Professional Documents
Culture Documents
1 Introduction Packaging
The utilization of the production assets is in BCS limited to the main processes
Brewhouse, Cellars, and Packaging (i.e. Bottling / Canning / Kegging and Special).
In Version 6, the structure of OPI for Brewhouse(s) is fully aligned with the well-known
structure for packaging. Secondly a separate chapter on Filtration OPI is included, to
provide the standardised framework for local calculations outside BCS. Thirdly, we now
also calculate a departmental summary of the utilisation parameters
Please note that all ratios (e.g. OPI, OPI-NONA, Effectivity and Efficiencies, etc.) are
time weighted averages in the circumstances that more than one brewhouse, cellar or
packaging lines are on site. In case of the brewhouse and packaging OPI, the weighted
average is based on the sum of theoretical production times divided by the sum of
manned times. The relative nominal speed of the lines is therefore indirectly taken into
account, via the theoretical production time calculation.
In many of our operating companies, the packaging operations have a significant impact
on the Cost of Goods Sold (COGS). Equipment performance is therefore an essential part
of these COGS. For the determination of equipment performance, the reference is
therefore the use of time from that equipment’s perspective: “What is being done with the
equipment at any moment in time”. Secondly, we assess in many cases the existence of a
(Wo)Men-Machine relationship.
Key Performance Indicators in packaging operations are OPI and OPI-NONA, where OPI
stands for Operational Performance Indicator (OPI) and OPI-NONA for Operational
Performance Indicator (OPI) minus time lost for No Order No Activity and Non Operator
Maintenance.
This chapter describes the time elements, which are used for the calculations of the
various equipment ratios. Correct allocation is therefore essential to ensure a correct
representation of all these ratios. To assist, each time element is supported by one or
more questions. In the event that a Yes is the correct answer to one of these questions, the
correct time element has been identified. Secondly, a Q&A section is available, to
provide guidance for the most frequently asked questions.
1.1.1 Unused Time Packaging
First of all, it should be realized that Manned Time = Total Time – Unused Time, with
Total = 7*24 = 168 hr/wk, 52 weeks per year. Because Total Time is a fact, Manned Time
is influenced by Unused Time only. BCS uses the Gregorian calendar as the bases for
automatically determining the amount of Total Time in a month. For the determination
of Unused Time, two aspects are to be assessed, being the engineering status of the
line, and / or the presence / absence of people. Please refer to the To Summary Chart as
reference.
Line aspects
1) Is the line under construction or is major re-engineering taking place?
When an existing line is re-engineered, the time taken for the significant changes (=
capacity and / or capability change requiring CAPEX) is not to be considered as Manned
Time because it is not related to the operational use of the line. The time spend on re-
engineering therefore has to booked as Unused. The line has to remain “in use” in BCS
Similarly, the installation period of a new line is not to be included. Operator shifts that
are getting their training for the new line is considered part of the investment project
and should not be included. For OPI calculations a project is deemed finished when:
the first time products complying with all tolerance ranges for finished products
are produced, or
finished product has been released to the market, or
successful Site Acceptance Test (SAT) has been performed, whatever comes
first.
Registrations of line performances henceforward are mandatory, irrespective of the
results, so the line has to be put ‘in use’ in BCS and reporting has to take place.
Concerning packaging lines that are no longer part of the planning process, the
following rules apply:
a) When there is a temporary cease of use of the lines, or they stopped production but
will be transferred to other production unit within the same OpCo continue reporting
the asset in BCS / BCA as currently.
b) In the rest of the cases (to be transferred to another OpCo or third party and/or,
permanent out of use and/or unknown future status) then you do not report in BCS /
BCA in that Unit when the line ceased production on a permanent basis.
Line people aspects
2) Are there ≤ 2 (or 50% of a minimum packaging crew size) people (production /
maintenance / engineering / 3rd party) on the line?
Unused Time means that nobody (production / maintenance / engineering / 3 rd party or
anybody else) is doing anything with the line. The lights are off and the door is closed.
However, good cost-efficient management advocates executing some activities (heating
of machinery, pre-loading of bottles, postproduction cleaning) are done without
complete teams being present. Unused Time includes the hours when a few men
(=Smallest of 2 or 50% of a minimum crew) are doing jobs enabling complete shifts to
start and stop efficiently. However, production units that want to have a clear calculation
method can increase the Manned Time proportionally. For instance, if 2 persons of a
team of 8 come 1 hour earlier, you can use 2/8 = 25% of 1 hour = 15 minutes for that
‘correction’.
NOTE: When more than 2 people on the line, the line is to be considered as manned,
and the proportionality does not apply anymore.
