for
engineering’
As a part of the future planning, there are objectives and targets to meet for the growth
and development for Greater Adelaide. The Plan is driven by 14 principles, as
illustrated on pages 57-59 of the Plan (Department of Planning and Local Government,
2010). These 14 principles are listed below:
Based on the development act for the design area it is essential to consider both
residential and commercial growth. This impacts the design, as it would increase the
future requirement of both a pedestrian/bicycle and vehicle overpass. It would be
highly recommended for two overpasses to be built over the North South Connector
for ease of access and fluid movement of traffic in the development areas. A
conceptual design for approximate locations of the overpasses can be seen in Figure 72.
242
‘Constructing a universal passion for
engineering’
These overpasses will be a 60km/h two way road with a shared path next, including a
safety barrier. The detailed design for the project will not consider the overpass in the
scope of works; however it has been identified as a future requirement.
Between Virginia and Port Adelaide there is currently a 19 km rail freight line which
has 12 level crossings. Not having the new Northern Connector railway, the efficiency
of rail operations would decrease for freight movement and cause increased travel
times and travel costs. There will also be an increase of safety risks at railway level
crossings with increased train and vehicle traffic, which will lead to some level
crossings, especially between Port Adelaide and Dry Creek. These will require future
upgrades to separate the local traffic from the railway.
243
‘Constructing a universal passion for
engineering’
Therefore, without the rail component of the project there will be: (Northern
Connector project team, July 2011)
Railway alignment proposed will be in the same location as described by the DPTI.
The railway line will be elevated by a minimum of 3m from the current level to act as
a rising sea wall barrier and to also keep the railway line from being submerged.
The use of noise barriers will be aligned adjacent to the railway line on either side to
reduce the impact of noise pollution and disturbance to the environmental and urban
areas.
7.5. Construction
7.5.1. Construction Noise
The project area is isolated from residents’ area; therefore the noise pollution from
construction will have minimal impact to residents. The construction operations will
be within the normal EPA’s standard hours between 7am and 7 pm, Monday to Friday.
In case of any future construction within the area after residential development, an
endorsement must be obtained from EPA by the contractors. There must be a detailed
construction noise and vibration Management Plan (CNVMP) in place; this will
ensure section 21.7 of EPA Operational Instruction is met.
From the feasibility study the construction site was proposed to be established
northeast of the design area. Base on the evidences presented from the feasibility
report and through site visits inspections, the proposed location is suitable for the site
compound because it poses minimum environmental impacts. Added to that, there are
244
‘Constructing a universal passion for
engineering’
existing roads would can be used as access points to the site. Figure 73 below shows
the location of the construction site.
245
‘Constructing a universal passion for
engineering’
The area of the construction site is 200 metres square, it will have two access points
by the magazine road, see Figure 74. The construction site office will be located near
the main access point, to ensure it can be found by the visitors and stakeholders
(Figure 75). Also, it is easier for the workers to sign in/out and receive updates before
commencing work. For general functionality of the construction site, the temporary
power supply will be from generators. Water supply will be by water tanks.
In order to reduce the environmental impact on the site, the compound must comply
with the environment Operation Act 1997, and waste will be collected weekly. There
will be two industry bins on site at all times. Mandatory signs will be installed on the
main entrance and around the temporary fences to ensure that the site complies with
246
‘Constructing a universal passion for
engineering’
the OH&S Act, Work Health and Safety Act 2012 (SA) and the Work Health and
Safety Regulations 2012 (SA).
The security measures undertaken will include installation of cameras to ensure the
site is protected and check in scanners to monitor unauthorized entry or exit. A
security contractor will be responsible for implementing the security procedures
including closing and locking of the gate after work hours and night patrol.
247
‘Constructing a universal passion for
engineering’
The noise barrier will span along both sides of the Northern connector and follow the
vertical and horizontal road alignments. The design life of the barrier system is 50
years. The general barrier system layout is shown the Figure 76 below. The area
behind the barrier is to be transformed into a recreational area including a shared
footpath and new vegetation, which will be incorporated into the landscaping design.
The objective of having a vegetation and recreation area is to reduce the psychological
effects of the barrier on the residents and yield a successful aesthetic outcome.
Vegetation also makes a reduction to the overall noise and air pollution.
248
‘Constructing a universal passion for
engineering’
system will be located 7 metres from the roads shoulder to accommodate the swale.
Moreover, the height of the barrier will have to be increase as this will ensures that
noise reduction efficiency of the barrier is not affected.
The barriers will be continuous along the Northern Connector without any gaps
between the panels or on ground level. If there are gaps at the bottom of the barrier
system, it must be filled with concrete, to further increase the barriers effectiveness in
noise reduction ability. Added to that, the barrier is to provide 160 degrees of
protection to each property as shown on Figure 77 below. Currently, there are no plans
of having access through the barrier system to the properties from the highway.
However, for future development it might be needed. As indicated in the right side
image of Figure 77, there must be an overlapping walls 3 times the width of the break
in order to ensure the barrier’s protection is not compromised.
The higher the noise barrier system, the more effective the noise reduction. The
restriction is the benefit-cost ratio for the height of the walls. The elevation of the
project area is relatively flat, making installation relatively easy. The noise barrier will
have a minimum height 3.5 meters in height along the total length, on both sides.
