Professional Documents
Culture Documents
In The Lands Tribunal of The Hong Kong Special Administrative Region
In The Lands Tribunal of The Hong Kong Special Administrative Region
BETWEEN
TAI FONG TRADE LIMITED Applicant
and
THE INCORPORATED OWNERS OF 1st Respondent
NOS.167 & 169 HOI BUN ROAD
LAM, CHAN & CO LTD 2nd Respondent
JUDGMENT
__________________
Background
1. The Applicant is and has been the owner of the 5 th floor of the
building known as Nos. 167 & 169 Hoi Bun Road, Kwun Tong,
Kowloon, Hong Kong (“the Building”) since 1996. Its associated
company was the owner of the 5th floor between 1983 and 1996. The 1st
2
2. The Building was erected in the 1960s. The building plans dated
back to 1965, and the occupation permit was issued in 1969. Thus, the
Building is almost 40 years old. There are only 7 levels in the Building,
namely the ground floor, the 1st floor, the 2nd floor, the 3rd floor, the 4th
floor, the 5th floor and the roof. The 5th floor is the floor immediately
below the roof. There is one owner to each of the levels (except the car
parking spaces on the ground floor). The size of each level is rather
large, with the dimension of 40m x 52m. According to the occupation
permit and the building plans, the Building is primarily designed to be
used as godown.
3. The parties have no dispute that there are various layers making up
the floor slab of the roof cum ceiling slab of the 5 th floor, from the top
downwards, as follows:-
4. It is also not in dispute that among the various layers, only the
waterproof membrane is waterproof, all the other layers (above and
below the waterproof membrane) are porous and not waterproof. The
concrete tile layer is still the original concrete tile layer existing at the
time when the Building was first constructed and has never been changed.
Likewise, the waterproof membrane has never been replaced.
5. Like many of the other floors in the Building, the 5 th floor was
formerly used as a factory. There had been structures, like 3 chimneys,
some air-conditioning cooling towers and a water tank, erected on the
roof serving the factories in the floors below. Amongst those structures, a
chimney and a water tank were erected by the Applicant’s predecessor in
about 1983, at which time the other 2 chimneys and many other structures
had already been erected on the roof. It is not disputed that in erecting
the chimneys and the water tank, certain parts of the waterproof
membrane were penetrated, as the anchorage for the chimneys had to be
anchored onto the structural slab (though the chimneys themselves did
not penetrate the floor slab) and the outward water pipe from the water
tank did penetrate the structural slab to go down to the 5th floor.
rental very much below the market rent. According to the Applicant, the
reason for not being able to rent out earlier and the low rental is that there
was widespread and substantial water leakage from the roof to the 5 th
floor affecting the use of the 5th floor. Despite complaints made by the
Applicant to the 1st and 2nd Respondents, the 1st and 2nd Respondents
failed to effect repair to the roof, and the water leakage problem
continues until today.
7. The Applicant’s case is that the water leakage has been caused by
2 factors as follows:-
(2) The lack of proper repair and maintenance of the floor of the
roof has aggravated the water leakage problem. It is the 2 nd Respondent’s
fault in failing to properly repair and maintain the roof.
8. Thus, the Applicant claims against the 1st and 2nd Respondents for:-
(5) Costs.
(1) The waterproof membrane forms part of the common parts of the
Building; and
(2) It is the duty and obligation of the 1st Respondent to repair the
defects in the waterproof membrane and to maintain the waterproof
membrane in a state of good and serviceable repair and clean condition.
(2) The 2nd Respondent should be responsible for the repair and
maintenance of the roof. In this regard, the 1 st Respondent has issued a
Notice of Contribution against the 2nd Respondent.
(3) The 1st Respondent denies that the water leakage was caused by
defects in the waterproof membrane, and alleges that it was the structures
6
(4) The 1st Respondent denies that the Applicant has suffered any loss
or damage as pleaded, or alternatively, the 1st Respondent avers that the
loss and damage were caused wholly or materially contributed to by the
Applicant’s own fault in erecting the chimney and water tank.
(1) The 2nd Respondent does not admit that it is under a duty to repair
and maintain the roof. The 2nd Respondent also issued a Notice of
Contribution against the 1st Respondent.