Some production units use a procedure that during the ‘run-out’ of a production run on
line A part of the team begins with the start-up of line B. This is – of course – a ‘best
practice’ to increase the output per hour. The Actual Production Time (which is
measured at the filler) is not influenced; the increase of the OPI NONA should result
from the shorter Planned Down Time. If e.g. 1 hour is gained this way, the Planned down
Time for each line should be reduced by 0.5 hour AND the Unused Time should be
increased by that same 0.5 hour.
Overtime made by a production or maintenance team is part of Manned Time, of
course, and must therefore be deducted from Unused Time.
However, when an entire shift is put to work outside their normal line workstations and
are performing other work than their normal production jobs, that time should not be
included in Manned Time, but be ‘booked’ as Unused Time. Examples are:
· Painting,
· Pallet sorting, etc.
Although these examples are beneficial to run the line, they are not considered as
operational utilisation of the line, as the (Wo)Man – Machine interaction is not present.
A good way to calculate the correct Manned Time is:
Manned Time = Total Time – Unused Time
= Actual production Time + External Stops Time + Planned Down Time + Change Over
Time + NONA Time + Non-Operator Maintenance Time
Questions Unused Time Answer
We fund some capacity & capability changes on Taking the equipment perspective, these changes are
our line from a maintenance budget, how should impacting on the line capability and or capacity, and
we allocate the time it takes to do these changes are therefore to be allocated under unused time. The
funding is irrelevant
We have a third party cleaning crew coming in When the cleaning crew is smaller than 2 people, Yes, if
on a Saturday to clean the line. Our operators are more than 2 people the lines is in use, and the time it
having a rest at home. Is the line unused? takes to clean is to be deducted from Unused and
reported under planned down time.
Our maintenance team does maintenance in one When the maintenance crew is smaller than 2 people,
8 hour shift per week. Operators are at home. Is than yes, if more than 2 people on the line, than the
the line unused? time taken for maintenance is to be deducted from
Unused and reported under Non Operator
Maintenance.
When 5 of the 12 operators (12 = minimum crew) Two aspects appear to be mixed up in the question: as
of a line stay after the shift cleaning the line at long as there are more than 2 People are on the line,
the end of the week (no other production than the line is manned. Then the question is what are
activities left), is this reported as unused time they performing (in your case end of production
(because 5<50% of the minimum crew) or cleaning) which is a planned activity, therefore it is to
planned down time (because 5>2)? be recorded as planned down time
Otherwise; how to interpret the definition: NOTE: When more than 2 people on the line, the line is
“unused time includes the hours when the to be considered as manned, and the proportionality
smallest of 2 or 50% of a minimum crew are does not apply anymore.
doing jobs enabling complete shifts to start and
stop efficiently”
1.1.6 External Stops Packaging
External stops are packaging line production interruptions, with their root cause outside
the control of the packaging teams. The question:
13) Is the packaging process not possible (line cannot run) as result of external
factors, not under the control of the packaging crew like: no beer, no utilities, no
packaging materials, no downstream warehouse space, no internal / external
transport etc.?
attracts a positive conformation.
BCS calculates the time of the External Stops from the actual production time entered in
the most detailed input screen:
External Stops = Available Production Time – Actual Production Time.
The registration of External Stops enables the calculation of the Line Performance that
represents the Efficiency without taking the External stops into account:
Line Performance = Theoretical Production Time / Actual Production Time
You should therefore exclude the External Stop hours from the Actual Production Times. That
will result in Line Performances with clean packaging team accountability.
Example:
Gross actual External stop Actual production time for OPI
production time (hours) reporting (hours)
(hours)
105 0 105-0 =105
213 15 213-15= 198
Questions External Stops Time Answer
We have 2 lines (L2 & L3). The root cause of all this is lack of CO2 and therefore
L3 fills softdrinks (CO2); and L2 cannot fill the time losses on both lines are to be allocated under
according to the planning of production, external stop !
2 L2 doesn’t fill because the Brewing department
cannot filter beer as there is insufficiency CO2.
3 During this stop, the L2 2 crew does training
and cleaning.
Where do I allocate the time losses:
1-NONA?
2-External Stop for lack of beer / CO2?
3- Stop planned for training & cleaning?
1.1.7 Break Down Time Packaging
Break downs are unplanned events of equipment failure. When the following question
is answered as “Yes”, we allocate that time as Break down Time:
14) Is the packaging process not possible for more than 5 minutes at the filler as
result of mechanical, electrical / instrumentation failure on components, sub-
assemblies or packaging line machinery and control systems or is the crew size
below the required minimum?
Is positively confirmed. Breakdowns and minimum crew size (i.e. as result of a strike) are
therefore an internal packaging line affair, and are not influenced by external factors
(See External Stops). Production stops longer than 5 minutes, measured at the filler, are
to be reported.
