Professional Documents
Culture Documents
Method Statement
For
Submitted By:
Advance Vision Co.
(Sub-Contractor)
Signature:
Date:
Page 1 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
List of Contents
2.0 PURPOSE 06
3.0 ACRONYMS 06
7.0 RESPONSIBILITIES
7.1 The Construction Manager 9
7.2 The Site Engineer 9-10
7.3 The QA/QC Engineer / Inspector 10
7.4 The Safety Engineer / Safety Officer 10
7.4 The Foremen 10-11
8.0 TECHNICAL SUBMISSIONS
8.1 Shop Drawing 11
8.2 Material Submittals for Fire Fighting System & Accessories 12-13
9.0 CONFORMANCE CRITERIA
9.1 The Contract Specification for Fire Fighting 13
9.2 Fire Protection Codes and Standards 13-14
9.3 Approved Shop Drawings 14
10.0 HEALTH AND SAFETY 14-15
10.1 Environmental Requirements 15-16
Page 2 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
List of Contents
Page 3 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
List of Contents
Page 4 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
List of Contents
Page 5 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
The scope of This Method Statement is to define all the sequence and work for
installation and testing of Fire Fighting System, as per our scope of work, at KAIA
PROJECT – Jeddah, K.S.A. and to ensure that all works / activities are in full
compliance with specifications, drawings and standards .
2.0 PURPOSE
The purpose of this Method Statement is to describe the quality control procedure
to be followed during installation of Fire Fighting System works activities.
3.0 ACRONYMS
Page 6 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
The criteria for occupancy classification is defined in NFPA 13: The categories
are broken in five areas based on building use type:
Light Hazard: Low quantity of combustibles with low heat release (e.g.,
churches, hospitals, museums)
Extra Hazard 1: High quantity of combustibles with high heat release and
no flammable or combustible liquids (e.g., aircraft hangers, saw mills)
Extra Hazard 2:High quantity of combustibles with high heat release and
flammable and combustible liquids (e.g., plastics processing, flammable
liquids spraying)
Page 7 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
FIRE Pre-
S.N. Building/Zone(421) WPSS FM200 IG-55 DELUGE FOAM HOSE Action
CABINET
1 Flans Glazing
2 Zone A-Terminal
Processor
3 Zone B-West
Domestic Pier
4 Zone C-East Doestic
Pier
5 Zone D-Central Pier
6 Zone E-International
Hub
7 Zone F-West
International Pier
8 Zone G-East
International Pier
9 Zone H-Garden
10 F155-APM
Maintenance Station
Page 8 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
FIRE Pre-
S.N. Building/Zone(421) WPSS FM200 IG-55 DELUGE FOAM HOSE Action
CABINET
21 B360-Saudi Airlines
“MCC”
22 H110 Data Center
23 H120 Data Center
7.0 RESPONSIBILITIES
To ensure that all preparation and application works are carried out
according to the contract specifications, shop drawings and
manufacturer data sheet.
Coordinate all the site activities required for the installation of the
fire fighting system, whether external or internal, according to the
project specification, manufacturer data sheet and approved shop
drawings.
Page 9 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 10 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 11 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 12 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 13 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 14 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 15 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Deliver pipes and tubes with factory end cap. Maintain the end
cap thru shipping, storage and handling to prevent damage to the
pipe end to prevent deposit of dirt, debris and moisture inside it.
Check Portable fire extinguisher for any damage in the body, the
availability of the hose and proper pressure by looking at the
sight glass.
Keep the extinguisher in the original pack and store it in a dry and
shaded location.
Page 16 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Leve Bar
Pipe Stand – use to level the pipe during threading & grooving.
Hack and Saw – use to cut full threaded rod prior to install pipe
support.
Chalk Line
Page 17 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
End Caps – use to plug all end pipes opening prior for leak
testing.
Page 18 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
o Insert washer below the nut, remaining bolt and thread the
nut finger tight onto bolt. Nuts must be tightened evenly by
alternating sides according to torque.
Page 19 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
1. Make sure the proper roll set is installed on the tool for
the pipe size and material to be grooved. Rolls are
marked with the pipe size, part number and the color
coded according to the pipe material.
Page 20 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 21 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 22 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
10. Remove the guard setting pad. Store the pad on the
hook provided under the hydraulic hand pump
support.
Page 23 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 24 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 25 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 26 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
12. Depress and hold down the safety foot switch. The
pipe will begin to rotate clockwise when viewed from
the front of the tool. As the pipe rotates, begin forming
the groove by pumping the handle of the hydraulic
hand pump slowly.