Based on the feasibility study of the design area, the noise barrier is capable of
reducing the noise level by more than 70%. However, the height of the barrier may be
altered depending on the outcome of the community consultations.
The barrier system will be constructed using a series of panels. Each panel will be 4
metres tall and 6 m wide and have a thickness of 150mm. The panels will be
supported by 200UC46 grade steel posts with the depth between the flanges 178mm
(refer to Figure 78(d1)). The spacing between the posts (column) will be calculated to
hold the 6m wide panels including the thickness (tw) of the posts, with a 10 mm
249
‘Constructing a universal passion for
engineering’
tolerance, refer to Table 31. The posts will be restrained by a bored footing with a
depth of 1.9m +/- 200mm, with a diameter of each footing bored hole of 450mm.
Table 31 below shows the tolerances which will be apply during construction phase of
the noise barrier.
250
‘Constructing a universal passion for
engineering’
Colour bond and corten steel were considered as noise barriers but due to the high
levels of salt in the area, concrete will be the preferred material for the barriers. The
noise barrier will be constructed using precast panels and installed with a franna crane,
using a spreader bar to reduce the manual labour needed for the construction. The
panels will be precast made in a workshop and transported to site during the
construction phase. There will be one thousand panels and one thousand and one
(200UC46) posts for this detailed design of the noise barriers.
Graffiti has a high probability of occurring and to minimise the maintenance cost, the
barrier system will be painted with an anti-graffiti coating in a dark grey colour. The
anti-graffiti coating prevents paint for bonding to the surface and saves cost in clean
up as well. This colour is more of a neutral tone to blend in with the surrounding
landscape. To aid the ease of clean up, the panels facing towards urban area will have
a smooth surface. This is to reduce the amount of time that would be required for
clean up if possible.
Stepping between each panel section for the noise barrier must be avoided. The height
of the barrier is to be consistent and no less than the minimum height. The top edges
are to be rounded in order to reduce the chance of people climbing the wall and this
will also assistance in the aesthetics. The posts will be coated with anti – corrosion
paint and anti-graffiti paint, to increase the lifespan and lower maintenance. The base
of the barrier must follow the ground level. If any gaps are formed between the panel
and ground, they must be filled with adequate materials, such as soil or concrete if
needed. Drainage points along the northern connector are being design by the
geotechnical department. The ends of the barrier system will have an arc formed in the
panel to introduce and end the noise barrier wall where needed. Figure 80 shows the
design of the noise barrier and Figure 81 shows the barrier alignment.
251
‘Constructing a universal passion for
engineering’
252
‘Constructing a universal passion for
engineering’
The panels cost was calculated by consulting Bianco precast, they provided the quota
for the panels and also the transportation charges. The costs of the steel and concrete
were calculated through the Australia Construction Handbook (Rawlinsons, 2015), see
Appendix G.5.
A shared path for pedestrians and cyclists will be developed on the eastern side of the
highway. The shared path is used for recreational and commuter purposes, the path
stretch adjacent to the highway, with access points for surrounding residents. The
shared path features different public facilities, such as lighting, signage, hand rails,
markings, etc. and will provide a safe and reliable pathway for the public. In addition,
the materials used for construction of the shared path and public facilities are aim to
be cost effective, environmental friendly and sustainable.
The shared path is designed to be a recreational pathway for public use, and will strive
to be a relaxing and enjoyable environment. The alignment of the shared path is
designed to follow the northern connector shown below (Figure 82), the black line
represents the shared path alignment.
253
‘Constructing a universal passion for
engineering’
254
‘Constructing a universal passion for
engineering’
Figure 83 - Shared Path Alignment continue (Blue – Little Para bike trail)(Google Map
2015)
In Figure 83 shown above, the shared path alignment is designed to connect to the
existing little para bike trail as shown in Figure 83 represented as the blue line.
In this alignment, the shared path is constructed on the salt pans, the noise barrier will
separate the highway and the shared path. The surrounding landscape of the shared
path will be revegetated for aesthetic and environmental purposes, including
establishments of wetland like environments to be integrated into the surrounding
environment.
In the future, the exiting salt pans are expected to reform as a residential area in line
with the 30 year Greater Adelaide Plan. Therefore multiple access points could be
designed to link between the surrounding residents area to the shared path. At the
moment, the only access point is from little para bike trail from the north side.
There are few items needed for the design of the shared path, which includes
horizontal curvature, gradient, and width of paths, drainage, and clearance.
255
‘Constructing a universal passion for
engineering’
The shared path will have a flat surface, and it is for commuting and recreational use.
The maximum design speed for cyclist is 20km/h, and therefore according to the table
7.1, section 7.3, Guide to Road Design Part 6A: Pedestrian and Cyclist paths, the
minimum radius for horizontal curvature is 10 meters when the design speed is
20km/h (Austroads 2009). The horizontal curvature would only be designed for the
section of the shared path which connects into the little para bikeway to the north, and
the shared path that enters the wetlands towards the south.
7.7.5. Gradient
The shared path is a flat surface; therefore the expected gradients for the path will be
less than 3%.
The location and the dimension of the shared path is important, because the shared
path is designed along the highway, and safety is paramount. According to the table
7.4, section 7.5.3, Guide to Road Design Part 6A: Pedestrian and Cyclist paths, it
states that the desirable shared path minimum width should be 3 meter as DPTI stated,
also cost effective as cyclist volumes will be low (Austroads 2009).
