Professional Documents
Culture Documents
ReportNo. 1149a-MAI
FILE COPY
Malawi: Appraisalof
NkulaFalls11HydroelectricProject
March 11, 1977
Energy& Water Supply Division
EasternAfrica RegionalOffice
Public Disclosure Authorized
H
Public Disclosure Authorized
Public Disclosure Authorized
HYDROELECTRICPROJECT
CURRENCY EQUIVALENTS
1 US$ = 97 Tambala
I Malawi Kwacha (MK) = 100 Tambala
1 Malawi Kwacha = US$1.10
January - December 31
FOR OFFICIALUSE ONLY
MALAWI
Table of Contents
Page No.
Description ........................................ 6
Estimated Cost ..................................... 6
Basis for Estimates ................................ 8
Financing .......................................... 8
Disbursements ...................................... 8
Detailed Design and Construction Supervision ....... 9
Construction Schedule .............................. 9
Procurement ........................................ 9
Environmental Studies .............................. 9
Effect of Nkula II on Existing Works .... ........... 9
This document has a rtticted distribution and may be used by recipients only in the perfotmance
of their officialduties.Its contentsmaynot otherwisebe disclosedwithoutWorldBankauthorizAtion.
TABLL OF CONTENTS (Continued)
Training ........................................... 13
Accounting and Auditing ............................ 13
Risks .............................................. 13
List of Annexes
ANNEX
ii. The project will develop a hydroelectric site at Nkula Falls with
a dam, a headrace tunnel and penstock system and a powerhouse sufficient
for an ultimate plant capacity of 90 MW of which 2 x 18 MW hydro units would
be included in the project with additional units being installed in the
future to meet increasing power demand. The site potential is expected to
be fully utilized by 1989. The estimated project cost is US$66.4 million
equivalent including an estimated foreign exchange cost of US$50.6 million.
Taking into account the estimated interest during construction of US$11.6
million, of which the foreign exchange component would be US$6.1 million,
the project's total financing requirements would be US$78.0 million, includ-
ing US$56.7 million in foreign exchange. Of these requirements up to
US$59.2 million equivalent is expected to be available from various lending
agencies. The Bank would provide US$25 million equivalent by way of a
US$9 million standard Bank Loan, a US$8 million Bank Loan on Third Window
Terms and US$8 million IDA Credit to help finance the foreign exchange
costs of civil works, ESCOM's training program and interest during construc-
tion on the Bank loans. AfDB, CDC, the Federal Republic of Germany and FED
are expected to provide up to about US$34 million. External finance would
cover the full foreign exchange requirements and possibly, a small proportion
of local costs. The remaining finance would be provided from ESCOM's internal
cash generation. Interest on AfDB, Federal Republic of Germany, FED, IDA and
Third Window Funds would be capitalized during construction and treated as
Government's contribution.
iv. Contracts for civil works, which would be partly financed by the
Bank Group would be awarded on the basis of international competitive bidding
in accordance with the Bank's guidelines for procurement.
finance of US$3 million equivalent was provided by AfDB for the foreign
exchange costs of 66-kV transmission system and distribution extensions. The
project was completed close to schedule in 1973, at a total cost of US$16.5
million including a 14% cost overrun. To help meet this overrun CDC and the
Industrial Development Bank of Malawi (INDEBANK) made further loans totalling
US$1.8 million. Cost overruns were due to unforeseen rock conditions and an
underestimate of contractors establishment costs.
vi. A second IDA Credit (426-MAI) of US$7.5 million was made in 1973,
to help finance the foreign exchange costs of the second stage of the Tedzani
Hydroelectric Scheme which added 24 MW to generating capacity. The project
also included a 14-MW gas turbine. CDC participated in the project finan-
cing with a loan of US$6 million. The project has essentially been completed
according to the original schedule, but the estimated cost of US$18 million
will be 27% over the appraisal estimate. CDC has provided a further US$2
million to help finance the cost overrun which is attributable to an un-
anticipated acceleration in world inflation.
viii. The project is the first part of the least cost alternative for
adding a further 90 MW of generating capacity to ESCOM's interconnected
system and the internal rate of return for the complete development would
be about 12%.
ix. The project is suitable for Bank Group finance of US$25 million
equivalent.
MALAWI
I. INTRODUCTION
1.01 This report appraises the first phase of the Electricity Supply
Commission or Malawi's (ESCOM) proposed Nkula II Hydroelectric Power Project.
The estimated project cost is MK 60.4 million (US$66.4 million), excluding
interest during construction, with a foreign currency component of MK 46.0
million (US$50.6 million). Estimated interest during construction would add
an estimated MY, 10.6 million (US$11.6 million) to ESCOM's total project
financing requirements. The Government of Malawi has asked the Bank Group
to help finance the foreign exchange costs and will receive further financing
assistance from the Commonwealth Development Corporation (CDC), the African
Development Bank (AfDB), the European Development Fund (FED) and the Federal
Republiz of Germany.
1.02 This will be the third Power Project in Malawi which has been
financed with Bank Group assistance. The main objective of all three pro-
jects is to develop the hydroelectric potential of the Shire River, which
has been the main source of ESCOM's additional generating capacity since
1966.
1.04 In 1970 through an IDA Credit (178-MAI) the Bank Group provided
US$5.25 million to help finance the foreign exchange costs of a project
adding a further 16 MW of hydro generating capacity through the first stage
of the Tedzani Falls development. The project also included a 3-MW diesel
generating station and transmission and distribution facilities. Parallel
finance of US$3 million equivalent was provided by the African Development
Bank.
1.09 All the above developments of the Shire River are based on the
recommendations of two British consulting firms, Kennedy and Donkin, and
Watermeyer, Legge, Piesold and Uhlmann who have been employed by ESCOM for
many years. Another British consulting firm, Coopers and Lybrand Associates
Ltd., also assisted in preparing the report on the proposed development.
Energy Resources
2.03 The only known fossil fuels in Malawi suitable for thermal genera-
tion are coal deposits at Livingstonia, a remote area of the Northern Region.
The development of these deposits is, at present, uneconomic due to their
distance from the main centers of population. In any case, local coal would
not be cheaper than coal imported from Mozambique and Rhodesia. Fuel oil is
not imported in bulk because there is little demand for it; diesel fuel in
Blantyre now costs about US$15.4 per million keal.
2.04 Geothermal power potential exists in the north of the country but
extensive investigations have still to be carried out before a real estima-
tion of the potential and feasibility of development can be established.