Page 27 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 28 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
3. A heavy duty pipe threader can also cut your pipe into
workable sections.
Page 29 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
8. Ream the cut end of the pipe to remove any burrs from
the cut using a reamer, which is a cylinder – shaped
rotary cutting tool that you run smoothly across the
freshly cut edges of the pipe to remove rough edges.
10. Place the die head over the pipe on the threader.
Page 30 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
15. Reverse the ratchet mechanism and turn the die head in
the opposite direction. Be care full to maintain control of
the threader as the dies are removed. Threads can be
damaged when the die head is being removed if you
don’t maintain control and move the piece smoothly.
17. Clean the pipe with cloth, removing any oil. Be careful,
the threads will be very sharp.
11.4.1 Sleeves
o Size of Sleeves against pipe diameter shall be installed as
per the approved shop drawing.
Page 31 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 32 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
o Site engineer shall ensure that the G.I. sleeve is tightly tied
with reinforced steel rod.
Page 33 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 34 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 35 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 36 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 37 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 38 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 39 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
3a. Make sure the locating collar engages the outer hole
properly. Check this engagement by rocking the upper
outlet housing in the hole.
Page 40 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Branch Connection
Page 41 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 42 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 43 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 44 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 45 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 46 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 47 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 48 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
g) The pipe will be checked for initial level and position and,
if necessary, adjusted on the pipe support, carefully
aligned prior to final connection.
Page 49 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 50 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 51 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 52 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 53 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 54 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 55 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 56 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
4. Select the hanger based on size of the pipe and install the
hanger rod to the drop in anchor.
5. Check the pipe length as per the approved shop drawing and
cut it by using speed metal cutting machine ensuring it
perpendicular to the pipe.
8. Remove the oil from the pipe end after the threading wrap with
abaca fiber with joint compound.
10. After the completing the pipe installation, clean out the
internal surface of pipe work by purging air.
s (feet) NOTE:
Page 57 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Pipe S ize Change W hen the change in pipe s ize is done at a tee, this is accom plished by
at a Tee using either a reducing tee or a standard tee and reduc ing f ittings. All
reducers m ust be concentric bell reducers or concentric reducing
couplings.
Pipe S ize Change W hen the change in pipe s ize is done at an elbow, this is accomplished b y
at an Elbow using either reducing elbows or a standard elbo w with concentric bell
reducers or concentric reducing couplings
Pipe S ize Change W hen the change in pipe s ize accomplished at a coupling, only concentric
at a Coupling bell reducers or concentric reducing c ouplings can be used.
Page 58 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
20 12 21 1 21 7 22.375 Upright
70.263
(8) (5.5) (9.5) (25) (9.5) (178) (568.3) -
35 22 38 1 31 7 32.5 Upright
Horizont
70.264
(15) (10) (17) (25) (14.5) (178) (825.5) - al
60 39 68 1 52 10.75 28 Horizont
Upright
70.265 al
(27) (18) (30.5) (25) (23.6) (273) (711.2) -
Horizont
100 63 108 1 77 10.75 38.75 Upright
70.266 al -
(44) (28.5) (49) (25) (34.9) (273) (984.3
( Valve
150/150 70.267 87 150 3 150 20 ) 23.63 Upright /
Up) )
i (39.5) (68) (80) (68) (508) (600.1) Inverted
215 124 216 3 155 20 28.87 Upright
70.268 -
(88) (56.5) (98) (80) (70.3) (508) (733.3
(Upright
Valve
375 217 378 3 225 20 ) 42.5 Up)
70.269 - )
(153) (98.5) (171.5 (80) (102.1 (508) (1079.5
( Valve
Upright
650 378 ) 660 3 ) 385 24 ) 50.625 Up)
70.27 - )
(267) (171.5 (299) (80) (174.6 (610) (1286)
( Valve
) ) Up)
Upright
1000 598 1045 3 550 24 70
70.271 -
(423) (271.5 (474) (80) (249.5 (610) (1778)
( Valve
) ₃ ) ₃ Up)
Fill Range 40 to 70 lbs / ft 630 to 1121 Kg / m
Page 59 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Factor to be considered.
FACTOR CONSIDERATON
Container brackets must be mounted securely to solid load-bearing surfaces that will
support the container load.
MOUNTING
Some installations may require additional mounting support not supplied by supplier
SURFACE
In general, the larger the container, the more difficult it will be to remove it from the
system for maintenance and service.