Note: Stops longer than 5 minutes as a result of primary and secondary packaging
material failures are not to be accounted for under Break down time, as they will be
accounted for under Speed Losses & Minor Stops.
All BCS data should be related to the filler, which does not mean that it is not very useful
to register breakdowns of the other equipment. However, for BCS the Breakdown >5
min. and the Number of breakdowns of the filler should be entered only. Due to the
buffers, it is possible that 1 breakdown of the palletizer of 10 minutes does not result in
a production interruption >5 min. at the filler.
Questions Breakdown Time Answer
Our line measurement system reports all For packaging Line OPI, we consider all machines as
stoppages of all machines. Which one should we one, and we measure the stoppages of the line
use for the registration of breakdown time, as it exclusively at the lowest point of the line V graph,
sometimes occurs that more than one machine where manning is available. The filler is therefore the
stops. designated point of measurement for line OPI. For the
time measurements at the filler with an automatic
reporting system a classification into breakdown or
speed losses is required, otherwise incorrect data is
used for both breakdown as well as speedlosses.
We have filler stoppages as result of No, breakdown is exclusively for the registration of
underperforming packaging materials, is this a failure of equipment and components.
breakdown?
1.1.8 Speed losses & minor stops Packaging
Speed losses and minor stops account together for the time losses due to small stops
(<5 min.) at the filler and having an actual filler speed below the Nominal Speed for that
SKU. When one of the following questions (and / or) is positively answered, speed losses
& minor stoppages are occurring.
15) Has the filler stopped for less than 5 minutes?
16) Is the filler ramping up or down?
17) Is the filler not running at nominal speed?
18) Has the filler stopped for more than 5 minutes, but not because of
Breakdown?
BCS calculates the Time of Speed losses and minor stops as:
Speed Loss & Minor stops = Total – Unused – Non Operator Maint. – Nona – Planned
down – Change over – External stops – Break down – Theoretical production Time –
Reject & Rework
Questions Speedlosses and Minor Answer
stops Time
Our operators have the experience that when Yes, actual running speeds below the nominal speed
they run the line below the nominal speed, it runs are always a speed loss. From this question, is appears
better. Is this a sped loss, as we tend to make that there are unresolved aspects in the lines
more products in a shift. preventing is from performing against the nominal
speed.
When we complete BCS we have negative Negative speedlosses in BC are indicative of incorrect
speedlosses, how is this possible? time allocation(s). Most common mistake is the
incorrect actual production time reporting, where
external stops are not deducted. Secondly, when the
line is running above the nominal speed, this can occur.
Normal V-shape designed line with Nominal Speed = 40.
Packer designed at 50, e.g. risk of failure of 1 out of 5 bottles to ‘serve’ the bottle-neck of the
filler at 40.
Situation 2:
1.1.12 Simultaneous events Packaging
Above mentioned data definitions provide the reference for singular events. However, in
practice, more than one event can take place and as a matter of improvement, this
should be stimulated where possible to improve the overall performance of the line
This section is providing guidance on how to allocate simultaneous events into the
various time components of the OPI calculation.
In BCS we distinguish two types of events:
Planned events:
Non-Operator Maintenance
Planned down
Change-over
The reference point for administration of simultaneous planned events:
the longest event is leading in terms of total timing and allocation.
Unplanned events:
NONA
External Stops
Breakdown
The reference point for administration of simultaneous unplanned events:
the first event is leading in terms of total timing and allocation.
The reference point for administration of simultaneous planned and unplanned events:
the first event is leading in terms of timing and allocation, any remainder of planned
Second event
Non NONA Planned Change External Break down
First event Operator down Over Stops
Maintenance Time
Planned Unplanned Planned Planned Unplanned Unplanned
Non
Longest Longest
Operator Planned - First Event X First Event
Event Event
Maintenance
First First
NONA Unplanned First Event - X First Event
event event
Scheduled Scheduled
Scheduled
planned planned
planned
Planned Longest down time, down time,
Planned Longest Event down time, -
down Time Event remainder to remainder
remainder
External to
to NONA
stops Breakdowns
Scheduled Scheduled
Scheduled
Change over Change over
Change
Longest time time
Change Over Planned Longest Event over time -
Event remainder to remainder
remainder
External to
to NONA
stops Breakdowns
External First First
Unplanned First Event X - First Event
Stops Event Event
First First
Breakdown Unplanned First Event First Event First Event -
Event Event
The Ratio’s below are not available in BCS
MST = Mean Stoppage Time
or
MST = Sum of all Minor stoppage times / number of Minor Stoppages (Assists)
and
MTBA = Mean Time Between Assists
or
MTBA = Sum of all up-times / number of Minor Stoppages (Assists)
or
MTBA = Operating Time / number of Minor Stops Assists
and
AO = Operational Availability
or
AO = MTBA / (MTBA + MST)