DREJTORIA E POLITIKAVE TE NDERTIMIT Mars - 2015

Manuali 1 PRODHIMI I MATERIALEVE TE NDERTIMIT

Nr. PUNTORI TRANSPORT MAKINERI MATERIAL Shp Fitim


EMERTIMI Njesia op çmimi Vlefta T/km çmimi Vlefta o.p çmimi Vlefta Sasia çmimi Vlefta Shuma pl TOTALI
Analize 8% 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

1.1/p Prodhim gur kave m3


Sp + p op 2.94 125 367.5
Shtese mbi page 65% leke 368 0.650 239
Gure T/km 0.085 20 2
Elektrokompresor 10m3/min op 0.04 1500 60
Elektrokompresor 20m3/min op 0.04 1800 72
Buldozer S 80/100 op 0.02 4800 96
Vete ngarkues 1.5 m3 op 0.01 2625 26.25
Eksploziv kg 0.3 150 45
Kapsolla elektrike cope 0.23 2 0.506
Tel ekektrik ml 0.15 20 3
Shuma: 606 2 254.25 49 911 73 91 1075

1.3/p Prodhim gur lumi m3


Sp + p op 2.7 125 337.5
Shtese mbi page 65% leke 338 0.650 219
Gur lumi 8.5 20 170
Shuma: 557 170 727 58 73 858

1.4/p Prodhim rërë lumi m3


Sp + p op 1.74 125 217.5
Shtese mbi page 65% leke 218 0.650 141
Ekskavator 0.25 m3 m3 8 20 160 0.06 2810 155 1.25 50 62.5
Shuma: 359 160 155 62.5 736 59 74 868

1.10/p Prodhim rërë shtufi nat. m3


Sp + p op 0.35 125 43.75
Shtese mbi page 65% leke 43.8 0.650 28
Te ndryshme T/km 7.5 20 150
Sonde BU - 200 op 0.04 1313 52.52 Rere
Ekskavator 1 m3 op 0.05 4000 184 1.21 150 181.5
Buldozer S 80/100 op 0.023 4800 110
Eksploziv kg 0.51 150 76.5
Page 1
Nr. PUNTORI TRANSPORT MAKINERI MATERIAL Shp Fitim
EMERTIMI Njesia op çmimi Vlefta T/km çmimi Vlefta o.p çmimi Vlefta Sasia çmimi Vlefta Shuma pl TOTALI
Analize 8% 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Kapsolla elektrike cope 0.02 2 0.04
Tel elektrik ml 0.2 20 4
Shuma: 72 150 346.92 262 831 66 83 981

1.11/p Prodhim rërë shtufi lavat m3


Sp + p op 1.15 125 143.75
Shtese mbi page 65% leke 144 0.650 93
Transport T/km 7.5 20 150
Elektropompe op 0.12 310 37
Vinc cjap me grejfer 0.5 op 0.17 126 21
Vibrator op 0.11 53 6
Pjata ushqyese op 0.22 105 23
Granulator > 4 m3/ore op 0.22 280 62
Larese shtufi bavareze op 0.22 472.5 104
Transportier 40 m op 0.06 105 6
Material shtufi m3 1.21 150 181.5
Shuma: 237 150 259 181.5 828 66 83 977

1.15/p Prodhim zhavor lumi m3

Ekskavator 2 m3 op 0.03 4500 122


Zhavor m3 8 20 160 1 50 50
Shuma: 160 122 50 332 27 33 391

1.17/p Prodhim rërë lavatrice m3


Sp + p op 0.88 125 110
Sigurime shoqerore 65% leke 110 0.650 72
Transport rere T/km 8.5 20 170
Transportier 25 m op 0.64 79 51
Shoshe vibruese > 9 m3/ore op 0.06 263 15
Shoshe rrotulluese 4-11 m3/h op 0.12 210 25
Gurthyese 400x600mm op 0.06 578 34
Larese rere > 5 m3 op 0.12 472.5 55
Elektropompe 40 KW op 0.06 310 18
Buldozer S 80/100 op 0.023 4800 110
Ekskavator 0.25 m3 op 0.017 2810 48
Zhavor m3 3 332 1036
Shuma: 182 170 355 1036 1743 139 174 2056

Page 2
Nr. PUNTORI TRANSPORT MAKINERI MATERIAL Shp Fitim
EMERTIMI Njesia op çmimi Vlefta T/km çmimi Vlefta o.p çmimi Vlefta Sasia çmimi Vlefta Shuma pl TOTALI
Analize 8% 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
1.18/p Prodhim zall lavatrice m3
Sp + p op 0.44 125 55
Sigurime shoqerore 65% leke 55 0.650 36
Transport rere T/km 8.5 20 170
Transportier 25 m op 0.32 79 25
Shoshe vibruese > 9 m3/ore op 0.03 263 8
Shoshe rrotulluese 4-11 m3/h op 0.06 210 12
Gurthyese 400x600mm op 0.03 578 17
Larese rere > 5 m3 op 0.06 472.5 27
Elektropompe 40 KW op 0.03 310 9
Buldozer S 80/100 op 0.01 4800 53
Ekskavator 0.25 m3 op 0.01 2810 31
Zhavor m3 1.5 331.5 487
Shuma: 91 170 183 487 931 74 93 1098

Prodhim çakell per betone


1.19/p ( granil ) m3
Sp + p op 0.48 125 60
Shtese mbi page 65% leke 60 0.650 39
Transport gur kave m3 0.782 20 16
Vibro ushqyes op 0.18 158 28
Transportier 15 m op 0.18 53 10
Transportier 25 m op 0.18 79 14
Gurthyese 400x600mm op 0.18 578 104
Granulator 4 m3 op 0.18 280 50
Shoshe rrotulluese > 10 m3/h op 0.35 210 74
Gur kave m3 1.05 911 956
Shuma: 99 16 280 956 1351 108 135 1594

1.19/1p Prodhim çakell makinerie m3


Sp + p op 0.48 125 60
Shtese mbi page 65% leke 60 0.650 39
Transport gur kave m3 0.782 20 16
Vibro ushqyes op 0.18 158 28
Transportier 15 m op 0.18 53 10
Transportier 25 m op 0.18 79 14
Gurthyese 400x600mm op 0.18 578 104
Granulator 4 m3 op 0.18 280 50
Gur kave m3 1.05 910.8 956.37

Page 3
Nr. PUNTORI TRANSPORT MAKINERI MATERIAL Shp Fitim
EMERTIMI Njesia op çmimi Vlefta T/km çmimi Vlefta o.p çmimi Vlefta Sasia çmimi Vlefta Shuma pl TOTALI
Analize 8% 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Shuma: 99 16 207 956.37 1278 102 128 1508

1.19/2p Prodhim çakell gurore m3


Sp + p op 0.35 125 43.75
Shtese mbi page 65% leke 43.8 0.650 28
Transport çakull gurore m3 0.782 20 16
Ekskavator 1 m3 op 0.02 4000 60
Buldozer S 80/100 KF op 0.05 4800 240
Mbeturine gur i coptuar 1.08 150.0 162
Shuma: 72 16 300 162 550 44 55 649

1.19/3p Prodhim rërë guri m3


Sp + p op 2.72 125 340
Shtese mbi page 65% leke 340 0.650 221
Transport gur kave m3 0.782 20 16
Vibro ushqyes op 0.27 95 26
Transportier 15 m op 0.27 53 14
Transportier 25 m op 0.27 79 21
Gurthyese 400x600mm op 0.27 578 156
Granulator 4 m3 op 0.27 280 76
Shoshe rrotulluese > 10 m3/h op 0.52 210 109
Gur kave m3 1.05 910.8 956
Shuma: 561 16 402.15 956 1935 155 194 2283

1.20/p Prodhim gelqere e pashuar ton


Sp + p op 12.8 125 1600
Shtese mbi page 65% leke 1600 0.650 1040
Transport gur kave m3 8.5 20 170
Qymyr guri me 2800 k kalori kg 23.9 20 478 2390 2.5 5975
Gur gelqeror kave m3 1.05 911 956.37
Shuma: 2640 648 6931.4 10219 818 1022 12059

1.20/1p Prodhim gelqere e shuar ton


Sp + p op 4.3 125 537.5
Shtese mbi page 65% leke 538 0.650 349
Shuarese gelqere op 0.75 158 119
Transportier 40 m op 0.31 105 33
Elektropompe 10 KW op 0.25 230 58
Vinc cjap me grejfer 0.5 op 0.25 126 32

Page 4
Nr. PUNTORI TRANSPORT MAKINERI MATERIAL Shp Fitim
EMERTIMI Njesia op çmimi Vlefta T/km çmimi Vlefta o.p çmimi Vlefta Sasia çmimi Vlefta Shuma pl TOTALI
Analize 8% 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Gelqere e pashuar ton 0.66 10219 6745
Shuma: 887 240.05 6745 7872 630 787 9289

1.21/p Prodhim llaç gelqere 1:3 m3


Sp + p op 3.36 125 420
Shtese mbi page 65% leke 420 0.650 273
Betonjere 250 liter op 0.9 174 156.6
Gelqere e shuar kg 339 7.87 2669
Uje liter 200 0.40 80
Rere m3 1.03 736 758
Shuma: 693 156.6 3507 4356 348 436 5140

1.22/p Prodhim llaç gelqere 1:2 m3


Sp + p op 3.36 125 420
Shtese mbi page 65% leke 420 0.650 273
Betonjere 250 liter op 0.9 174 156.6
Gelqere e shuar kg 435 7.872 3424
Uje liter 200 0.40 80
Rere m3 0.89 736 655
Shuma: 693 156.6 4159 5009 401 501 5910

1.23/p Prodhim llaç perzier M1 m3


Sp + p op 3.36 125 420
Shtese mbi page 65% leke 420 0.650 273
Betonjere 250 liter op 0.9 174 156.6
Gelqere e shuar kg 105 7.872 827
Çimento 32.5 N kg 114 8.1 923
Uje liter 200 0.40 80
Rere m3 1.03 736 758
Shuma: 693 156.6 2588 3438 275 344 4056

1.23/p Prodhim llaç perzier M2,5 m3

Sp + p op 3.36 125 420


Shtese mbi page 65% leke 420 0.650 273
Betonjere 250 liter op 0.9 174 156.6

Page 5
Nr. PUNTORI TRANSPORT MAKINERI MATERIAL Shp Fitim
EMERTIMI Njesia op çmimi Vlefta T/km çmimi Vlefta o.p çmimi Vlefta Sasia çmimi Vlefta Shuma pl TOTALI
Analize 8% 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

Gelqere e shuar kg 87 8 685


Çimento 32.5 N kg 206 8.1 1669
Uje liter 200 0.40 80
Rere m3 1.01 736 743
Shuma: 693 156.6 3177 4026 322 403 4751

1.23/p Prodhim llaç perzier M5 m3


Sp + p op 3.36 125 420
Shtese mbi page 65% leke 420 0.650 273
Betonjere 250 liter op 0.9 174 156.6
Gelqere e shuar kg 70 7.87 551
Çimento 32.5 N kg 253 8.1 2049
Uje liter 200 0.40 80
Rere m3 0.92 736 677
Shuma: 693 156.6 3357 4207 337 421 4964

1.23/p Prodhim llaç perzier M7.5 m3


Sp + p op 3.36 125 420
Shtese mbi page 65% leke 420 0.650 273
Betonjere 250 liter op 0.9 174 156.6
Gelqere e shuar kg 60 7.872 472
Çimento 32.5 N kg 277 8.1 2244
Rere m3 0.9 736 662
Shuma: 693 156.6 3378 4228 338 423 4989

1.24/2 Prodhim llaç çim M2.5 (1:6) m3


Sp + p op 3.36 125 420
Shtese mbi page 65% leke 420 0.650 273
Fabrike betoni op 0.1 1800 180
Çimento 32.5 N kg 206 8.1 1668.6
Uje liter 200 0.40 80
Rere m3 1.13 736 832
Shuma: 693 180 2580 3453 276 345 4075

1.24/2 Prodhim llaç çim M5(1:4.5) m3


Sp + p op 3.36 125 420
Shtese mbi page 65% leke 420 0.650 273
Fabrike betoni op 0.1 1800 180
Page 6
Nr. PUNTORI TRANSPORT MAKINERI MATERIAL Shp Fitim
EMERTIMI Njesia op çmimi Vlefta T/km çmimi Vlefta o.p çmimi Vlefta Sasia çmimi Vlefta Shuma pl TOTALI
Analize 8% 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Çimento 32.5 N kg 251 8.1 2033
Uje liter 200 0.40 80
Rere m3 1.04 736 765
Shuma: 693 180 2878 3751 300 375 4427

1.24/2 Prodhim llaç çim M7.5(1:4) m3


Sp + p op 3.36 125 420
Shtese mbi page 65% leke 420 0.650 273
Fabrike betoni op 0.1 1800 180
Çimento 32.5 N kg 270 8.1 2187
Uje liter 200 0.40 80
Rere m3 0.95 736 699
Shuma: 693 180 2966 3839 307 384 4530

1.24/p Prodhim llaç çim C7/10(1:3) m3


Sp + p op 3.36 125 420
Shtese mbi page 65% leke 420 0.650 273
Fabrike betoni op 0.1 1800 180
Çimento 32.5 N kg 410 8.3 3403
Uje liter 200 0.40 80
Rere m3 0.92 736 677
Shuma: 693 180 4160 5033 403 503 5939

1.25/p Prodhim llaç çim C16/20(1:2) m3


Sp + p op 3.36 125 420
Shtese mbi page 65% leke 420 0.650 273
Fabrike betoni op 0.1 1800 180
Çimento 32.5 N kg 527 8.7 4585
Uje liter 200 0.40 80
Rere m3 0.89 736 655
Shuma: 693 180 5320 6193 495 619 7308

1.26/1 Beton C-6/10 (Me zall) m3


Sp + p op 1.14 185 210.9
Shtese mbi page 65% leke 211 0.650 137
Fabrike betoni op 0.1 1800 180
Rere m3 18 20 360 0.49 736 361
Zall m3 28 20 560 0.77 931 717
Çimento 32.5 N kg 190 8.1 1539

Page 7
Nr. PUNTORI TRANSPORT MAKINERI MATERIAL Shp Fitim
EMERTIMI Njesia op çmimi Vlefta T/km çmimi Vlefta o.p çmimi Vlefta Sasia çmimi Vlefta Shuma pl TOTALI
Analize 8% 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Uje liter 200 0.4 80
Shuma: 348 920 180 2696 4144 332 414 4890

1.26/2 Beton C-6/10 (Me cakell) m3


Sp + p op 1.14 185 210.9
Shtese mbi page 65% leke 211 0.650 137
Fabrike betoni op 0.1 1800 180
Rere m3 18 20 360 0.51 736 375
Cakell m3 28 20 560 0.79 1351 1067
Çimento 32.5 N kg 200 8.1 1620
Uje liter 200 0.4 80
Shuma: 348 920 180 3143 4591 367 459 5417

1.27/1 Beton C-7/10 (Me zall) m3


Sp + p op 1.14 185 210.9
Shtese mbi page 65% leke 211 0.650 137
Fabrike betoni op 0.1 1800 180
Rere m3 18 20 360 0.49 736 361
Zall m3 28 20 560 0.78 931 726
Çimento 32.5 N kg 232 8.1 1879
Uje liter 200 0.4 80
Shuma: 348 920 180 3046 4494 360 449 5303

1.27/2 Beton C-7/10 (Me cakell) m3


Sp + p op 1.14 185 210.9
Shtese mbi page 65% leke 211 0.650 137
Fabrike betoni op 0.1 1800 180
Rere m3 17 20 340 0.48 736 353
Cakell m3 25 20 500 0.77 1351 1040
Çimento 32.5 N kg 243 8.1 1968
Uje liter 200 0.4 80
Shuma: 348 840 180 3442 4810 385 481 5676