All standards follow AustRoads Guide to Road Design - Part 6A, Pedestrian and
Cyclist Paths (2009). For crossfall and drainage he shared paths drainage gradient will
be designed to prevent any bodies of water pooling on the surface and keep debris
from being washed onto the path. Since the surrounding area of shared path is flat, the
straight section of the path will have crowning to shed the water to the sides of the
path. The normal cross fall of pavement on a straight alignment will be 2% to 4% on a
sealed surface. This design aims to be economic, low maintenance and aesthetically
fit into surrounding environment. The path will at least be elevated above the adjacent
ground with the path shoulders meeting the paths surface level. The paths shoulders
will have a suitable crossfall flatter than 1 in 8.
256
‘Constructing a universal passion for
engineering’
7.7.8. Clearance
The cyclist minimum clearance height is 2.2 meters high as described in section 4.2.2,
Road design Part 6A: Pedestrian and Cyclist paths (Austroads 2009), the clearance for
the cyclist should be a minimum 0.3 meters for the bicycle design envelope, therefore
any tree branches less than 2.5 meters vertically above the pathway should be trimmed
off.
The salt pans area would not have this issue as there is no vegetation, however, the
Dry Creek wetlands near Magazine Road (Figure 84) could potentially have trees
branches lower than 2.5 meters, and the clearance clause will apply, and the designed
clearance for pedestrians and cyclists will be 0.5 metres.
The safest distance from the path to the highway shoulder will be at least 3.5 meters.
In addition, a series of safety sound barriers will be constructed on the eastern side of
the highway to separate the shared path. The distance from the highway shoulder to
the sound barrier is 7 meters; therefore the safety distance from the highway shoulder
to shared path is met.
257
‘Constructing a universal passion for
engineering’
Figure 85 - Asphalt paving Mike Tur Tur Bikeway, Guanghao Li, 6th May 2015
There are different types of lane markings for the shared path, such as broken line and
continuous line. Continuous lines will be painted along curves, and at corners of the
258
‘Constructing a universal passion for
engineering’
pathway (Figure 86) to restrain and inform cyclists and pedestrians from overtaking.
The broken line painted along the straight section of the pathway (Figure 87) allows
cyclists to overtake other users when the opposite lane is clear and safe to do so.
Figure 86 - Continuous line marking.Linear Park, Guanghao Li, 6th May 2015
259
‘Constructing a universal passion for
engineering’
Figure 87 - Broken line markings.Mike Tur Tur Bikeway, Guanghao Li, 6th May 2015
In the future, access points will be established along the alignment for entry and exit
points to the surrounding suburubs. Giveway markings are required at these
interescetions to inform users to give way on the shared path. Giveway markings are
shown in Figure 88.
Figure 88 - Give way marking. Mike Tur Tur Bikeway, Guanghao Li, 6th May 2015
260
‘Constructing a universal passion for
engineering’
The Austroads Guide Part 6A and Table 2 of AS/NZS 1158.3.1 outline the lighting
categories for pathways and cycle ways. This path will also be a commuter’s path,
lighting after dark will provide a safe route and encourage more people to use the path
during dark hours. The lighting system aims to be sustainable and environmentally
friendly. Each light pole will be independent and self-sustainable by storing solar
energy during the day into batteries for use during the night. The lighting levels are
based on the objective of allowing the users to see other users and potential hazards.
Rider visibility is mandatory and it is illegal not to have a flashing or steady white
light on the front and red on the rear that is clearly visible from at least 200m (DPTI
2014). The lights used in the light poles, have to comply with the standards and
provide enough output lumens for the path. Urban pedestrian areas require 20 lux to
as low as 3 to 5 lux and the uniformity of lightings is also highly important. The ratio
of average illumination to the minimum illumination should be no greater than 6:1 for
low traffic areas. Therefore lighting on the path will be adequate to have the light
poles spaced out every 30m with the appropriate lumens for lighting. This will be a
more cost effective solution instead of installing the light poles every 12m as
previously required to provide a safe lit path for all users during the night. A
comparable example of how the light pole will look like from the linear park is shown
in Figure 89.
261
‘Constructing a universal passion for
engineering’
Figure 89 - Solar powered lighting.Linear Park, Guanghao Li, 13th May 2015
7.9.2. Fencing
Fencing is to be installed where necessary along the shared path to ensure all users
safety. A fence will be needed to have a physical barrier of separation to a location or
place. Fences will have to be installed in areas in the wetlands near Magazine Road to
separate users falling into large water bodies. Extra fencing will be required in future
plans for perimeters of playgrounds and possibly near future suburban development.
The design of fencing will follow the materials shown in Figure 90, which will include
a metal finished handrail with timber poles strung with stainless steel wire. This
combination will give a great impression for the public, exhibiting a modern design
with natural materials such as timber.
262
‘Constructing a universal passion for
engineering’
Figure 90 - Selected fencing design.Esplanade, West Beach, Guanghao Li, 13th May 2015
7.9.3. Signage
Signage is another essential facility for a shared path, and will be placed in
appropriate locations to inform pathway users. The signage will include give-way
signs, pedestrian and cyclist signs, direction signs, information signs, warning signs,
etc.