2.07 The industrial sector accounts for the bulk of electricity con-
sumption. During 1970-1975, industrial users accounted for about 63% of
total energy sales, followed by the commercial sector with about 18% and the
residential sector with about 17%. A statistical summary for 1970 and 1975
together with a forecast for 1980 is given below and Annex I gives fuller
details. Between 1967 and 1975 annual growth of total sales ranged from a
high of 23% in 1975 to a low of 8% in 1974 influenced largely by varying
rainfalls, which affected annual power requirements for irrigation, and by
industrial expansion.
Actual Forecast
1970 1975 1980
Proportion of Sales:
2.11 Apart from the proposed project, which will meet the growing demand
in the interconnected system, ESCOM's development program in the period 1975-
1980 includes extensions of existing distribution facilities and construction
of a 541-km, 132-kV transmission line from Tedzani and Nkula Falls II to
Chinteche in Northern Malawi, which will supply expected industrial loads
in the Chinteche area. 1/ The first stage of this line, which will be routed
to Salima, with a branch line to Lilongwe, is being constructed with Canadian
finance channelled through AfDB and is expected to be operational by 1978 or
1979. If the second stage of the 132-kV line from Salima to Chinteche were to
be postponed, it would have no significant effect on the timing of the installa-
tion of the additional generators required to bring the project facilities to
maximum use (see para. 4 in Annex 11).
Rural Electrification
2.13 Government has yet to determine its goals for rural electrifica-
tion. This type of development electrification would be unprofitable; Gov-
ernment's prior social objective is to extend electric service to the urban
poor. Some electrification of poor urban areas is taken into consideration
in housing development programs; however, comprehensive plans have yet to be
developed for supplying electricity to the bulk of the urban poor.
Description
3.01 The project will be the major part of ESCOM's 1975-1980 generating
program. It consists of:
(d) Training.
3.03 The location and dimensions of the dam, waterways, sizes of the
plant and individual generating units, and dimensions of the other major
equipment (such as transformers and switchgear equipment) are acceptable
and have all been determined by ESCOM's consultants, as a result of a series
of cost optimization studies based on the estimated load growth in the power
system, the prevailing local conditions (hydrological, geological and topo-
graphical), and sound engineering principles.
3.04 Although there are no competing claims for the waters of the Shire
River upstream of Nkula II, continued availability of water in sufficient
quantities for the project would be essential. Government will not permit any
abstraction of water from the Shire River or its tributaries upstream of Nkula
that would reduce the potential output of the Nkula II Hydro station (unless
the Bank agrees that such abstraction would be economically justified), and
will permit ESCOM to divert water from3the Shire River in such amounts as may
be necessary (but not less than 170 m Is) for the purpose of power generation
at Nkula Falls II. A similar covenant was included in Credit for the Second
Power Project.
Estimated Cost
3.05 The estimated total cost of the project is MK 60.4 million (US$66.4
million equivalent), of which MK 46.0 million (US$50.6 million), about 76%,
would be foreign exchange. These costs are before interest and commitment
-7-
Contingencies:
Total Project Cost 14.4 46.0 60.4 15.8 50.6 66.4 100.0
Interest during
construction (IDC) /2 5.1 5.5 10.6 5.5 6.1 11.6
Total Financing
Requirements 19.5 51.5 71.0 21.3 56.7 78.0
/2 Foreign IDC consists of interest on Bank, FED, CDC, AfDB and Federal
Republic of Germany loans.
Financing
Disbursements
3.10 It is proposed to use the Bank/IDA finance to help meet foreign ex-
change costs by disbursing the foreign costs of civil works and ESCOM's train-
ing program, and interest during construction on the Bank Loans.
-9-
3.11 If any of the Bank Group Funds remains undisbursed after completion
of the project, they would be canceled. An estimated disbursement schedule
is given in Annex 5.
Construction Schedule
3.13 Tender documents have already been prepared and issued for the main
project components. Contractors' offers for the construction of the main
civil works were received in December 1976. Construction is expected to
commence mid-1977, and to be completed in 1980. The project construction
schedule is shown in Annex 6.
Procurement
3.14 Contracts for civil works, to be partially financed from the Bank
Group funds and also gates, penstocks and screens which would be financed by
AfDB, will be awarded shortly on the basis of international competitive
bidding, following the Bank's Guidelines for Procurement. Other contracts
will be awarded in accordance with co-financiers procurement procedures.
Environmental Studies
3.16 The proposed Nkula II Dam will raise the natural water level of the
Shire River about 7 m (maximum). Although this change will have an effect on
- 10-
the existing Nkula I hydroelectric facilities and on the water intake facili-
ties of Blantyre Water Board (BWB), only minor inexpensive modifications to
these facilities will be needed for the facilities to function satisfactorily.
4.01 The proposed project represents the least cost solution for meeting
Malawi's growing power demand until the early 1980's.
Market Growth
4.03 About two-thirds of ESCOM's industrial sales are to four large con-
sumers. By far the largest industrial customers are SUCOMA, a sugar estate
and the Blantyre Water Board, both of whom use electricity primarily for pump-
ing water. Growth in industrial sales between 1967 and 1975 has varied between
30% in 1975 to 4% in 1974 with an average annual growth rate of 16%. After
taking into account the plans of major industrial consumers, the growth rate
from 1977 to 1984 is projected to average 11% per annum. The average annual
growth rate for commercial electricity sales is projected at 10% from 1977 to
1984, as compared to 15% between 1967 and 1976.
4.04 Sales to low density residential consumers, who are mainly higher
ranking government officials and expatriates living in Blantyre, Lilongwe
and Zomba, are projected to increase at an average rate of 9% between 1976
and 1984. As a percentage of total sales, low density sales are expected
to decline from 16% in 1976 to 12% in 1980.
4.05 Sales to ESCOM's high density residential consumers, who live mainly
in the larger towns in Government low rental housing, started from a low base
and had the highest growth between 1967 and 1975, ranging between 18% in
1975 and 50% in 1967 with an average growth rate of 34%. Such high growth
rates are not expected to continue in the future and a gradual fall in demand
growth to about 20% by 1984 is expected. Detailed historical sales figures
from 1967 to 1976 and projected sales figures from 1976 to 1984 are shown
in Annex 7 together with corresponding trends in maximum demand and generation.
4.07 The projected maximum demand and energy requirements are shown in
Annexes 8 and 9, which demonstrate that, with the commissioning of the second
stage Tedzani Project, the interconnected system would be capable of meeting
peak demand and energy requirements until 1980 after which the generating
capacity to be provided by the project would be required.
Return on Investment
4.12 Measuring the rate of return on the complete development and using
present tariff levels in calculating benefits gives a rate of return of 11.5%.
For the project only the rate of return would be 9%. The method of calcu-
lating the rate of return is described in Annex 11.
5.Oi The US$9 million standard Bank Loan would be made directly to ESCOM.