1.28/p Beton C-12/15 (Me zall) m3


Sp + p op 1.14 185 210.9
Shtese mbi page 65% leke 211 0.650 137
Fabrike betoni op 0.1 1800 180
Rere m3 18 20 360 0.49 736 361
Zall m3 28 20 560 0.77 931 717

Page 8
Nr. PUNTORI TRANSPORT MAKINERI MATERIAL Shp Fitim
EMERTIMI Njesia op çmimi Vlefta T/km çmimi Vlefta o.p çmimi Vlefta Sasia çmimi Vlefta Shuma pl TOTALI
Analize 8% 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Çimento 32.5 N kg 245 8.3 2034
Uje liter 200 0.4 80
Shuma: 348 920 180 3191 4639 371 464 5474

1.28/1 Beton C12/15 (Me cakell) m3


Sp + p op 1.14 185 210.9
Shtese mbi page 65% leke 211 0.650 137
Fabrike betoni op 0.1 1800 180
Rere m3 17 20 340 0.48 736 353
Cakell m3 25 20 500 0.77 1351 1040
Çimento 32.5 N kg 257 8 2133
Uje liter 200 0.4 80
Shuma: 348 840 180 3607 4975 398 497 5870

1.29/p Beton C-16/20 (Me zall) m3


Sp + p op 1.14 185 210.9
Shtese mbi page 65% leke 211 0.650 137
Fabrike betoni op 0.1 1800 180
Rere m3 17 20 340 0.47 736 346
Zall m3 27 20 540 0.76 931 707
Çimento 32.5 N kg 287 8 2382
Uje liter 200 0.4 80
Shuma: 348 880 180 3515 4923 394 492 5810

1.29/1 Beton C16/20 (Me cakell) m3


Sp + p op 1.14 185 210.9
Shtese mbi page 65% leke 211 0.650 137
Fabrike betoni op 0.1 1800 180
Rere m3 17 20 340 0.47 736 346
Cakell m3 24 20 480 0.75 1351 1013
Çimento 32.5 N kg 302 8 2507
Uje liter 200 0.4 80
Shuma: 348 820 180 3946 5294 424 529 6247

1.30/p Beton C-20/25 (Me zall) m3


Sp + p op 1.14 185 210.9
Shtese mbi page 65% leke 211 0.650 137
Fabrike betoni op 0.1 1800 180
Rere m3 17 20 340 0.47 736 346

Page 9
Nr. PUNTORI TRANSPORT MAKINERI MATERIAL Shp Fitim
EMERTIMI Njesia op çmimi Vlefta T/km çmimi Vlefta o.p çmimi Vlefta Sasia çmimi Vlefta Shuma pl TOTALI
Analize 8% 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Zall m3 27 20 540 0.76 931 707
Çimento 42.5 R kg 294 8.7 2558
Uje liter 200 0.4 80
Shuma: 348 880 180 3691 5099 408 510 6017

1.30/1 Beton C-20/25 (Me cakell) m3


Sp + p op 1.14 185 210.9
Shtese mbi page 65% leke 211 0.650 137
Fabrike betoni op 0.1 1800 180
Rere m3 17 20 340 0.46 736 339
Cakell m3 24 20 480 0.76 1351 1027
Çimento 42.5 R kg 312 8.7 2714
Uje liter 200 0.4 80
Shuma: 348 820 180 4160 5508 441 551 6499

1.31/p Beton C-25/30 (Me zall) m3


Sp + p op 1.14 185 210.9
Shtese mbi page 65% leke 211 0.650 137
Fabrike betoni op 0.1 1800 180
Rere m3 16 20 320 0.44 736 324
Zall m3 27 20 540 0.74 931 689
Çimento 42.5 R kg 368 8.7 3202
Uje liter 200 0.4 80
Shuma: 348 860 180 4294 5682 455 568 6705

1.31/1 Beton C-25/30 (Me cakell) m3


Sp + p op 1.14 185 210.9
Shtese mbi page 65% leke 211 0.650 137
Fabrike betoni op 0.1 1800 180
Rere m3 15 20 300 0.43 736 316
Cakell betoni m3 23 20 460 0.73 1351 986
Çimento 42.5 R kg 388 8.7 3376
Uje liter 200 0.4 80
Shuma: 348 760 180 4758 6046 484 605 7135

1.34/p Beton C-37/45 (Me zall) m3


Sp + p op 1.14 185 210.9
Shtese mbi page 65% leke 211 0.650 137
Fabrike betoni op 0.1 1800 180

Page 10
Nr. PUNTORI TRANSPORT MAKINERI MATERIAL Shp Fitim
EMERTIMI Njesia op çmimi Vlefta T/km çmimi Vlefta o.p çmimi Vlefta Sasia çmimi Vlefta Shuma pl TOTALI
Analize 8% 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Rere m3 15 20 300 0.42 736 309
Zall m3 23 20 460 0.63 931 586
Çimento 42.5 R kg 525 8.7 4568
Uje liter 200 0.4 80
Shuma: 348 760 180 5543 6831 546 683 8061

1.34/1 Beton C-37/45 (Me cakell) m3


Sp + p op 1.14 185 210.9
Shtese mbi page 65% leke 211 0.650 137
Fabrike betoni op 0.1 1800 180
Rere m3 14 20 280 0.4 736 294
Cakell betoni m3 20 20 400 0.63 1351 851
Çimento 42.5 R kg 556 8.7 4837
Uje liter 200 0.4 80
Shuma: 348 680 180 6063 7271 582 727 8580

Prodhim elememente b/a te


1.37/p parapergatitura me brinje 8-10cm m3
Sp + p op 26.3 185 4856
Sigurime shoqerore 16.7% leke 4856 0.167 811
Beton C-16/20 m3 1.122 20 22 1.02 5294 5400
Kallep inventari m2 22.5 140 3150
Gozhde kg 0.11 90 9.9
Solar kg 4.4 87 382.8
Vinc op 1.2 53 63.6
Vibrator op 0.6 53 31.8
Shuma: 5667 22 95.4 8942 14727 1178 1473 17378

Prodhim elememente b/a te


1.38/p parapergatitura me brinje 11-20cm m3
Sp + p op 16.4 185 3034
Sigurime shoqerore 16.7% leke 3034 0.167 507
Beton C-16/20 m3 1.122 20 22 1.02 5294 5400
Kallep inventari m2 12 140 1680
Gozhde kg 0.06 90 5
Solar kg 2.4 87 209
Vinc op 1.2 53 63.6
Vibrator op 0.6 53 31.8

Page 11
Nr. PUNTORI TRANSPORT MAKINERI MATERIAL Shp Fitim
EMERTIMI Njesia op çmimi Vlefta T/km çmimi Vlefta o.p çmimi Vlefta Sasia çmimi Vlefta Shuma pl TOTALI
Analize 8% 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Shuma: 3541 22 95.4 7294 10952 876 1095 12924

Prodhim elememente b/a te


1.39/p parapergatitura me brinje 21-30cm m3
Sp + p op 11.6 185 2137
Sigurime shoqerore 16.7% leke 2137 0.167 357
Beton C-16/20 m3 1.122 20 22 1.02 5294 5400
Kallep inventari m2 7 140 980
Gozhde kg 0.04 90 4
Solar kg 1.4 87 122
Vinc op 1.2 53 63.6
Vibrator op 0.6 53 31.8
Shuma: 2494 22 95.4 6505 9117 729 912 10758

Prodhim elememente b/a te


1.40/p parapergatitura me brinje 31-40cm m3
Sp + p op 8.82 185 1631.7
Sigurime shoqerore 16.7% leke 1632 0.167 272
Beton C-16/20 m3 1.122 20 22 1.02 5294 5400
Kallep inventari m2 5 140 700
Gozhde kg 0.03 90 3
Solar kg 1 87 87
Vinc op 1.2 53 63.6
Vibrator op 0.6 53 31.8
Shuma: 1904 22 95.4 6189 8211 657 821 9690

Prodhim elememente b/a te


1.41/p parapergatitura me brinje 41-50cm m3
Sp + p op 7.56 185 1398.6
Sigurime shoqerore 16.7% leke 1399 0.167 234
Beton C-16/20 m3 1.122 20 22 1.02 5294 5400
Kallep inventari m2 4 140 560
Gozhde kg 0.02 90 2
Solar kg 0.75 87 65
Vinc op 1.2 53 63.6
Vibrator op 0.6 53 31.8
Shuma: 1632 22 95.4 6027 7777 622 778 9177
Page 12
Nr. PUNTORI TRANSPORT MAKINERI MATERIAL Shp Fitim
EMERTIMI Njesia op çmimi Vlefta T/km çmimi Vlefta o.p çmimi Vlefta Sasia çmimi Vlefta Shuma pl TOTALI
Analize 8% 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

Prodhim plinta b/a te


parapergatitura C-16/20 me vellim
1.45/p deri 1m3 m3
Sp + p op 7.21 185 1334
Sigurime shoqerore 16.7% leke 1334 0.167 223
Beton C-16/20 m3 1.122 20 22 1.02 4923 5022
Kallep inventari m2 9 140 1260
Gozhde kg 0.05 90 5
Solar kg 1.8 87 157
Vinc op 1.2 53 63.6
Vibrator op 0.6 53 31.8
Shuma: 1557 22 95.4 6443 8117 649 812 9579

Prodhim trare b/a te


parapergatitura C-20/25 me
1.47/p mure te holle m3
Sp + p op 24 185 4440
Sigurime shoqerore 16.7% leke 4440 0.167 741
Beton C-20/25 m3 1.122 20 22 1.02 5099 5201
Kallep inventari m2 15 140 2100
Gozhde kg 0.13 90 12
Solar kg 3 87 261
Vinc op 1.2 53 63.6
Vibrator op 0.6 53 31.8
Shuma: 5181 22 95.4 7574 12873 1030 1287 15190

Prodhim kollona b/a te


1.48/p parapergatitura C-20/25 tip govate m3
Sp + p op 21.4 185 3950
Sigurime shoqerore 16.7% leke 3950 0.167 660
Beton C-20/25 m3 1.122 20 22.44 1.02 5508 5618
Kallep inventari m2 13 140 1820
Gozhde kg 0.11 90 10
Solar kg 3 87 261
Vinc op 1.2 53 63.6
Vibrator op 0.6 53 31.8
Shuma: 4609 22 95.4 7709 12436 995 1244 14675

Page 13
Nr. PUNTORI TRANSPORT MAKINERI MATERIAL Shp Fitim
EMERTIMI Njesia op çmimi Vlefta T/km çmimi Vlefta o.p çmimi Vlefta Sasia çmimi Vlefta Shuma pl TOTALI
Analize 8% 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Prodhim soleta b/a tip govate
1.49/p 0.069m3/m2, h=30cm, C-16/20 m2
Sp + p op 1.22 185 226
Sigurime shoqerore 16.7% leke 226 0.167 38
Beton C-16/20 m3 0.770 20 15 0.089 5294 471
Kallep inventari m2 1.5 140 210
Avull ton 0.054 450 24
Solar kg 3 87 261
Vinc op 0.05 53 2.65
Vibrator op 0.08 53 4.24
Shuma: 263 15 6.89 966 1252 100 125 1478

Prodhim soleta b/a tip govate


1.50/p 0.109m3/m2, h=40cm, C-25/30 m2
Sp + p op 1.92 185 355.2
Sigurime shoqerore 16.7% leke 355 0.167 59
Beton C-25/30 m3 1.210 20 24 0.109 6046 659
Kallep inventari m2 2.1 140 294
Avull ton 0.11 450 50
Solar kg 0.42 87 37
Vinc op 0.13 53 6.89
Vibrator op 0.18 53 9.54
Shuma: 415 24 16.43 1039 1494 120 149 1763

Prodhim soleta b/a te


parapergatitura me tulla me vrima
1.51/p h=16cm m2
Sp + p op 1.51 185 279
Sigurime shoqerore 16.7% leke 279 0.167 47
Beton C-16/20 m3 0.880 20 18 0.081 5294 429
Kallep inventari m2 0.7 140 98
Tulla me 6 vrima cope 0.005 20 0.1 16 25 400
Solar kg 0.34 87 30
Vinc op 0.17 53 9.01
Vibrator op 0.1 53 5.3
Shuma: 326 18 14.31 956 1314 105 131 1551

Page 14
Nr. PUNTORI TRANSPORT MAKINERI MATERIAL Shp Fitim
EMERTIMI Njesia op çmimi Vlefta T/km çmimi Vlefta o.p çmimi Vlefta Sasia çmimi Vlefta Shuma pl TOTALI
Analize 8% 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Prodhim soleta b/a te
parapergatitura me tulla me vrima
1.52/p h=25cm m2
Sp + p op 2.44 185 451.4
Sigurime shoqerore 16.7% leke 451 0.167 75
Beton C-16/20 m3 1.507 20 30 0.137 5294 725
Kallep inventari m2 1 140 140
Tulla me 6 vrima cope 0.007 20 0.14 24 25 600
Solar kg 0.54 87 47
Vinc op 0.2 53 10.6
Vibrator op 0.17 53 9
Shuma: 527 30 20 1512 2089 167 209 2465

Prodhim soleta te plota b/a


paraperg, t=6-10cm per kanale e
1.53/p shtresa m3
Sp + p op 13.6 185 2516
Sigurime shoqerore 16.7% leke 2516 0.167 420
Beton C-16/20 m3 11.22 20 224.4 1.02 4923 5022
Kallep inventari m2 5.8 140 812
Hekur betoni kg 0 80 0
Solar kg 4 87 348
Vinc op 0.15 53 7.95
Vibrator op 0.6 53 31.8
Shuma: 2936 224 39.75 6182 9382 751 938 11071

Prodhim soleta te plota b/a


1.54/p paraperg, t=6-10cm ne lartesi m3
Sp + p op 13.6 185 2516
Sigurime shoqerore 16.7% leke 2516 0.167 420
Beton C-16/20 m3 11.22 20 224 1.02 4923 5022
Kallep inventari m2 5.8 140 812
Hekur betoni kg Shenim: Hekuri me analize te vecante. 0 80 0
Solar kg 4 87 348
Vinc op 1.2 53 63.6
Vibrator op 0.6 53 31.8
Shuma: 2936 224 95.4 6182 9438 755 944 11137

Page 15
Nr. PUNTORI TRANSPORT MAKINERI MATERIAL Shp Fitim
EMERTIMI Njesia op çmimi Vlefta T/km çmimi Vlefta o.p çmimi Vlefta Sasia çmimi Vlefta Shuma pl TOTALI
Analize 8% 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

Prodhim soleta b/a te paranderura,


1.56/p h=11cm, 2 e 7 vrima C-25/30 m2
Sp + p op 2.2 185 407
Sigurime shoqerore 16.7% leke 407 0.167 68
Beton C-25/30 m3 0.913 20 18 0.083 5682 472
Kallepi mbi vleren e betonit leke 471.6 2% 9.4
Kallep inventar m2 0.2 140 28
Mirembajtje kallepi leke 28 20% 5.6
Solar kg 0.43 87 37.41
Vinc 0.13 53 6.89
Vibrator 0.18 53 9.54
Elektro argano 0.18 45 8
Shuma: 475 18 25 552 1070 86 107 1262

Prodhim soleta b/a te paranderura,


1.57/p h=16cm, me 2 vrima C-25/30 m2
Sp + p op 4.13 185 764
Sigurime shoqerore 16.7% leke 764 0.167 128
Beton C-25/30 m3 1.144 20 23 0.104 5682 591
Kallepi mbi vleren e betonit leke 591 3% 18
Kallep inventar m2 0.3 140 42
Mirembajtje kallepi leke 17.73 20% 4
Solar kg 0.41 87 36
Vinc 0.2 53 10.6
Vibrator 0.27 53 14
Elektro argano 0.27 45 12
Shuma: 892 23 37 690 1641 131 164 1937