263
‘Constructing a universal passion for
engineering’
264
‘Constructing a universal passion for
engineering’
Figure 93 - Free standing give way sign. Mike Tur Tur Bikeway, Guanghao Li, 13th May
2015
The Northern Connector information signs will be based on the signs located in Linear
Park. These information signs will feature current location, distances, drinking water
tap, toilet locations, resting areas, etc. shown in Figure 94.
265
‘Constructing a universal passion for
engineering’
Figure 94 - Information sign Linear Park, Guanghao Li, 13th May 2015
Rest areas and benches will be placed along the shared path for users during their
activities. Bench chairs are to be placed along the pathway every 1 kilometer, bike
racks are also recommended to install beside each bench chair. See Figure 95 for an
example of a bench and bike racks.
266
‘Constructing a universal passion for
engineering’
Figure 95 - Example bench chair with bike racks. Glenelg, Guanghao Li, 6th May 2015
Tables, chairs and barbeque facilities are to installed under shelters near access points
to provide picnic areas for public use, and the shelter can alternatively be used during
rain periods for cyclists and pedestrians (Figure 96). These facilities will be installed
once residential development has occurred.
A common public toilet block is to be placed near the future picnic areas. These toilet
blocks will be connected to the mains power and sewer lines for the new residential
267
‘Constructing a universal passion for
engineering’
suburbs for low maintenance. These facilities will be installed once residential
development is being developed. See Figure 97 for an example of a toilet block.
(Editor 5/8/07)
The filtered drinking water fountain is shown in Figure 98, provides a water outlet for
water bottle refills and a drinking fountain outlet at the front. The drinking water refill
station will be placed every 2 km along the shared path.
268
‘Constructing a universal passion for
engineering’
Figure 98 - Drinking water fountain. Glenelg, Guanghao Li, 6th May 2015
To reduce the environmental impact of recreational use along the shared path, bins
and dog excrement bag dispensers will be placed every 2km along the shared path and
near seated or picnic areas to help reduce litter and encourage use. The bins are to be
secured to prevent litter spillage and vandalism. An example is shown in Figure 99.
269
‘Constructing a universal passion for
engineering’
Figure 99 - Wheelie bin. Linear Park Guanghao Li, 13th May 2015
270
‘Constructing a universal passion for
engineering’
7.11. Landscaping
Landscaping is important to allow people to interact with the place and adds a visual
feature of the area to live and visit. Each side of the North South connector road and
shared path will be revegetated with different plants that will be incorporated into the
surrounding wetlands environment. In addition, educational signage will be placed at
different location to provide information of the plants, wetlands, areas history, etc.
The existing landscaping includes the Northern Arm Creek mangrove, wetlands at
Magazine Road, and Salt crystallization pans. However, due to the Northern
Connector (South) alignment selection, the highway is constructed at the centre of the
salt pans and the existing landscaping will have to be modified. The landscaping
section is divided into 3 sections, which have been labelled on the Figure 100 below.
271
‘Constructing a universal passion for
engineering’
Section 1, at the start of the Northern Connector heading north, connects to the South
Road Super way and will be crossing the wetlands from Northern Arm Creek
mangrove. This is the first section of current landscaping that will be modified
surrounding the road and shared path. Following will be section 2 and 3 to undergo
revegetation.
A simple revegetation map is illustrated in the Figure 101. The green colour boxes
indicated the areas that needs to revegetation to incorporate into the surrounding
environment.
The landscaping design will included artificial ponds, flora revegetation, educational
signage and visual markers.
7.11.2.2. Flora
Flora plays an important role in the landscaping for the northern connector because of
the future development of the suburb, the salt pans have to be sustainable,
environmentally friendly and inhabitable. Different kinds of plants will be used in the
revegetation program; these include native plants and non-native plants, terrestrial
vegetation and aquatic flora. There are 12 types of vegetation that will be used in the
Northern Connector, including 7 native and 5 non-natives. Some of these types are:
A variety of these plants will be selected for the revegetation program and planted
throughout the entire length of the corridor. The landscaping of the wetlands will be
designed to continue the Greenfield Wetlands habitat is shown in Figure 103.
Cottonbush (BlogSpot)
Since the Northern Connector is constructed in the middle of the salt pans, Cotton
bush and Nitre Bush are the most suitable plants for this area and will be selected
plants for the revegetation program.
There are five types of aquatic flora which are identified by the environmental team,
these include:
167. Samphire
168. Grey Mangrove
169. Common Reed
170. Flat-sedge
171. Water Buttons
172. Samphire, Common Reed, Grey Mangrove, Flat-sedge and Water Buttons will
be selected for the revegetation program, see Table 33.
Table 33: Aquatic Flora
Flora and Fauna species In front of pond and eastern side of the 4
information shared path
7.12.1. Sculpture
A sculpture will be placed at the start of the northern end of the highway. The
sculpture design will be open for a future competition for the community and for local
artist to create a sculpture for the area. The competition will be conducted by the local
council once the alignment has been completed.
7.12.2. Playgrounds
As a part of the residential development, playgrounds and picnic areas will be further
developed as a stage 2 for the urban design shared path and landscaping. Areas
situated along the path will be recognised as suitable locations for the playgrounds in
relations to the design of the suburbs when they are being planned and developed.
Councils will contact the suppliers and manufacturers to find suitable playgrounds
which are both safe and suitable for the uses.