The Government of Malawi would be the borrower in the case of the US$8 mil-
lion Bank Loan on Third Window terms and US$8 million IDA Credit. Government
would relend the latter US$16 million finance to ESCOM (the beneficiary)
(para. 6.08).
Institutional Framework
5.03 Under the Act the Commission consists of a chairman and not less
than three or more than five other members, all of whom are appointed by
the Minister. At the present time, ESCOM reports to the Ministry of Trade,
Industry and Tourism.
5.05 Under its Act ESCOM is at all times subject to the general direc-
tion of the M'inisterand requires ministerial approval of borrowings, capital
and revenue budgets and tariff changes. However, good working relationships
exist between the Minister and ESCOM which is allowed considerable initiative
in day-to-day operations and whose recommendations are usually accepted.
5.07 ESCOM's total staff at the end of 1975 was about 1,200. Of about
110 senior positions, 33 were occupied by expatriates including three of
the four top management posts. However, through a well-considered training
program, the number of expatriates has been graduallv reduced and by 1980
ESCOM seeks to localize its entire staff.
5.09 ESCOM's staff is competent to carry out the project with engineer-
ing consulting assistance and to carry out other capital works during the
project implementation period. To ensure the continuation of ESCOM's manage-
ment capability, were new appointments to the positions of General Manager,
Chief Engineer, Secretary and Financial Controller will not be made before
taking into account the views expressed by the Bank Group on the proposed
appointments.
Training
5.11 At the present time, ESCOM has 13 students studying overseas for
degrees in mechanical and electrical engineering, one in civil engineering,
and a further five students taking technician courses. In 1977 it is expected
that five students will obtain their degrees and will join the Commission to-
gether with a further two students who have had technician training. ESCOM
also has two students studying abroad for professional accounting qualifi-
cations and one returned to Malawi in 1976.
Risks
VI. FINANCE
6.01 ESCOM's earnings over the last few years have been good and it is
expected that this will continue during the project construction period and
subsequently. ESCOM's actual and projected financial statements, consisting
of income statements, cash flow projections and balance sheets, are given
in Annexes 14, 15, and 16, respectively. The notes and assumptions for the
financial statements are in Annex 17, and a statement of loans outstanding
at December 31, 1975 and a debt statement are presented in Annex 18.
…(millions of Kwachas) -
6+03 The rate of return ornaverage net fixed assets valued at historical
cost was at a high of 14% in 1972, declining temporarily below the present
covenanted level of 10% to 8% in 1974 when the Tedzani Falls Hydroelectric
scheme was added to the asset base, and then increasing to 13.6% in 1975.
Between 1970 and 1975 net fixed assets in operation, expressed in historic
costs, increased 2.3 times from MK 9.7 million in 1970 to MK 22.0 million in
1975. It is estimated that during the same period, ESCOM financed 23% of
capital expenditures, including interest during construction, from internal
cash generation. Considering the high level of capital expenditures during
this period, this is considered satisfactory.
6.04 ESCOM's debt/equity ratio improved from 85/15 at the end of 1970
to 76/24 at the end of 1975 as a consequence of a good level of net income
during this period. Despite this, however, ESCOM's cash position has been
tight because internal cash generation has been absorbed by increasing levels
of capital expenditure.
Tariffs
6.06 For the purpose of measuring ESCOM's rate of return on net fixed
assets, these assets would be revalued at December 31, 1975 at a gross value
of MK 45.01 million less accumulated depreciation of MK 11.8 million. The
revaluation was estimated using the United Kingdom Manufacturers Export
Index, with some modifications. Although a better method of revaluing assets
should be established in future, the initial revaluation at December 31, 1975
is acceptable as existing assets would be relatively small compared to assets
to be placed in operation between 1976 and 1980. ESCOM will revalue its
fixed assets annually in accordance with methods acceptable to the Bank and,
after consultation with Government is expected to submit a proposal shortly.
In the financial projections an assumed annual 8-1/2% revaluation of fixed
assets has been made between 1976 and 1981, the year after the Nkula Falls II
Hydroelectric Project becomes operational.
1/ This would bring ESCOM's tariffs into the middle range for Eastern
African countries.
- 16 -
Millions of Millions of
Kwachas US Dollars %
Requirements
Nkula II
6.08 In the financing plan it has been assumed that the proceeds of the
proposed IBRD Loan of MK 8.2 million (US$9 million) would be made to ESCOM
over 20 years, including a 4-1/2-year grace period, at an 8-1/2% interest.
The actual interest rate would be that prevailing at the time the project is
presented to the Board, but an adjustment to this rate will not materially
effect the financing plan. Government intends to make the proceeds of the
Third Window Loans and IDA Credits available to ESCOM at the same interest
rate as the standard Bank Loan, with interest during the construction period
being added to the onlending and, repayments being made to Government over
20 years commencing 1981. It has been assumed in the financial projections
that FED, Federal Republic of Germany and AfDB funds would be made available
to ESCOM on similar terms to IDA and Third Window finance. 1/
6.09 The CDC loan would be for a 20-year term, including a 5-year grace
period, and at an 8-1/2% interest rate.
million (US$3.96 million) cash deficit in 1977 despite good earnings from
operations. As a condition of effectiveness, ESCOM would make arrangements
satisfactory to the Bank to provide such funds. It is expected that part
of the estimated fund requirements would come from the continuance of ESCOM's
present overdraft facilities of MK 1.25 million (US$1.37 million). In the
financial projections it has been assumed that ESCOM would borrow MK 2.4 mil-
lion (US$2.64 million) in 1977 to be repaid in 1978. ESCOM has already
borrowed MK 1 million (US$1.1 million) from Indebank in 1977 to be repaid
in 1978.
6.14 ESCOM will not incur debt, without prior Bank approval, unless future
debt service is covered at least 1.5 times by internal cash generation.
(a) that ESCOM will consult with the Bank regarding any proposed
appointments to the positions of General Manager, Chief
Engineer, Secretary and Financial Controller (para. 5.09);
(b) that ESCOM will maintain its tariffs at a level which will
yield at least 12% on its average revalued net fixed assets
in 1978 and 1979 and 8% thereafter (para. 6.05); and
7.03 Subject to the foregoing, the project is suitable for Bank Group
finance of US$25 million equivalent.