Prodhim soleta b/a te paranderura,


1.58/p h=16cm, me 5 vrima C-25/30 m2
Sp + p op 2.96 185 547.6
Sigurime shoqerore 16.7% leke 548 0.167 91
Beton C-25/30 m3 1.144 20 23 0.104 5682 591
Kallepi mbi vleren e betonit leke 591 2% 12
Kallep inventar m2 0.3 140 42
Mirembajtje kallepi leke 42 20% 8.4
Solar kg 0.41 87 35.67
Vinc 0.2 53 10.6

Page 16
Nr. PUNTORI TRANSPORT MAKINERI MATERIAL Shp Fitim
EMERTIMI Njesia op çmimi Vlefta T/km çmimi Vlefta o.p çmimi Vlefta Sasia çmimi Vlefta Shuma pl TOTALI
Analize 8% 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Vibrator 0.27 53 14
Elektro argano 0.27 45 12
Shuma: 639 23 37 689 1388 111 139 1638

Prodhim soleta b/a te paranderura,


1.59/p h=22cm, me 2 e 3 vrima C-25/30 m2
Sp + p op 3.63 185 672
Sigurime shoqerore 16.7% leke 672 0.167 112
Beton C-25/30 m3 1.144 20 23 0.131 5682 744.4
Kallepi mbi vleren e betonit leke 744.4 2% 14.9
Kallep inventar m2 0.35 140 49
Mirembajtje kallepi leke 49 20% 9.8
Solar kg 0.36 87 31.32
Vinc 0.2 53 10.6
Vibrator 0.27 53 14
Elektro argano 0.27 45 12
Shuma: 784 23 37 849 1693 135 169 1998

Prodhim soleta me tulla me


1.60/p veshe, h=20cm, te drejta m2
Sp + p op 1.46 185 270
Sigurime shoqerore 16.7% leke 270 0.167 45
Llac cimenti 1:2 m3 0.014 6193 86.7
Tulla sap cope 13.00 20 260 30 40 1200.0
Solar kg 0.36 87 31.3
Vinc 0.2 53 10.6
Vibrator
Elektro argano
Shuma: 315 260 10.6 1318 1904 152 190 2247

Prodhim soleta me tulla me


1.62/p veshe, h=24cm, te drejta m2
Sp + p op 1.46 185 270
Sigurime shoqerore 16.7% leke 270 0.167 45
Llac cimenti 1:2 m3 0.017 6193 105
Tulla sap cope 17.00 20 340 30 45 1350
Solar kg 0.36 87 31.32
Vinc 0.3 53 15.9
Page 17
Nr. PUNTORI TRANSPORT MAKINERI MATERIAL Shp Fitim
EMERTIMI Njesia op çmimi Vlefta T/km çmimi Vlefta o.p çmimi Vlefta Sasia çmimi Vlefta Shuma pl TOTALI
Analize 8% 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Vibrator
Elektro argano
Shuma: 315 340 15.9 1487 2158 173 216 2546

Panele te plota horizontale b/a


1.72/p C-16/20 m3
Sp + p op 11.8 185 2183
Sigurime shoqerore 16.7% leke 2183 0.167 365
Beton C-16/20 m3 1.03 5294 5453
Tako druri cope 1.3 50 65
Tel bari kg 0.01 100 1
Solar kg 1.4 87 122
Avull ton 0.08 450 36
Energji elektrike kw 22 10 220
Transport leke 12.50 20 250
Shuma: 2548 250 5896 8694 696 869 10259

Prodhim blloqe betoni me vrima


1.73/p 20x20x40cm cope
Sp + p op 0.08 185 14.8
Sigurime shoqerore 16.7% leke 14.8 0.167 2
Çimento 32.5 N kg 0.015 20 0.3 3.1 8.1 25.1
Rere e lare lavatrice m3 0.055 20 1.1 0.006 1743 10.6
Zall i lare lavatrice 5-10mm m3 0.056 20 1.1 Mak 0.007 931 6.1
Solar kg 0.01 37 0.5 0.018 87 1.6
Shuma: 17 3 0.5 43 64 5 6 75

Prodhim blloqe betoni me vrima


1.74/p 25x20x40cm cope
Sp + p op 0.06 185 11.1
Sigurime shoqerore 16.7% leke 11.1 0.167 2
Çimento 32.5 N kg 0.020 20 0.4 3.73 8.1 30.2
Rere e lare lavatrice m3 0.067 20 1.3 0.007 1743 12.9
Zall i lare lavatrice 5-10mm m3 0.067 20 1.3 Mak 0.008 931 7.4
Solar kg 0.02 37 0.6 0.019 87 1.7
Shuma: 13 3.1 0.6 52 69 6 7 81

Prodhim blloqe betoni me vrima


1.75/p 10x20x40cm cope

Page 18
Nr. PUNTORI TRANSPORT MAKINERI MATERIAL Shp Fitim
EMERTIMI Njesia op çmimi Vlefta T/km çmimi Vlefta o.p çmimi Vlefta Sasia çmimi Vlefta Shuma pl TOTALI
Analize 8% 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Sp + p op 0.09 185 17
Sigurime shoqerore 16.7% leke 16.7 0.167 3
Çimento 32.5 N kg 0.002 20 0.04 1.6 8.1 13
Rere e lare lavatrice m3 0.005 20 0.1 0.003 1743 5
Zall i lare lavatrice 5-10mm m3 0.005 20 0.1 Mak 0.003 931 3
Solar kg 0.01 37 0.3 0.12 87 10
Shuma: 19 0.2 0.3 32 52 4 5 61

Shtylla b/a C-25/30 te


1.78/p paranderura per minjera cope
Sp + p op 0.96 185 177.6
Sigurime shoqerore 16.7% leke 178 0.167 30
Beton C-25/30 m3 0.163 20 3.3 0.013 6046 79
Hekur betoni 3-5mm2 kg 1.5 82 123
Hekur betoni 6-10mm2 kg 0.130 20 2.6 1.07 76 81
Kallep metalik 16/200 m2 mak vinc 0.02 53 0.8 0.08 152 12
Mirembajtje kallepi 10% m2 mak vibrator 0.01 53 0.7 12.16 10% 1.22
Solar kg mak d/hekur 0.03 210 6.7 0.07 87 6
Shuma: 207.26 5.9 8.3 302 524 42 52 618

Garnitura b/a C-16/20,


1.79/p 100x20x4cm per minjera cope
Sp + p op 0.96 185 177.6
Sigurime shoqerore 16.7% leke 178 0.167 30
Beton C-16/20 m3 0.103 20 2.1 0.008 5294 43.409
Hekur betoni 3-5mm2 kg 0.47 82 38.54
Kallep metalik 16/200 m2 mak vinc 0.00 53 0.053 0.08 152 12.16
Mirembajtje kallepi 10% m2 mak vibrator 0.01 53 0.265 12.16 2% 0.2432
Solar kg mak d/hekur 0.00 210 0.00 0.1 87 8.7
Shuma: 207.26 2 0.3 103 313 25 31 369

Pllaka b/a C-16/20 60x20x8cm


1.81/p per kanale cope
Sp + p op 0.34 185 63
Sigurime shoqerore 16.7% leke 62.9 0.167 11
Beton C-16/20 m3 0.125 20 2.5 0.01 4923 49.2
Hekur betoni 3-5mm2 kg 0.07 82 5.7
Hekur betoni 6-10mm2 kg 0.035 20 0.7 0.57 76 43.3
Kallep metalik 16/200 m2 mak vinc 0.01 53 0.636 0.08 152 12.2

Page 19
Nr. PUNTORI TRANSPORT MAKINERI MATERIAL Shp Fitim
EMERTIMI Njesia op çmimi Vlefta T/km çmimi Vlefta o.p çmimi Vlefta Sasia çmimi Vlefta Shuma pl TOTALI
Analize 8% 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Mirembajtje kallepi 10% m2 mak vibrator 0.01 53 0.53 12.16 2% 0.2
Solar kg mak d/hekur 0.01 210 1.26 0.1 87 8.7
Shuma: 73 3.2 2.426 119 198 16 20 234

Pergatitje hekur betoni i


1.85/p zakonshem Ø 6 - 10 mm2 kg
Sp + p op 0.05 185 9.25
Sigurime shoqerore 16.7% leke 9.25 0.167 2
Hekur betoni kg 0.005 20 0.1 1.02 76 78
Prerje e drejtim hekuri makin op 0.01 63 0.3
Kthim hekuri op 0.00 63 0.2
Vinc op 0,0005 53 0.025
Shuma: 11 0.1 0.5 78 89 7 9 105

Pergatitje hekur betoni i


1.86/p zakonshem Ø > 12 mm2 kg
Sp + p op 0.03 185 5.55
Sigurime shoqerore 16.7% leke 5.55 0.167 1
Hekur betoni kg 0.005 20 0.1 1.03 80 82.4
Prerje e drejtim hekuri makin op 0.002 63 0.1
Kthim hekuri op 0.004 63 0.3
Hekur betoni per zgjatim kg Elektro argano 0.001 45 0.1 0.004 80 0.32
Vinc op 0,0005 53 2.5
Shuma: 6.5 0.1 2.9 83 92 7 9 109

Pergatitje hekur betoni i periodik


1.87/p Ø 6-10 mm2 kg
Sp + p op 0.03 185 5.55
Sigurime shoqerore 16.7% leke 5.55 0.167 1
Hekur betoni kg 0.005 20 0.1 1.03 82 84.46
Prerje e drejtim hekuri makin op 0.002 63 0.1008
Kthim hekuri op 0.004 63 0.252
Hekur betoni per zgjatim kg Elektro argano 0.001 45 0.0585 0.004 82 0.3
Vinc op 0,0005 53 2.5
Shuma: 6.5 0.1 2.91 85 94 8 9 111

Pergatitje hekur betoni i periodik


1.88/p Ø > 12 mm2 kg
Sp + p op 0.03 185 5.55

Page 20
Nr. PUNTORI TRANSPORT MAKINERI MATERIAL Shp Fitim
EMERTIMI Njesia op çmimi Vlefta T/km çmimi Vlefta o.p çmimi Vlefta Sasia çmimi Vlefta Shuma pl TOTALI
Analize 8% 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Sigurime shoqerore 16.7% leke 5.55 0.167 1
Hekur betoni kg 0.005 20 0.1 1.03 78 80.34
Prerje e drejtim hekuri makin op 0.002 63 0.1008
Kthim hekuri op 0.004 63 0.252
Hekur betoni per zgjatim kg Elektro argano 0.001 45 0.0585 0.004 78 0.3
Vinc op 0,0005 74 2.5
Shuma: 6.5 0.1 2.91 81 90 7 9 106

Pergatitje hekur Ø 3-5 mm2, б =


1.89/p 6500 kg/cm2 per tulla me vesh, sap. kg
Sp + p op 0.07 185 13.5
Sigurime shoqerore 16.7% leke 13.5 0.167 2
Hekur betoni kg 0.005 20 0.1 1.01 95 96
Prerje e drejtim hekuri makin op 0.012 63 0.756
Kthim hekuri op 0.006 63 0.378
Vinc op 0,0005 53 0.25
Shuma: 16 0.1 1.4 96 113 9 11 134

Pergatitje konstruksione
1.99/p metalike te perbera ton
Sp + p op 85 185 15725
Sigurime shoqerore 16.7% leke 15725 0.167 2626 Gazogjen
Hekur profil e shirit kg 5.15 20 103 1.5 72 108 810 80 64800
Llamarine e zeze kg Tranxhe elektrike 1.5 210 315 220 75 16500
Karbit kg Saldatrice 15 74 1110 1 183 183
Elektroda kg Trapano elektrik 1.5 95 142.5 10 180 1800
Oksigjen op Vinc ure 3,0 53 150 10 122 1220
Shuma: 18351 103 1825.5 84503 104783 8383 10478 123643

Pergatitje konstruksione
1.100/p metalike te thjeshta ton
Sp + p op 80 185 14800
Sigurime shoqerore 16.7% leke 14800 0.167 2472 Gazogjen
Hekur profil e shirit kg 5.15 20 103 1.5 72 108 910 80 72800
Llamarine e zeze kg Tranxhe elektrike 1 210 210 120 75 9000
Kthim hekuri op Saldatrice 5 74 370 1.5 183 274.5 karbit
Elektroda kg Trapano elektrik 2 95 190 4.0 180 720
Vinc op Vinc ure 2.0 53 100 15 122 1830 oksigjen

Page 21
Nr. PUNTORI TRANSPORT MAKINERI MATERIAL Shp Fitim
EMERTIMI Njesia op çmimi Vlefta T/km çmimi Vlefta o.p çmimi Vlefta Sasia çmimi Vlefta Shuma pl TOTALI
Analize 8% 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Shuma: 17272 103 978 84625 102977 8238 10298 121513

Pergatitje kapriata me hekur


1.102/p betoni ton
Sp + p op 121 185 22385
Sigurime shoqerore 16.7% leke 22385 0.167 3738 Gazogjen
Hekur betoni kg 6.00 20 120 1.5 72 108 860 80 68800
Saldatriqe op 24 74 1776 1.5 183 274.5 karbit
Tranxhe elektrike liter 0.6 210 126 4 150 600
Trapano elektrik op 0.14 95 13.3 15.0 122 1830 oksigjen
Elektroda kg 30.0 250 7500
Vinc op 0,25 53 125 1.0 125 125 dadi e bulona
Hekur profil e shirit kg 50,0 80 3500
Llamarine d > 2 mm kg 120,0 75 7800
Shuma: 26123 120 2148.3 90430 118821 9506 11882 140209

Pergatitje kapriata metalike me


1.105/p profile ton
Sp + p op 85 185 15725
Sigurime shoqerore 16.7% leke 15725 0.167 2626 Gazogjen
Hekur betoni kg 6 20 120 1.5 72 108
Saldatriqe op 25 74 1850 2.5 183 457.5 karbit
Gazogjen liter
Tranxhe elektrike op 3 210 630 25.0 122 3050 oksigjen
Elektroda kg Trapano 3 95 285 23,0 250 5750
autovinc op 2 3100 6820
Hekur profil e shirit kg 730.0 80 65700
Llamarine d > 2 mm kg 300,0 75 21000
Shuma: 18351 120 9693 95958 124122 9930 12412 146463

Pergatitje shkalle metalike me Ø


1.107/p e profile ton
Sp + p op 91 185 16835
Sigurime shoqerore 16.7% leke 16835 0.167 2811
Hekur Ø kg 20.4 20 408 240 80 19200
Hekur profil e shirit kg 400 80 32000
Llamarine d > 2.5 mm kg 380 75 28500
Elektroda kg 6 180 1080
Karbit kg 1.5 183 274.5

Page 22
Nr. PUNTORI TRANSPORT MAKINERI MATERIAL Shp Fitim
EMERTIMI Njesia op çmimi Vlefta T/km çmimi Vlefta o.p çmimi Vlefta Sasia çmimi Vlefta Shuma pl TOTALI
Analize 8% 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Oksigjen liter 15 122 1830
Saldatrice elektrike op 9.5 74 703
Gazogjen op 3 80 240
Tranxhe elektrike op 2 210 420
Autovinc op 0.2 3100 620
Vinc ure op 1.5 53 79.5
Shuma: 19646 408 2062.5 82885 105001 8400 10500 123902

Pergatitje zgara metalike


1.111/p dekorative per dritare e lloxha ton
Sp + p op 344 185 63640
Sigurime shoqerore 16.7% leke 63640 0.167 10628
Hekur Ø kg 20.4 20 408 630 80 50400
Hekur profil e shirit kg 380 80 30400
Karbit kg 12 183 2196
Oksigjen liter 100 122 12200
Elektroda kg 21 180 3780
Saldatrice elektrike op 42 74 3108
Gazogjen op 20 80 1600
Autovinc op 0.2 3100 620
Shuma: 74268 408 5328 98976 178980 14318 17898 211196