Project
Client
Project Start
Project Finish
Department Members Hourly Rate Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Hours Worked Sub Total Amount
Project Managers $240.00 5 12 12 13 24 28 94 $22,560.00
Assistant Project Manager $220.00 4 12 5 7 18 27 73 $16,060.00
Transport Leader $180.00 11 13 13 9 20 66 $11,880.00
Transport 1 $150.00 3 12 16 20 10 61 $9,150.00
Transport 2 $150.00 3 6 13 13 7 42 $6,300.00
Transport 3 $150.00 7 10 13 13 14 57 $8,550.00
Transport 4 $150.00 4 8 5 5 10 32 $4,800.00
Urban Design Leader $180.00 6 6.5 8 10 15 10.5 56 $10,080.00
Urban Design 1 $150.00 15 15 20 20 25 95 $14,250.00
Urban Design 2 $150.00 19 17 19 17 6 78 $11,700.00
Urban Design 3 $150.00 15 12 14 17 12 70 $10,500.00
Environmental Leader $180.00 5 5 8 8 11.5 9 46.5 $8,370.00
Environmental 1 $150.00 6 26 8 11 51 $7,650.00
Environmental 2 $150.00 5 8 4 11 23 51 $7,650.00
Environmental 3 $150.00 6 9 12.5 10 37.5 $5,625.00
Environmental 4 $150.00 5 5 15 15 15 55 $8,250.00
Geotechnical Leader $180.00 15 15 15 22 21 88 $15,840.00
Geotechnical 1 $150.00 15 15 16 20 21 87 $13,050.00
284
‘Constructing a universal passion for
engineering’
Geotechnical 2 $150.00 8 10 10 12 18 58 $8,700.00
Water Leader $180.00 5 9 6 12 22 7 61 $10,980.00
Water 1 $150.00 15 15 15 15 60 $9,000.00
Water 2 $150.00 0 $0.00
Water 3 $150.00 10 10 10 10 10 50 $7,500.00
Structural Leader $180.00 15 16 26 33 90 $16,200.00
Structural Leader $180.00 10 12 26 24 72 $12,960.00
Structural 1 $150.00 15 15 6 36 $5,400.00
Structural 2 $150.00 16 20 20 20 16 92 $13,800.00
Structural 3 $150.00 15 15 15 28 73 $10,950.00
Structural 4 $150.00 11 13 26 24 74 $11,100.00
Structural 5 $150.00 7 12 16 35 $5,250.00
TOTAL HOURS TOTAL FEE
1841 $304,105.00
DETAILED DESIGN STAGE: NORTH-SOUTH CORRIDOR – NORTHERN CONNECTOR, STAGE 1 (SOUTH) - JUNE 2015 285
‘Constructing a universal passion for
engineering’
Appendix A3
In consultation with Desmond Khoo from DPTI, and drawing on his expert
knowledge of the project, it was found that some sections needed further
considerations. An investigation will be made into the following items below.
Transport
- The safety phones need to be located on either side of the road and more often.
Water and Geotechnical
- The design of a swale may create a large footprint with future developments in
the area. A new water drainage system may have to be investigated in the future.
- The sea wall design (future consideration) might not be practical as a structure
by itself. The alignment was chosen to ensure that as much land as possible isn’t
affected by sea level rise. In consultation with Desmond it was suggest that the road
alignment and the fact that it is slightly raised from the salt pans might be the best
solution.
- Consideration of bore log data, the other bore logs need to be analysed in order
to obtain a stronger bore log analysis.
Structural
- In the design methodology a cofferdam has been suggested to restrict river flow
and create a dry platform for construction. Through Desmond it has been suggested
that this is too expensive and an alternate method needs to be sought. Currently DPTI
are also aiming to come up with a solution to this problem.
- There are also environmental issues with constructing on a salt pan. Sulphuric
acid can occur through oxidisation of the sulphate soils, the pH level is 2 for sulphuric
acid, which is incredibly corrosive, and this can cause materials to be affected. Section
5.15.4 discusses acid protection on the structure; however an investigation will be
conducted with the Environmental department to investigate acid protection during the
construction phase.
286
‘Constructing a universal passion for
engineering’
- The construction noise will affect the horses in the Globe Derby park area from
noise and vibration impacts, Section 6.7 and 6.8 discuss noise and vibration only on
residential locations.
Urban Design
- The bike path along the highway has to also be reconsidered. There were a
number of amenities mentioned in the report, however due to the location of the path;
they will probably not be needed. The path is not near high density housing and will
most probably only attract a small number of cycling enthusiasts. If a development
does not currently exist, then an in depth investigation should not be considered.
- Possible solutions to beautify the region such as lagoons, sculptures etc that
have been discussed. However they fall outside of DPTI’s scope for the project. This
will most probably be considered by a developer for the area in the future.
- Due to the location of the site, noise barriers will not have to be considered by
DPTI. This is due to the project being located away from residential housing. If
housing occurs on the site in the future than it is the responsibility of the developer to
implement.
- The Community Liaison Group needs to be redefined in terms of its available
times, need weekdays, weekends and morning/night etc.