1965 1966 1967 1968 1969 1970 19;t 19/2 1973 1974 1975
3. System Demand (MW) 9.6 13.2 16.5 19.2 21.5 21.9 24.2 28.5 34.3 39.3 48.2
5. Transmission System
66 kV lines (miles) 63 102 333
33 kV and lower (miles) 574 906 1,415
Total length of overhead lines (miles) 637 1,008 1,748
33 kV and lower Cables (miles) 12 27 42
66 kV Substation Capacity (MVA) - 59 134
33 kV and lower Substation Capacity (MVA) 53 89 159
Total Substation Capacity (MVA) 53 148 293
6. Average Tariff
In Malawian Tambala/kWh 2.84 2.26 1.90 1.83 2.00 2.00 2.05 2.02 2.09 2.12 2.39
In USG/kWh 3,12 2.49 2.09 .0l 2.20 2.20 2.25 2.22 2.30 2.33 2.63
7. Staff
Total Staff 675 604 728 838 790 853 954 1,103 1,253 1,110 1,206
Number of Expatriates 45 40 38 37 35 33
8. Number of Connections 5,317 6,494 7,042 7,829 8,702 9,709 10,539 11,698 12,814 14,312 15,300
February 1976
ANNEX 2
Page 1
MALAWI
MALAWI
Toprhy
Geology
Hydrology
6. The outflow of Lake Malawi which will be the source of most of the
water to be used by hydro plant is partially controlled by the Liwonde
Barrage, comprising a sill at river bed level and 14 tainter gates 9.15 m
long by 6.70 m high with 0.61 m high flash-boards atop each gate. Partial
control only is achieved by the dam because at low lake levels or very large
flows channel control will develop between the dam and the lake. Low lake
levels are possible because the difference in average inflow to the lake
and evaporation is small considering the size of the lake. The converse is
also true if inflows are unusually large. Present Malawi policy is to main-
tain a lake level at elevation 473.5 m and avoid levels higher than 474.8 m,
the highest level reached in 1964 before the dam was in operation. Tanzania
which forms part of the lake shoreline with Malawi and Mozambique is said to
be in agreement with these policies but Malawi has 3conducted studies which
considered minimum lake outflows higher than 170 m Is. 3These considerations
would involve higher lake levels. For instance a 230 m /s minimum flow would
mean lake levels up to 475.9 m. Although no damage estimates have been made
for lake levels above 474.8 m, it is the consultants judgement that Malawi
would suffer as much or more than the other shoreline countries, Mozambique
and Tanzania. Therefore, it is unlikely that Malawi in its own interest would
allow lake levels to go too high.
Silt
7. The Shire carries a silt load which sometimes exceeds 2,000 parts
per million. It is of a nature which is highly erosive to turbine runners
requiring replacement and repair sometimes in less than one year; despite
the most arduous efforts to flush the silt downstream, it will probably
reduce the small volumes of storage available to the Shire projects which
is valuable for daily regulation. Tedzani I Project included a siltation
chamber in the water ways as a solution to this problem, but it proved to be
a dismal failure. A spare turbine runner is included in the cost estimates
to replace damaged runners during maintenance period.
MALAWI
Part A
1.02 Dam & Intake 2.44 5.61 8.05 2.68 6.18 8.86
1.08 Physical Congingency 20% 1.32 3.07 4.39 1.45 3.38 4.83
1.10 Engineering & Admin. 10% 0.94 2.40 3.34 1.03 2.64 3.67
2.00 Gates
/1 Price contingencies: 17.3% for local currency of civil works; 17.2% for
foreign currency of civil works; 27.7% for local currency of equipment;
and 16% for foreign currency of equipment have been added (see page 4
of this Annex).
ANNEX 4
Page 2
2.05 Physical Contingency 10% 0.04 0.29 0.33 0.05 0.32 0.37
2.07 Engineering & Admin. 10% 0.05 0.25 0.30 0.05 0.28 0.33
1.02 Physical Contingency 10% 0.17 0.94 1.11 0.18 1.04 1.22
1.04 Engineering & Admin. 10% 0.14 0.84 0.98 0.16 0.92 1.08
2.02 Physical Contingency 10% 0.04 0.30 0.34 0.04 0.33 0.37
2.04 Engineering & Admin. 10% 0.04 0.26 0.30 0.04 0.29 0.33
3.02 Physical Contingency 10% 0.01 0.02 0.03 0.01 0.02 0.03
3.04 Engineering & Admin. 10% 0.01 0.02 0.03 0.01 0.02 0.03
/1 Price contingencies: 17.3% for local currency of civil works; 17.2% for
foreign currency of civil works; 27.7% for local currency of equipment;
and 16.0% for foreign currency of equipment have been added (see page 4
of this Annex).
ANNEX 4
Page 3
Price Escalation
Assumptions
3. The above calculations give a price escalation of 17.3% for local currency
of civil works; 17.2% for foreign currency of civil works; 27.7% for local
currency of equipment; 16% for foreign currency of equipment; and 17.4%
on the total Project base cost.
…---------------------
Millions of Kwachas ------------------------
Civil Works Equipment
Local Foreign Local Foreign Total
Years Currency Currency Total Currency Currency Total Project
MALAWI
1977/78
1978/79
1979/80
1980/81
1981/82
1/ Total Bank loans is US$17 million of which US$8 million Third Window. Bank
Loans wil be disbursed pro-rata on the basis of 9:8 ratio. Third Window
Loan disbursements are shown in parenthesis.