Pergatitje zgara metalike te


1.111/p thjeshta per dritare e lloxha ton
Sp + p op 265 185 49025
Sigurime shoqerore 16.7% leke 49025 0.167 8187
Hekur Ø kg 20.4 20 408 650 80 52000
Hekur profil e shirit kg 360 80 28800
Karbit kg 12 183 2196
Oksigjen liter 100 122 12200
Elektroda kg 21 180 3780
Saldatrice elektrike op 42 74 3108
Gazogjen op 20 80 1600
Autovinc op 0.2 3100 620
Shuma: 57212 408 5328 98976 161924 12954 16192 191071

1.114/p Prodhim mastiçë bitumi ton


Sp + p op 12.8 125 1600
Sigurime shoqerore 16.7% leke 1600 0.167 267
Page 23
Nr. PUNTORI TRANSPORT MAKINERI MATERIAL Shp Fitim
EMERTIMI Njesia op çmimi Vlefta T/km çmimi Vlefta o.p çmimi Vlefta Sasia çmimi Vlefta Shuma pl TOTALI
Analize 8% 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Te ndryshme ton 1 20 20
Mak per zierje asfalti op 2 525 1050
Bitum M-5 (buke) ton 0.6 90000 54000
Bitum M-3 (leng) ton 0.4 80000 32000
Material mbushes ton 0.1 1600 160
Dru zjarri m3 0.6 2500 1500
Shuma: 1867.2 20 1050 87660 90597 7248 9060 106905

1.117/p Bazamak shkalle me granil m2


Sp + p op 3.05 185 564
Sigurime shoqerore 16.7% leke 564.3 0.167 94
Çimento 32.5 N ton 0.1 20 2 20 8.1 162
Granil m3 0.32 20 6.4 0.04 1351 54
Lavigatrice op 0.75 84 63
Kallep m2 0.2 558 112
Hekur betoni Ø 3 - 5 mm kg 1.5 95 143
Shuma: 658 8 63 470 1200 96 120 1416

1.117/p Pragje dritare me granil m2


Sp + p op 3.05 185 564
Sigurime shoqerore 16.7% leke 564.3 0.167 94
Çimento 32.5 N ton 0.1 20 2 20 8.1 162
Granil m3 0.32 20 6.4 0.04 1351 54
Lavigatrice op 0.75 84 63
Kallep m2 0.15 60 9
Hekur betoni Ø 3 - 5 mm kg 1.5 95 143
Shuma: 658 8 63 368 1097 88 110 1295

1.120/p Parapet ballkon me granil m2


Sp + p op 2.7 185 500
Sigurime shoqerore 16.7% leke 500 0.167 83
Çimento 32.5 N ton 0.1 20 2 20 8.1 162
Granil m3 0.32 20 6.4 0.04 1351 54
Lavigatrice op 0.75 84 63
Kallep m2 0.15 60 9
Hekur betoni Ø 3 - 5 mm kg 1.7 95 162
Shuma: 583 8 63 387 1041 83 104 1228

1.123/p Shpatulla dritare granili m2

Page 24
Nr. PUNTORI TRANSPORT MAKINERI MATERIAL Shp Fitim
EMERTIMI Njesia op çmimi Vlefta T/km çmimi Vlefta o.p çmimi Vlefta Sasia çmimi Vlefta Shuma pl TOTALI
Analize 8% 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Sp + p op 2.07 185 383
Sigurime shoqerore 16.7% leke 383 0.167 64
Çimento 32.5 N ton 0.1 20 2 16 8.1 130
Granil m3 0.24 20 4.8 0.03 1351 41
Lavigatrice op 0.75 84 63
Kallep m2 0.15 60 9
Hekur betoni Ø 3 - 5 mm kg 1.5 95 143
Shuma: 447 7 63 322 838 67 84 989

1.122/p Parapet muri rrethus granil m2


Sp + p op 2.1 185 389
Sigurime shoqerore 16.7% leke 388.5 0.167 65
Çimento 32.5 N ton 0.15 20 3 28 8.1 227
Granil m3 0.48 20 10 0.04 1351 54
Lavigatrice op 0.75 84 63
Kallep m2 0.15 60 9
Hekur betoni Ø 3 - 5 mm kg 1.5 90 135
Shuma: 453 13 63 425 954 76 95 1126

1.124/p Bordura betoni 12x25cm M


Sp + p op 0.66 125 82.5
Sigurime shoqerore 16.7% leke 82.5 0.167 14
Beton C-16/20 m3 0.375 20 8 0.03 5294 159
Kallep inventari m2 0.2 140 28
Solar kg 0.24 87 21
Shuma: 96 8 208 311 25 31 368

1.125/p Bordura betoni 25x25cm M


Sp + p op 0.86 125 107.5
Sigurime shoqerore 16.7% leke 108 0.167 18
Beton C-16/20 m3 0.788 20 16 0.063 5294 334
Kallep inventari m2 0.4 140 56
Solar kg 0.5 87 44
Shuma: 125 16 433 574 46 57 678

1.126/p Bordura betoni 15x35cm M


Sp + p op 0.88 125 110
Sigurime shoqerore 16.7% leke 110 0.167 18
Beton C-16/20 m3 0.663 20 13 0.053 5294 281

Page 25
Nr. PUNTORI TRANSPORT MAKINERI MATERIAL Shp Fitim
EMERTIMI Njesia op çmimi Vlefta T/km çmimi Vlefta o.p çmimi Vlefta Sasia çmimi Vlefta Shuma pl TOTALI
Analize 8% 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Kallep inventari m2 0.25 140 35
Solar kg 0.32 87 28
Shuma: 128 13 343 485 39 49 572

1.127/p Bordura betoni 20x35cm M


Sp + p op 0.9 125 112.5
Sigurime shoqerore 16.7% leke 113 0.167 19
Beton C-16/20 m3 0.875 20 18 0.07 5294 371
Kallep inventari m2 0.35 140 49
Solar kg 0.43 87 37
Shuma: 131.29 18 457 606 48 61 715

1.128/p Bordura betoni 25x35cm M


Sp + p op 1 125 125
Sigurime shoqerore 16.7% leke 125 0.167 21
Beton C-16/20 m3 1.12 20 22 0.088 5294 466
Kallep inventari m2 0.45 140 63
Solar kg 0.54 87 47
Shuma: 146 22 576 744 60 74 878

1.129/p Tuba betoni Ø 200 mm M


Sp + p op 0.47 185 86.95
Sigurime shoqerore 16.7% leke 87 0.167 15
Cimento M 400 kg 0.15 20 3 10.4 8.3 86.3
Rere e lare m3 0.59 20 11.8 0.022 1743 38.3
Zall lavatrice m3 0.27 20 5.4 0.01 931 9.3
Kallep inventar m2 1.48 305 451.4
Mirembajtje kallepi 10% 451.4 10% 45.1
Solar kg 0.22 87 19.1
Betonjere op 0.02 174 3.48
Vinc op 0.01 53 0.53
Shuma: 101 20 4 650 775 62 78 915

1.130/p Tuba betoni Ø 300 mm M


Sp + p op 0.8 185 148
Sigurime shoqerore 16.7% leke 148 0.167 25
Çimento 32.5 N kg 0.30 20 6 19.6 8.3 162.7
Rere e lare m3 1.13 20 22.6 0.042 1743 73.2
Zall lavatrice m3 0.54 20 10.8 0.01 931 9.3

Page 26
Nr. PUNTORI TRANSPORT MAKINERI MATERIAL Shp Fitim
EMERTIMI Njesia op çmimi Vlefta T/km çmimi Vlefta o.p çmimi Vlefta Sasia çmimi Vlefta Shuma pl TOTALI
Analize 8% 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Kallep inventar m2 2.16 305 658.8
Mirembajtje kallepi 10% 658.8 10% 65.9
Solar kg 0.33 87 28.7
Betonjere op 0.03 174 5.22
Vinc op 0.02 53 1.06
Shuma: 172.72 39 6 999 1217 97 122 1436

1.131/p Tuba betoni Ø 400 mm M


Sp + p op 0.87 185 160.95
Sigurime shoqerore 16.7% leke 161 0.167 27
Çimento 32.5 N kg 0.38 20 7.6 28.4 8.3 235.7
Rere e lare m3 1.65 20 33 0.061 1743 106.3
Zall lavatrice m3 0.68 20 13.6 0.025 931 23.3
Kallep inventar m2 2.82 305 860.1
Mirembajtje kallepi 10% 860.1 10% 86.0
Solar kg 0.43 87 37.4
Betonjere op 0.04 174 6.96
Vinc op 0.02 53 1.06
Shuma: 188 54 8 1349 1599 128 160 1887

1.132/p Tuba betoni Ø 500 mm M


Sp + p op 1.66 185 307.1
Sigurime shoqerore 16.7% leke 307 0.167 51
Çimento 32.5 N kg 0.38 20 7.6 42.4 8.3 351.9
Rere e lare m3 2.46 20 49.2 0.091 1743 158.6
Zall lavatrice m3 1.16 20 23.2 0.043 931 40.0
Kallep inventar m2 3.52 305 1073.6
Mirembajtje kallepi 10% 1074 10% 107.4
Solar kg 0.53 87 46.1
Betonjere op 0.06 174 10.44
Vinc op 0.02 53 1
Shuma: 358 80 12 1778 2228 178 223 2629

1.133/p Tuba betoni Ø 600 mm M


Sp + p op 1.78 185 329.3
Sigurime shoqerore 16.7% leke 329 0.167 55
Çimento 32.5 N kg 0.75 20 15 49.6 8.3 411.7
Rere e lare m3 2.89 20 57.8 0.107 1743 186.5
Zall lavatrice m3 1.35 20 27 0.05 931 46.5

Page 27
Nr. PUNTORI TRANSPORT MAKINERI MATERIAL Shp Fitim
EMERTIMI Njesia op çmimi Vlefta T/km çmimi Vlefta o.p çmimi Vlefta Sasia çmimi Vlefta Shuma pl TOTALI
Analize 8% 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Kallep inventar m2 4.14 305 1262.7
Mirembajtje kallepi 10% 1263 10% 126.3
Solar kg 0.62 87 53.9
Betonjere op 0.08 174 13.92
Vinc op 0.02 53 1.166
Shuma: 384 100 15 2088 2587 207 259 3052

1.129/1p Tub betoni Ø200 mbeshtetj M


Sp + p op 1.02 185 188.7
Sigurime shoqerore 16.7% leke 189 0.167 32
Çimento 32.5 N kg 0.18 20 3.6 12 8.3 99.6
Rere e lare m3 0.68 20 13.6 0.025 1743 43.6
Zall lavatrice m3 0.35 20 7.0 0.013 931 12.1
Kallep inventar m2 1.78 305 542.9
Mirembajtje kallepi 10% 542.9 10% 54.3
Solar kg 0.22 87 19.1
Betonjere op 0.02 174 3.828
Vinc op 0.01 53 0.53
Shuma: 220 24 4 772 1020 82 102 1204

1.130/1p Tub betoni Ø300 mbeshtetj M


Sp + p op 1.2 185 222
Sigurime shoqerore 16.7% leke 222 0.167 37
Çimento 32.5 N kg 0.33 20 6.6 22 8.3 182.6
Rere e lare m3 1.27 20 25.4 0.047 1743 81.9
Zall lavatrice m3 0.65 20 13.0 0.024 931 22.3
Kallep inventar m2 2.16 305 658.8
Mirembajtje kallepi 10% 658.8 10% 65.9
Solar kg 0.33 87 28.7
Betonjere op 0.03 174 5
Vinc op 0.02 53 1.06
Shuma: 259 45 6 1040 1351 108 135 1594

1.131/1p Tub betoni Ø400 mbeshtetj M


Sp + p op 1.45 185 268.25
Sigurime shoqerore 16.7% leke 268 0.167 45
Çimento 32.5 N kg 0.50 20 10.0 33 8.3 273.9
Rere e lare m3 2.43 20 48.6 0.09 1743 156.9
Zall lavatrice m3 0.95 20 19.0 0.035 931 32.6

Page 28
Nr. PUNTORI TRANSPORT MAKINERI MATERIAL Shp Fitim
EMERTIMI Njesia op çmimi Vlefta T/km çmimi Vlefta o.p çmimi Vlefta Sasia çmimi Vlefta Shuma pl TOTALI
Analize 8% 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Kallep inventar m2 2.82 305 860.1
Mirembajtje kallepi 10% 860.1 10% 86.0
Solar kg 0.42 87 36.5
Betonjere op 0.04 174 6.264
Vinc op 0.02 53 1.06
Shuma: 313 78 7 1446 1844 148 184 2176

1.132/1p Tub betoni Ø500 mbeshtetj M


Sp + p op 1.91 185 353.35
Sigurime shoqerore 16.7% leke 353 0.167 59
Çimento 32.5 N kg 0.75 20 15.0 50 8.3 415.0
Rere e lare m3 2.86 20 57.2 0.106 1743 184.7
Zall lavatrice m3 1.43 20 28.6 0.053 931 49.3
Kallep inventar m2 3.52 305 1073.6
Mirembajtje kallepi 10% 1074 10% 107.4
Solar kg 0.53 87 46.1
Betonjere op 0.11 174 18.444
Vinc op 0.0 53 1.166
Shuma: 412 101 20 1876 2409 193 241 2843

1.133/1p Tub betoni Ø600 mbeshtetj M


Sp + p op 2.3 185 425.5
Sigurime shoqerore 16.7% leke 426 0.167 71
Çimento 32.5 N kg 0.89 20 17.8 59 8.3 489.7
Rere e lare m3 3.43 20 68.6 0.127 1743 221.3
Zall lavatrice m3 1.73 20 34.6 0.064 931 59.6
Kallep inventar m2 4.14 305 1262.7
Mirembajtje kallepi 10% 1263 10% 126.3
Solar kg 0.62 87 53.9
Betonjere op 0.11 174 18.3
Vinc op 0.02 53 1.2
Shuma: 497 121 19 2214 2851 228 285 3364

1.138/p Dritare druri kase binar m2


Sp + p op 5.9 185 1091.5 2.00 20 40
Sigurime shoqerore 16.7% leke 1092 0.167 182
Energji elektrike kw 3 10 30.0
Lende e holle pishe e stazh m3 0.003 54000 162.0
Lende e trashe pishe e stazh m3 0.04 54000 2160.0

Page 29
Nr. PUNTORI TRANSPORT MAKINERI MATERIAL Shp Fitim
EMERTIMI Njesia op çmimi Vlefta T/km çmimi Vlefta o.p çmimi Vlefta Sasia çmimi Vlefta Shuma pl TOTALI
Analize 8% 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Ngjites GNS-2 (tutkall) kg 0.36 1015 365.4
Inglizina T 10/12 cope 2.65 508 1346.2
Mentesha 50x52cm cope 1.27 1050 1333.5
Vida druri cope 18.7 10 187.0
Spanjoleta cope 0.64 254 162.6
Shufra spanjoletash cift 0.64 110 70.4
Kraheza cope 0.64 270 172.8
Bilbile cope 0.64 180 115.2
Gozhde kg 0.2 90 18.0
Vaj lini kg 0.11 203 22.3
Oketi cope 1.28 142 181.8
Zumpara m 0.12 150 18.0
Klorur amoni kg 0.004 140 0.6
Grasese elektrike op 0.35 180 63
Cirkular op 0.33 140 46.2
Sharre shirit op 0.42 137 57.54
Plan op 0.38 126 47.88
Sumpatriqe op 0.32 150 48
Trapon elektrik op 0.24 95 22.8
Shuma: 1274 40 285 6346 7945 636 794 9375

