Professional Documents
Culture Documents
(APPELLATE JURISDICTION)
CIVIL APPLICATION NO. 03-2-11/2018 (B)
BETWEEN
AND
Between
And
HEARD TOGETHER
1
IN THE FEDERAL COURT OF MALAYSIA
(APPELLATE JURISDICTION)
CIVIL APPLICATION NO. 02(i)-104-11/2018 (B)
BETWEEN
AND
Between
And
2
Between
And
CORAM:
GROUNDS OF JUDGMENT
Introduction
3
2. This was the issue in the two related appeals before us. It
necessarily involves a comprehension and application of section 10
of the Arbitration Act 2005.
4
binding on parties consider the “merits” or “existence” of
the disputes raised by the defendant?
6. The Appellant before us, Tindak Murni Sdn Bhd was the
defendant in the High Court at Shah Alam in Civil Suit No. BA-22-
NCVC-70-02/2017 (‘the civil suit’). The Respondent, Juang Setia Sdn
Bhd, was the plaintiff that initiated the civil suit.
5
relation to any matter arising in connection with the contract, to
arbitration.
10. Clauses 34.2 to 34.6 provide for the process of arbitration and
the provision of an award, which is binding on the parties.
11. Clause 34.4 stipulates that the Arbitrator shall have power to
open up, review and revise any, inter alia, certificate and to determine
all matters in dispute submitted to him as if no such certificate had
been given.
The Dispute
6
There was no response from the Employer as a result of which the
Contractor issued a notice of termination of the contract pursuant to
Clause 26.1(i) of the contract.
14. The Contractor then filed the civil suit. The claim was for the
sum alleged to be owing to it under three interim certificates
amounting to RM2,684,924-55 being the value of works done.
18. The application to set aside the judgment in default was first
heard before the Registrar of the High Court who determined that
there was a defence on the merits in that there were disputes and/or
7
triable issues justifying the matter being heard on its merits.
Accordingly the judgment in default was set aside on 31 July 2012.
19. The Employer as defendant did not file a defence as this would
constitute a ‘step in the proceedings’ precluding the referral of the
matter to arbitration. An application for a stay pending arbitration
instead was filed on 10 August 2017. The objective was to stay the
court proceedings pending arbitration premised on the arbitration
clause.
(a) The appeal against the order setting aside the judgment
in default; and
(b) The application for a stay pending arbitration.
22. In so determining the High Court Judge found, inter alia that:
(i) There was a defence on the merits as there were issues
or disputes of fact that required resolution at trial, in
relation to the Employer’s contention that there were
8
defects in the work undertaken which precluded recovery
of the sum claimed by the Contractor; and
24. In essence the Court of Appeal dealt solely with the setting
aside of the judgment in default. Having concluded that the judgment
9
in default was erroneously set aside, it did not consider or address the
application for a stay pending arbitration.
25. The Court of Appeal dealt with the two applications (i.e. the
setting aside and the stay) separately (as did the High Court), as if the
two had no nexus whatsoever with the other. In dealing with the
application to set aside the judgment in default the Court of Appeal
undertook an extensive study of and provided a treatise on the law
relating to certificates of payment.
27. Nowhere is there any mention of the arbitration clause nor the
law relating to arbitration. The Court of Appeal determined that the
certificates of payment in dispute were in fact, conclusive. It thereby
effectively dismissed outright any possibility of defects in the work
done. It then determined that there were no merits in the defence, and
that the High Court had erred in setting the judgment in default aside.
The Court of Appeal then allowed the contractor’s appeal, restoring
the judgment in default. The application for a stay pending arbitration
was simply not addressed at all.
10
dismissed. It was entirely untenable for them to conclude that the stay
ought to be allowed in the face of their finding that the judgment in
default was regular. It was their manner of approaching the two
appeals that led to this result. We were of the view that the approach
adopted by the Court of Appeal was flawed, as we analyse further
below.