ELECTRICITY SUPPLY COMMISSION OF MALAWI
CONSTRUCTION OF STAGE 11NKULA FALLS HYDROELECTRIC PROJECT
CONSTRUCTION PROGRAM
Quartersl 11 .L.jL..l1
CIVIL ENGINEERING PROGRAM
ENGINEERING
S R
PENST'OCKS & MANIFOLD T A
CONSTRUCTION
MOBILIZATION CLOSORE
MODIFICATIONS NKULA I m 1# Is _ a
PLANT PROGRAM
CONTRACT NO. I
WATER AVAIL-ABLE
TURBINES/AL-FERNATORS/CRANE R
CONTRACT NO. 2
SWITCHGEAR/TRANSFORMERS T
CONTRACT NO. 3
World BaeE-1569WiRI
ANNEX 7
Page I
MALAWI
Southern Region 1/ 44.84 55.74 62.01 71.93 76.83 95.78 106.97 111.94 146.30
Lilongwe 2/ 1.66 1.89 2.07 2.43 2.94 3.46 4.33 3.80 4.30
Others _/ 0,13 0.18 0.33 0.36 0.42 0.51 _ 0.77 0.85 0.99
Total 46.63 57.81 64.41 74.72 79.74 4/ 99.75 112.07 116.57 151.59
Growth Rate % 24.2 24.0 11.4 16.0 7.1 - 25.0 12.3 4.0 4A 30.0
Soutbern Region 14.49 16.77 18.54 20.33 21.49 23.06 24.03 25.50 27.10
Lilongwe 0.76 0.87 1.08 1.36 1.72 2.20 2.95 4.24 4.90
Others 0.08 0.08 0.11 0.16 0.13 0.17 0.31 0.40 0.66
Total 15.33 17.72 19.73 21.85 23.34 25.43 27.29 30.14 32.46
Growth Rate %/ 26.8 15.6 11.3 10.7 6.8 8.9 7.3 10.4 7.7
Southern Region 12.77 14.56 16.38 18.64 20.99 23.56 26.32 29.43 34.40
Lilongwe 0.85 1.06 1.25 1.44 1.74 2.46 3.69 6.42 7.50
Others 0.20 0.42 0.46 0.67 0.74 0.90 1.22 1.42 1.65
Total 13.82 16.04 18.09 20.75 23.47 26.92 31.23 37.27 43.55
Growth Rate 7 36.8 16.0 12.8 14.7 13.1 14.7 16.0 19.3 16.8
Southern Region 0.43 0.62 0.88 1.27 1.72 2.37 2.93 3.84 4.50
Lilongwe 0.05 0.07 0.08 0.10 0.13 0.18 0.22 0.39 0.49
Others 0.01 0.01 0.01 0.02 0.03 0.05 0.07 0.09 0.10
Total 0.49 0.70 0.97 1.39 1.87 2.60 3.22 4.32 5.09
Growth Rate 1. 50.8 42.8 38.6 43.3 34.5 39.0 23.8 34.2 17.8
Southern Region 0.59 0.62 0.68 0.81 0.81 1.04 1.08 1.13 1.21
Lilongwe 0.14 0.16 0.17 0.17 0.20 0.21 0.21 0.21 0.21
Others
Total 0.73 0.78 0.85 0.98 1.01 1.25 1.29 1.34 1.42
Growth Rate 2T 27.8 6.8 9.0 15.3 3.1 23.8 3.2 3.9 5.6
Southern Region 0.34 0.39 0.42 0.46 0.47 0.48 0.48 0.53 0.61
Lil=ngwa 0.11 0.25 0.34 0.46 0.47 0.60 0.04 0.05 0.06
Others 0.01 0.01 0.01 0.01 0.16 0.23 0.23 0.28 0.30
Total 0.46 0.65 0.77 1.08 1.17 1.30 0.80 0.88 0.99
Soothern Region 73.46 88.70 98.91 113.44 122.31 146.29 161.81 172.37 214.12
Lilongwe 3.57 4.30 4.99 5.96 7.20 9.11 11.44 15.11 17.46
Others 0.43 0.70 0.92 1.22 1.48 1.85 2.59 3.04 3.50
Rogian's Total 77.46 93.70 104.80 120.62 130.99 157.25 175.84 190.52 235.08
Export to Moaembique - 0.22 0.90 1.28 1.47 1.90 2.20 1.73 2.00
Total Sales 77.46 93.92 105.70 121.90 132.46 159.15 178.04 192.25 237.10
Growth Rate 7. 26.6 21.2 12.5 15.3 8.7 20.1 11.9 8.0 23.3
Units Generated (GWh) 85.16 102.38 116.11 133.02 144.92 175.25 195.30 213.33 259.51
Maxiiun Demand (MW) 1/ 16.5 19.2 21.5 21.9 24.2 28.5 34.3 39.3 48.2
System Load Pactor / 1/ 55.6 57.6 58.0 65.3 63.8 66.5 64.0 61.6 61.3
3/ Others include Mu-zuz and Chintechi which will be connected to the interconnected system by 1981, and also Dedze, Liwonde and Mengochi which were connected to
the System in 1974.
4/ Low growth rates are due to lower energy consumption by SUCOMA a najor industrial consuner.
IBRD
Jaorary 1976
ANNEX 7
Page 2
MALAWI
Sputhern Region 154.27 166.08 184.78 197.99 219.07 232.05 249.67 268.59 290.35
Lilongw~e 5.43 6.38 6.80 8.72 9.92 11.03 12.90 14.91 16.90
Others 1.04 1.15 1.34 1.44 14.09 61.83 61.91 62.04 62.10
Total 160.74 173,61 192.92 208.15 243,08 304.91 324.48 345.54 369.35
Growth Rate % 6.0 8.0 11.1 7.9 16.8 25.4 6.4 6,5 6.9
Southoro Region 29.74 32.12 34.69 37.46 40.46 43.70 47.19 50.97 55.00
flot-gwc 5.69 6.91 8.27 10.05 12.50 14.50 15.10 15.74 16.45
0.52 0.58 0.66 0.72 0.80 0.89 0.97 1.07 1.17
mooDl 35.95 39.61 43.62 48.23 53.76 59.09 63.26 67.78 72.62
Dotth late *, 10.7 10.2 10.1 10.6 11.5 9.9 7,1 7.1 7.1
S'0100th- Rcomai 38.10 42.20 46.75 51.78 57.36 63.54 70.38 77.97 86.40
5al atoazo 9.84 10.93 11.99 13.98 14.68 16.C1 17.01 18.00 19.20
1.97 2.13 2.36 2.60 3.04 3.42 3.83 4.28 5.91
T,t.l 49.91 55.26 61.10 68.36 75.08 82.97 91.22 100.25 111.51
rc-tlth Rato ' 14.6 10.7 10.6 11.9 9.8 10.5 9.9 9.9 11.2
Solthern Region 6.30 8.18 9.08 12.36 15.99 19.90 24.20 29.00 35.00
Saroco 0.66 0.87 1.32 1.67 2.22 2.95 3.33 3.90 4.60
tOthers 0.13 0.16 0.19 0,21 0.24 0.28 0,31 0.35 0.40
S;.0.h5rn 04 ax' 1.30 1.35 1.40 1.45 1.50 1.60 1.70 1.80 1.90
0.25 0.30 0.30 0.30 0.35 0.35 0.40 0.40 0.50
le-s
C 0.13 0.25 0.35 0.40 0.50 0.50 0.50 0.56 0.60
S Rog On 0.60 0.70 0.80 0.90 1.00 1.10 1.20 1.30 1.40
-. ;-ra,u 9.l0 0.IO 0.10 0.10 0.10 0.10 0.10 0.10 0.10
C l, ers 0.15 0.15 0.15 0.19 0.20 0.20 0.20 0.20 0.20
xor m'.egion
8e^i 230.31 250.63 276.90 301.94 335,38 361.89 394.34 429.63 470.05
21.97 25.67 29.97 34.82 39.84 44.94 48.73 53.05 57.75
Ot-sr. 3.93 4.47 5.00 5.56 20.12 67.07 67.83 68.52 70.38
To.tl 256.21 280.77 311.87 342.32 395.34 473.90 510.90 551.20 598.28
EF0001 to
-- 1otbiq-e 2.29 2.63 3.03 3.48 4.00 4.60 5.20 6.00 6.90
?otsl Sales 258.50 283.40 314.90 345.80 399.74 478.50 516.10 557.20 605.18
leo.l-ex R. lt %. 9.0 9.6 11.1 9.8 15.6 19.7 7.9 8.0 8.6
boL.s booeonerot (G.ih) 283.00 310.27 344.75 378.58 437.63 523.86 565.03 610.02 662.55
