Professional Documents
Culture Documents
Sewerage PDF
Sewerage PDF
HANDBOOK
ON
SEWERAGE AND SEWAGE
TREATMENT
Once the disposal points are tentatively selected, further design is guided by the following basic
design considerations:
a. Engineering
b. Environmental
c. Process
d. Cost
These considerations are discussed below in detail:
a) Engineering Considerations ( Para 1.3.1 of CPHEEO Manual)
Topographical, engineering and other considerations which figure prominently in
project design are noted below:
1. Design period, stage wise population to be served and expected sewage flow
and fluctuations
2. Topography of general area to be served, its slope and terrain. Tentative sites
available for treatment plant, pumping stations and disposal works
3. Available hydraulic head in the system up to high flood level in case of
disposal to a nearby river or high tide level in case of coastal discharge or the level of the
irrigation are to be commanded in case of land disposal
4. Ground water depth and its seasonal fluctuation affecting construction, sewer
infiltration, structural design (uplift considerations)
5. Soil bearing capacity and type of strata expected to be met in construction
6. On site disposal facilities, including the possibilities of segregating the sullage
water and sewage and reuse or recycle sullage water within the households
b) Environmental Considerations: (Para 1.3.2 of CPHEEO Manual)
The environmental and socio-economic impacts of a sewage treatment plant may
prove adverse during the operation stage. Therefore the following aspects should be
considered during design.
i) Surface water Hydrology and Quality
ii) Ground water quality
iii) Coastal water quality
iv) Odour and Mosquito nuisance
v) Public Health and
vi) Land scaping
c) Process Considerations: ( Para 1.3.3 of CPHEEO Manual)
Process considerations involve factors which affect the choice of treatment method, its
design criteria and related requirements such as the following:
i) Waste water flow and characteristics
ii) Degree of treatment required
iii) Performance characteristics
iv) Other process requirements such as land, power operating equipments,
skilled staff, nature of maintenance problems, extent of sludge production
and its disposal requirements, loss of head through plant in relation to
available head etc
Up to 5,000 75-150
In cities where Floor Space Index (FSI) or Floor Area Ratio (FAR) limits are fixed by
the local authority this approach may be used for working out the population density. FSI or
FAR is the ratio of total floor area (of all the floors) to the plot area. The densities of
population on this concept may be worked out as in the following example:
Assume that a particular development plan rules provide for the following reservations
for different land uses.
Roads 20 %
Gardens 15%
Markets 2%
Total 44%
sewers should be designed for a minimum waste water flow of 100 litres per cpaita per day.
Industries commercial buildings often use water other than the municipal supply and may
discharge their liquid wastes into the sanitary sewers. Estimates of such flows have to be
made separately. The details of requirements of water for institutions and industries are
discussed in Chapter 2 of Manual on Water Supply and Treatment. Industrial wastes have to
be treated to the standards prescribed by the regulatory authorities before being discharged
into sewers. For some areas, it is safe to assume that the future density of population for
design purpose to be equal to the saturation density. It is desirable that all sewers serving a
small area be designed on the basis of saturation density.
Infiltration into sewer may occur through pipes, pipe joints and structures. The
probable amount has to be evaluated carefully.
b. Flow Assumptions : (Para 3.2.5 of CPHEEO Manual)
The flow in sewers varies considerably from hour to hour and also
seasonally, but for the purposes of hydraulic design it is the estimated peak flow that is
adopted. The peak factor or the ratio of maximum to average flow depends upon contributory
population and the following values are recommended. These peak factors will be applied to
the projected population for the design year considering an average wastewater flow based on
allocation
Up to 20,000 3.0
The peak factors also depend upon the density of population, topography of the site,
hours of water supply and therefore it is desirable to estimate the same in individual cases, if
required. The minimum flow may vary from 1/3 to 1/2 of average flow.
c Ground water infiltration : (Para 3.2.7 of CPHEEO Manual)
Estimate of flow in sanitary sewers may include certain flows due to infiltration of
ground water through joints. The quantity will depend on workmanship in laying of sewers
and level of the ground water table and permeability of the surrounding soil. Since sewers are
designed for peak discharges, allowance for ground water infiltration for the worst condition
in the area should be made. Suggested estimates for ground water infiltration for sewers laid
below ground water table are as follows:
a) Pre-investment Planning
- Identification of a project
- Preparation of project report
b) Appraisal and Sanction
c) Construction of facilities and carrying out support activities
d) Operation and maintenance
e) Monitoring and feed back
Since project preparation is quite expensive and time consuming, all projects
should normally proceed through three stages and at the end of each stage a decision should be
taken whether to proceed to the next planning stage and commit the necessary manpower and
financial resources for the next stage. Report at the end of each stage should include a time
table and cost estimate for undertaking the next stage activity and a realistic schedule for all
future stages of project development, taking into consideration time required for review and
approval of the report, providing funding for the next stage, mobilizing personnel or fixing
agency (for the next stage of project preparation) data gathering, physical surveys, site
investigations etc.