1.139/p Dritare druri kase bylme m2


Sp + p op 6.8 185 1258 2.38 20 48
Sigurime shoqerore 16.7% leke 1258 0.167 210
Energji elektrike kw 3 10 30.0
Lende e holle pishe e stazh m3 0.022 54000 1188.0
Lende e trashe pishe e stazh m3 0.056 28420 1591.5
Ngjites GNS-2 (tutkall) kg 0.36 1015 365.4
Inglizina T 10/12 cope 2.65 508 1346.2
Mentesha 50x52cm cope 1.27 280 355.6
Vida druri cope 18.7 10 187.0
Spanjoleta cope 0.64 254 162.6
Shufra spanjoletash cift 0.64 110 70.4
Kraheza cope 0.64 270 172.8
Bilbile cope 0.64 180 115.2
Gozhde kg 0.19 90 17.1
Vaj lini kg 0.11 203 22.3
Oketi cope 1.28 142 181.8
Zumpara m 0.12 150 18.0

Page 30
Nr. PUNTORI TRANSPORT MAKINERI MATERIAL Shp Fitim
EMERTIMI Njesia op çmimi Vlefta T/km çmimi Vlefta o.p çmimi Vlefta Sasia çmimi Vlefta Shuma pl TOTALI
Analize 8% 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Klorur amoni kg 0.004 140 0.6
Grasese elektrike op 0.35 180 63
Cirkular op 0.33 140 46.2
Sharre shirit op 0.42 137 57.54
Plan op 0.38 126 47.88
Sumpatriqe op 0.32 150 48
Trapon elektrik op 0.24 95 22.8
Shuma: 1468 48 285 5824 7626 610 763 8998

1.143/p Dritare druri dyfishe m2


Sp + p op 10.4 185 1924 4.50 20 90
Sigurime shoqerore 16.7% leke 1924 0.167 321
Energji elektrike kw 3 10 30.0
Lende e holle pishe e stazh
(importi clesia 1) m3 0.006 54000 324.0
Lende e trashe pishe e stazh
(importi clesia 1) m3 0.095 54000 5130.0
Ngjites GNS-2 (tutkall) kg 0.66 1015 669.9
Inglizina T 10/12 cope 4.1 508 2082.8
Mentesha 50x52cm cope 2.04 280 571.2
Vida druri cope 25.5 10 255.0
Spanjoleta cope 1.02 254 259.1
Shufra spanjoletash cift 1.02 110 112.2
Kraheza cope 1.02 270 275.4
Bilbile cope 1.02 180 183.6
Gozhde kg 0.36 90 32.4
Vaj lini kg 0.16 203 32.5
Oketi cope 2.04 142 289.7
Zumpara m 0.27 150 40.5
Klorur amoni kg 0.007 140 1.0
Grasese elektrike op 0.52 180 93.6
Cirkular op 0.5 140 70
Sharre shirit op 0.63 137 86.31
Plan op 0.55 126 69.3
Sumpatriqe op 0.48 150 72
Trapon elektrik op 0.36 95 34.2
Shuma: 2245 90 425 10289 13050 1044 1305 15399

1.143/p-a Dritare druri dopio xham m2

Page 31
Nr. PUNTORI TRANSPORT MAKINERI MATERIAL Shp Fitim
EMERTIMI Njesia op çmimi Vlefta T/km çmimi Vlefta o.p çmimi Vlefta Sasia çmimi Vlefta Shuma pl TOTALI
Analize 8% 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Sp + p op 8.3 185 1535.5 3.75 20 75
Sigurime shoqerore 16.7% leke 1536 0.167 256
Energji elektrike kw 3 10 30.0
Lende e holle pishe e stazh
(Vendi) m3 0.011 28420 312.6
Lende e trashe pishe e stazh
(Vendi) m3 0.044 28420 1250.5
Ngjites GNS-2 (tutkall) kg 0.4 1015 406.0
Inglizina T 10/12 cope 2.65 508 1346.2
Mentesha 50x52cm cope 1.27 280 355.6
Vida druri cope 18.7 10 187.0
Spanjoleta cope 0.64 254 162.6
Shufra spanjoletash cift 0.64 110 70.4
Kraheza cope 0.64 270 172.8
Bilbile cope 0.64 180 115.2
Gozhde kg 0.2 90 18.0
Vaj lini kg 0.12 203 24.4
Oketi cope 1.28 142 181.8
Zumpara m 0.12 150 18.0
Klorur amoni kg 0.002 140 0.3
Grasese elektrike op 0.42 180 75.6
Cirkular op 0.41 140 57.4
Sharre shirit op 0.5 137 68.5
Plan op 0.45 126 56.7
Sumpatriqe op 0.38 150 57
Trapon elektrik op 0.29 95 27.55
Shuma: 1792 75 343 4651 6861 549 686 8096

1.153/p Vetrate druri m2


Sp + p op 5.4 185 999 2.50 20 50
Sigurime shoqerore 16.7% leke 999 0.167 167
Energji elektrike kw 2.5 10 25.0
Lende e holle pishe e stazh
(material Vendi) m3 0.051 28420 1449.4
Lende e trashe pishe e stazh
(material Vendi) m3 0.029 28420 824.2
Ngjites GNS-2 (tutkall) kg 0.31 1015 314.7
Inglizina T 10/12 cope 0.74 508 375.9
Vida druri cope 3.06 10 30.6

Page 32
Nr. PUNTORI TRANSPORT MAKINERI MATERIAL Shp Fitim
EMERTIMI Njesia op çmimi Vlefta T/km çmimi Vlefta o.p çmimi Vlefta Sasia çmimi Vlefta Shuma pl TOTALI
Analize 8% 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Gozhde kg 0.02 90 1.8
Vaj lini kg 0.04 203 8.1
Zumpara m 0.09 150 13.5
Klorur amoni kg 0.003 140 0.4
Brava cope
Shula cope 0.3 125 37.5
Grasese elektrike op 0.35 180 63
Cirkular op 0.33 140 46.2
Sharre shirit op 0.42 137 57.54
Plan op 0.38 126 47.88
Sumpatriqe op 0.33 150 48.75
Trapon elektrik op 0.24 95 22.8
Shuma: 1166 50 286 3081 4583 367 458 5408

1.148/p Prodhim dritare metalike ton


Sp + p op 150 185 27750
Sigurime shoqerore 16.7% leke 27750 0.167 4634
Te ndryshme m2 0.75 20 15
Elektrosaldatrice op 37 74 2738
Gazogjen op 16 80 1280
Tranxhe elektrike op 9 53 477
Trapano elektrik op 5 95 475
Vinc op 10 53 530
Aksesor (detale metalike) kg 90 105 9430.4
Hekur profil kg 900 80 72000.0
Hekur shirit kg 30 80 2400.0
Elektroda kg 20 180 3600.0
Karbit kg 10 183 1830.0
Oksigjen liter 100 122 12200.0
Shuma: 32384 15 5500 101460 139360 11149 13936 164444

1.166/p Dyer druri kashe derrase m2


Sp + p op 7.5 185 1387.5
Sigurime shoqerore 16.7% leke 1388 0.167 232
Energji elektrike kw 1.25 20 25 3.5 10 35.0
Avull ton 0.05 450 22.5
Lende e holle pishe e stazh
(material Vendi) m3 0.036 28420 1023.1

Page 33
Nr. PUNTORI TRANSPORT MAKINERI MATERIAL Shp Fitim
EMERTIMI Njesia op çmimi Vlefta T/km çmimi Vlefta o.p çmimi Vlefta Sasia çmimi Vlefta Shuma pl TOTALI
Analize 8% 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Lende e trashe pishe e
stazh(material Vendi) m3 0.062 28420 1762.0
Ngjites GNS-2 (tutkall) kg 0.34 1015 345.1
Inglizina T 12/14 cope 1.2 508 609.6
Gozhde kg 0.1 90 9.0
Brava cope 0.58 1000 580.0
Vida druri cope 7 10 70.0
Vaj lini kg 0.14 203 28.4
Zumpara m 0.24 150 36.0
Klorur amoni kg 0.003 140 0.4
Grasese elektrike op 0.42 180 76
Cirkular op 0.41 140 57
Sharre shirit op 0.5 137 69
Plan op 0.45 126 57
Sumpatriqe op 0.38 150 57
Trapon elektrik op 0.29 95 28
Shuma: 1619 25 343 4521 6508 521 651 7680

1.182/p Dyer metalike ton


Sp + p op 180 185 33300
Sigurime shoqerore 16.7% leke 33300 0.167 5561
Energji elektrike kw 6.50 20 130 3.5 10 35
Elektrosaldatrice op 37 74 2738
Gazogjen op 16 80 1280
Tranxhe elektrike op 9 210 1890
Trapano elektrik op 10 95 950
Vinc op 10 53 530
Aksesor (detale metalike) kg 250 105 26196
Hekur profil kg 900 80 72000
Hekur shirit kg 30 80 2400
Elektroda kg 20 180 3600
Karbit kg 10 183 1830
Oksigjen liter 100 122 12200
Shuma: 38861 130 7388 118261 164640 13171 16464 194275

1.189/1p Pllaka granili boje 25/25 m2


Sp + p op 2.7 125 337.5
Sigurime shoqerore 16.7% leke 338 0.167 56
Çimento 42.5 R kg 0.06 20 1.2 11 8.7 95.7

Page 34
Nr. PUNTORI TRANSPORT MAKINERI MATERIAL Shp Fitim
EMERTIMI Njesia op çmimi Vlefta T/km çmimi Vlefta o.p çmimi Vlefta Sasia çmimi Vlefta Shuma pl TOTALI
Analize 8% 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Çimento e bardhe 42.5 R kg 0.02 20 0.4 4 12 48.0
Rere e lare m3 0.14 20 2.8 0.015 1743 26.1
Granil guri i thyer 1-2-3mm m3 0.06 20 1.2 0.008 1351 10.8
Boje cimentito kg 0.201 112 22.5
Energji elektrike kw 1 10 10.0
Te ndryshme 3% 213.2 3% 6.4
Shuma: 394 6 220 619 50 62 730

1.190/1p Pllaka granili boje 30/30 m2


Sp + p op 2.7 125 337.5
Sigurime shoqerore 16.7% leke 338 0.167 56
Çimento 42.5 R kg 0.07 20 1.4 13.5 8.7 117.5
Çimento e bardhe 42.5 R kg 0.02 20 0.4 4.2 12 50.4
Rere e lare m3 0.27 20 5.4 0.03 1743 52.3
Granil guri i thyer 1-2-3mm m3 0.09 20 1.8 0.011 1351 14.9
Boje cimentito kg 0.25 112 28.0
Energji elektrike kw 1 10 10.0
Te ndryshme 3% 273 3% 8.2
Shuma: 394 9 281 684 55 68 807

1.188/1p Pllaka granili t-ri 30/30/2.7 m2


Sp + p op 2.7 125 337.5
Sigurime shoqerore 16.7% leke 338 0.167 56
Çimento 42.5 R kg 0.07 20 1.4 9.5 8.7 82.7
Çimento e bardhe 42.5 R kg 0.02 20 0.4 7.3 12 87.6
Rere e lare m3 0.27 20 5.4 0.005 1743 8.7
Granil guri i thyer 1-2-3mm m3 0.09 20 1.8 0.032 1351 43.2
Boje cimentito kg 0.25 112 28.0
Energji elektrike kw 1 10 10.0
Te ndryshme 3% 260.2 70% 182.1
Shuma: 394 9 442 845 68 85 997

1.192/1p Pllaka mozaik boje 40/40 m2


Sp + p op 6.7 125 837.5
Sigurime shoqerore 16.7% leke 838 0.167 140
Çimento 42.5 R kg 0.07 20 1.4 12 8.7 104.4
Çimento e bardhe 42.5 R kg 0.02 20 0.4 3 12 36.0
Rere e lare m3 0.27 20 5.4 0.015 1743 26.1
Granil guri i thyer 1-2-3mm m3 0.09 20 1.8 0.01 1351 13.5

Page 35
Nr. PUNTORI TRANSPORT MAKINERI MATERIAL Shp Fitim
EMERTIMI Njesia op çmimi Vlefta T/km çmimi Vlefta o.p çmimi Vlefta Sasia çmimi Vlefta Shuma pl TOTALI
Analize 8% 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Boje cimentito kg 0.1 112 11.2
Copa mermeri pllake m2 0.28 20 5.6 0.7 1500 1050.0
Energji elektrike kw 1 10 10.0
Te ndryshme 3% 201.3 3% 6.0
Shuma: 977 15 1257 2249 180 225 2654

1.201/1p Pllake mermeri 0.02-0.06m2 m2


Sp + p op 11.3 125 1412.5
Sigurime shoqerore 16.7% leke 1413 0.167 236
Energji elektrike kw 34 10 340.0
Bllok mermeri m3 0.70 20 14 0.05 30450 1522.5
Disqe diamanti leke 1523 20% 304.5
Lama sharre leke 1523 8% 121.8
Materiale ndihmes leke 1523 3% 45.7
Shuma: 1648 14 2334 3997 320 400 4716

1.201/1p Pllake mermeri 0.08-0.10m2 m2


Sp + p op 9.9 125 1237.5
Sigurime shoqerore 16.7% leke 1238 0.167 207
Energji elektrike kw 34 10 340
Bllok mermeri m3 0.70 20 14 0.05 30450 1522.5
Disqe diamanti leke 1523 15% 228.38
Lama sharre leke 1523 6% 91.35
Materiale ndihmes leke 1523 3% 45.675
Shuma: 1444 14 2227.9 3686 295 369 4350

1.32/p Prodh tuba b/a Ø 700 t=10 M


Sp + p op 3.8 185 703
Sigurime shoqerore 16.7% leke 703 0.167 117
Çimento 32.5 N kg 0.30 20 6 59 8.1 477.9
Rere lavatrice m3 0.90 20 18 0.1 1743 174.3
Zall lavatrice m3 1.26 20 25.2 0.14 931 130.3
Hekur betoni kg 0.10 20 2 22 76 1672.0
Kallep metalik m2 5 305 1525.0
Solar kg 0.74 87 64.4
Mirembajtje kallepi 10% leke 1525 10% 152.5
Betonjere op 0.17 174 30
Vinc op 0.04 53 2.12
Shuma: 820 51 32 4196 5100 408 510 6018

Page 36
Nr. PUNTORI TRANSPORT MAKINERI MATERIAL Shp Fitim
EMERTIMI Njesia op çmimi Vlefta T/km çmimi Vlefta o.p çmimi Vlefta Sasia çmimi Vlefta Shuma pl TOTALI
Analize 8% 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

1.33/p Prodh tuba b/a Ø 800 t=10 M


Sp + p op 3.8 185 703
Sigurime shoqerore 16.7% leke 703 0.167 117
Çimento 32.5 N kg 0.33 20 6.6 65 8.1 526.5
Rere lavatrice m3 0.99 20 19.8 0.11 1743 191.7
Zall lavatrice m3 1.44 20 28.8 0.16 931 148.9
Hekur betoni kg 0.10 20 2.0 22 76 1672.0
Kallep metalik m2 5.6 305 1708.0
Solar kg 0.85 87 74.0
Mirembajtje kallepi 10% leke 1708 10% 170.8
Betonjere op 0.16 174 27.84
Vinc op 0.0 53 2.12
Shuma: 820 57 30 4492 5399 432 540 6371

1.34/p Prodh tuba b/a Ø 1000 t=10 M


Sp + p op 4.6 185 851
Sigurime shoqerore 16.7% leke 851 0.167 142
Çimento 32.5 N kg 0.51 20 10.2 101 8.1 818.1
Rere lavatrice m3 1.62 20 32.4 0.18 1743 313.7
Zall lavatrice m3 2.16 20 43.2 0.24 931 223.4
Hekur betoni kg 0.14 20 2.8 27 76 2052.0
Kallep metalik m2 7 305 2135.0
Solar kg 1.05 87 91.4
Mirembajtje kallepi 10% leke 2135 10% 213.5
Betonjere op 0.27 174 46.98
Vinc op 0.06 53 3.18
Shuma: 993 89 50 5847 6979 558 698 8235