Environmental
Appendix B Transport
288
‘Constructing a universal passion for
engineering’
Appendix C Geotechnical
Water Properties
----------------
Unit weight of water: 9.810 Unit weight of water/medium above ground:
9.810
-------------
-10.00 19.00 0.00 19.00 30.00 21.00 67.00 21.00
97.00 19.00
100.00 19.00
Failure Surface
---------------
Initial circular surface for critical search defined by: XL,XR,R
Intersects: XL: 0.00 YL: 19.00 XR: 30.00 YR: 21.00
Variable Restraints
-------------------
Parameter descriptor: XL XR R
Range of variation: 17.00 13.00 10.00
Trial positions within range: 10 10 10
–––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––
–––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––
There were: 1001 successful analyses from a total of 1001 trial circles
——————————————————————————————————
————————
300
‘Constructing a universal passion for
engineering’
Appendix D Stormwater
301
‘Constructing a universal passion for
engineering’
Appendix E Structural
Appendix F Environment
Appendix F.1 – Vegetation Map
"We would like to acknowledge this land that we meet on today is the traditional lands
of the Kaurna people and that we respect their spiritual relationship with their country.
We also acknowledge the Kaurna people as the custodians of the greater Adelaide
region and that their cultural and heritage beliefs are still important to the living
Kaurna people today."
The following text is suggested for use/adaptation for events and gatherings that take
place outside of the metropolitan area2.
"We acknowledge and respect the traditional custodians whose ancestral lands we are
meeting upon here today. We acknowledge the deep feelings of attachment and
relationship of Aboriginal peoples to country. We also pay respects to the cultural
authority of Aboriginal peoples visiting/attending from other areas of South
Australia/Australia present here."
The statements above will be included on all information signs to acknowledge the
traditional custodians of the land.
Stone artefacts
Stone artefacts are classified as any stone tools and waste material produced during
the manufacture of these tools. These artefacts are the most common surviving
artefacts located in Adelaide and the Kaurna area. These stone artefacts were made
from flint, quartz, chert, silcrete and volcanic rocks, see Figure 105 and Figure 106.
Mounds
Figure 107 - Aboriginal habitation mound, Riverland, Murray Valley (Government of South
Australia 2015)
Hearths contain the remains of ancient campfires and earth ovens. Fire-shattered
stones and baked clay lumps were often used to cook food and can be exposed by
erosion. In some floodplains of the State’s north, shortages of stone led to the use of
other materials including pieces of termite mounds, see Figure 108.
Tool-making workshops
These workshops contain flaking debris from making stone tools and are often found
in areas where raw stone is abundant. The debris is the result of fragments of stones
being broken off during the tool-making process, see Figure 109.
Figure 109 - Grinding stone workshop with broken grinding stone (Australian Cultural
Heritage Management 2011)
Dwellings
Dwelling made by the Kaurna people were often built from tree branches and sticks.
The most common structure were semi-circular windbreaks, which were used for one
or two night then abandoned. These structures are rare and they were quickly blown
away, burnt or decayed. More permanent structure has consisted of wooden frames
and the remains of these are more common, see Figure 110.
Water sources
beds or along bodies of water to supply water. Natural rock hollows have also been
known to be enlarged to their capacity to collect water. These wells and rock hollows
were often covered with stones or branches to protect against evaporation or animals
fouling the water, see Figure 111.
Scarred trees
Bark from trees was used by the Aboriginal people for most of their implements, tools
and weapons. Removal of bark and timber has led to scars on trees that can remain for
years to come. The most prominent scaring of a tree is from the removal of bark to
form a canoe. Although these tree are uncommon in the project area there may be
some discovered as there is a body of water near the site. Scars were also formed from
toeholds used to climb trees to capture animals or gather eggs and honey see Figure
112.
Rock art
Aboriginal rock art can be found throughout all of Australia and are one of the most
common artefacts discovered. This art is mainly found in the sheltered walls of caves,
rock overhangs, in rock shelters and on the sheltered faces of large boulders, see
Figure 113.
Burials
Burial is the most common method of disposal of the dead in South Australia by the
Aboriginal people. Shallow graves covered by logs or rocks to mark the grave and
keep animals out are the most common burial. It is of upmost importance not to
disturb burial sites and to use the action plan explained in this report, see Figure 69 -
Action Plan for Indigenous Artefacts and Sites, in 7.1.4 Action Plan.
Parameters
UDL = 7.75 kN/m from the wind load calculations
Cover = 25 mm
Actual capacity
Where
L = 4000mm
Based on the structural calculations, the current design of the noise barrier satisfy the
structural designs.
Pavement Marking Florescent Paint Full distance 18/ meter 5 kilometres 90000
317
‘Constructing a universal passion for
engineering’
DETAILED DESIGN STAGE: NORTH-SOUTH CORRIDOR – NORTHERN CONNECTOR, STAGE 1 (SOUTH) - JUNE 2015 318
‘Constructing a universal passion for
engineering’
319
‘Constructing a universal passion for
engineering’
8. References -
Transport
1. Road signs- Specifications, 2001, Australian Standard, AS 1743-2001,
Standards Australia international, Retrieved 23 May 2015.
2. Part 2: Traffic control devices for general use, ‘Manual of uniform traffic
control devices’, 2009, Australian Standard, AS 1742.2-2009, Standards Australia
international, Retrieved 13 May 2015.
3. Speed Limits. Government of South Australia, Department of Planning,
Transport and Infrastructure. Retrieved 24 May 2015.
