Professional Documents
Culture Documents
Location
Need for Underpass
Need for Trenchless Technology
Role of IISc
Role of BBR
General
Arrangement
Longitudinal Section
The Challenge
To finish the entire project
including access roads and
appurtenances in 148 days
Strategies Adopted
Near perfect and optimised schedule
worked out
Identifying of right sub-
sub-agencies
Mechanised Tunnel formwork
High--strength RMC (28 N/mm2 in 48 hrs.)
High
Adoption of Soil Nailing Technique
Constant Monitoring and updating of
schedules as and when necessary
Intitation of Work
Excavation for Approach Ramp
Soil Nailing for Retaining Soil
Pit for Casting the Element
Reinforcement for Pushing Raft
Concreting of Raft
Shutter for Bottom 1/3 Casting
Shutters of Bottom 1/3 Portion of Element
Shutter for Top 2/3 Casting
Top Shutter Component being Lowered
Top Shutter Components Assembled and
Rebar Work in Progress
Reinforcement
Details
Element ready for Casting
Fully Cast First
Element
Getting ready to cast Bttom 1/3 of 2nd Element
Bottom 1/3 of Second Element being cast
Fixing of Drag Sheet
Jacks in place for Pushing
Pushing in Progress
Light at the end of Tunnel!
Concreting of Approach Ramps
The completed Underpass
The completed Underpass
The completed Underpass - inside view
The completed Underpass - inside view
Drainage / Rain water harvesting
system
Quality Control
Safety and Environmental Concerns
CONCLUDING REMARKS
The experience of executing this type of prestigious and
technologically innovative project has revealed that
– the ‘Box-
‘Box-Jacking’ Technology is the most suitable one for
the construction of under-
under-passes across busy highways/
expressways.
– This fast-
fast-track trench-
trench-less technology may be exploited
advantageously, not only to construct underpasses for
pedestrian and vehicular traffic, but also to provide
facilities such as metro rails and service vents across
highways and expressways.
– This technology provides a distinctive advantage over
‘cut--and
‘cut and--cover’ method in such situations, due to its
execution without interruption of traffic above with the
constraints of tight time schedule.