Doasad
C-xiort (7'I) 53.3 59.8 66.6 73.1 81.9 95.4 103.4 112.0 121.3
Syst-m Load Faot . 60.1 59.5 59.5 59.1 61.0 62.7 62.0 62.0 62.3
osoary 1776
ANNEX8
MALAWI
NKULA FALLS 11HYDROELECTRIC PROJECT
ESCOM INTERCONNECTED SYSTEM <
INSTALLED AND FIRM CAPACITY AND MAXIMUM DEMAND
0z
220
210 _ Z >, X|
210~~~~~~~~~~~~~~~~~~~~~~~~
o cc
200 2
190
LU Z
180 Z
2 Z
0 H -
170 OM Z.
z
150 _>t B INSTALLED r .. -- H
140 - DNCAPACITY zU
L -
x
130 , HZ H_
10 -C
<
120 - o I
< l0 0
N ,
JJ ~~~~~~~~~~0
LU
H
90 - -(
- ~~~~~~~~0
~ N
80 2 0'uJ
70 Z --
70
50 :E
C)
INSTALLED
~~~~~~~~~~~~~MAXIMUM
DEMAND
co CAPACITY
io ACUA DEMAN V) RJCEDDMN
100~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ol
Han-169
20 * .
FIRM
10 CAPACITY
1965 66 67 68 69 70 71 72 73 74 75176 77 78 79 80 81 82 83 84 85 86 87 88
ACTUAL DEMAND -PROJECTED DEMAND
VVo,idBank-1 5899
ANNEX 9
MALAWI
NKULA FALLS 11HYDROELECTRIC PROJECT
ESCOM - INTERCONNECTED SYSTEM
INSTALLED AND FIRM ENERGY
GENERATION CAPACITY AND SYSTEM
ENERGY REQUIREMENT
0
1100
m <
1000
z~~~~
800 < IT
I~~
LU x
100 _ j
~ w
LU~~~~~~~~c
~~~~~~~ I
-
LLI
600 N
N
7 I-
I,
z *T INSTALLED
ENERGY
0 GENERATION
500 ui 0~~~~~~~~ CAPACITY
SYSTEM ENERGY
0 ~~~~~~~~~~~~~~~~~~REQUIREME
HYDRO
GENERATION
200 - ~~~~~~~~~~~~~~~CAPACITY
100
FIRM ENERGY GENERATION
CAPACITY
1965 66 67 68 69 70 71 72 73 74 75_1 76 77 78 79 80 81 82 83 84 85 86 87 88
- - ~~~~ACTUAL PROJECTED
WVo,dB..k-15697(R)
ANNEX 10
Page 1
MALAWI
1/ The report, issued in May 1975, is entitled "Project Report for Nkula
Falls Hydroelectric Scheme Stage II" and was prepared by three British
consulting firms: Kennedy and Donkin; Watermeyer, Legge, Piesold &
Uhlmann; Coopers & Lybrand Associates Ltd.
ANNEX 10
Page 2
Method of Comparison
6. The alternative plans have been extended over the period of 40 years
to attain a common facility point and also to reach a point of insignificance
for the present worth factor.
Capital Cost
Load Growth
10. The growth of demand has been projected on the basis of a detailed
analysis of future electricity consumption of large industrial consumers and
on the correlation between demand of the remaining consumers and the expected
ANNEX 10
Page 3
February 1976
ANNEX 10
Page 4A
MALAWI
Alternative #1
Miarch 1977
ANNEX 10
Page 4B
MALAWI
Alternative #2
March 1977
ANNEX 10
Page 4C
MALAWI
Alternative #3
December 1976
ANNEX 10
Page 4D
MALAWI
Alternative #4
December 1976
ANNEX 11
Page 1
MALAWI
Return on Investment
MALAWI
---------------------------iMillions of Kwachas-----------------------
---------Capital Costs--------
Nkula Dam Transmission Operation & Total Revenues
Years lst&2nd Units & Distribution Maintenance Cost (T 3.10/kWh)
MALAWI
…----------------------------…Millions
of Kwachas------------------------
-------------Capital Costs------------
Nkula Falls II Dam
1st & 2nd 3rd, 4th & Transmission Operation & Total Revenues
Years Units 5th Units & Distribution Maintenance Cost (T 3.10/kWh)
|General Manaqler
IChrtie
Engiineer Firiancial Controller A Secretary
l~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
FEngi~~ccunat
temControl hif erone Ofie
TechnicalEngineer
S.rvi_es
Distribuation Stiperintendent. BrnhCnole_AsittSceav Chief Auditor
-L ~~Training
Offlicerl
World Bank-15792
ANNEX 13
Page 1
MALAWI
There are a number of areas described in this Annex which are key
factors in the efficient operation of the utility and the success of the
project. These have been discussed with the Borrower and the Consultant
and further discussions will be held during negotiations to determine firm
targets for these key factors against which actual progress will be monitored.
1. Construction of Project
2. Staffing
not be exceeded during the next five years. Where staffing levels are
excessive, efforts should be made to reduce staff through limitation on
recruitment, early retirement, etc.
3. Training
3.1 Personnel under training in the country and abroad should be moni-
tored on an annual basis against the targets set under the following headings,
to meet normal wastage and turnover requirements:
4. System Operations
Financial Indicators
ELECTRICITY SALES (GWh) 178 192 237 260 285 317 348 401 479 518 557
AVE. REVENUE PER kWh (TAMBALA) 2.14 2.16 2.42 2.60 3.10 4.03 4.43 4.43 4.87 4.87 4.87
OPERATING REVENUES
OPERATINGEXPENSES
OPERATIONAND MAINTENANCE 619 605 721 956 1108 1285 1490 1728 2004 2164 2337
FUEL 216 127 306 588 255 300 216 233 251 270 50
ADMINISTRATION - GENERAL 545 698 755 1100 1276 1480 1717 1992 2310 2495 2695
DEPRECIATION .-- 811 ...-- 1-1- 1049 .. 2112 -- _2220___2222 .. 315Q .. 4861 --- 6248 -- Z2254 ___Z341
TOTAL OPERATINGEXPENSES __2121 __"2440 ___2824 .__4356 ____4852 __5Z22 ._._6523 .814 A _11313 __12183 __12423
OPERATINGINCOME 1631 1714 2963 2427 3976 6983 8843 8950 12014 13043 14703
OTHERINCOMENET .__.__44 _ _42 --- 14Q Q _____ _ _6Q ZZ -----
_ __20 -- 1Qo
NET INCOMEBEFOREINTEREST 1675 1756 3103 2504 4016 7033 8903 9020 12094 13133 14803
INTEREST CHARGEDOPERATIONS _ _.1122 __11192 ..._
._Z2....