(2) The 2nd Respondent denies that the water leakage was caused by
it’s failure to repair or maintain the roof, and alleges that it was the
structures previously erected on the roof but subsequently removed in
2002 which caused the leakage.
(3) The 2nd Respondent denies that the Applicant has suffered any loss
or damage as pleaded, or alternatively, the 2nd Respondent avers that the
loss and damage were caused wholly or materially contributed to by the
Applicant’s own fault in erecting the chimney and water tank.
(4) The 2nd Respondent raised the issue that the cause of action did not
first accrue to the Applicant within 6 years before the commencement of
the action and hence the claim is barred by the Limitation Ordinance.
7
However, at the trial, the 2nd Respondent abandoned this issue and I do
not need to deal with it any more.
Water leakage
12. From the evidence before me, and also the site visit I had at the
trial, it is clear that the water leakage problem at the ceiling of the 5 th
floor is very serious. I accept that the only source of water causing the
leakage is from rainwater. As observed by Mr. Albert Chan, the
Applicant’s expert, there is no water supply or drainage pipe at the
ceiling, except ceiling mounted exposed fire services sprinkler water
pipes, but there is no sign of water leakage from such pipes. As to the
roof, again as observed by Mr. Chan, there is no water supply or drainage
pipes that run on the surface of the roof, except a fire service water pipe
running along the periphery of the roof, but the 1st Respondent’s expert,
Mr. W.K. Kwong, confirms that the fire service water pipe is in good
condition.
13. I accept the evidence of Mr. Lau Wah (the Applicant’s director and
factual witness) that the water leakage problem at the 5th floor started in
or not long before 1997. The first batch of water leakage spots were
noticed by the Applicant a couple of years before 1997, and those were
actually the spots in the middle of the ceiling, where had been no
structures erected on the corresponding part of the roof. For the leakages
in the vicinity around the place where there used to be structures erected,
they were discovered close to 1997, some 14 years or more after the
structures had been erected. Since the water leakage was discovered, the
problem has deteriorated over time. The water leakage problem has
become extremely widespread and substantial. It affects almost each and
every part of the ceiling.
8
14. The presence of the whole series of metal trays and PVC water
drainage pipes connecting the trays around the ceiling of the 5 th floor is
telling of the seriousness and extent of the leakage problem. Clearly, the
trays are there to collect water dripping from the ceiling. It is a very
elaborate water collecting system, the erection of which is no doubt costly
and time-consuming. No one would have undertaken such an arduous
task unless the water leakage problem is substantial and widespread.
(1) “In general, majority of the ceiling surface was being affected by
water leakage. The areas of damp staining and flaking paintwork were
scattered all around the ceiling and adjacent walls.”
(3) “the ceiling of the Premises had been suffering from serious water
leakage problem. … The water leakage affected areas were scattered all
around the ceiling surfaces of the Premises and that the damage had been
related to the condition of weather. It became more serious in rainy
seasons and less serious in dry seasons.”
9
(4) “the leakage spots were distributed evenly all over the ceiling
within the Premises. The RITS results taken on the same day which was
after several rainy days traced and found that the leakage took place at
each of these individual spots from roof… This indicates that the leakage
has been taking place at various locations and scattered all over the roof
area.”
(5) “There were two major areas where the growing damp stains and
water seepage spread from directly above at roof/ceiling level downwards
to the two enclosing walls, east and west of the Premises”
(6) “areas and spots being affected by the water leakage problem, with
defects including water staining, debonded/hollow plaster, cracking,
concrete spalling/exposed steel reinforcement bars, bulging, bubbling and
peeled off paintwork” are identified as per the layout plan prepared by
Mr. Chan. “The number of defective spots was noted to be 37 and this
figure does not include the internal wall damage.”
18. The RITS scanning carried out by the Applicant’s expert after a
few days of rain further confirms that there is water leakage at various
spots all over the ceiling of the 5th floor. The leaking spots, as observed
with RITS scanning, largely correspond with the visual observations of
Mr. Chan. The RITS scanning results confirms that the water leakage
problem is widespread and affecting virtually every part of the 5th floor.
19. The 1st Respondent’s expert, Mr. W.K. Kwong, also conducted
RITS scanning, but I accept the Applicant’s comments on Mr. Kwong’s
RITS scanning. Mr. Kwong’s scanning was done from above the roof
11
surface, and such way of scanning would only show the water ponded or
accumulated at the top layers of the roof surface above the waterproof
membrane. It would not really show the positions of water leakage.