1.35/p Prodh tuba b/a Ø 1200 t=12 M


Sp + p op 5.8 185 1073
Sigurime shoqerore 16.7% leke 1073 0.167 179
Çimento 32.5 N kg 0.73 20 14.6 146 8.1 1182.6
Rere lavatrice m3 2.25 20 45.0 0.25 1743 435.7
Zall lavatrice m3 3.24 20 64.8 0.35 931 325.8
Hekur betoni kg 0.19 20 3.8 38 76 2888.0
Kallep metalik m2 8.3 305 2531.5
Solar kg 1.3 87 113.1
Mirembajtje kallepi 10% leke 2532 10% 253.2

Page 37
Nr. PUNTORI TRANSPORT MAKINERI MATERIAL Shp Fitim
EMERTIMI Njesia op çmimi Vlefta T/km çmimi Vlefta o.p çmimi Vlefta Sasia çmimi Vlefta Shuma pl TOTALI
Analize 8% 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Betonjere op 0.39 174 67.86
Vinc op 0.09 53 4.77
Shuma: 1252 128 73 7730 9183 735 918 10836

1.36/p Prodh tuba b/a Ø 1500 t=14 M


Sp + p op 9 185 1665
Sigurime shoqerore 16.7% leke 1665 0.167 278
Çimento 32.5 N kg 1.06 20 21 212 8.1 1717.2
Rere lavatrice m3 3.24 20 65 0.36 1743 627.4
Zall lavatrice m3 4.59 20 92 0.51 931 474.8
Hekur betoni kg 0.26 20 5 52 76 3952.0
Kallep metalik m2 10.3 305 3141.5
Solar kg 1.6 87 139.2
Mirembajtje kallepi 10% leke 3142 10% 314.2
Betonjere op 0.39 174 68
Vinc op 0.09 53 4.77
Shuma: 1943 183 73 10366 12565 1005 1256 14827

Prodhim soletone b/a C-16/20


1.48/p per ura m3
Sp + p op 8.6 185 1591
Sigurime shoqerore 16.7% leke 1591 0.167 266
Beton C-16/20 m3 12.24 20 245 1.02 5294 5399.7
Vibrator op 0.92 53 48.76
Vinc op 0.6 53 31.8
Kallep inventar m2 2.7 305 823.5
Mirembajtje kallepi 10% leke 823.5 10% 82.4
Gozhde kg 0.015 90 1.4
Solar kg 0.4 87 34.8
Shuma: 1857 245 80.56 6342 8524 682 852 10058

Prodhim pilota b/a C-16/20 per


1.49/p ura m3
Sp + p op 9.9 185 1831.5
Sigurime shoqerore 16.7% leke 1832 0.167 306
Beton C-16/20 m3 12.24 20 245 1.02 5294 5399.7
Vibrator op 0.92 53 48.76
Vinc op 0.6 53 31.8
Kallep inventar m2 4 305 1220.0

Page 38
Nr. PUNTORI TRANSPORT MAKINERI MATERIAL Shp Fitim
EMERTIMI Njesia op çmimi Vlefta T/km çmimi Vlefta o.p çmimi Vlefta Sasia çmimi Vlefta Shuma pl TOTALI
Analize 8% 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Mirembajtje kallepi 10% leke 1220 10% 122.0
Gozhde kg 0.02 90 1.8
Solar kg 0.6 87 52.2
Shuma: 2137 245 80.56 6796 9258 741 926 10925

1.50/p Prodhim lugje e pila b/a C-16/20 m3


Sp + p op 18.3 185 3385.5
Sigurime shoqerore 16.7% leke 3386 0.167 565
Transport t/km 12.24 20 245
Beton C-16/20 m3 1.02 5294 5400
Vibrator op 1.3 53 68.9
Vinc op 0.6 53 31.8
Kallep inventar m2 9 305 2745
Mirembajtje kallepi 10% leke 2745 10% 275
Gozhde kg 0.05 90 5
Solar kg 1.4 87 122
Shuma: 3951 245 100.7 8546 12842 1027 1284 15153

Prodhim mbajtese e bazamente


1.51/p lugje b/a C-16/20 parabolik m3
Sp + p op 26.5 185 4902.5
Sigurime shoqerore 16.7% leke 4903 0.167 819
Beton C-16/20 m3 12.24 20 245 1.02 5294 5400
Vibrator op 1.3 53 68.9
Vinc op 0.6 53 31.8
Kallep inventar m2 14.5 305 4423
Mirembajtje kallepi 10% leke 4423 10% 442
Gozhde kg 0.07 90 6
Solar kg 2.2 87 191
Shuma: 5721 245 100.7 10462 16529 1322 1653 19504

Prodhim lugje b/a C-37/45


1.52/p parabolik L=5m, T - 100 cope
Sp + p op 6.5 185 1202.5
Sigurime shoqerore 16.7% leke 1203 0.167 201
Beton C-37/45 m3 12.24 20 245 0.19 6831 1297.9
Hekur Ø 4mm kg 5.5 95 522.5

Page 39
Nr. PUNTORI TRANSPORT MAKINERI MATERIAL Shp Fitim
EMERTIMI Njesia op çmimi Vlefta T/km çmimi Vlefta o.p çmimi Vlefta Sasia çmimi Vlefta Shuma pl TOTALI
Analize 8% 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Hekur Ø 6mm kg 2.2 76 167.2
Solar kg 1.8 87 156.6
Avull ton 0.15 450 67.5
Energji elektrike kw 6.5 10 65.0
Shuma: 1403 245 2277 3925 314 392 4631
Prodhim lugje b/a C-37/45
1.53/p parabolik L=5m, T - 150 cope
Sp + p op 7.3 185 1350.5
Sigurime shoqerore 16.7% leke 1351 0.167 226
Beton C-37/45 m3 12.24 20 245 0.23 6831 1571.1
Hekur Ø 4mm kg 6.5 95 617.5
Hekur Ø 6mm kg 2.2 76 167.2
Solar kg 2.2 87 191.4
Avull ton 0.18 450 81.0
Energji elektrike kw 6.5 10 65.0
Shuma: 1576 245 2693 4514 361 451 5327

Prodhim lugje b/a C-37/45


1.54/p parabolik L=5m, T - 280 cope
Sp + p op 8.1 185 1498.5
Sigurime shoqerore 16.7% leke 1499 0.167 250
Beton C-37/45 m3 12.24 20 245 0.31 6831 2117.6
Hekur Ø 4mm kg 8.2 95 779.0
Hekur Ø 6mm kg 3.2 76 243.2
Solar kg 3 87 261.0
Avull ton 0.25 450 112.5
Energji elektrike kw 6.5 10 65.0
Shuma: 1749 245 3578 5572 446 557 6575

Prodhim lugje b/a C-37/45


1.55/p parabolik L=5m, T - 450 cope
Sp + p op 8.5 185 1572.5
Sigurime shoqerore 16.7% leke 1573 0.167 263
Beton C-37/45 m3 12.24 20 245 0.45 6831 3074.0
Hekur Ø 4mm kg 15.2 95 1444.0
Hekur Ø 6mm kg 5.9 76 448.4
Solar kg 3.7 87 321.9
Avull ton 0.36 450 162.0
Energji elektrike kw 7 10 70.0

Page 40
Nr. PUNTORI TRANSPORT MAKINERI MATERIAL Shp Fitim
EMERTIMI Njesia op çmimi Vlefta T/km çmimi Vlefta o.p çmimi Vlefta Sasia çmimi Vlefta Shuma pl TOTALI
Analize 8% 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Shuma: 1835 245 5520 7600 608 760 8968

Prodhim lugje b/a C-37/45


1.56/p parabolik L=5m, T - 600 cope
Sp + p op 11 185 2035
Sigurime shoqerore 16.7% leke 2035 0.167 340
Beton C-37/45 m3 12.24 20 245 0.59 6831 4030
Hekur Ø 4mm kg 19.1 95 1815
Hekur Ø 6mm kg 5.9 76 448
Solar kg 4.4 87 383
Avull ton 0.47 450 212
Energji elektrike kw 7 10 70
Shuma: 2375 245 6958 9577 766 958 11301

Prodhim elemente b/a C-16/20


1.57/p per kaskada m3
Sp + p op 28.6 185 5291
Sigurime shoqerore 16.7% leke 5291 0.167 884
Beton C-16/20 m3 12.24 20 245 1.02 4923 5021.9
Vibrator op 1.3 53 68.9
Vinc op 0.6 53 31.8
Kallep inventar m2 16.7 140 2338.0
Mirembajtje kallepi 10% leke 2338 10% 233.8
Gozhde kg 0.08 90 7.2
Solar kg 2.5 87 217.5
Shuma: 6175 245 100.7 7818 14339 1147 1434 16919

Prodhim elemente b/a C-16/20


1.58/p per priza,hyrje dalje. m3
Sp + p op 19.6 185 3626
Sigurime shoqerore 16.7% leke 3626 0.167 606
Beton C-16/20 m3 12.24 20 245 1.02 4923 5021.9
Vibrator op 1.3 53 68.9
Vinc op 0.6 53 31.8
Kallep inventar m2 9.5 140 1330.0
Mirembajtje kallepi 10% leke 1330 10% 133.0
Gozhde kg 0.05 90 4.5
Solar kg 1.5 87 130.5
Shuma: 4232 245 100.7 6620 11197 896 1120 13212

Page 41
Nr. PUNTORI TRANSPORT MAKINERI MATERIAL Shp Fitim
EMERTIMI Njesia op çmimi Vlefta T/km çmimi Vlefta o.p çmimi Vlefta Sasia çmimi Vlefta Shuma pl TOTALI
Analize 8% 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

Prodhim lugje te vegjel b/a C-


1.59/p 16/20 m3
Sp + p op 22.1 185 4088.5
Sigurime shoqerore 16.7% leke 4089 0.167 683
Beton C-16/20 m3 12.24 20 245 1.02 4923 5021.9
Vibrator op 1.3 53 68.9
Vinc op 0.6 53 31.8
Kallep inventar m2 2.9 305 884.5
Mirembajtje kallepi 10% leke 884.5 10% 88.5
Gozhde kg 0.06 90 5.4
Solar kg 1.8 87 156.6
Shuma: 4771 245 100.7 6157 11274 902 1127 13303

Prodhim soleta b/a per ura dhe


1.60/p hekurudha C-16/20, HD = 2M m3
Sp + p op 8.8 185 1628
Sigurime shoqerore 16.7% leke 1628 0.167 272
Beton C-16/20 m3 12.24 20 245 1.02 4923 5021.9
Vibrator op 0.92 53 48.76
Autovinc op 0.38 2800 1064
Kallep inventar m2 2.9 140 406.0
Mirembajtje kallepi 10% leke 406 10% 40.6
Gozhde kg 0.02 90 1.8
Solar kg 0.5 87 43.5
Shuma: 1900 245 1113 5514 8771 702 877 10350

Prodhim soleta b/a per ura dhe


1.61/p hekurudha C-20/25, HD=3~4M m3
Sp + p op 8.2 185 1517
Sigurime shoqerore 16.7% leke 1517 0.167 253
Beton C-20/25 m3 12.24 20 245 1.02 5099 5201.1
Vibrator op 0.66 53 34.98
Autovinc op 0.13 2800 364
Kallep inventar m2 4.9 140 686.0
Mirembajtje kallepi 10% leke 686 10% 68.6
Gozhde kg 0.03 90 2.7

Page 42
Nr. PUNTORI TRANSPORT MAKINERI MATERIAL Shp Fitim
EMERTIMI Njesia op çmimi Vlefta T/km çmimi Vlefta o.p çmimi Vlefta Sasia çmimi Vlefta Shuma pl TOTALI
Analize 8% 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Solar kg 0.75 87 65.3
Shuma: 1770 245 399 6024 8438 675 844 9957

Prodhim soleta b/a per ura dhe


1.62/p hekurudha C-20/25,HD=5~6M m3
Sp + p op 7.9 185 1461.5
Sigurime shoqerore 16.7% leke 1462 0.167 244
Beton C-20/25 m3 12.24 20 245 1.02 5099 5201.1
Vibrator op 0.66 53 34.98
Autovinc op 0.13 2800 364
Kallep inventar m2 4.5 140 630.0
Mirembajtje kallepi 10% leke 630 10% 63.0
Gozhde kg 0.02 90 1.8
Solar kg 0.7 87 60.9
Shuma: 1706 245 399 5957 8306 664 831 9801

Prodhim soleta b/a per ura dhe


1.63/p hekurudha C-25/30,HD=8~10M m3
Sp + p op 7.4 185 1369
Sigurime shoqerore 16.7% leke 1369 0.167 229
Beton C-25/30 m3 12.24 20 245 1.02 5682 5796
Vibrator op 0.66 53 34.98
Autovinc op 0.13 3100 403
Kallep inventar m2 4.1 140 574
Mirembajtje kallepi 10% leke 574 10% 57
Gozhde kg 0.02 90 2
Solar kg 0.6 87 52
Shuma: 1598 245 438 6481 8762 701 876 10339

Prodhim tombino kendrejte b/a


1.64/p C-16/20 per hekurudha m3
Sp + p op 18.5 185 3422.5
Sigurime shoqerore 16.7% leke 3423 0.167 572
Beton C-16/20 m3 12.24 20 245 1.02 5294 5399.7
Vibrator op 1.3 53 68.9
Autovinc op 0.2 3100 620
Kallep inventar m2 9.5 140 1330.0

Page 43
Nr. PUNTORI TRANSPORT MAKINERI MATERIAL Shp Fitim
EMERTIMI Njesia op çmimi Vlefta T/km çmimi Vlefta o.p çmimi Vlefta Sasia çmimi Vlefta Shuma pl TOTALI
Analize 8% 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Mirembajtje kallepi 10% leke 1330 10% 133.0
Gozhde kg 0.05 90 4.5
Solar kg 1.4 87 121.8
Shuma: 3994 245 689 6989 11917 953 1192 14062

Prodhim kollona e rama b/a C-


1.65/p 16/20 per hekurudha m3
Sp + p op 10.1 185 1868.5
Sigurime shoqerore 16.7% leke 1869 0.167 312
Beton M 200 m3 12.24 20 245 1.02 5294 5399.7
Vibrator op 1.2 53 63.6
Autovinc op 0.13 3100 403
Kallep inventar m2 12.5 140 1750.0
Mirembajtje kallepi 10% leke 1750 10% 175.0
Gozhde kg 0.06 90 5.4
Solar kg 1.9 87 165.3
Shuma: 2181 245 467 7495 10387 831 1039 12257

Prodhim kollona e rama b/a M-


1.66/p 300 per hekurudha m3
Sp + p op 10.1 185 185
Sigurime shoqerore 16.7% leke 185 0.167 31
Beton C-16/20 m3 12.24 20 245 1.02 6046 6167
Vibrator op 0.92 53 48.76
Autovinc op 0.13 3100 403
Kallep inventar m2 5.4 140 756
Mirembajtje kallepi 10% leke 756 10% 76
Gozhde kg 0.03 90 3
Solar kg 0.8 87 70
Shuma: 216 245 452 7071 7984 639 798 9421

Prodhim trare " T " b/a C-20/25


1.67/p me H.D = 7.5-10M per ura m3
Sp + p op 32.3 185 5975.5
Sigurime shoqerore 16.7% leke 5976 0.167 998
Beton C-20/25 m3 12.24 20 245 1.02 5508 5618
Vibrator op 1.2 53 63.6
Autovinc op 0.13 3100 403
Kallep inventar m2 12.5 305 3813
Page 44
Nr. PUNTORI TRANSPORT MAKINERI MATERIAL Shp Fitim
EMERTIMI Njesia op çmimi Vlefta T/km çmimi Vlefta o.p çmimi Vlefta Sasia çmimi Vlefta Shuma pl TOTALI
Analize 8% 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Mirembajtje kallepi 10% leke 3813 10% 381
Gozhde kg 0.06 90 5
Solar kg 1.9 87 165
Shuma: 6973 245 467 9982 17667 1413 1767 20847