._82Q 52 ___1608 _1526 --- _23B2 _...2263 ---2650 ---Z42 __---2124
NET INCOME 785 579 1984 1052 2408 5437 6521 6757 4444 5643 7629
RATE OF RETURN 10.1 8.1 13.6 6.8 8.4 12.1 13.5 8.3 7.8 8.2 9.5
OPERATINGRATIO (%) 57 59 49 64 55 45 43 50 48 48 46
AVERAGENET FIXED ASSETS 1/ 16205 21060 27249 35777 47202 57841 65276 108036 153541 159524 154726
ii
1/ On historical basis to 1975, then revalued basis thereafter IlZ
IIMX
March 1977 1
ANNEX 15
NKULA FALLS II HYDROELECTRICPROJECT
_jeI
q_December31 19 1977 1978 1979 1980 1981 1981 1982 1983
NET INCOME BEFORE INTEREST 2504 4016 7033 8903 9020 12094 43570 13133 14803
-DEPRECIATION 1212 ___2220 _22Z 3150 _48L .__6248 __21418 .2__z254 --- 2341
TOTAI INTERNALCASH6ENEUATION4216 6236 9760 12053 13881 18842 64988 20387 22144
OPERATIONAL RE-
QUIREMENTS
-WORKING CAPITAL 1022 106 506 375 360 661 3030 375 514
-DEBT SERVICE -222i ___4123 _20D4 _2831 2068 --10O32 -- 42842 _. 112t __11544
TOTAL 3801 --- 4222 --- 2510 ___8206 --- _2428 ._l0628 __45822 __11639 __12058
NET AVAILABLE
F'ROM OPERATIONS 415 2007 250 3847 4453 8144 19116 874B 10086
CONSIRUCTION
REOUITREMENTS
rEDZANI 2 GAS TURBINE 5126 3067 0 0 0 0 8193 0 0
TRANSMISSIONLINE 1 2009 4112 1023 0 0 0 7144 0 0
TRANSMISSIONLINE 2 0 0 401 5218 2626 0 8245 0 0
FRUPOSED PROJECT 432 11088 18675 21050 4895 4250 60390 0 0
GENERAL DEVELOPMENIT 1028 1450 1500 1500 2000 2200 9678 2400 2600
GENE:RATION ---- _0_____o0------_0 ___ 0 ______Q
-…-… _ ------ Q0 ___2000 ___8500
TOTAL CONSTRUCTION .8525 l9Z212 _..21522 __22268 -.._2521 __ 6450 __23650 _.__4400 _11±100
REQUIREMENTS
BALANCE TO FINANCE 8180 17710 21349 23921 5068 -1694 74534 -4348 1014
FINANCED BY:
INDEBANK 0 1000 0 0 0 0 1000 0 0
AF'DB-TRANS LINE I 1472 3021 1037 0 0 0 5530 0 0
UNARANGD-TRANS. LINE 2 0 0 335 4392 2621 0 7348 0 0
IDA-NKULA II 0 5370 2742 700 754 0 9566 0 0
THIRD WINDOW-NKULA II 0 0 3024 3300 1446 670 8440 0 0
IBRD-NKULA II 0 0 3210 3240 970 760 8180 0 0
ADB-NKULA II 0 1073 2216 341 741 230 4601 0 0
GERMANY-NKULA II 0 833 70 2860 538 200 4501 0 0
CDC--NKULA II 0 3000 5000 4500 0 0 12500 0 0
F'ED-ENK\ULAII 0 1824 2875 4955 820 0 10474 0 0
CIC-TEDZANI II 1692 0 0 0 0 0 1692 0 0
IDA-TEDZANI II 4208 541 436 0 0 0 5185 0 0
FINANCING REQUIREMENTS- 1977 0 2400 0 0 0 0 2400 0 0
CAFITAL. CONTRIBUTIONS _.223 -- 25Q 300 ___ __4 5 - 500 __21Z.3 .600
_655
TGOTAL 7645 19312 21245 24688 8340 2360 83590 550 600
SURPLUS(DEFICIT) OF FUNDS -535 1602 -104 767 3272 4054 9056 4898 -414
DEBT SERVICECOVERAGE 1.5 1.5 1.1 1.5 1.5 1.9 1.5 1.9 1.9
March 1J977
ANNEX 16
MALAWI
NKULA_FALLS 1 -HYDROELECTRIC
PROJECT
ELECTRICITYSUPPLYCOMISSION OF MALAWI
BaLance Sheets
(Thousands
of Kwachas)
DECEMBER31 ta----
-------- -- ……---- -------- -------
Forecast …------------
:.1973 1974 1 975 1976 1.977 :1978 1979 1980 19813 1982 1.983i
ASSETS
I-I ANT IN UPLRAl ION 2656~9 27970 45014 53231i4( / 4032 818 2 5 9619 3' 1.795i6 0 206 0.54 208454 25I1 Ob4
)..ESS. UEI'RECIA 'rION .~....5226 ....-- 6622 ...- l293 -150.A260.~22214.22252..442 441013.513L55Z .a86S!b
NE. FI hIANf 20843 21278 33221 38333 56072 "5961 70941. 145131 :1615951 15. /07/
Wt*9K EN PKOR13138, 10311 3896 9226 14321 18652 41510 6 3 665- 53 04 5j2 3 25J23 31.
J
4
1leI N ,1:
OPERATION4ALREQUIREMENTS 73 0 336 25( 290 330 370 410 450, 490 530
TEMPORARY SURPLUS 0 0 1) 0 '543 38:15 '0 67 12767 12353
RECEIVABLES-CON
SUNERS 349 600 664 3:1.4 1060 1!533 11350,, 2132 ~,27~991 30o2/7 .325 f
RECEIVABLES-OTHERS Ii 0 231 753 :3.003 350 400 400 4!50 450 500 500
IWVENTORIES .~51. 61 .. 858..___.1001 .. 1100 ....... 12011.141131 .18011
_.O -.- 2000 _.....2A01
i IA-CURRENT ASSETS I1I.I6
I118 :1441 2611 3506,4 2800 3 463 4563 8407 13368 18784 19036
235040 266:1.5 4 505 5 57:18 77524 '104584 139169 158842 175842 1744 827
i131I
4i I. 3 I
43!, I )I N1:0
I.1 EAk N.I.NLi 426:. 65 08~ 563) 9968 15405 21926 28683 33127 387~70 4639',
CAPITAL CONTRIBSUTION b669 91 9:3
Y9 1.i1g :,.