20. I also accept the Applicant’s comments on the RITS scan test
conducted by the 2nd Respondent’s expert, which was done after localized
ponding of part of the roof. The ponding test was done after and during
days with fine weather, and as such the water from the ponding would be
the only source of water one may find at the 5th floor. According to Mr.
Poon, the localized ponding was supposed to be targeted at the parts of
the roof where the previous structures were found. However, the ponding
was flouted with problems. The locations of the ponds were wrong – with
edges of water ponds cutting through half of the areas occupied by the
chimneys and the water tank. The erection of the ponds themselves was
done sloppily – with water leaking out from the ponds here and there. It
is misleading to suggest that the water leakage problem at the 5th floor is
not serious or that the water leakage was caused by the structures
previously erected on the roof just based on the few spots of leakage
discovered from the RITS scanning under localized ponding. Such
localized ponding can only show localized leakage. It may well be able
to show that there is leakage at places where the structures used to be –
because water is ponded there and because the part of the waterproof
membrane at that place has failed. It cannot however show whether it
was the former structure or the aging of the waterproof membrane that
caused the leakage. Neither can it show that there is no leakage at places
where there were no structures. The RITS scanning by the 2 nd
Respondent’s expert did not show water leakage at other places where no
water was ponded. However all the other evidence shows that there is
12
22. The experts for all the parties agree that given the limited thickness
of the structural slab of the floor of the roof, water leaking through the
waterproof membrane would not travel for very long horizontal distance
before coming out from the ceiling of the 5 th floor, even though their
evidence on the horizontal distance that the water can travel differ from
each other. However, as the size of the 5th floor ceiling is huge, and there
is water leakage at virtually every part of the ceiling, given the small
horizontal distance which the experts estimate the water seeping through
the waterproof membrane can travel, it is obvious that there are many
points of leakage and they cover almost the entire ceiling. It is clearly not
a case that there was only one or a few spots, or one or some localized
parts of the waterproof membrane having failed. It is clearly a case
13
Building is telling that the thickness of the concrete cover had nothing to
do with the spalling.
24. Mr. Poon also sought to suggest that the spalling of concrete at the
5th floor was caused by “exposure under ambient marine environment”. If
that were really the case, one would expect that the whole of the Building
would have been similarly affected and had similar concrete spalling.
However, that was not the situation. The ground floor has good
condition, with no obvious spalling. The condition of the common
staircase, except the roof of the hood of the staircase, was generally good.
It is unreasonable for Mr. Poon to suggest that the 5 th floor would have
greater exposure to such “ambient marine environment” than the ground
floor. While there is nothing between the 5 th floor level of the Building
and the sea, for the ground floor there is only a wire mesh fence at ground
level between the Building and the sea, which could not have effectively
fended off the ground floor from the marine environment at all. Further,
the premises on the ground floor has a completely open façade facing the
sea whereas the premises on the 5th floor has most of the side facing the
sea enclosed by wall. It is simply inconceivable that the 5 th floor would
have been more affected by the so-called “ambient marine environment”
than the ground floor. The impact of carbonates and sulphates from the
sea breeze would affect the 5th floor of the Building just as any other floor
of the Building.
25. Thus, I find that the water leakage from the roof through the
defective waterproof membrane to the 5th floor had caused damages to the
ceiling and the walls of the 5th floor.
15
Whose responsibility
26. There is no dispute amongst the parties’ experts that all layers in
the floor slab of the roof are porous except the waterproof membrane.
Thus, when water is leaking from the roof surface to the ceiling of the 5 th
floor, it must be due to the defects of the waterproof membrane.
Whoever is responsible for the defects of the waterproof membrane will
be responsible for the damages to the 5th floor caused by water leakage.
29. It is also common ground of the experts for the parties that the
layer of cement/sand screeding above the waterproof membrane is for the
protection of the waterproof membrane. It follows that this layer of
cement/sand screeding should also be a common part of the Building, and
is within the responsibility of the 1st Respondent to maintain and repair.