The basic design of a project is influenced by the authorities/organizations who are
involved in approving, implementing, operating and maintaining the project. Therefore the
institutional arrangements, through which a project will be brought into operation, must be
considered at the project preparation stage. Similarly responsibility for project preparation
may change at various stages. Arrangements in this respect should be finalized for each stage
of project preparation. Some times more than one organization may have a role to play in the
various stages of preparation of a project. It is therefore necessary to identify a single entity to
be responsible for overall management and coordination of each stage of project preparation.
It is desirable that implementing authority is identified and those responsible for operation of a
project are consulted at the project preparation stage.
Audit Approach
Inter-alia the following points could arise:
1. Whether population forecast was worked out correctly and the estimate of waste
water assessed correctly for the design period. Over estimation of population would
lead to creation of infrastructure in excess of the actual requirement involving extra
cost. Under assessment lead to creating additional infrastructure to meet the
requirement of the full design life involving extra cost.
2. Cases where pump set designed for ultimate stage may be verified and extra cost
involved on erection of pumpset and motor for ultimate stage instead of intermediate
stage and also power consumption on higher capacity of motor may be worked out
and commented.
3. Whether various components of sewerage system were designed and constructed for
the stipulated designed period if not financial implication may be commented.
4. Whether detailed survey and investigation carried out and alignment for pumping
main, sewer main fixed correctly taking into account topography of the ground and
level difference needed for laying the sewers and location of outfall and disposal
works. The following point could emerge
(i) Cases where the sewage could not reach the collection well due to level
differences
Hydraulic elements of circular sewers possess equal self cleansing properties at all
depths. The self cleansing properties for different conduit are given below:
i) Sanitary Sewer: For design peak flow – 0.8 metre/sec
For present peak flow – 0.6 metre/sec
ii) Open drain: - 0.75 to 0.9 metre/sec
iii) Inverted siphon: - 1.00 metre/sec
iv) Minimum velocity for force main: - 0.3 metre/sec
• Maximum permitted depth of flow: The pipes will be designed to flow at depth indicated
below where the maximum permissible depth of flow in sewers for established velocity
criteria:
Diameter in Depth of flow which will convey
mm (d) designed quantity
Up to 400 0.50 d
400 to 900 0.67 d
Above 900 0.75 d
• Velocity: (Para 3.4.3 of CPHEEO Manual) The flow in sewer varies from hour to hour
and also seasonally. But for the purpose of hydraulic design, estimated peak flow is
adopted. The size of Sewer is to have adequate capacity for the peak flow to be achieved at
the end of design period so as to avoid steeper gradient and deeper excavation. It is
desirable to design sewers for higher velocity wherever possible. The sanitary sewer is
designed to obtain adequate scouring velocities at the average or at least at the maximum
flow at the beginning of the design period for a given flow and slope. Velocity is little
influenced by pipe diameter. The recommended slope for minimum velocity is given
below which ensure minimum velocity of 0.60 metre/sec.
• Table 3.7 of CPHEEO Manual)
Present peak flow (lps) Slope per 1000 m
2 6.0
3 4.0
5 3.1
10 2.0
15 1.30
20 1.20
30 1.00
After arriving at slopes for present peak flows, the pipe size should be decided on the basis
of ultimate design peak low and the permissible depth of flow. The minimum diameter of
public sewer may be 150 mm. In hilly areas, where extreme slope are prevalent, the size of
sewer may be 100 mm.
• Depth of cover: One meter cover on pipeline is normally sufficient to protect the
pipelines from external damage.
2 Sewer Appurtenances (Chapter 4 of CPHEEO Manual)
Sewer appurtenances are devices necessary in addition to pipes and conduits for the pipes
functioning of any complete system of sanitary, storm or combined sewers. They include
structures and devices such as various types of manholes, lamp holes, gully traps, intercepting
chambers, flush tanks, ventilation shafts, catch basins, street inlets, regulators, siphons, grease
traps, side float weir, leaping weir, venture-flumes and out fall structures.
• The width/diameter of the manhole should not be less than the internal diameter
of the sewer plus 150 mm benching on both sides (150 mm + 150 mm).
• Manhole covers: A minimum clear opening of 60 cm is recommended.
• Floor slab of manhole: RCC 150 mm thick to withstand uplift.
• Drop manholes: Required when the maximum difference in inverts between the
shallowest incoming and the outgoing sewer of a manhole is more than 60 cm.
2. Flushing Tank:
• Located at the head of a sewer. They are designed for 10 minutes flow as a self-
cleansing velocity of 0.6 m/sec.
• Capacities:
150 mm sewer - 6400 litres
200 mm sewer - 11000 litres
250 mm sewer - 18000 litres
The capacity of these tanks is usually 1/10 of the cubic capacity of sewer length to be
flushed.