11
(II) Submissions for the Employer Prosecuting the Appeals
31. Counsel for the Employer (the appellant) submitted that the
Court of Appeal had erred in failing entirely to consider the arbitration
clause and its effects, particularly in light of section 10 of the
Arbitration Act 2005. It had instead erroneously proceeded to deal
solely with the “merits” of the “dispute”, concluding that there was no
defence on the merits.
12
dealt with on its merits as parties had originally agreed. By reason of
the decision of the Court of Appeal, the Employer had effectively been
shut out or deprived of its rights to have the matter determined by
arbitration.
35. When the appeals came up for disposal before the High Court,
the judgment in default had already been set aside. Neither had the
Employer taken any step in the proceedings. Pursuant to section 10
of the Arbitration Act 2005 the stay pending arbitration granted by
the High Court ought to have been upheld by the Court of Appeal.
This is more so in light of section 8 of the Arbitration Act 2005 which
prescribes a statutory non-interventionist approach by the Courts, as
well as the principles of party autonomy which underscore the law
relating to arbitration.
36. Counsel for the Contractor submitted that the appeal on the
default judgment had to be determined first as there would be no need
for the court to consider the appeal on the stay if the default judgment
is maintained. His reasons for this were, inter alia, that:
13
(b) A judgment of the High Court has constitutional force and
recognition under Article 121(3) of the Federal
Constitution. It stipulates that a judgment of the courts or
a judge has full force and effect according to its tenor
throughout the Federation and may be executed or
enforced accordingly;
37. The starting point for an analysis of the issues in these appeals
requires firstly a consideration of the arbitration clause in the
14
governing contract so as to ascertain whether it comprises a valid
agreement to arbitrate.
39. The emphasised portions make it clear that the first step is to
ascertain whether there is in fact an agreement to arbitrate in respect
of the dispute in question. (See inter alia TNB Fuel Services Sdn
Bhd v. China National Coal Group Corp [2013] 1 LNS 288).
15
an agreement, or in the form of a separate agreement. The former
situation is applicable to the present facts.
“34.0 Arbitration
34.1 In the event that any dispute or difference arises between the
Employer, or the Architect on his behalf, and the Contractor, either
during the progress or after completion or abandonment of the Works
regarding:
34.1(iv) the rights and liabilities of the parties under Clauses 25.0,
26.0, 31.0 or 32.0 or
16
then such disputes or differences shall be referred to arbitration.”
[emphasis ours]
43. Applying sections 9(1) and (2) of the Arbitration Act 2005, it
follows that clause 34 of the governing contract comprises an
arbitration agreement.
45. The clause read in its entirety warrants the construction that a
dispute relating to a claim for monies certified, countered by a defence
or set-off of defective works, “shall” be referred to arbitration. The use
of the word “shall” underscores the mandatory nature of the
agreement between the parties. The fact that the dispute falls within
the scope of the arbitration clause further fortifies this conclusion.
17
48. The plain answer can only be that it makes no difference
whatsoever. There are several reasons for this.
(i) Firstly, section 10 stipulates that the court can act only as
stipulated under the section. When analysed section 10
only allows consideration of the following matters:
18
The breach of the arbitration agreement however
remains just that, namely a breach or even a repudiatory
breach, but unless and until such a breach is accepted by
the innocent party, namely the Employer, the contract
remains valid and subsisting (see section 65 of the
Contracts Act 1950).
19
(iv) Fourthly, the Employer’s application to stay the court
proceedings pending arbitration raised a jurisdictional
point which the Court was bound to consider. This could
only have been done if the Court of Appeal had
considered the form and substance of the appeals in
totality and appreciated the significance of both
applications. While both applications were indeed
separate, i.e. the setting aside of the judgment in default
and the stay pending arbitration, it is crystal clear that the
two applications (and thus appeals) were inextricably
intertwined. It was incumbent upon the Court of Appeal to
consider the effect of hearing the first appeal relating to
the setting aside in vacuo, as it were, without even
mentioning or addressing the stay pending proceedings.