16
30. As to the function of the concrete tile layer on the very surface of
the roof, the experts for the Applicant and the 1st Respondent on the one
hand and the expert for the 2nd Respondent on the other hand have
different views. However, I accept the Applicant’s submission in this
regard and find that the concrete tile layer is not a common part of the
Building but a layer of which the 2 nd Respondent as the owner has the
exclusive right to use and the 2 nd Respondent should bear the
responsibility for the repair and maintenance of this layer.
31. First of all, the standard roof details from the Architectural
Services Department (“ASD”) show that concrete tile layer is
dispensable. There is no need for any concrete tile layer or covering (or
any similar further layer) on top of the cement/sand screeding. It can be
seen from the standard roof details that they were produced by ASD in
1995, and yet as confirmed by Mr. Kwong in his oral evidence, such
specifications are till being used by ASD today. Mr. Poon also said in his
oral evidence that “there are cases without the tiles”. It is clear to me that
any suggestion by Mr. Poon that the concrete tile layer is a must for the
roof is wholly unsustainable.
32. As to the use of any layer like the concrete tile layer on the roof,
Mr. Kwong, who is an architect with particular expertise in matters of
building design as compared to Mr. Poon who is a building surveyor,
gives evidence that the concrete tile layer is “to provide a sound surface
for pedestrian traffic of routine maintenance and activity at the main roof
level”. Mr. Kwong also gives evidence that “merely a layer of
Cement/Sand Rendering could also perform the function of protection” of
the waterproof membrane. Thus, the concrete tile layer is not for the
17
33. Mr. Chan also shares the view of Mr. Kwong. Mr. Chan gives
evidence that “The concrete tiles serve as a finishing layer and form a
‘load’ covering that also provide a wearing surface for maintenance and
pedestrian traffic.” He agrees with Mr. Kwong that “the upper layer
cement sand screeding could already properly perform the function of
protection of waterproof layer against damage, and though the concrete
tiles on top of it could also serve similar function, such concrete tiles
would primarily serve other functions, such as slip protection, finishing
characteristics or facilitate use of the roof.”
34. Mr. Chan further said that “Even for the waterproof material which
would require protection, as mentioned above, the layer of cement/sand
screeding on top of the waterproof layer would have provided sufficient
and proper protection for the waterproof layer. The roof can properly do
without any further layer of tile on top of that cement/sand screeding
layer. … what is important is that such layer of concrete tiles … above
the cement/sand screeding is dispensable from the waterproofing point of
view.”
35. However, Mr. Chan also said in his report that “The waterproof layer
and the cement/sand screeding on top of it protecting it from exposure to
direct sunlight and damage by maintenance traffic are together forming
an integral part of the roofing system. This roofing system performs the
function of waterproofing to guard against water leakage to the interior of
the building.” Mr. Chan has clarified this in his oral evidence and said
that while theoretically the concrete tile layer can be said to have some
18
36. I agree with the Applicant that Mr. Chan’s evidence should be
considered as a whole and not taken out of context. He clearly opined
that the concrete tile layer is not primarily for the protection of the
waterproof membrane.
38. The 2nd Respondent, as an owner, has actually the exclusive right to
possession and use of the roof. The 2 nd Respondent can even have extra
storeys erected on top of the roof according to clause 23 of the Deed of
Mutual Covenant of the Building. Thus, in terms of the right to use the
premises, the 2nd Respondent has the usual right (and indeed more than
the usual right) which an owner of a unit or a floor would have over his
unit or floor. As pointed out by Mr. Chan, it would be very much up to
the 2nd Respondent to decide what sort of layer he wants to put on the
19
surface of the roof, just like what an owner of an internal storey or flat of
a building can do to his flooring. Conceptually, the concrete tiles on the
surface of the roof of a building, the right to exclusive possession of
which being given to the roof owner, are no different from the wooden,
carpet, tile or marble floorings of an internal unit of a building owned by
an individual owner.
40. I therefore reject the 2nd Respondent’s argument that the concrete
tile layer is not “indispensable” and forms part of a “monolithic” system.
The mere fact that the concrete tile layer could offer extra protection to
the layers underneath would not make it a common part of the Building.
If this argument is correct, then any additional layer, such as metal plate,
20
which can afford extra protection to the layers below, would become a
common part.
41. In order to maintain his contention that all of the layers in the floor
slab are “indispensable” and form a “monolithic” system, Mr. Poon
contends that even though there was probably no separate layer of
insulation foam in the roof, the insulation function would have been taken
up by the space underneath the “legged tiles” on the surface of the roof.
