Delay Details PDF
Delay Details PDF
SACS,Data
PAC-COM-XX &
Delay in TR room readiness,Cabling from Switches,WLAN,CCTV Cameras
SEC-13,COM-14 cannot be Commissioning,SAT & PAT, &
Inside building Readiness,TR TR rooms to Data outlets,Providing had been delayed,AFIS system
19 ROC VISITOR CENTER kicked off as scope work is not Handover of Data 16-Nov-13 3-Jul-14
readiness,furniture. power,Providing permanent Ceilings & & ID Badging cannot ne
completed. Network,WLAN & Services
doors,counters. installed as there is no
including SACS & CCTV,
furniture inside the building.
Baseline Vs Actual Start
15-Jul-15
27-Dec-14
10-Jun-14
22-Nov-13
6-May-13
18-Oct-12
1-Apr-12
Server Room CTR IA CTR IB Boundary wall RESEARCH CENTER Communication ROC 42 FEC's. Southern Eastern Gatehouse Eastern Gatehouse Southern Intermediate Intermediate Inner Road SCREENING SCREENING SCREENING SCREENING CONFERENCE LIBRARY MUSALLA ROC VISITOR
Readiness & Land Manhole readiness Gatehouse Inside Gatehouse Outside gatehouse Gatehouse Gatehouse Gatehouse Readiness & Power FACILITY FACILITY FACILITY LIBRARY FACILITY RESEARCH CENTER CENTER
Scaping Inside Gatehouse Outside gatehouse Inside Gatehouse Outside gatehouse on CONFERENCE INTERMEDIATE CENTER
CENTER ENTRANCE
BL Project Start 27-Apr-13 22-Jun-13 22-Jun-13 4-May-13 1-Jun-13 8-Jun-13 10-Jun-13 22-Jun-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13
Actual Start 27-Apr-13 22-Jun-13 22-Jun-13 4-Jul-14 25-Mar-14 30-Jan-14 7-May-14 10-May-15 22-Dec-14 22-Dec-14 22-Mar-14 30-Jun-14 14-Sep-14 10-May-15 10-May-15 15-Aug-14 10-May-15 15-Aug-14 10-May-15 10-May-15 10-May-15 3-Jul-14
600
500
426
401 401
400
331
297 302
300 272 272
236 226
200
126
100
1 1 1
0
Server Room CTR IA CTR IB Boundary wall RESEARCH Communication ROC 42 FEC's. Southern Eastern Eastern Southern Intermediate Intermediate Inner Road SCREENING SCREENING SCREENING SCREENING CONFERENCE LIBRARY
Readiness & CENTER Manhole Gatehouse Gatehouse Gatehouse Gatehouse Gatehouse Gatehouse Readiness & FACILITY FACILITY FACILITY FACILITY CENTER
Land Scaping readiness Inside Inside Outside Outside Inside Outside Power on CONFERENCE INTERMEDIATE LIBRARY RESEARCH
Gatehouse Gatehouse gatehouse gatehouse Gatehouse gatehouse CENTER ENTRANCE CENTER
Delay 1 1 1 426 297 236 331 687 401 401 126 226 302 540 540 272 540 272 540 540
Delay
BASELINE VS ACTUAL START
BL Project Start Actual Start
20-Jul-15
15-Feb-15
4-Nov-14
14-Sep-14 14-Sep-14
15-Aug-14 15-Aug-14
24-Jul-14
4-Jul-14 30-Jun-14 3-Jul-14
3-Jun-14
7-May-14
12-Apr-14
25-Mar-14 22-Mar-14
20-Feb-14
DEC 2013
30-Jan-14 DEC 2013
30-Dec-13
9-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13
16-Nov-13 16-Nov-13
18-Sep-13
29-Jul-13
22-Jun-13
22-Jun-13
7-Jun-13 22-Jun-13
8-Jun-13 10-Jun-13
1-Jun-13
17-Apr-13 27-Apr-13 4-May-13
24-Feb-13
4-Jan-13
Boundary wall Intermediate Intermediate Inner Road SCREENING FACILITY SCREENING FACILITY
Communication Southern Gatehouse Eastern Gatehouse Eastern Gatehouse Southern Gatehouse SCREENING FACILITY SCREENING FACILITY CONFERENCE ROC VISITOR
Server Room CTR IA CTR IB Readiness & Land RESEARCH CENTER ROC 42 FEC's. Gatehouse Gatehouse Readiness & Power CONFERENCE INTERMEDIATE LIBRARY MUSALLA
Manhole readiness Inside Gatehouse Inside Gatehouse Outside gatehouse Outside gatehouse LIBRARY RESEARCH CENTER CENTER CENTER
Scaping Inside Gatehouse Outside gatehouse on CENTER ENTRANCE
BL Project Start 27-Apr-13 22-Jun-13 22-Jun-13 4-May-13 1-Jun-13 8-Jun-13 10-Jun-13 22-Jun-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13
Actual Start 27-Apr-13 22-Jun-13 22-Jun-13 4-Jul-14 25-Mar-14 30-Jan-14 7-May-14 10-May-15 22-Dec-14 22-Dec-14 22-Mar-14 30-Jun-14 14-Sep-14 10-May-15 10-May-15 15-Aug-14 10-May-15 15-Aug-14 10-May-15 10-May-15 10-May-15 3-Jul-14