1442 1742 2142 2592 .3092 3642 4242
REVALUATIONSURPLUS 1.......1...
. ........ 3 1192.2 .. 12235 -- 22001 _._22068 -- 33021 _42435 _45445 _4U4.ALJ
1114I3W EQUITY .43 85- 51 62 18580 22.72Y 28645 39148 51136 64373 81654 87847 96076
3 114i1 I FR SF8 f
UF 1. 1028 1.9668S 23366 2993. 1 4//73 64069 3k6 708 92932 92405 88631 84261
CURRENTLIAXILITIES_
II LI0
114 ,PAY: IL 1: 16:/ 14.3:1. 1.921 1.356, 9336 1143 1225 1537 17835 1926 2080
im At
8 CURRENT :.36271 7115,,. .3112,, .W107 .1:.06 1367 :1325 1537 1783 1926 2080
LIABILITIES .. .... ... .. .. ... . .... . . ... .
213040 26615 4,50,1 578)J.L */5324 104584 139169 158842 175842 178404 182417
DEBT/EQUITY RATIO 80 79 56 57 63 62 63 59 53 50 47
CURRENTRATIO 0.7 0.8 0.8 9.O 2.8 2.5 3.4 5.5 7.5 9.9 9.3
March 1977
ANNEX 17
Page 1
MALAWI
Balance Sheet
Receivables - Consumers
Receivables - Others
6. These include amounts owing for capital works, advance payments and
other miscellaneous items. Increases of MK 50,000 bi-annually have been made
to estimated amount outstanding at December 31, 1977.
ANNEX 17
Page 2
Work in Progress
Inventories
Payables
9. These have been assumed to increaseby 18% per year from 1976 to
1981 and 8% thereafterin line with operating expenses.
(a) The MK 8.18 million (US$9 million) IBRD loan would be for
a 20 year term with a 4-1/2 year grace period with the
first principal repaymentbeing on June 1, 1982. The
assumed interest rate is 8-1/2%.
Millions of Malawi
Kwachas
11. It has been estimated that ESCOM would have a MK 2.4 million financ-
ing gap in 1977 and it has been assumed that this amount would be borrowed at
10% interest and repaid in 1978. ESCOM has already obtained a one year 10%
loan from Indebank, which will be repaid in 1978.
12. ESCOM has overdraft facilities with the National Bank of Malawi up
to MK 1.25 million.
Capital Expenditures
It has been assumed that the transmission line would be built be-
tween 1978 and 1980 at a cost of MK 8.2 million (US$9.0 million). This is
based on ESCOM's consultants estimates adjusted for price increases. The
justification for the transmission line is related to the proposed pulp mill
and associated township at Chinteche.
Total Currency
Interest Original ±or,aiai lRepaid to Fluctuations
Original Reuaain~inIg Rate Amo'alt 1975 31.12.1975 Surplus/Deficit Balance
IDA - Nkula II
Borrowings 5,370 2,?42 700 754
Amortization 94 201 219
Interest 228 573 719 781 809 797 779
Commitment Charges 16 21 8 3
IDC - X 100 100 100 100
DC 244 594 728 784
IBRD - Nkula II
Borrowings 3,210 3,240 970 760
Amortization 544 544
Interest 136 411 589 663 684 649
Comoitment Charges 19 25 9 3
AfDB - Nkula II
Borrowings 1,073 2,216 341 741 230
Amortization 76 143 155
Interest 46 185 294 340 378 379 366
Commitment Charges 13 18 9 5 1
IDC - % 100 100 100 100
IDC 59 204 303 345
Germany - Nkula II
Borrowings 833 70 2,860 538 200
Amortization 54 90 98
Interest 35 74 198 343 372 374 366
IDC - X 100 100 100 100
IDC 35 74 198 343
CDC - Nkula II
Borrowings 3,000 5,000 4,500
Amortization 416 833
Interest 127 467 871 1,062 1,062 1,045 992
FED - hkula II
Borrowings 1,824 2,875 4,955 820
Amtrtization 103 220 239
Interest 78 277 610 855 886 872 853
DC - % 100 100 100 100
IDC 78 277 610 855
Borrowings
CDC - Tedzani II 1,692
IDA - Tedzani II 4,208 541 436
Indebank 1,000
Financing Requirements 1977 2,400
5 900 3,941 436
Amortization of loans outstan.1fj
12131/75 and other loans 827 1,200 4,649 1,465 1,468 1,529 1,521 1,589
Interest
Loans outstanding 12/31/75
and other loans 1,895 2,074 1,887 1,962 1,855 1,746 1,633 1,520
Indebank 75 25
Financing Requirements 1977
- 1/2 year 120
DEBT SUMMARY
MALAWI
SEPTEMBER 1, 1976
SCALE I: DOMESTIC
Demand @ K6-.0/kW/month
Units @ 1.5t/unit
Demand @ K59/kW/annum
Units @ 0.8t/unit
I/ kilowatt-hours
IBRD 12214
MAY 1976
MALAWI
NKULAFALLSHYDROELECTRIC
SCHEME
STAGEII
Roads
______
----- Rivers
TgCR,\'. Proposed reservofr - . PUM STATION
INTAKETOWER
7_roxr-Exishng embankments
''HEAD OND
BLANTYRE
WATER
BOARD
PERRY
WALKERS PUMP
STATION
PI
0
SLJRGECHAtOBER
EXISTINEGSTiN NA
~~~~~~~~~~
~E~~~ ~~~~~~~~~~0
0
EXISTNGE
CHAMBER i~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~5
' ZAMBIA
4,'
'0''
1 L SWITCH
YARD, //
FXIS' I\NGO <&
p~~~ ~~~~~~~~~~~~~~~~~~~~~~~~
,A AN N"IA
POWERd, KANTS .- A
.~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~mp
e.,dp.
,ldse,,en
,,r locprancc b 5h,
:~~~~~~~~~~~- 04
IBRD 2369R4
~~~~
ilN et~~~~SeIiego $
>76r/-Z ~AT 9\
O M MB I Q U E
Mcr,~~~~~, MOZAMBIO UB~~~~~Zff
Z A M B I A (_ <eIOG EChip.k0t
MALAWI
PROPOSEDHYDROELECTRICPROJECT ) N1,e7
I RAI LROADS
NTERNATIONAL 3OUNDAR ES MptoP\ongo
R9V,0DA
F-* S AAA9 BLANTYRE j
ZAIRE A
< -X, ~~T
A N Z A N I A '\ 7 ' /
>., ;1 \ ~~~~~~~~~
~ ~ ~~ ~~ ~ n~~Chikwcc...a
j
ZAMBIA 9 tr~ \z Z
\DOIA LONGWE \ - ,
KROOEA 1_
5
0 X
S[URY
SARO -' 0A