House Service Connection (Para 4.4 of CPHEEO Manual)
-- For large diameter of sewers, house service connections may be given through rider sewers,
which should be connected through manhole or drop manhole. Where there is no Y or T left
for new connection insertion of new Y or T is not prescribed.
-- House service connection should be minimum size of 150 mm diameter sewer with minimum
slope of 1:60 laid as far as possible to a straight line and grade.
-- The House service connection sewer line has to be connected to the manhole and will be
joined with sewer pipe already embedded within the wall of the manhole while constructing
the manhole. The House service connection will be taken up to the property boundary. The
property owner shall connect the sewer line laid up to the property boundary with House
service connection.
The Vitrified clay pipes is advantageous over other pipe material on high resistance to
corrosion and erosion due to grit and high velocities. Though a minimum crushing strength of
1600 kg/m is usually adopted for all sizes manufactured presently, vitrified clay pipes of
crushing strength 2800 kg/m and over are manufactured in other countries. The strength of
vitrified clay pipes often necessitates special bedding or concrete cradling to improve field
supporting strength. The stoneware pipes and fittings shall withstand internal hydraulic test
pressure of 0.3 Mpa and 0.15 Mpa respectively without showing sign of injury or leakage. The
pressure shall be applied at a rate not exceeding 0.075 Mpa in 5 seconds (IS 3006:1979).
The vertical dead load to which a conduit is subjected under trench conditions is the
resultant of two major forces. The first component is the weight of the prism of soil within the
trench and above the top of the pipe and the second is due to the friction or shearing forces
generated between the prism of soil in the trench and the sides of the trench produced by
settlement of backfill. The resultant load on the horizontal plane at the top of the pipe within the
trench is equal to the weight of the backfill minus these upward shearing forces.
Computation of loads: The load on rigid conduits in trench condition is given by the
Marston’s formula in the form
Wc= Cd w B2d
Wc = the load on the pipe in kg per linear metre
.w = the unit weight of backfill soil in kg/m3
Bd= the width of trench at the top of the pipe in m and
Cd= the load coefficient which is a function of a ratio of height of fill to width of trench
(H/Bd)
H = Depth of refilling of soil from top of pipe to the ground level in metres.
Weights of common filling materials (w) and values of Cd for common soil conditions
encountered are given in Table 1 and 2 respectively.
The weights of common filling materials (w) are given in the table below
Table 1
Materials Weight (kg/m3)
Dry sand 1600
Table 2
Values of Cd for calculating loads on pipes in trenches (Wc=CdWB2d)
Ratio H/B Safe working values of Cd
2. Load on conduit due to super imposed loads: (Para 6.4 of CPHEEO Manuals)
The type of super imposed loads which generally encountered in buried conduits may be
(a) concentrated load and (b) distributed load.
a) Concentrated Load: (Para 6.4.1 of CPHEEO Manual ) The formula for load due to
super imposed concentrated load such as a truck wheel is given in the following form by Holl’s
integration of Boussinesq’s formula
Wsc = Cs (PF/L)
Wsc= the load on the conduit in kg/m
P = the concentrated load in kg acting on the surface
F = the impact factor (1.0 for air field runways, 1.5 for highway traffic and air field taxi
ways, 1.75 for railways traffic) and
Cs= the load coefficient which is a function of
Bc L
----- and ----
2H 2H
Where
H = the height of the top of the conduit to ground surface in m
Bc= the outside width of conduit in m and
L=the effective length of the conduit to which the load is transmitted in m
Values of Cs for various values of (Bc/2H) and (L/2H) are obtained from Table 3
The effective length of the conduit is defined as the length over which the average load
due to surface traffic units produces the same stress in the conduit wall as does the actual load
which varies in intensity from point to point. This is generally taken as 1m or the actual length
of the conduit if it is less than 1 m
b) Distributed load : (Para 6.4.2 of CPHEEO Manual For the case of distributed
superimposed loads, the formula for load on conduit is given by
Wsd = Cs p F Bc
Where
Wsd= the load on the conduit in kg/m
.p = the intensity of the distributed load in kg/m2
f = the impact factor
Bc= The width of the conduit in m
Cs = the load coefficient, a function of D/2H and L/2H from Table 3
H = the height of the top of conduit to the ground surface in m and
D and L are width and length in m respectively of the area over which the distributed
load
Field supporting Strength (Para 6.5.2 of CPHEEO Manual)
The field supporting strength of a rigid conduit is the maximum load per unit length,
which the pipe will support while retaining complete serviceability when installed under
specified conditions of bedding and backfilling. The field supporting strength, however does not
include any factor of safety. The ratio of the strength of a pipe under any stated condition of
loading and bedding to its strength measured by three edge bearing test is called the load factor.
The load factor does not contain a factor of safety. Load factors have been determined
experimentally and analytically for the commonly used construction condition for both trench
and embankment conduits.