That effect was to ignore the existence of an arbitration
agreement and to exclude the application section 10 of
the Arbitration Act 2005. The Court of Appeal missed
an essential jurisdictional issue, namely whether the
dispute ought to be dealt with by way of litigation or
arbitration.
20
and Hasil Bumi Perumahan Sdn Bhd & 5 Ors v United
Malayan Banking Bhd [1994] 1 CLJ 328).
Having done so, the following consequences ensue from section 10:
50. The failure of the Court of Appeal to even cite or consider these
issues amounts to a fatal flaw, warranting the intervention of this
Court.
21
(V) Is the Agreement to Arbitrate Null, Void or Inoperative or
Incapable of Being Performed?
51. Counsel for the contractor did not submit that the arbitration
agreement was null, void or inoperative. As stated earlier the thrust of
the argument was simply that a judgment of the court, albeit a
judgment in default, could not be subordinated to an arbitration
agreement such as that contained in Clause 34.
22
simply as set out in section 10, which we have explained
in extenso above.
23
Prior to the amendment to section 10 the
Courts expended considerable time and effort in
determining whether a ‘dispute’ subsisted by virtue
of the earlier wording of section 10:
24
With the removal of limb (b) however, the issue
of the subsistence or otherwise of a dispute between
the parties is rendered obsolete and irrelevant.
1
Published by Sweet & Maxwell in 2019.
25
The Merits of the Contractor’s Contention that No
Dispute Subsists Between the parties
26
with a copy to the Employer, and the Contractor shall be
entitled to payment thereafter within the Period of Honouring
Certificates stated in the Appendix. Provided always that the
Architect shall have the discretion to make interim valuations
whenever he considers necessary for ascertaining the
amount to be stated as due in an Interim Certificate.”
27
It was further submitted that the court must consider
the contract in its entirety, give effect to every clause and
harmonise each clause with the other clauses.
28
incorrect given the express provision of Clause 30.3(ii).
Contrary to what was submitted, it provides that in the
event of disputes relating to the Employer’s right to set-off
from the interim certificates by reason of defective works,
such disputes were mandatorily required to be referred to
arbitration as set out in Clause 34. The use of the words
“shall be referred to an arbitrator for judgment under
Clause 34.0” bears this out.
29
56. On this issue Raja Azlan Shah Ag. LP (as His Royal Highness
then was) approved of the following passage in Jaginder Singh &
Ors v The Attorney-General:2
“...The Court can dispense justice only if Counsel will not mislead,
otherwise justice will suffer from the infirmity of the Court itself being devoid
of justice. People seldom pause to ask sometimes what safety the ordinary
individual has in the hands of the lawyers if the Court itself, in which he
seeks redress, is no longer safe to be in the same hands.”
57. In the instant appeals it is trite that the governing contract must
be read and construed holistically and that the parties are not entitled
to pick and choose clauses which are in their favour and ignore
clauses which do not support their case.
2
Jaginder Singh & Ors v The Attorney-General [1983] CLJ Rep 176, at page 178.
3
Accessed at http://www.kehakiman.gov.my/sites/default/files/ETHICS%20for%
20Malaysian%20Judges%20O%202011_.pdf on 30.09.2019.
30
34 is misguided and has no merit whatsoever. The Court of Appeal
therefore erred in determining that there were no merits in the
defence, and that the Contractor was undisputably entitled to the sum
claimed. The affirmation of the judgment in default was therefore
flawed.
59. In its written submissions, the Contractor also alleged inter alia
(as summarised above) that a judgment of the High Court has
constitutional force and recognition under Article 121(3) of the
Federal Constitution. As such it has full force and effect according
to its tenor throughout the Federation and may be executed or
enforced accordingly. This submission is irrelevant to the issues in
this appeal as the validity of a judgment in default in the context of an
imminent execution or a winding up action is not the subject matter of
these appeals.