While it is true that the use of a layer of insulation foam in the roof was
not common in buildings of such age, and it is unlikely that the floor of
the roof in the Building would have such a layer of insulation foam, Mr.
Poon’s contention that the insulation function would be taken up by the
“legged tiles” is clearly wrong. If legged tiles were used, probably many
would have cracked upon installation of the illegal structures, but there is
no widespread cracking of the concrete tiles found along the places where
the structures were previously erected If legged tiles were used, the tile
joints would not be sealed up, so as to allow air flow underneath the tiles
and to achieve heat insulation purpose. However, the tiles on the roof all
have joints sealed up (except for those where the joints have cracked).
Indeed, there was a piece of broken and debonded concrete tile found on
the roof and it is not a “legged tile”. Chances are clearly that all of the
concrete tiles are not “legged”. In any event, as Mr. Kwong confirms, the
insulation layer if present is only “to protect the space (unit) right
underneath the main roof level from solar heat”, i.e. protecting the top
floor of the building from the heat, rather than protecting the waterproof
membrane from the heat. Mr. Poon himself also agreed that the purpose
of the insulation layer is to protect the top floor of the building from the
heat. Clearly, the insulation layer would have nothing to do with
waterproof membrane.
21
43. There is no dispute that the waterproof membrane has not been
repaired, replaced or re-done by the 1st Respondent or anyone since it was
first laid there when the Building was erected in the 1960s. According to
Mr. Chan, the normal life span of a waterproofing layer like the one in the
Building would be around 15 to 25 years. Mr. Poon said it was around 20
to 30 years. Mr. Kwong initially said that he had seen waterproofing
layer which could last as long as 40 years, but upon further examination,
he clarified that that would be an exceptional case, waterproofing layer
would normally fail by the 30-year mark and it would not be surprising to
see waterproofing membrane starting to fail after 20 years. From these
evidence, it is clear to me that by the time the water leakage started in the
Building, i.e. in mid-1990s or around 1997, the normal life span of the
waterproof membrane of the Building had probably lapsed, and the
waterproof membrane would have started to fail and required a complete
replacement. As Mr. Chan put it, by 1997, after lapse of some 29 years
since completion of construction of the Building in 1968, there is a high
probability – “99% probability” – that there would be leakage because of
aging of the waterproof membrane. Indeed, with the widespread water
leakage all over the ceiling of the 5th floor, it is clearly the case that the
waterproof membrane had gone well beyond its life span.
22
46. However, the Applicant’s claim is not just against the 1st
Respondent, it also contends that the 2nd Respondent is liable for the
repair or reinstallation of the waterproof membrane. The Applicant relies
on various provisions in the Deed of Mutual Covenant of the Building
(clauses 9 and 13, paragraph 5 of Part II of the 3 rd Schedule and
paragraph 4 of the 4th Schedule) as well as section 34H of the Ordinance
23
to hold the 2nd Respondent responsible for repairing and maintaining the
roof. However, as I have ruled above, the waterproof membrane does not
belong to the 2nd Respondent, they do not have the responsibility to repair
it unless they have damaged it as a result of their own fault. Their
liability under these provisions of the DMC or the Ordinance is confined
to the repair of the concrete tile layer.
47. No doubt the 2nd Respondent has never repaired or maintained the
concrete tile layer of the roof and the surface concrete tiles are still the
same tiles when the Building was constructed. Some of the tiles are
cracked, bulging or even heaving. There is a large extent of vegetation
growing along the cement joints of the original concrete tiles. Mr.
Kwong opines that with the cracks, vegetation grows, and as the
vegetation grows the cracks get bigger, allowing vegetation to grow more
and bigger, a vicious cycle aggravating the condition of the roof, and
eventually, the roots keep digging deeper damaging the waterproof
membrane. The Applicant therefore argues that the lack of repair and
maintenance of the surface of the roof by the 2nd Respondent has also
caused the water leakage problem to the 5th floor.