Supporting strength in Trench conditions (Para 6.5.3 of CPHEEO Manual)
Classes of bedding:
Four classes, A, B, C and D of bedding are used most often for pipes in trenches. Class A
bedding may be either concrete cradle or concrete arch. Class B is a bedding having a shaped
bottom or compacted granular bedding with a carefully compacted backfill. Class C is ordinary
bedding having a shaped bottom or compacted granular bedding but with a lightly compacted
backfill. Class D is on with flat bottom trench with no care being taken to secure compaction of
backfill at the sides and immediately over the pipe and hence is not recommended. Class B or C
bedding with compacted granular bedding is generally recommended. Shaped bottom is
impracticable and costly and hence is not recommended. The pipe bedding materials must
remain firm and not permit displacement of pipes which include Red gravel, coarse sand,
crushed gravel etc. The material has to be uniformly graded or well graded.
Well graded material is most effective for stabilizing trench bottom and has a lesser tendency
to flow than uniformly graded materials. However, uniformly graded material is easier to place
and compact above sewer pipes.
LOAD FACTORS FOR DIFFERENT CLASSES OF BEDDING (Table 6.6 of CPHEEO Manual)
The granular material used must stabilize the trench bottom in addition to providing a firm
and uniform support for the pipe. Well graded crushed rock or gravel with the maximum size not
exceeding 25 mm is recommended for the purpose.
Where rock or other unyielding foundation material is encountered bedding may be
according to one of the Class A,B or C but with the following additional requirements.
Class A: The hard unyielding material should be excavated down to the bottom of the
concrete cradle.
Class B or C: The hard unyielding material should be excavated below the bottom of the pipe and
pipe bell to a depth of atleast 15 cm.
The width of the excavation should be atleast 1.25 times the outside dia of the pipe and it
should be refilled with granular material.
Total encasement of non-reinforced rigid pipe in concrete may be necessary where the
required safe supporting strength cannot be obtained by other bedding methods. The load factor
for concrete encasement varies with the thickness of concrete.
Problem: Determine the structural requirement of 200 mm dia stone ware pipe laid in a trench
to a width of 0.8 m in depth of 1.30 metre in ordinary soil and wheel load of 6.25
tonnes.
Audit Approach
Interalia the following audit points could be seen
1. Cases where due to defective design and execution of sewer and sewer appurtenances,
the designed quantity of sewer could not reach the collection well causing overflow or
leakages. This untreated sewage water due to leakage would pollute the river or lake
causing public ill health and pollution. This aspects may be analysed.
2. Though stoneware pipe were sufficient for collection sewer up to 350 mm dia, CI pipes
are being used. The safety factor and design criteria for the sewer has to be examined
and the extra cost on use of pipes other than stone ware for collection systems upto 350
mm dia may be commented.
3. Even in case of use of other pipes, the class of pipe used may be analysed with reference
to designed pressure and extra cost on use of higher class of pipe may be commented.
4. Whether trenches were excavated to the specified width or not the extra cost due to
higher width of trenches may be commented.
Dry well: (Para 9.6.1 of CPHEEO) The size of the dry well should be adequate to house
number of pumps at the desired capacity of pumping.
Wet Well: (Para 9.6.2 of CPHEEO) The size of the wet well is influenced by the sewage
capacity to be provided. The capacity of the well is to be so kept that with any combination of
inflow and pumping the cycle of operation for each pump will not be less than 5 minutes and the
maximum detention time in the wet well will not exceed 30 minutes of average flow.
• In the wet well baffles should be provided at required places to ensure uniform flow at
each pump suction.
• Wherever possible grid removal ahead of pumping should be adopted to increase the life
of the pumps.
PUMPS: (Para 9.7 of CPHEEO Manual)
The selection of pump is based on many consideration such as the type of pump, the size
of pump, the number of pumps, the capacity or flow rate of each pump range of throttling of
each pump, the head of pumping and others.
• Capacity of the pump shall be adequate to meet the peak rate of flow with 50% stand by.
To obtain the least operating cost, the pumping equipments should be selected to perform
efficiently at all flow including the peak flow. Two or more pumps are always desirable at
sewage pumping station. The size and number of unit for larger pumping station, shall be
so selected that the variations of inflow can be handled by throttling of the delivery values
or by varying the speed of the pump without starting and stopping the pump too frequently
or necessitating excessive storage. (Para 9.7.1 of CPHEEO Manual)
• The capacity of a pump is usually stated in terms of Dry Weather Flow (DWF) estimated
for the pumping station. The general practices is to provide 3 pumps for small capacity
pumping station comprising of 1 pump of 1 DWF, 1 of 2 DWF and third of 3 DWF
Capacity. For large capacity pumping station, 5 pumps are usually provided comprising of
2 of ½ DWF 2 for 1 DWF and 1 of 3 DWF capacity including standby. (Para 9.7.1 of
CPHEEO Manual)
• The total head of pumping has to be calculated taking note of four factors; (Para 9.7.5 of
CPHEEO Manual)
(i) the difference between the static level of the liquid in the suction sump in the wet
well and the highest point on the discharge side ie. Static head.