Prodhim trare " T " b/a C-20/25


1.68/p me H.D = 15-20M per ura m3
Sp + p op 32.3 185 5975.5
Sigurime shoqerore 16.7% leke 5976 0.167 998
Beton C-20/25 m3 12.24 20 245 1.02 5508 5618
Vibrator op 1.4 53 74.2
Autovinc op 0.18 3100 558
Kallep inventar m2 12.5 305 3813
Mirembajtje kallepi 10% leke 3813 10% 381
Gozhde kg 0.06 90 5
Solar kg 1.9 87 165
Shuma: 6973 245 632 9982 17833 1427 1783 21043
Prodhim trare " T " b/a C-25/30
1.69/p me H.D = 15-20M per ura m3
Sp + p op 32.3 185 5975.5
Sigurime shoqerore 16.7% leke 5976 0.167 998
Beton C-25/30 m3 12.24 20 245 1.02 6046 6167
Vibrator op 1.4 53 74.2
Autovinc op 0.18 3100 558
Kallep inventar m2 12.5 305 3813
Mirembajtje kallepi 10% leke 3813 10% 381
Gozhde kg 0.06 90 5
Solar kg 1.9 87 165
Shuma: 6973 245 632 10532 18382 1471 1838 21691

Prodhim trare " T " b/a C-25/30 me


1.70/p H.D > 20 M per ura automobilistike m3
Sp + p op 28.4 185 5254
Sigurime shoqerore 16.7% leke 5254 0.167 877
Beton C-25/30 m3 12.24 20 245 1.02 6046 6167
Vibrator op 1.4 53 74.2
Autovinc op 0.26 3100 806
Kallep inventar m2 10.5 305 3203
Mirembajtje kallepi 10% leke 3203 10% 320
Page 45
Nr. PUNTORI TRANSPORT MAKINERI MATERIAL Shp Fitim
EMERTIMI Njesia op çmimi Vlefta T/km çmimi Vlefta o.p çmimi Vlefta Sasia çmimi Vlefta Shuma pl TOTALI
Analize 8% 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Gozhde kg 0.05 90 5
Solar kg 1.6 87 139
Shuma: 6131 245 880 9834 17090 1367 1709 20166

Prodhim trare " T " b/a C-25/30 me


1.71/p H.D > 15 M per ura hekurudha m3
Sp + p op 20 185 3700
Sigurime shoqerore 16.7% leke 3700 0.167 618
Beton C-25/30 m3 12.24 20 245 1.02 6046 6167
Vibrator op 1.35 53 71.55
Autovinc op 0.26 3100 806
Kallep inventar m2 6.5 305 1983
Mirembajtje kallepi 10% leke 1983 10% 198
Gozhde kg 0.03 90 3
Solar kg 1 87 87
Shuma: 4317.9 245 878 8438 13878 1110 1388 16376

Prodhim pllaka betoni C-12/15 t


1.72/p = 5cm m2
Sp + p op 0.9 125 112.5
Sigurime shoqerore 16.7% leke 113 0.167 19
Beton C-12/15 m3 0.61 20 12 0.051 4639 236.6
Kallep inventar m2 0.44 140 61.6
Mirembajtje kallepi 10% leke 61.6 10% 6.2
Solar kg 0.07 87 6.1
Shuma: 131 12 310 454 36 45 536

Prodhim pllaka betoni C-12/15 t


1.73/p = 10cm m2
Sp + p op 1.3 125 162.5
Sigurime shoqerore 16.7% leke 163 0.167 27
Beton C-12/15 m3 1.22 20 24 0.102 4639 473.2
Kallep inventar m2 0.61 140 140.0
Mirembajtje kallepi 10% leke 140 10% 0.1
Solar kg 0.09 87 87.0
Shuma: 190 24 700 914 73 91 1079

Prodhim pllaka betoni C-12/15 t


1.74/p = 10cm 1x1m dhe 2x2m m3

Page 46
Nr. PUNTORI TRANSPORT MAKINERI MATERIAL Shp Fitim
EMERTIMI Njesia op çmimi Vlefta T/km çmimi Vlefta o.p çmimi Vlefta Sasia çmimi Vlefta Shuma pl TOTALI
Analize 8% 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Sp + p op 10.5 125 1312.5
Sigurime shoqerore 16.7% leke 1313 0.167 219
Beton C-12/15 m3 12.24 20 245 1.02 4639 4731.7
Vinc op 0.6 53 31.8
Kallep inventar m2 3.4 140 476.0
Mirembajtje kallepi 10% leke 476 10% 47.6
Solar kg 0.51 87 44.4
Shuma: 1532 245 32 5300 7108 569 711 8387

Prodhim pllaka betoni C-16/20 t


1.75/p = 3.5cm 0.4x0.6m m2
Sp + p op 0.77 125 96.25
Sigurime shoqerore 16.7% leke 96.3 0.167 16
Beton C-16/20 m3 0.43 20 9 0.04 5294 211.8
Kallep inventar m2 0.22 140 30.8
Mirembajtje kallepi 10% leke 30.8 10% 3.1
Solar kg 0.03 87 2.6
Shuma: 112 9 248 369 30 37 436

Prodhim blloqe betoni C-7/10


1.76/p 1x1x1m dhe 1x1x0.5m m3
Sp + p op 7 125 875
Sigurime shoqerore 16.7% leke 875 0.167 146
Beton C-7/10 m3 12.24 20 245 1.02 4494 4583.8
Vibrator op 0.75 53 39.75
Autovinc op 0.6 2800 1680
Kallep inventar m2 4 140 560.0
Mirembajtje kallepi 10% leke 560 10% 56.0
Gozhde kg 0.02 90 1.8
Solar kg 0.6 87 52.2
Shuma: 1021 245 1720 5254 8239 659 824 9723

Prodhim blloqe betoni C-7/10


1.77/p 0.6x0.6x0.6m dhe 0.8x0.8x0.8m m3
Sp + p op 8 125 1000
Sigurime shoqerore 16.7% leke 1000 0.167 167
Beton C-7/10 m3 12.24 20 245 1.02 4494 4583.8
Vibrator op 0.75 53 39.75
Autovinc op 0.6 2800 1680
Page 47
Nr. PUNTORI TRANSPORT MAKINERI MATERIAL Shp Fitim
EMERTIMI Njesia op çmimi Vlefta T/km çmimi Vlefta o.p çmimi Vlefta Sasia çmimi Vlefta Shuma pl TOTALI
Analize 8% 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Kallep inventar m2 5.8 140 812.0
Mirembajtje kallepi 10% leke 812 10% 81.2
Gozhde kg 0.03 90 2.7
Solar kg 0.9 87 78.3
Shuma: 1167 245 1720 5558 8690 695 869 10254

Prodhim blloqe betoni C-7/10


1.78/p 0.4x0.4x0.4m dhe 0.5x0.5x0.5m m3
Sp + p op 9.5 125 1187.5
Sigurime shoqerore 16.7% leke 1188 0.167 198
Beton C-7/10 m3 12.24 20 245 1.02 4494 4583.8
Vibrator op 0.75 53 39.75
Autovinc op 0.6 2800 1680
Kallep inventar m2 9 140 1260.0
Mirembajtje kallepi 10% leke 1260 10% 126.0
Gozhde kg 0.05 90 4.5
Solar kg 1.4 87 121.8
Shuma: 1386 245 1720 6096 9446 756 945 11147

Prodhim blloqe betoni C-7/10 Ø


1.79/p 40 - 60 cm m3
Sp + p op 13.3 125 1662.5
Sigurime shoqerore 16.7% leke 1663 0.167 278
Beton C-7/10 m3 12.24 20 245 1.02 4494 4583.8
Vibrator op 0.75 53 39.75
Autovinc op 0.6 2800 1680
Kallep inventar m2 8 305 2440.0
Mirembajtje kallepi 10% leke 2440 10% 244.0
Gozhde kg 0.04 90 3.6
Solar kg 1.2 87 104.4
Shuma: 1940 245 1720 7376 11280 902 1128 13311

Prodhim blloqe betoni C-7/10 Ø


1.80/p 70 - 100 cm m3
Sp + p op 11.4 125 1425
Sigurime shoqerore 16.7% leke 1425 0.167 238
Beton C-7/10 m3 12.24 20 245 1.02 4494 4584
Vibrator op 0.75 53 39.75
Autovinc op 0.6 2800 1680
Page 48
Nr. PUNTORI TRANSPORT MAKINERI MATERIAL Shp Fitim
EMERTIMI Njesia op çmimi Vlefta T/km çmimi Vlefta o.p çmimi Vlefta Sasia çmimi Vlefta Shuma pl TOTALI
Analize 8% 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Kallep inventar m2 4.8 305 1464
Mirembajtje kallepi 10% leke 1464 10% 146
Gozhde kg 0.03 90 3
Solar kg 0.72 87 63
Shuma: 1663 245 1720 6260 9887 791 989 11667

1.85/p Pergatitje detale metalike ne b/a ton


Sp + p op 187 185 34595 5.15 20 103
Sigurime shoqerore 16.7% leke 34595 0.167 5777
Hekur betoni ton 0.24 76000 18240
Elektrosaldatriçe op 35 74 2590
Gazogjen op 10 72 720
Oksigjen liter 100 122 12200
Tranxhe per llam e profile op 5 53 265
Elektroda kg 28.0 180 5040
Karbit kg 10.0 183 1830
Hekur profil e shirit ton 0.22 80000 17600
Llamarine d > 2 mm ton 0.51 75000 38250
Tuba celiku ton 0.03 75000 2250
Bulona e dado ton 0.03 125000 3750
Shuma: 40372 103 3575 99160 143210 11457 14321 168988

ANALIZA TEKNIKE TE REJA

Prodhim konglomerati "Fab" 18


1.86/a T/ore, me granil, rere dhe filer ton
Sp + p
Asisten 2 op 0.07 125 9.3
Impiantist 2 op 0.07 185 13.69
Fadromist 1 op 0.06 185 11.84
Shofer 1 op 0.06 185 11.84
Shtese mbi page 65% leke 46.6 0.65 30 t/km çmimi vlera
Granil m3 29.3 20 586
Rrere m3 13.1 20 262
Filer m3 1.2 20 24 t/h leke/h leke/t
te ndryshme leke 10.0 20 200
Impianti op 0.85 7875 133.88
Fadrom op 0.85 3800 64.6
Page 49
Nr. PUNTORI TRANSPORT MAKINERI MATERIAL Shp Fitim
EMERTIMI Njesia op çmimi Vlefta T/km çmimi Vlefta o.p çmimi Vlefta Sasia çmimi Vlefta Shuma pl TOTALI
Analize 8% 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Grupi i gjeneratorit op 0.85 680 11.56
Kamion op 0.85 1800 30.6
Granil 10/30 m3 0.382 931 356
Rrere 2/5 m3 0.161 828 133
Filer m3 0.033 828 28
Solar kg 6 87 522
Bitum kg 35 80 2,800
Shuma: 77 1072 241 3839 5229 418 523 6170

Prodhim binder me "Fab" 18


1.89/p T/ore, granil guri e rere lavatriçe ton
Sp + p op 0.69 185 128
Shtese mbi page 65% leke 128 0.650 83
Fabrike asfaltobetoni 18T/h op 0.06 1020 57.1
Kazan 10000l op 0.11 74 8.2
Ushqyes mekanik op 0.11 126 14.0
Transportier L-10m op 0.11 79 8.8
Elektropompe tymthithese 10kw op 0.06 64 3.5
Ekskavator ne ekonomi 0.25 op 0.03 2810 92.7
Granil nga zalli i lare i thyer m3 0.36 1351 492
Rere e lare ton 0.24 1743 423
Bitum kg 49.00 80 3920
Briket kg 20.00 90 1800
Solar kg 12.00 87 1044
Dru zjarri kg 2.65 3.1 8
Shuma: 211 184 7688 8083 647 808 9537

Prodhim binder me "Fab" 18 T/ore,


1.89/1p granil zalli e rere lavatriçe ton
Sp + p op 1.69 185 313
Shtese mbi page 65% leke 313 0.650 203
Fabrike asfaltobetoni 18T/h op 0.06 1020 57.12
Kazan 10000l op 0.11 74 8.214
Ushqyes mekanik op 0.11 126 13.986
Transportier L-10m op 0.11 79 8.769
Elektropompe tymthithese 10kw op 0.06 64 3.52
Ekskavator ne ekonomi 0.25 op 0.03 2810 92.73
Granil nga zalli i lare i thyer m3 0.37 1351 496

Page 50
Nr. PUNTORI TRANSPORT MAKINERI MATERIAL Shp Fitim
EMERTIMI Njesia op çmimi Vlefta T/km çmimi Vlefta o.p çmimi Vlefta Sasia çmimi Vlefta Shuma pl TOTALI
Analize 8% 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Rere e lare m3 0.25 1743 427
Bitum kg 39.00 80 3120
Briket kg 20.00 90 1800
Solar kg 12.00 87 1044
Dru zjarri kg 2.65 3.1 8
Shuma: 516 184 6895 7595 608 760 8963

Prodhim asfaltobetoni, "Fab" 18


1.93/p T/ore,granil guri e rere lavatriçe ton
Sp + p op 0.69 185 128
Shtese mbi page 65% leke 128 0.650 83
Fabrike asfaltobetoni 18T/h op 0.06 1020 57.12
Kazan 10000l op 0.11 74 8.214
Ushqyes mekanik op 0.11 126 13.986
Transportier L-10m op 0.11 79 8.769
Elektropompe tymthithese 10kw op 0.06 64 3.584
Ekskavator ne ekonomi 0.25 op 0.03 2810 92.73
Granil nga guri i thyer m3 0.29 1351 386
Rere e lare m3 0.24 1743 415
Bitum kg 68.00 80 5440
Briket kg 22.00 90 1980
Solar kg 12.00 87 1044
Dru zjarri kg 2.65 3.1 8
Pluhur guri m3 0.09 1523 134
Shuma: 211 184 9408 9803 784 980 11567

Prodhim asfaltobetoni, "Fab" 18


1.93/1p T/ore,granil zalli e rere lavatriçe ton
Sp + p op 0.69 185 128
Shtese mbi page 65% leke 128 0.650 83
Fabrike asfaltobetoni 18T/h op 0.06 1020 57.12
Kazan 10000l op 0.11 74 8.214
Ushqyes mekanik op 0.11 126 13.986
Transportier L-10m op 0.11 79 8.769
Elektropompe tymthithese 10kw op 0.06 64 3.584
Ekskavator ne ekonomi 0.25 op 0.03 2810 92.73
Granil nga guri i thyer m3 0.29 1351 390

Page 51
Nr. PUNTORI TRANSPORT MAKINERI MATERIAL Shp Fitim
EMERTIMI Njesia op çmimi Vlefta T/km çmimi Vlefta o.p çmimi Vlefta Sasia çmimi Vlefta Shuma pl TOTALI
Analize 8% 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Rere e lare m3 0.24 1743 420
Bitum kg 57.50 80 4600
Briket kg 22.00 90 1980
Solar kg 12.00 87 1044
Dru zjarri kg 2.65 3.1 8
Pluhur guri m3 0.09 1523 134
Shuma: 211 184 8577 8972 718 897 10587

Pergatitje shtylla metalike


1.94/p T/larte, me saldim 35-110 KV ton
Sp + p op 50 185 9250
Sigurime shoqerore 16.7% leke 9250 0.167 1545
Te ndryshme ton 5.1 20 102
Aparat gazogjeni op 1 80 80
Trapano elektrike op 2 95 190
Saldatrice 24 kw e 500A op 23 74 1702
Tranxhe e kombinuar op 1 53 53
Tranxhe llamarine 19 mm op 1 53 53
Tokmak elektrik op 0.8 63 50.4
Vinc ure 5 T me manovrator op 1.1 580 638
Vinc kulle 4-6 T me " op 1.5 590 885
Hekur profil kg 900 80 72000
Hekur pllake kg 118 75 8850
Hekur betoni kg 3 76 228
Bullona e dadi deri 20cm kg 0.5 125 62.5
Elektroda kg 14 180 2520
Karbit kg 1 183 183
Oksigjen liter 10 122 1220