Respondent takes away all the concrete tiles, leaving the cement/sand
screeding layer exposed to open air and water, and vegetation grows on
this layer, the Applicant cannot hold the 2nd Respondent liable for
anything. As an owner of the concrete tiles, the 2 nd Respondent is entitled
to do whatever they like to this layer. They can change the tiles and also
to remove the tiles. As the tiles are not for the protection of the
waterproof membrane, the Applicant cannot insist that the tiles must be
there intact. The same argument will apply when the 2nd Respondent
simply did nothing to maintain the tiles and cracks occurred. The 2 nd
Respondent is under no duty to provide an intact concrete tile layer to
protect the waterproof membrane. As the protection is afforded by the
cement/sand screeding layer, when vegetation grows at this layer, it is the
duty of the 1st Respondent to remove the vegetation in order to protect the
waterproof membrane from being damaged by the roots of the plants.
49. In any event, there is no actual evidence that there are roots of the
vegetation going through the cement/sand screeding layer and the
waterproof membrane causing the leakage. It is only a theory given by
the expert. It is possible that the vegetation is only growing in between
the cement/sand screeding layer and the concrete tile layer. It is also not
possible to say whether the vegetation had caused damage to the
waterproof membrane before it failed its waterproof function due to
aging. Thus, there is no conclusive proof that the vegetation had caused
the water leakage.
52. The unchallenged fact is that by 1983, the Applicant’s chimney and
water tank, and the other 2 chimneys, wooden huts, etc, had already been
erected, and yet there was no water leakage problem discovered or
noticed until mid-1990s. This shows that in carrying out the erection
works, waterproofing materials had been applied on areas affected. The
leakage only came years afterwards and started first at spots where there
had never been any structures. Given the consensus amongst the experts
that the waterproof membrane only had a lifespan of some 20-30 years,
by the time the water started to leak, the end of the lifespan of the
waterproof membrane had actually come. If the waterproof membrane at
anchorage points for chimney or water tank etc. had not been properly
repaired after the installation, one would expect there to have water
leaking within 1 rainy season, but not until some 14 years later. Thus, it
is reasonable to assume that the repair work was properly and
successfully done. In any event, even if one or two of the leakage spots
26
53. The Respondents also seeks to rely on the additional loading by the
structures previously there to suggest that such additional loading might
have damaged the floor slab of the roof and the waterproof membrane. I
accept the Applicant’s submission in this regard. There is simply no
evidence to support this contention. No figures about the loading
capacity of the roof, nor figures of the weight of the structures were
produced. Without those figures, one could not say with any degree of
certainty whether the loading capacity would be exceeded. Indeed, visual
inspection of the roof shows no obvious or widespread damage by
additional load to the surface of the roof. There is also no evidence that
the load of such installation had damaged the waterproof membrane. On
the contrary, many of the tiles along the base of the chimneys or the water
tank were not damaged. It is therefore purely speculative for the
Respondents to suggest that the load of the structures would have
damaged or affected the waterproof membrane.
54. Thus, I do not find that the structures erected on the roof had
anything to do with the water leakage, and even if they do, the effect is
insignificant, and the Applicant is not responsible for the damage caused
by the water leakage. In other words, only the 1 st Respondent is
27
55. The first head of loss suffered by the Applicant is the expenses
incurred by the Applicant as a result of the water leakage problem. Over
the years, as the water leakage problem has become more serious and
widespread, the Applicant has to incur expenses to install more and more
water trays and an elaborate water collection system at the ceiling of the
5th floor, with water trough along the edge of the wall, to collect and drain
away the dripping water. The cost of installation of the drainage system
together with the repairs to the system and the repairs to the ceiling
amount to $95,828.00. There are also cleaning expenses at the roof to
reduce the frequency of water flooding caused by the water leakage
amounting to $26,715.00. The water leakage has also caused damage to
the first services sprinklers and piping installed at the ceiling of the 5th
floor, for which the Applicant has incurred expenses for their repairs.
The amount is $17,700.00. The Applicant has produced the relevant
receipts and I find them to have been reasonably incurred to remedy the
water leakage. So these amounts are allowed.
57. The Applicant’s main claim is the loss of rental. The Applicant
alleges that because of the persistent water leakage problem, the normal
use of the 5th floor has been adversely affected. Despite the erection of
the elaborate water collection system, to minimize the direct impact of the
dripping water on the use of the premises, it is wholly understandable that
any potential tenant viewing the premises would hardly agree to lease the
premises unless he had no choice and would ask for a significant
reduction in rental were they going to rent it. It was after the premises
had been put on the market for a long time before a tenant was secured on
1 December 2000.
59. Furthermore, the evidence of Mr. Lau Wah is that the Applicant
carried out renovation to the subject premises which was completed in
29
February 1998 and the subject premises was place in the market for rent.