(ii) the rate of flow and size of the discharge mouth determine the velocity at the point of
discharge (ie. Velocity head or kinetic head)
(iii) the difference in the pressure on the liquid in the suction sump and at the point of
delivery rate, delivery pressure will be higher than the atmospheric pressure (i.e.
Pressure head)
(iv) the frictional losses across the pipes, values, bend and all such appurtenance (i.e.
Frictional loss)
• Normally outdoor transformer sub station are provided and may be indoors also on public
safety protection etc.,
Audit Approaches
Interalia the following could be seen
• Cases where pumps and motor designed for ultimate stage instead of 15 years may be
identified and comments on wasteful expenditure on installation of higher capacity of pump
set and recurring extra cost of power consumption due to higher capacity may be included.
• Whether pumpsets are installed to the prescribed level for DWF or in excess of
requirements. Unwarranted installation cost on extra pumpset may be commented
• Cases of failure of pumpset resulting in non pumping of Sewage loading for pollution may
also be commented after analyzing the causes for failure of pumpset.
• Cases where transformer of the stand bye or one stand bye besides diesel Generator of the
same capacity provided especially by CMWSS (Metro Water) Chennai. Normally one
duplicate (Stand bye) is required for. The excess provision of transformer and the cost
there of may be commented..
5. SEWAGE TREATEMENT
(Chapter 10 of CPHEEO Manual )
3. Unit operations/processes, their functions and devices used for domestic wastewater treatment
(Table 10-1 of CPHEEO Manual)
Unit operations and
S.No Functions Treatment Devices
process
1 SCREENING Removal of large floating, Bar racks and screens of
suspended and settleable solids various description
2 GRIT REMOVAL Removal of inorganic Grit chamber
suspended solids
3 PRIMARY Removal of organic and Primary sedimentation
SEDIMENTATION inorganic settable solids tank
4 a) AEROBIC BIOGICAL Conversion of colloidal, Activated sludge process
SUSPENDED GROWTH dissolved and residual units and its
PROCESS suspended organic matter into modifications, waste
settable biofloc and stable stabilisation Ponds,
inorganics Aerated Lagoons.
b) AEROBIC BIOGICAL Same as above Trickling Filter, Rotating
ATTACHED GROWTH Biological Contactor
PROCESS
5 ANAEROBIC Conversion of organic matter Anaerobic Filter, Bed
BIOLOGICAL GROWTH into CH4 & CO2 and organic Submerged Media
PROCESSES relatively stable organic Anaerobic Reactor,
residue Upflow Anaerobic
Sludge Blanket Reactor;
Anaerobic Rotating
Biological Contactor
6 ANAEROBIC Same as above Anaerobic Digester
STABILISATION OF
ORGANIC SLUDGES
The purpose of sedimentation of sewage is to separate the settleable solids so that the
settled waste water, if discharged into water courses, does not form sludge banks and when used
for land disposal does not lead to clogging of soil pores and excessive organic loading. Primary
sedimentation of sewage also reduces the organics load on secondary treatment units.
Sedimentation is used in waste water treatment to remove (i) inorganic suspended solids or grit in
grit chamber (ii) organic and residual inorganic solids, free oil and grease and other floating
materials, etc. The settleable solids to be removed from waste water in primary or secondary
settling tank after grit removal.
Several factors such as flow variations, density currents, solids concentration, solids
loading, area, detention time and overflow rate influence the design and performance of
sedimentation tanks. Sedimentation tanks are designed for average flow conditions. Hence,
during peak flow periods, the detention period gets reduced with increase in the overflow rate and
consequent overloading for a short period. If hourly flow variations are wide as in the case of
some industrial waste flows, it may be necessary to build an equalization tank, ahead of the
treatment units so that uniform loading is made possible in all treatment units.
For primary sedimentation tanks, both, surface overflow rate and detention period
(hydraulic residence time) are important criteria as the solids to be settled are flocculent in nature
and undergo flocculation. The major design parameters for secondary settling tanks designed to
remove bioflocculated solids are solids loading rate or solid flux as well as surface over flow rate.
The plan surface area of secondary settling tanks is determined using both criteria and the greater
of the two is adopted for design. In addition, other design parameters are depth, displacement
velocity (horizontal velocity of flow) and weir loading rate.
The overflow rate represents the hydraulic loading per unit surface area of tank in unit time
expressed as m3/d/m2 . Overflow rates must be checked both at average flows and peak flow. The
smaller values in the ranges given are applicable to small plants of capacities less than 5 mld.
The solids loading rate or solid flux is an important decision variable for the design of
secondary sedimentation tank receiving bioflocculated solids. The solid flux represents the solids
loading per unit surface area of tank per unit time and is expressed as kg SS/m2 d.