SERVICEABILITY
However, smaller containers that are located in a sub -floor space, under a
computer bank,or above the ceiling over the same computer bank can be difficult
as well.
FLOOR SPACE Consideration should be gi ven to the space available to install the container(s).
Page 60 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 61 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 62 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 63 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 64 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 65 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 66 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 67 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 68 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 69 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 70 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
11.4.12.10 Interface
Page 71 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
The design concentration for the gas shall comply with the
requirements of NFPA 2001 and will have to be approved by
the Consultant. The discharge duration of the gas shall be
within 60 seconds and pipes have been sized accordingly.
Page 72 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 73 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 74 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 75 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Procedure:
Page 76 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 77 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 78 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 79 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 80 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 81 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
11.4.13.11 Interface
Page 82 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 83 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Water for the foam system is drawn from the bladder type
foam tank and extinguishing panel are located within the
generator room.
Page 84 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
All the components use for the system including but not
limited to bladder tank, foam concentrate, pre action valves,
isolation valves, sprinklers, foam proportioner, etc. shall be
UL listed / FM approved and shall be approved by
Consultant.
Install piping and other components level and plumb. Install pipe
and fittings, valves, and discharge devices according to
requirement listed in NFPA 16.
Page 85 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 86 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 87 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 88 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 89 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
p) Walk along the pipe line route & Inspect for any
leakage. If any leakage is found, drain off the water
from the system by opening the filllng point at the
lowest end of the system .Rectify the leak by
tightening the joint or replacing of defective pipe I
fitting as the case may be.
Page 90 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 91 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
11.4.14.7 Interface
Page 92 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
The size of the deluge valve, its flow rate, the system water
supply pressure and type of detection system are all
determined by the size and type of fire risk involved.
Page 93 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
11.4.15.1 Interface
Interfacing with other services is required for Fire
Protection Systems in order to make the system
effective.
Interfacing can be achieved by connecting any dry cont
act (potential free) outputs from the system to the
service where we have to get the system interfaced.
Elevators should be captured to ground floor or any
other safe floor in case of fire.
Double-knock system shall be with:
o Sensing of heat (bulb fuses) by the sprinkler.
o Detection of Smoke / fire through fire alarm
system (FAS) detectors.
Page 94 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 95 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
11.4.16.1 Interface
Deluge system are used for fast, total application
of water in Extra-Hazardous areas and in water-
spray systems. Deluge valves are essentially
check valves with a clapper latched in the closed
position (see picture below). The actuating
system unlatches the valve, allowing the water to
enter the piping system and flow out the heads.
Page 96 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 97 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 98 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Installation:
1. Install double door fire hose cabinets in
locations and at mounting heights indicated
as per approved shop drawing.
2. Fasten cabinets to structure, square and
plumb.
3. Provide inside latch and lock for break-glass
panels.
4. Fasten mounting brackets to inside surface
of fire hose cabinet square and plumb.
5. Install hose rack assembly at the upper
compartment. Include hose valve, hose rack,
water-retention device, hose pins and hose.
Operation – semiautomatic. Hose with swivel
inlet, coupling, gaskets and nozzle.
Page 99 of 104
THE ENGINEER:
New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 421-422-DCS-MST-M-00717-05
Contract No.: J-10-421/422-PF-0 Date Issued: February 12, 2014
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Installation:
1. Install double door fire hose cabinets in
locations and at mounting heights indicated
as per approved shop drawing.
2. Fasten cabinets to structure, square and
plumb.
3. Provide recessed fire hose cabinet.
4. Provide inside latch and lock for break-glass
panels.
5. Fasten mounting brackets to inside surface
of fire hose cabinet square and plumb.
6. Install hose rack assembly at the upper
compartment. Include hose valve, hose rack,
water-retention device, hose pins and hose.
Operation – semiautomatic. Hose with swivel
inlet, coupling, gaskets and nozzle.
7. Hose – NPS 1-1/2 (DN40). Length – 100 feet
(30 meter). Jacket is made high tenacity
polyster yarn. Lining material is Poly
Urethane. Cover made of synthetic material.
8. Nozzle: spray nozzle. Made of chrome-
plated brass. Adjustable from shutoff to fog
spray or straight stream.
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Method Statement For Fire Protection Installation & Testing (Packaged 421)
11.4.20 References:
Manufacturer’s Recommendation.
Material’s Submittals.
11.4.21 Attachment