Shuma: 10795 102 3651.4 85064 99612 7969 9961 117542

Pergatitje shtylla metalike


1.95/p T/larte, me saldim 220 KV ton
Sp + p op 68 185 12580
Sigurime shoqerore 16.7% leke 12580 0.167 2101
Te ndryshme ton 5.1 20 102
Aparat gazogjeni op 1.5 72 108
Trapano elektrike op 7 95 665
Saldatrice 24 kw e 500A op 15 74 1110

Page 52
Nr. PUNTORI TRANSPORT MAKINERI MATERIAL Shp Fitim
EMERTIMI Njesia op çmimi Vlefta T/km çmimi Vlefta o.p çmimi Vlefta Sasia çmimi Vlefta Shuma pl TOTALI
Analize 8% 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Tranxhe e kombinuar op 4 53 212
Tranxhe llamarine 19 mm op 3.3 53 174.9
Tokmak elektrik op 2 63 126
Vinc ure 5 T me manovrator op 2.3 580 1334
Vinc kulle 4-6 T me " op 2 590 1180
Hekur profil kg 885 80 70800
Hekur pllake kg 135 75 10125
Hekur betoni kg 1 80 80
Bullona e dadi deri 20cm kg 1 125 125
Elektroda kg 13 250 3250
Karbit kg 1 183 183
Oksigjen liter 12 122 1464
Shuma: 14681 102 4909.9 86027 105720 8458 10572 124749

Pergatitje shtylla metalike


1.96/p T/larte, me bulona 220 KV ton
Sp + p op 72 185 13320
Sigurime shoqerore 16.7% leke 13320 0.167 2224
Te ndryshme ton 5.1 20 102
Aparat gazogjeni op 1 72 72
Trapano elektrike op 3.6 95 342
Saldatrice 24 kw e 500A op 0.6 74 44.4
Tranxhe e kombinuar op 11 53 583
Tranxhe llamarine 19 mm op 1.5 53 79.5
Tokmak elektrik op 0.6 63 37.8
Vinc ure 5 T me manovrator op 2.9 580 1682
Vinc kulle 4-6 T me " op 1.2 590 708
Pjale + prese mekanike op 4 84 336
Hekur profil kg 903 80 72240
Hekur pllake kg 117 75 8775
Hekur betoni kg 1 80 80
Bullona e dadi deri 20cm kg 50 125 6250
Elektroda kg 4.5 180 810
Karbit kg 1 183 183
Oksigjen liter 12 122 1464
Te ndryshme mbi materisle leke 89802 0.80% 718.42
Shuma: 15544 102 3885 90520 110052 8804 11005 129861

Page 53
Nr. PUNTORI TRANSPORT MAKINERI MATERIAL Shp Fitim
EMERTIMI Njesia op çmimi Vlefta T/km çmimi Vlefta o.p çmimi Vlefta Sasia çmimi Vlefta Shuma pl TOTALI
Analize 8% 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Bazamente b/a per shtylla
97-98 metalike T L m3
Sp + p op 12 185 2220
Sigurime shoqerore 16.7% leke 2220 0.167 371
Beton C - 16/20 m3 12.24 20 245 1.02 4923 5022
Vinc cjap 5 ton op 0.8 270 216
Vibrator thellesie op 0.7 53 37.1
Kallep inventar m2 7 140 980
Solar kg 1.5 87 131
Skele inventar m2 2 130 260
Shuma: 2591 245 253.1 6392 9481 758 948 11188

Kundrapesha b/a per shtylla


1.99/p metalike T L m3
Sp + p op 12 185 2220
Sigurime shoqerore 16.7% leke 2220 0.167 371
Beton C - 16/20 m3 12.24 20 245 1.02 4923 5022
Vinc cjap 5 ton op 0.8 270 216
Vibrator thellesie op 0.7 53 37.1
Kallep inventar m2 13 140 1820
Solar kg 2 87 174
Detale metalike kg 17.5 143.2 2506
Shuma: 2591 245 253.1 9522 12611 1009 1261 14881

Pergatitje traversa metalike TU


1.101/p dhe TM, per linja 04-10 KV ton V.O T U = 04 - 5 KV & 6 - 10 KV = T M
Sp + p op 91 185 16835
Sigurime shoqerore 16.7% leke 16835 0.167 2811
Te ndryshme ton 5.1 20 102
Aparat gazogjeni op 3 72 216
Trapano elektrike op 2.5 95 237.5
Saldatrice 24 kw e 500A op 17 95 1615
Tranxhe e kombinuar op 3 53 159
Tranxhe llamarine 19 mm op 3 53 159
Prese mekanike op 21 84 1764
Vinc ure 5 T me manovrator op 0.9 580 522
Vinc kulle 4-6 T me " op 1 590 590
Hekur profil kg 816 80 65280
Hekur pllake kg 204 75 15300

Page 54
Nr. PUNTORI TRANSPORT MAKINERI MATERIAL Shp Fitim
EMERTIMI Njesia op çmimi Vlefta T/km çmimi Vlefta o.p çmimi Vlefta Sasia çmimi Vlefta Shuma pl TOTALI
Analize 8% 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Elektroda kg 20 180 3600
Karbit kg 1 183 183
Oksigjen liter 10 122 1220
Shuma: 19646 102 5262.5 85583 110594 8848 11059 130501

Pergatitje traversa metalike T L,


1.101/1 per linja 35 e 110 KV ton
Sp + p op 81 185 14985
Sigurime shoqerore 16.7% leke 14985 0.167 2502
Te ndryshme ton 5.1 20 102
Aparat gazogjeni op 5 72 360
Trapano elektrike op 3 95 285
Saldatrice 24 kw e 500A op 15 74 1110
Tranxhe e kombinuar op 4 53 212
Tranxhe llamarine 19 mm op 1 53 53
Prese mekanike op 2 84 168
Vinc ure 5 T me manovrator op 1 580 580
Vinc kulle 4-6 T me " op 1 590 590
Hekur profil kg 898 80 71840
Hekur pllake kg 122 75 9150
Elektroda kg 20 180 3600
Karbit kg 1 183 183
Oksigjen liter 10 122 1220
Shuma: 17487 102 3358 85993 106940 8555 10694 126190

Pergatitje konstruksion metalik


1.101/2 per N/st 35 e 110 KV ton
Sp + p op 66 185 12210
Sigurime shoqerore 16.7% leke 12210 0.167 2039
Te ndryshme ton 5.1 20 102
Aparat gazogjeni op 1 72 72
Trapano elektrike op 2 95 190
Saldatrice 24 kw e 500A op 23 74 1702
Tranxhe e kombinuar op 1 53 53
Tranxhe llamarine 19 mm op 1 53 53
Vinc ure 5 T me manovrator op 1 580 580
Vinc kulle 4-6 T me " op 1.5 590 885
Hekur profil kg 918 80 73440
Hekur pllake kg 82 75 6150

Page 55
Nr. PUNTORI TRANSPORT MAKINERI MATERIAL Shp Fitim
EMERTIMI Njesia op çmimi Vlefta T/km çmimi Vlefta o.p çmimi Vlefta Sasia çmimi Vlefta Shuma pl TOTALI
Analize 8% 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Hekur betoni kg 21 80 1680
Elektroda kg 20 180 3600
Karbit kg 1 183 183
Oksigjen liter 10 122 1220
Shuma: 14249 102 3535 86273 104159 8333 10416 122908

Pergatitje konstruksion metalik


1.101/3 per N/st 220 KV ton
Sp + p op 79 185 14615
Sigurime shoqerore 16.7% leke 14615 0.167 2441
Te ndryshme ton 5.1 20 102
Aparat gazogjeni op 1 72 72
Trapano elektrike op 2 95 190
Saldatrice 24 kw e 500A op 23 74 1702
Tranxhe e kombinuar op 1 53 53
Tranxhe llamarine 19 mm op 1 53 53
Vinc ure 5 T me manovrator op 1 580 580
Vinc kulle 4-6 T me " op 1.5 590 885
Hekur profil kg 918 80 73440
Hekur pllake kg 102 75 7650
Hekur betoni kg 1 80 80
Elektroda kg 20 180 3600
Karbit kg 1 183 183
Oksigjen liter 10 122 1220
Shuma: 17056 102 3535 86173 106866 8549 10687 126102

Pergatitje konstruksion metalik


1.101/4 per antena radio-televizori ton
Sp + p op 203 185 37555
Sigurime shoqerore 16.7% leke 37555 0.167 6272
Te ndryshme ton 5.1 20 102
Aparat gazogjeni op 1 72 72
Trapano elektrike op 2 95 190
Saldatrice 24 kw e 500A op 23 74 1702
Tranxhe e kombinuar op 1 53 53
Tranxhe llamarine 19 mm op 1 53 53
Tokmak elektrik op 0.8 63 50.4
Vinc ure 5 T me manovrator op 0.9 580 522

Page 56
Nr. PUNTORI TRANSPORT MAKINERI MATERIAL Shp Fitim
EMERTIMI Njesia op çmimi Vlefta T/km çmimi Vlefta o.p çmimi Vlefta Sasia çmimi Vlefta Shuma pl TOTALI
Analize 8% 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Vinc kulle 4-6 T me " op 1.5 590 885
Hekur profil kg 900 80 72000
Hekur pllake kg 118 75 8850
Hekur betoni kg 3 80 240
Bulona e dadi kg 0.5 125 62.5
Elektroda kg 14 180 2520
Karbit kg 1 183 183
Oksigjen liter 10 122 1220
Shuma: 43827 102 3527.4 85076 132532 10603 13253 156387

Pergatitje konstruksion metalik


1.101/5 per centina tunelesh ton
Sp + p op 90 185 16650
Sigurime shoqerore 16.7% leke 16650 0.167 2781
Te ndryshme ton 5.1 20 102
Aparat gazogjeni op 1.5 72 108
Saldatrice 24 kw e 500A op 27 74 1998
Tranxhe e kombinuar op 3 53 159
Vinc ure 5 T me manovrator op 1.4 580 812
Vinc kulle 4-6 T me " op 0.7 590 413
Hekur profil kg 930 80 74400
Hekur pllake kg 90 75 6750
Elektroda kg 30 180 5400
Karbit kg 25 183 4575
Oksigjen liter 25 122 3050
Shuma: 19431 102 3490 94175 117198 9376 11720 138293

Pergatitje konstruksion metalik


1.101/6 per shtylla teleferiku ton
Sp + p op 142 185 26270
Sigurime shoqerore 16.7% leke 26270 0.167 4387
Te ndryshme ton 5.1 20 102
Aparat gazogjeni op 6 72 432
Trapano elektrike op 15 95 1425
Saldatrice 24 kw e 500A op 58 74 4292
Tranxhe e kombinuar op 2 53 106
Tranxhe llamarine 19 mm op 2 53 106
Vinc ure 5 T me manovrator op 4 580 2320
Vinc kulle 4-6 T me " op 1.5 590 885

Page 57
Nr. PUNTORI TRANSPORT MAKINERI MATERIAL Shp Fitim
EMERTIMI Njesia op çmimi Vlefta T/km çmimi Vlefta o.p çmimi Vlefta Sasia çmimi Vlefta Shuma pl TOTALI
Analize 8% 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Hekur profil kg 815 80 65200
Hekur pllake kg 205 75 15375
Elektroda kg 21 180 3780
Karbit kg 1 183 183
Oksigjen liter 10 122 1220
Shuma: 30657 102 9566 85758 126083 10087 12608 148778

Pergatitje konstruksion tuba


1.101/7 celiku per ngritje shtyllash ton
Sp + p op 77 185 14245
Sigurime shoqerore 16.7% leke 14245 0.167 2379
Te ndryshme ton 5.1 20 102
Aparat gazogjeni op 1 72 72
Saldatrice 24 kw e 500A op 23 74 1702
Tranxhe llamarine 19 mm op 1 53 53
Vinc ure 5 T me manovrator op 1 580 580
Vinc kulle 4-6 T me " op 1 590 590
Tuba celiku kg 964 110 106040
Hekur pllake kg 50 75 3750
Bulona e dadi kg 6 125 750
Elektroda kg 20 180 3600
Karbit kg 1 183 183
Oksigjen liter 10 122 1220
Shuma: 16624 102 2997 115543 135266 10821 13527 159614

Prodhim argjile per betonet e


187/1p diafragmes neH/Centrale m3
Sp + p op 6 185 1110
Sigurime shoqerore 16.7% leke 1110 0.167 185.37
Transport te ndryshme ton 20 20 400
Mulli me cekic op 2.4 1313 3151.2
Argjile m3 1 150.0 150
Dru zjarri m3 0.03 2500 75
Shuma: 1295 400 3151 225 5072 406 507 5984

Prodhim ankera me hekur Ø te


188/p zakonshem ton
Sp + p op 130 185 24050
Sigurime shoqerore 16.7% leke 24050 0.167 4016

Page 58
Nr. PUNTORI TRANSPORT MAKINERI MATERIAL Shp Fitim
EMERTIMI Njesia op çmimi Vlefta T/km çmimi Vlefta o.p çmimi Vlefta Sasia çmimi Vlefta Shuma pl TOTALI
Analize 8% 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Transport te ndryshme ton 10.2 20 204
Forxhe kovaci op 1.02 68 69.36
Eshke kovaci kg 50 91 4550
Hekur betoni Ø ton 0.83 80000 66400
Hekur per pykat (llamarine) ton 0.19 75000 14250
Shuma: 28066 204 69.36 85200 113540 9083 11354 133977

Prodhim ankera me hekur Ø


188/1 periodik ton
Sp + p op 130 185 24050
Sigurime shoqerore 16.7% leke 24050 0.167 4016
Transport te ndryshme ton 10.2 20 204
Forxhe kovaci op 1.02 68 69.36
Eshke kovaci kg 50 91 4550
Hekur betoni Ø ton 0.83 78000 64740
Hekur per pykat (llamarine) ton 0.19 75000 14250
Shuma: 28066 204 69.36 83540 111880 8950 11188 132018

Prodhim asfaltobetoni me
ngjyre, "Fab" 8-10T/ore,granil e
1.91/2p rere guri ton
Sp + p op 1.25 185 231
Shtese mbi page 65% leke 231 0.167 39
Fabrike asfaltobetoni 8-10T/h op 0.11 640 71
Kazan 10000l op 0.22 74 16
Ushqyes mekanik op 0.22 126 28
Transportier L-10m op 0.22 79 18
Elektropompe tymthithese 10kw op 0.11 64 7
Ekskavator ne ekonomi 0.25 op 0.07 2810 188
Granil nga guri i thyer m3 0.29 1100 319
Rere guri m3 0.24 1523 367
Bitum kg 57.50 80 4600
Briket kg 22.00 90 1980
Boje cimentito ( ngjyra ) kg 25.00 110 2750
Pluhur guri m3 0.09 1523 136
Shuma: 270 328 10152 10750 860 1075 12685

Shenime teknike:
1. Në analizat teknike betonet nuk janë paraqitur sipas markave, por sipas klasave, bazuar sipas standartit
Page 59
Nr. PUNTORI TRANSPORT MAKINERI MATERIAL Shp Fitim
EMERTIMI Njesia op çmimi Vlefta T/km çmimi Vlefta o.p çmimi Vlefta Sasia çmimi Vlefta Shuma pl TOTALI
Analize 8% 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Shqiptar dhe Europian, SSH-EN 206.
2. Çimentoja është paraqitur sipas klasave bazuar në standartet shqiptare dhe europiane SSH-EN 197-1.
3. Në analizat teknike Sigurimet shoqërore, që paguhen nga punëdhënësi, janë marrë 16.7%
në zbatim të VKM Nr.414, datë 27.06.2012.