Weir loading influences the removal of solids in sedimentation tank, particularly in
secondary settling tanks where flocculated solids are settled. There is no positive evidence that
weir loading has any significant effect on removal of solids in primary settling tanks. However,
certain loading rates based on practice are recommended both for primary as well as secondary
tanks. For all primary, intermediate and secondary settling tanks, except in the case of secondary
tanks for activated sludge process, weir loading of the order of 125m3/d.m. for average flows is
recommended. For secondary settling tanks in activated sludge or its modifications, the weir
loading is around 185 m3/d.m. The loading should however ensure uniform withdrawal over the
entire periphery of the tank to avoid short circuiting or dead pockets. Performance of existing
sedimentation tanks can be improved by merely increasing their weir length.
The depth sets the detention time in the settling tank and also influences sludge thickening
in secondary settling tanks of activated sludge plants.
Design parameters for settling tanks or clarifiers
(Table 12.1 of CPHEEO manual)
Note: Para 10.4 of CPHEEO manual stipulates the design of the clarifier for
average flow.
The rate of removal of BOD and SS is maximum during the first 2 to 2½ hours of settling
and thereafter decreases appreciably. Hence, increase in the detention time beyond 2 to 2½ hours
will not increase the percentage removal of BOD or SS proportionately. Longer detention period
may affect the tank performance adversely due to setting in of septic conditions, particularly in
tropical climate. Experience has shown that a detention period of 2 to 2½ hours for primary
settling tanks and 1½ to 2 hours for secondary settling tanks will produce the optimum results.
Longer detention periods in secondary settling tanks may result in denitrification which
adversely affects the settling efficiency.
The principal purposes of sludge digestion are to reduce its offensive odour, pathogenic
contents and to improve its dewatering characteristics. This can be achieved through any of the
following biological process (i) anaerobic digestion & (ii) aerobic digestion. During the process
of sludge digestion, sludge gas is emanated. Sludge gas is normally composed of about 60 to 70%
methane and 25 to 35% carbon dioxide by volume with smaller quantities of other gases like
hydrogen sulphide, hydrogen, nitrogen and oxygen. The combustible constituent in the gas is
primarily the methane. Hydrogen sulphide in addition to its corrosive properties causes nuisance
during the burning of the gas. In term of solids digested, the average gas production is about
0.9m3/kg. of volatile solids destroyed at a normal operating pressure of 150 to 200mm of water.
Minimum or maximum rates of gas production will however depend upon the mode of
feeding of raw sludge into the digester. The minimum and maximum gas production rates may
vary from 45% to more than 200%. In the continuous feeding system, the difference between the
maximum and the minimum is considerably reduced. Intermittent mixing of digester contents is
also responsible for wide fluctuations in gas production rates.
Sludge gas should be collected under positive pressure in the gas holder from the primary
and the secondary units besides from the sludge digester. A gas dome above the digester roof
should be used for gas take off.
A distance of atleast 30m should be kept between a waste gas burner and a digestion tank
or gas holder to avoid the possibility of igniting the gas mixture. Waste gas burners should be
located in the open for easy observation. Where the gas is to be used as domestic fuel or for
power generation, additional equipments like compressor, etc. may have to be used.
Carbon credits :
The “United Nations Frame Work Convention on Climate Change” based in Bonn,
Germany created the concepts of issuing certificates of Carbon credits to countries that reduce
their emissions by implementing environment – friendly projects. In sewage treatment methane
gas (bio gas) generates during the process of sludge digestion and the bio gas can be used for
generating electricity there by avoiding the bio gas being let into air. Carbon credit is given for
utilizing the bio gas by the United Nation body.
Note : Chennai Metro Water is set to receive Rs.4 crore annually from United Nation
body for using bio gas in sewage Treatment (The Hindu dated 3.6.2007)
Audit Approaches
1. Whether the treatment plant was designed and constructed to the norms prescribed.
Extra capacity of various components of treatment unit may be commented.
2. Cases of failure of treatment units leading for non treatment of sewage and resultant
impact in public health, pollution etc. has to be analysed and commented.
3. Table 12.1 of CPHEEO Manual prescribes design paramateres for settling tank or
clarifier (Primary & Secondary) para 12.4.2.2 of CPHEEO Manual prescribes the
detection time. Longer detention time may affect adversely the performance of the tank
and setttling efficiency. Longer duration of detention time would if adopted in the
design parameters would increase the volume of the clarifier involving extra cost. The
correctness of design parameters adopted has to be analyzed and commented.
4. Para 10.4 of CPHEEO Manual stipulates the design of clarifier for average flow. But in
case where design of clarifier for peak flow has to be analysed which involves increase
in capacity of clarifier. The excess capacity of clarifier has to be commented.
5. The guidelines of National River Conservation Project provided to utilize the gas
produced from sewage treatment for operation and maintenance of the sewage treatment
plant. Para 17.4 of CPHEEO Manual also prescribes various parameters on gas
generation and utility. Failure to design the sewage treatment for storing the gas and
utilizing it may be commented.