31
61. The other submission that the doctrine of merger prevents an
arbitration clause from ‘severing’ a judgment because the cause of
action has merged in the judgment and the judgment acquires a
higher status [per Lord Sumption in Virgin Atlantic Airways Limited
(Respondent) v Zodiac Seats UK Limited [2013] UKSC 46] is
similarly inapplicable in the instant appeal. A cursory reading of the
case discloses that it is a judgment relating to the adjudication of
patents which went through a full trial in the English Courts. The
appeal in the Supreme Court of the United Kingdom relates primarily
to the problems arising from the system of parallel jurisdiction for
determining the validity of European patents. Its relationship to the
instant appeals is completely obscure.
32
63. It is in this context that Lord Sumption made a statement on the
doctrine of merger, in relation to res judicata. He explained the
doctrine of merger as treating a cause of action as extinguished, once
a judgment has been given upon it, and the claimant’s sole right as
being a right upon the judgment. He also stated that this principle is a
substantive rule about the legal effect of an English judgment which
is regarded as of a higher nature and therefore as superseding the
underlying cause of action, premised upon a decision dating back to
1844 (King v Hoare) (1844) 13 M & W).
65. If it was the intent of counsel to suggest that the cause of action
that subsisted was merged in the judgment in default and accordingly
the agreement to arbitrate could not survive such a merger, as the
plaintiff/Contractor’s sole right was that on the judgment, then it is a
non-starter.
33
that the agreement to arbitrate stands vitiated by reason of the
doctrine of merger ensuing from the principle of res judicata.
34
judgment was obtained because no appearance was entered. The
defects complained of by the Employer were never heard nor dealt
with notwithstanding the arbitration agreement. The principle or
doctrine cannot therefore ‘bite’. Put another way it is simply
inapplicable to the present factual and legal matrix, particularly when
the judgement in default is being actively sought to be set aside. The
attempt to stifle the Employer form having its case heard by way of
arbitration, as agreed between the parties amounts to a breach of the
fundamental principles of natural justice.
70. Finally the submission for the Contractor that any subordination
of a judgment of the High Court had to be specifically and deliberately
legislated is misplaced as the effect of Clause 34 is not to subordinate
a judgment in default. Neither does section 10 of the Arbitration Act
2005 have the effect of ‘subordinating’ a judgment in default. This is
because the parties had chosen and agreed to arbitration as the sole
and exclusive mode of dispute resolution in respect of any dispute or
difference arising from this contract. The breach of this agreement by
the Contractor and the subsequent obtaining of a judgment in default
cannot then be said to amount to a subordination of a judgment by an
arbitration clause.
35
agreement to arbitrate. This is the very mischief which section 10
seeks to prohibit.
Appellate Intervention
72. For the reasons stated above we determined that the Court of
Appeal had erred in law in arriving at the decision it did. The Court of
Appeal erred in that it:
36
(c) The Court of Appeal erred in that it effectively only
considered one of the appeals before it and let the result
of that appeal determine the result of the second appeal.
In other words the second appeal was never considered
on its merits. It amounted to a failure to adjudicate on the
second appeal;
37
Court. In so doing we reminded ourselves of the confines within which
this court, as an appellate court, is bound to exercise its powers. It is
only to do so in the face of clear errors of law (see MMC Oil & Gas
Engineering Sdn Bhd v Tan Bock Kwee & Sons Sdn Bhd [2016]
2 MLJ 428; Henderson v Foxworth Investments Limited [2014]
UKSC 41).
75. We were satisfied that there were clear errors of law in the
decision of the Court of Appeal and that it was plainly wrong.
38
Answer: We answer the question in the negative.
Signed
NALLINI PATHMANATHAN
Judge
Federal Court of Malaysia
39