8.1. Geotechnical
1. AUSTROADS 2009, Guide to pavement technology, 2nd edn, Austroads, Sydney.
2. DPTI 2015, Guide to bikeway, pavement design construction & maintenance for
South Australia, 2nd edn, DPTI, South Australia.
3. DTEI 2010, Northern connector planning study-Additional geotechnical investigation,
DTEI , South Australia.
4. AUSTROADS 1992, AUSTROADS Bridge Design Code, 1st edn, Austroads, Sydney.
5. Australian Standards 2002, Earth-retaining structures, AS 4678-2002, Standards
Australia, Sydney.
6. Das, BM 2007, Theoretical foundation engineering, J. Ross Pub, Ft. Lauderdale, FL.
7. UNSW 2007, Soil moisture classification, terraGIS, viewed on 07/06/2015,
8. <http://www.terragis.bees.unsw.edu.au/terraGIS_soil/sp_water-
soil_moisture_classification.html>.
8.2. Water
1. Australian Online Coastal Information, Australian Government Geoscience Australia,
Adelaide region viewed on 01/06/2015
<http://www.ozcoasts.gov.au/climate/Map_images/Adelaide/mapLevel2.jsp>
2. Government of South Australia, Australian Online Coastal Information, Adelaide
Region, viewed on 01/06/2015,
<http://www.ozcoasts.gov.au/climate/Map_images/Adelaide/mapLevel2.jsp>
8.3. Structural
1. American Association of State Highway and Transportation Officials (AASHTO),
2007, Bridge construction practices using incremental launching, Viewed 25/05/2015
<https://www.google.com.au/webhp?sourceid=chrome-
instant&rlz=1C1YBKB_enAU508AU511&ion=1&espv=2&ie=UTF-
8#q=bridge%20construction%20practices%20using%20incremental%20launching>
2. Concrete Experts International, 2006, Acid attack on Concrete, Concrete Experts
International, Viewed 03/06/2015 <http://www.concrete-experts.com/pages/acid.htm>
3. Malik, A 2013, Acid attack on concrete, University of Alberta, Viewed 03/06/2015
<http://www.slideshare.net/AyazWaseem/acid-attack-on-concrete>
4. EPIREZ, 2015, Acid Resistant Epoxy Binder (133AR), ITW Polymers & Fuilds,
Viewed 03/06/2015 <http://www.itwpf.com.au/epirez/product.aspx?productid=44>
5. New York State Department of Transportation 2008, Fundamentals of Bridge
Maintenance and Inspection, NYSDOT Maintenance Division, viewed 3 June 2015,
<ftp://ftp.odot.state.or.us/Bridge/Maintenance/Fundamentals%20of%20Bridge%20Maintena
nce%20and%20Inspection.pdf >
6. Space Gass, 2015, ‘Structural Engineering Software’, viewed 7 June 2015,
<http://spacegass.com/about/index.htm>
7. The Government of South Australia, 2015, ‘The 30 year plan for greater Adelaide’,
viewed 25 May 2015, <http://www.sa.gov.au/topics/housing-property-and-land/building-
and-development/land-supply-and-planning-system/the-planning-strategy-for-south-
australia/the-30-year-plan-for-greater-adelaide>
8. Foster, S. J. Et Al. 2007. Reinforced Concrete Basics (2E): Analysis and Design of
Reinforced Concrete Structures. Pearson Original Edition. Pearson Prentice Hall
8.4. Urban
1. Aboriginal & Torres Strait Islander Heritage Protection Act 1984 (Cwth)
2. ACHM (2004). Archaeological Excavation and Reburial of Human Skeletal
Remains Unearthed during Development Works. Report prepared for City of
Salisbury, May 2004
3. ACHM (2003). Remediation of a Traditional Kaurna Burial at Mawson Lakes,
Adelaide, South Australia. Report prepared for Land Management Corporation, July
2003
4. Anon. 1985 The Heritage of South Australia and Northern Territory: The
Illustrated Register of the National Estate. Macmillan in association with the
Australian Heritage Commission: South Melbourne.
5. Australian Cultural Heritage Management 2011, Desktop report of Aboriginal
and European heritage, viewed 28 May 2015,
<http://www.dpti.sa.gov.au/__data/assets/pdf_file/0004/99166/Desktop_Report_of_A
boriginal_and_European_Cultural_Heritage_for_the_Andrews_Road_Investigation,_
March_2011_Australian_Cultural_Heritage_Management_Pty_Ltd.pdf>
Detailed Design Stage: North-South Corridor – Northern Connector, Stage
1 (South) - June 2015 321
‘Constructing a universal passion for
engineering’
http://www.salisbury.sa.gov.au/Council/About_Our_City/Sustainable_Futures_Salisb
ury_City_Plan_2020. Viewed 05 June 2015.
29. Bicycle Network 2015, Trial of signage on Nicholson Street path, Inner: Parks
and Gardens in the City of Melbourne. Available at:
https://www.bicyclenetwork.com.au/media/vanilla_content/images/nicholson%20stree
t%20path%203.jpg. Viewed 05 June 2015
30. Editor5807, Own work, File:Yarmouth Common public toilets.JPG. Available
at:
http://upload.wikimedia.org/wikipedia/commons/5/5c/Yarmouth_Common_public_toil
ets.JPG. Viewed 05 June 2015.