6. STABILIZATION PONDS
(Chapter 15 of CHPEEO manual)
Stabilization ponds are open, flow-through earthen basins specifically designed and
constructed to treat sewage and biodegradable industrial wastes. Stabilization ponds provide
comparatively long detention periods extending from a few to several days. During this period
organic matter in the waste is stabilized in the pond. Pond systems in which oxygen is provided
through mechanical aeration are called aerated lagoons. Lightly loaded ponds used as tertiary
step in waste treatment for polishing of secondary effluents and removal of bacteria are called
maturation ponds.
Under many situations in warm climate countries pond systems are cheaper to construct
and operate compared to conventional methods. The only disadvantage of pond systems is the
relatively large land that they require. Pond systems must be considered as an alternative when
treatment of waste water or upgrading of existing facilities are planned and the life time costs of
various other treatment system should be calculated and compared.
CLASSIFICATION
1. Aerobic
Aerobic ponds are designed to maintain completely aerobic conditions. They are used for
primary effluent which allow penetration of light throughout the liquid depth. The ponds are kept
shallow with depth less than 0.5m and BOD loadings of 40 – 120 kg/ha.d. The pond contents may
be periodically mixed. Such ponds develop intense algal growth and have been used on
experimental basis only.
2. Anaerobic
Completely anaerobic ponds are used as pretreatment for high strength industrial wastes
and sometimes for municipal wastewaters. They are also used for digestion of municipal sludges.
Depending on temperature and waste characteristics, BOD load of 400 – 3000 kg/ha.d and 5-50
day detention period would result in 50-85 percent BOD reduction. Such ponds are constructed
with a depth of 2.5 – 5m to conserve heat and minimize land area requirement. Usually they have
an odour problem.
3. Faculative
The facultative pond functions aerobically at the surface while anaerobic conditions
prevail at the bottom. The aerobic layer acts as a good check against odour evolution from the
pond. The treatment effected by this type of pond is comparable to that of conventional secondary
treatment processes. The facultative pond is hence best suited and most commonly used for
treatment of sewage.
Introduction
Waste stabilization ponds (WSP) are shallow man made basins into which wastewater
flows and from which after a retention time of several days (rather than several hours in
conventional treatment processes), a well-treated effluent is discharged. WSP systems comprise a
series of ponds – anaerobic, facultative and several maturation. The different functions and modes
of operation of these three different types of pond are described in Section 3 of this manual. The
WSP are low cost, high efficiency low energy, low maintenance and above all a sustainable
method of waste water treatment. They are highly appropriate under many conditions in India.
3. Maturation Ponds
Maturation ponds may be single pond or series of ponds constructed for removal of faecal
coliform, Helminth egg ponds require careful design to ensure that their faecal coliform removal.
BOD loading on the first maturation pond must not be higher than that on the preceding
facultative pond and it is preferable that is significantly lower. The maximum permissible BOD
loading or the first maturation pond is taken as 75 percent of that on the preceding facultative
pond. The loading on the first maturation pond is calculated on the assumption that 80 percent of
the BOD has been removed in the proceeding anaerobic and facultative ponds ( or 70% for
temperature below 200C, The maturation pond area is calculated from the equation.
Am = 2 Qi Om/(2D+0.001e Om)
Where Am = Area of maturation pond
Qi = mean flow m3/day
Om = Retention time in days
D = Pond depth in metric usually 1.5m
e = Net evaporation rate mm/day
Note:
In the past waste stabilisation pond technology was used for establishing sewage treatment
plant in some areas. For treating one million litres of sewage a day 2.5-3 acres land was required.
Now new technologies requiring less land such as fluid aerobic bio-reactor, sequencing batch
reactor and modified activated sludge process have emerged. They are cost effective. In 2006
Govt. of Tamil Nadu constituted Experts Committee with the task of identifying and
recommending technology options on urban local bodies. Depending upon the requirement and
suitability, the expert committee gives its advice to each local body (Source : The Hindu
27.4.2007)
Thus the concept of WSP system may not be of much need in Tamilnadu.
a) Screening :
Coarse Screens : made of bars with opening of 7.5 to 15 cm
Bar screens : made of bars with openings of 5 to 10 cm
Amount of materials removed by Screens : 3 to 180 cum/million cum of sewage
screened
b) Grit Removal:
Velocity in grit channels : 30 cm/sec
Size of grit particles removed : 0.15 mm to 0.20 mm grains of sp.gr. 2.30 to
2.65
Amount of grit removed : 6 to 72 cum/million cum of sewage treated.
ii. Primary Treatment:
Plain settling of sewage to remove organic matter to the extent possible
Usual efficiencies : 30% COD removal and 50% suspended solids removal
iii. Secondary Treatment
a) Intermittent sand filters
b) Trickling filters or
c) Activated sludge units
2. Grit Chambers:
Horizontal velocity of flow : 0.15 to 0.30 m/sec
Detention time : 60 sec. (for 3 DWF)
Surface loading rate : 40 m3/m2/hour
Grit collection : 12 to 27 cum/million cum.
