Professional Documents
Culture Documents
16 - 1
JOB
A B C
1 5 8 6
Worker 2 6 7 9
3 4 5 3
PROBLEM NO. 16 - 3
ROUTE
A B C D E
1 4 5 9 8 7
2 6 4 8 3 5
Truck 3 7 3 10 4 6
4 5 2 5 5 8
5 6 5 3 4 9
PROBLEM NO. 16 - 4
WORKER
A B C
1 12 8 11
2 13 10 8
Job
3 14 9 14
4 10 7 12
PROBLEM NO. 16 - 5
WORKER
A B C D E
1 14 18 20 17 18
2 14 15 19 16 17
Job 3 12 16 15 14 17
4 11 13 14 12 14
5 10 16 15 14 13
PROBLEM NO. 16- 6
Processing Remaining
Time Due Date Number of
Job (days) (days) Operations
A 8 20 2
B 10 18 4
C 5 25 5
D 11 17 3
E 9 35 4
PROBLEM NO. 16 - 9
TIME (HOURS)
Order Step 1 Step 2
A 1.20 1.40
B 0.90 1.30
C 2.00 0.80
D 1.70 1.50
E 1.60 1.80
F 2.20 1.75
G 1.30 1.40
PROBLEM NO. 16 - 10
TIME (HOURS)
Job Machine A Machine B
a 16 5
b 3 13
c 9 6
d 8 7
e 2 14
f 12 4
g 18 14
h 20 11
PROBLEM NO. 16 - 11
CUTTING POLISHING
Job Start Finish Start Finish
A 0 2 2 5
B 2 6 6 9
C 6 11 11 13
D 11 15 15 20
E 15 17 20 23
F 17 20 23 24
G 20 21 24 28
PROBLEM NO. 16 - 14
Remaining Remaining
Processing Number of
Job Time (days) Due Date Operations
a 5 8 2
b 6 5 4
c 9 10 4
d 7 12 3
e 8 10 2
PROBLEM NO. 16 - 17
Setup
Time (hrs.) Following Job's Setup Time (hrs.)
A B C
A 2.4 - 1.8 2.2
Preceding Job B 3.2 0.8 - 1.4
C 2.0 2.6 1.3 -
PROBLEM NO. 16 - 21
Setup
Time (hrs.) Following Job's Setup Time (hrs.)
A B C D
A 2 - 5 x 4
B 1 7 - 3 2
Preceding Job
C 3 x 2 - 2
D 2 4 3 6 -
PROBLEM NO. 16 - 22
Period
1 2 3 4 5
Planned 24 24 24 24 20
Input
Actual 25 27 20 22 24
Period
1 2 3 4 5
Planned 24 24 24 24 23
Output
Actual 24 22 23 24 24
PROBLEM NO. 16 - 23
Period
1 2 3 4 5 6
Planned 200 200 180 190 190 200
INPUT
Actual 210 200 179 195 193 194
Period
1 2 3 4 5 6
Planned 200 200 180 190 190 200
OUTPUT
Actual 205 194 177 195 193 200
PROBLEM NO. 16 - 24