31. Google Map 2015, Salt Crystallization Pans, Adelaide, South Australia,
Imagery ©2015 Google, Scale Undetermined, ‘Google Maps’, Viewed on
5/June/2015, https://www.google.com.au/maps/@-
34.8158629,138.5927325,9202m/data=!3m1!1e3
32. Wagland Landscaping 2012, Pond & Lake Excavation, Wagland Landscaping
Design & Construction. Available at:
http://www.waglandlandscaping.co.uk/images/wildlife_pond-500x325px.jpg. Viewed
05 June 2015.
33. Weekend NOTES 2015, Top Free Things to do in Adelaide- October 2014,
Weekend NOTES. Available at: http://www.weekendnotes.com/im/001/04/free-things-
to-do-in-adelaide-fun-things-to-do-in-36023121.jpg. Viewed 05 June 2015
34. M.Fagg, Eucalyptus camaldulensis, WATER for a HEALTHY COUNTTRY.
Available at: http://www.cpbr.gov.au/cpbr/WfHC/Eucalyptus-
camaldulensis/Eucalyptus-camaldulensis-tree-photo.html. Viewed 05 June 2015
35. BlogSpot, toowoombaplants2008, Natives of the Region suitable for Gardens,
Toowoomba Plants. Available at:
http://2.bp.blogspot.com/_2auPgkwYYKY/TPh0qWNKTcI/AAAAAAAABcQ/O4fytAfiq
Do/s1600/01%2BGomphocarpus%2Bphysocarpus%2BBalloon%2Bcottonbush%2BG
oombungee%2BDec10.jpg. Viewed 05 June 2015
36. The Atlas Of Living Australia, Chenopodium nitrariaceum (F.Muell.) F.Muell.
ex Benth., Australina Species. Available at:
http://bie.ala.org.au/repo/1034/124/1240232/raw.jpg. Viewed 05 June 2015
37. John, June 2012, Scallops, Samphire & Dorset Pancetta, West Dorset Foodie.
Available at: http://www.westdorsetfoodie.co.uk/wp-
content/uploads/2012/06/DSCN0021.jpg. Viewed 05 June 2015
38. Department of Agriculture and Fisheries, Common mangroves, Grey
mangrove. Available at:
https://www.daf.qld.gov.au/__data/assets/image/0020/57215/avicenna-tree.jpg.
Viewed 05 June 2015
39. University of Connecticut, Common Reed, Phragmites australis, Coastal
Detailed Design Stage: North-South Corridor – Northern Connector, Stage
1 (South) - June 2015 324
‘Constructing a universal passion for
engineering’
8.5. Environment
1. West Ryde Railway Station Development WASTE MANAGEMENT & RE-USE
PLAN CONSTRUCTION 31 January 2007. [ONLINE] Available at:
http://www.planning.nsw.gov.au/asp/pdf/05_0130_westryde_appk_waste_managemen
t_plan_construction.pdf. [Accessed 27 May 2015].
2. Nazech, Elkhobar and Zaldi, Denanda and Trigunarsyah, Bambang (2008)
3. Identification of construction waste in road and highway construction projects.
In: The Eleventh East Asia-Pacific Conference on Engineering and Construction, 19-
21 November 2008, Taipei, Taiwan.
4. ResourceCo - Disposal. 2015. ResourceCo - Disposal. [ONLINE] Available at:
http://www.resourceco.com.au/products-services/resourceco/pricing/disposal.html.
[Accessed 25 July 2015].
5. Acid Sulphate Soils Guideline - treatment and management. 2015. Acid Sulphate
Soils Guideline - treatment and management. [ONLINE] Available at:
http://www.wicc.southcoastwa.org.au/reports/ass2/ass2b.html. [Accessed 25 July
2015].
6. First Aid Kits - 1st Aid Kits - Fire Trader Australia Pty Ltd. 2015. First Aid Kits
- 1st Aid Kits - Fire Trader Australia Pty Ltd. [ONLINE] Available at:
http://www.firetraderstore.com.au/first-aid-kits---1st-aid-kits.html. [Accessed 03 June
2015].
7. DEH. 2002. Provisional list of state threatened ecosystems. Department for
Environment and Heritage, Adelaide.
8. KBR. 2011. Northern Connector Technical Report. Fauna. Department for
Transport, Energy and Infrastructure, SA.
9. AECOM Australia 2011. Northern Connector Technical Report. Noise and
Vibration. Department for Transport, Energy and Infrastructure.
10. DPTI. 2011. Vegetation Removal Policy. Department for Planning, Transport
and Infrastructure, SA.
Detailed Design Stage: North-South Corridor – Northern Connector, Stage
1 (South) - June 2015 325
‘Constructing a universal passion for
engineering’
11. DTEI 2011. Northern Connector Technical Report- Flora, Department for
Transport, Energy and Infrastructure, Walkerville SA.
12. Laut, P. Heyligers, P.C. Keig, G. Loffler, E., Margules, C. Scott, R. M. and
Sullivan, M. E. 1977. Environments of South Australia. CSIRO, Canberra.
13. (AECOM and KBR) AECOM Australia Ptu Ltd. KBR Pty Ltd. 2009. The Effect
of Noise on Wetland Birds: Barker Inlet Wetlands. Prepared for DETI Adelaide.