3. Settling Tanks: (Plain sedimentation)
Detention time : 2.0 to 2.5 hours
Overflow rate : 27 to 45 m3/day/m2
Depth of tank : 3.0 to 4.0 m
Velocity of flow : 0.30 to 1.50 m/min
Solids loading :30 kg/m2/day
4. Intermittent Sand Filters:
Design loading on filters million litres/hectare/day
1) For raw sewage : 0.5
2) For presettled sewage (after screen and grit removal): 1.0
3) Primary treatment complete (after settling) : 3.0
5. Dosing Tanks:
Enough flow to flood one unit of filter to a depth of 5 to 10 cm.
Each filter bed should receive 1 or 2 doses per day .
Average rate of dosage : 30 litres/sec for 500 m2(
(with intermittent dosing and resting of sand beds)
6. Trickling filters : Low rate High rate
i) Hydraulic loading
(in million litres/hectare metre/day) 10 to 40 100 to 400
ii) Organic loading
(in tonne BOD/hectare metre/day) 1.1 to 3.5 3.5 to 17.5
iii) Depth in m 1.8 to 3.0 1.0 to 2.4
Recirculation None 1:1 to 1:4
Filter volume 5 to 10 times 1
iv) Power requirements
(kw/million litres) None 30 to 180
Dosing interval 5 min. 15 sec.
Nature of dosing Intermittent Continuous
7. Activated Sludge Units
Design Parameters for activated sludges aeration tank capacities and permissible loadings
Process Plant Design Aeration Plant Design Aerator Kg
flow (mld) Retention kg/BOD5/day loading BOD5/day
Period kg/BOD5/m3 Kg MLSS
(hours)
Conventional Upto 2.25 7.57.5 to Upto 450 0.50 0.50 to 0.25
2.25 to 6.06.0 up 450 to 1350 0.50 to 0.65
6.756.75 up 1350 up 0.65 up
Modified or High rate All 2.5 up 900 up 1.60 1 or less
Step Aeration 2.50 to 6.75 7.5 to 5.0 450 to 1350 0.50 to 0.80 0.5 to 0.2
6.75 up 5.0 up 1350 up 0.80
Contact stabilization Upto 2.25 3.0* Upto 450 0.50 0.5 to 0.2
2.25to 6.75 3.0to 2.0* 450 to 1350 0.50 to 0.80
6.75 up 1.5 to2.0* 1350 up 0.80 up
Extended aeration All 24 All 0.20 0.10 to 0.05
* Detention time in contact zone which is 30 to 35% of total aeration capacity.
Re-aeration zone comprises the balance of the aeration capacity.
8. Design parameters for Secondary or Final Settling Tanks of Activated Sludge Plants
Type of Process Average Design flow (mld) Detention time Surface settling
(hours) rates (m3/m2/day
Conventional, Upto 2.25 3.0 27
modified or High 2.25 to 6.75 2.5 32
rate & Step aeration 6.75 up 2.0 37
Contact stabilisation Upto 2.25 3.6 23
2.25to 6.75 3.0 27
6.75 up 2.5 32
Extended aeration Upto 0.23 4.0 14
0.23 to 0.69 3.6 14
0.69 up 3.0 27
11.Disinfection of sewage
Chlorine dosages required inmg/1
Raw sewage : 20 to 25
Primary settling tank effluent : 20
Trickling filter effluent : 15
Activated sludge effluent :8
Sand filter effluent :6
13.Anaerobic Pond:
BOD loading = 880kg/hectare/day
Water depth = not less than 2.5 m - not more than 3.0 m
Detention period = 4 days
BOD removal = 50 to 60%
Facultative Pond
Same design criteria as in (a) but influent BOD would be less.
c) for hospitals, educational institutions, small colonies, etc. even chance odours must be absent
and single facultative pond is designed as below:
BOD loading = 110 kg/hectare/day
Water depth = not more than 1.5 to 1.7 m
Detention period = 35 to 40 day
HAND BOOK
ON
Office of the
Principal Accountant General (Civil Audit)
Tamil Nadu and Pondicherry
Chennai
HAND BOOK
ON
Office of the
Principal Accountant General (Civil Audit)
Tamil Nadu and Pondicherry
Chennai
Preamble 01
Sewage Treatment 27
Stabilisation Pond 33
GRIT PARSHALL
FLUME
RA
SCREEN
GRIT PRIMARY
AERATION TREATED
CLARIFIER SECONDARY
CHAMBER SEWAGE
TANK CLARIFIER
S
IN
SL
EXCESS
SLU
SL DIG CEN
EST
GAS
GAS
EXCESS GAS
G
FOR PO