However, the earliest invoice for works carried out in the 5 th floor
produced by the Applicant was dated 16 April 1998. That invoice
included an item for works relating to tiles and cement in the furnace
room. Mr. Lau also said that he had thought of renting out the subject
premises to an associated company. Mr. Jack Wong, director of Flourish
Property Agency Limited, estate company engaged in the leasing of the
subject premises also said that he became involved in the leasing of the
subject premises at the end of 1999, but cannot tell when his company
started to be engaged. Mr. Wong produced his company’s computer
records showing only those from 1999. He explained that because of the
conversion of the computer system, the records before 1999 were not
retrievable. The computer records produced by Mr. Wong showed
leasing information of various units of the subject building as well as
other industrial building, including some which had been leased out after
being placed in the market. However, Mr. Wong has not produced the
record of the subject premises which would have shown when the subject
premises was put on the market and the asking rent. It will be seen form
the computer records that most of the units were open in the market for a
considerable period of time. From 1999 to 2001, the asking rent of these
units were also dropping. I accept that it is unlikely that the subject
premised would be successfully let out immediately after being placed in
the market. It would be even more difficult to let out if the asking rent
were not reduced when the market condition was poor during the years
from 1998 to 2000. Neither Mr. Lau nor Mr. Wong has given evidence if
the asking rent had been reduced during the time when the subject
premises was put on the market. It would not be unreasonable to assume
that there would be a period of waiting time in the market for the subject
premises.
30
60. Thus, I find that the alleged loss of rental before the subject
premises was actually let out should be disregarded.
61. As to the market rent, the Applicant’s expert, Ms. Pamela Lam has
provided a valuation report and the 1st Respondent’s expert, Mr. Thomas
Li has also provided his report. The 2 experts have also respectively
given oral evidence. I accept the Respondents’ submission that the
subject premises is for godown use as stated in the occupation permit.
Although the Conditions of Sale and the Deed of Mutual Covenant permit
industrial use, conversions complying with relevant regulations would be
necessary if other legally permitted use is intended. Mr. Li explained that
it would be more difficult to convert godown than factory to office use
and the demands for godown premises would be quite different from
those for factory premises. Mr. Li has used floors in the same building
with the same size and orientation, requiring minimal adjustments. The
only factors for adjustments are time and level. Any adjustment would
contain a subjective element and in a valuation, the less adjustment the
better. As Ms. Lam has used comparables in other buildings which are
industrial buildings, more adjustments have to be made. Ms. Lam has
62. Taking all the factors and evidence into account, I am of the view
that Mr. Li’s evidence is more reasonable and reliable than Ms. Lam’s. I
will therefore adopt Mr. Li’s valuation. I accept that the Applicant has
suffered a loss of rental as assessed by Mr. Li. A comparison of the
market rent and actual rent received by the Applicant is set out below:
($59,000 - $47,750) x 24
($49,000 - $47,750) x 24
($57,000 - $55,000) x 24
32
Total: $616,717
Conclusion
membrane, failing which the Applicant be at liberty and at the cost of the
1st Respondent to carry out the works themselves;
(3) The 1st Respondent do pay the Applicant damages in the sum of
$756,960.00 together with interest thereon at judgment rate from today
until satisfaction;
(4) The 1st Respondent do pay the Applicant further damages together
with interest thereon at judgment rate to be assessed if not agreed;
(6) Costs order nisi: Save where there is previous costs order, the 1 st
Respondent do pay the Applicant their costs of the proceedings against
the 1st Respondent with certificate for counsel to be taxed on District
Court Scale if not agreed; and
(7) Costs order nisi: Save where there is previous costs order, the
Applicant do pay the 2nd Respondent their costs of the proceedings with
certificate for counsel to be taxed on District Court Scale if not agreed.
34
Mr. T.M. LEE, instructed by M/S Lo & Lo, for the Applicant
Mr. Dickson K.F. PANG of M/S Y.C. Lee, Pang, Kwok & Ip for the 1 st
Respondent
Mr. Thomas T.M. KWAN, instructed by M/S Kwan & Chow, for the 2 nd
Respondent