Construction activity PMCC System effected by Commissioning & PAC BL Project

S.No Location Activity Details Delay Details Actual Start


effected by delay delay effected by delay Start
Only 80% of the wall was
FOFSS,Sec-04 had been
Delay on constructing the boundary wall ready,Intermediate fence became ready FOFSS,all the 4000m of FOFSS
1 Boundary wall Readiness & Land Scaping delayed which affects the CCTV & FOFSS 4-May-13 4-Jul-14
of ROC and installing the metal fence. by sep-2014 & 3 other portions are still cable has been delayed.
system handover & warranty.
not ready.
1 SACS controller,11 Drop
SACS controllers,Manual
Inside Gatehouse (Skimming,Final Delay of the inside gatehouse readiness SEC-10 had been arms,4 LPRS & 1 Violation
control panels,bypass
Painting, raised floor & Furniture and affected all the security equipment delayed.SACS,LPRS,UVIS, loop, 8 Crash Barrier,10 Card
panels,LPRS & UVIS
power) systems related to the GH. Drop arms,Card readers,4 UVIS & 2 CCTV
2 Eastern Gatehouse Readiness & Power on workstations. 16-Nov-13 22-Dec-14
readers,Violation loop,Crash cameras
Dealy in the Power on from the main Barrier.System Handover & 11 Drop arms,4 LPRS & 1
Outside gatehouse (Power & Final Crash Barriers,Drop
source & Final Asphalting to install the Warranty is affected. Violation loop, 8 Crash
Asphalting) Arms,LPRS,UVIS.
safety loop sensors. Barrier,4 UVIS
1 SACS controller,11 Drop
SACS controllers,Manual
Inside Gatehouse (Skimming,Final Delay of the inside gatehouse readiness SEC-04 & SEC-14 had been arms,4 LPRS & 1 Violation
control panels,bypass
Painting, raised floor & Furniture and affected all the security equipment delayed.SACS,LPRS,UVIS, loop, 9 Crash Barrier,10 Card 22-Jun-13 Not ready
panels,LPRS & UVIS
power) systems related to the GH. Drop arms,Card readers,4 UVIS & 2 CCTV
3 Southern Gatehouse Readiness & Power on workstations
readers,Violation loop,Crash cameras
Dealy in the Power on from the main Barrier.System Handover & 11 Drop arms,4 LPRS & 1
Outside gatehouse (Power & Final Crash Barriers,Drop
source & Final Asphalting to install the Warranty is affected. Violation loop, 9 Crash 16-Nov-13 22-Mar-14
Asphalting) Arms,LPRS,UVIS.
safety loop sensors. Barrier,4 UVIS
1 SACS controller,11 Drop
Inside Gatehouse (Skimming,Final Delay of the inside gatehouse readiness SACS controllers,Manual SEC-04 & SEC-11 had been
arms,4 LPRS & 1 Violation
Painting, raised floor & Furniture and affected all the security equipment control panels,bypass delayed.SACS,LPRS,Drop 16-Nov-13 30-Jun-14
loop, 9 Crash Barrier,10 Card
Intermediate Gatehouse Readiness & Power power) systems related to the GH. panels,LPRS workstations arms,Card readers,Violation
4 readers & 2 CCTV cameras
on loop,Crash Barrier.System
Dealy in the Power on from the main Handover & Warranty is
Outside gatehouse (Power & Final 2 Drop arms,2 LPRS & 2 Crash
source & Final Asphalting to install the Crash Barriers,Drop Arms,LPRS affected. 16-Nov-13 14-Sep-14
Asphalting) Barriers
safety loop sensors.
Dealy in the Power on from the main Hydraulic raising bollards &
SEC-11 had been delayed, 20 hydraulic raising bollards &
source & Final Asphalting to install the drop arms , LPRS & card
5 Inner Road Readiness & Power on Final Asphalting & Power on System Handover & Warranty 12 drop arms , 2 LPRS & 10 16-Nov-13 Not ready
safety loop sensors for security readers , Safety Loops &
is affected. card readers.
equipments. Active Equipment Installation.

Installing X-ray machines, 1 Sacs Controller,6 Card


Metal detectors,SACS readers,3 X_ray machines,6
Power, Doors & Turnstiles & Final painting
No power provided, Final Furniture not controllers,CCTV cameras, SEC-14 has been delayed. Card readers,1 Data
6 SCREENING FACILITY CONFERENCE CENTER and skimming, and raised floors & 16-Nov-13 Not Ready
yet installed & Raised floor not yet ready. turnstiles & card readers & System warranties is affected. switch,Manual Control Panels
furnitures, CubeIT, turnstile.
Data switches,Emergency for bollards, 1 Emergency
phones Phones
Installing X-ray machines,
Metal detectors,SACS 1 Sacs Controller,6 Card
Power, Doors & Turnstiles & Final painting
SCREENING FACILITY INTERMEDIATE No power provided, Final Furniture not controllers,CCTV cameras, SEC-11 has been delayed. readers,1 X_ray machines,1
7 and skimming, and raised floors & 16-Nov-13 15-Aug-14
ENTRANCE yet installed & Raised floor not yet ready. turnstiles & card readers & System warranties is affected. Data switch,1 Metal Detector,
furnitures, CubeIT, turnstile.
Data switches,Emergency 1 Emergency phones
phones
Installing X-ray machines,
1 Sacs Controller,3 X_ray
Metal detectors,SACS
Power, Doors & Turnstiles & Final painting SEC-14 has been delayed. machines,1 Data switch,1
No power provided, Final Furniture not controllers,CCTV cameras,
8 SCREENING FACILITY LIBRARY and skimming, and raised floors & System handover & warranty Manual Control Panels for 16-Nov-13 Not Ready
yet installed & Raised floor not yet ready. turnstiles & card readers &
furnitures, CubeIT, turnstile. is affected. bollards & 1 metal detector,1
Data switches,Emergency
Emergency phone
phones
Installing X-ray machines, 1 Sacs Controller,6 Card
Metal detectors,SACS readers,3 X_ray machines,6
Power, Doors & Turnstiles & Final painting SEC-11 has been delayed.
No power provided, Final Furniture not controllers,CCTV cameras, Card readers,1 Data
9 SCREENING FACILITY RESEARCH CENTER and skimming, and raised floors & System handover & warranty 16-Nov-13 15-Aug-14 A
yet installed & Raised floor not yet ready. turnstiles & card readers & switch,Manual Control Panels
furnitures, CubeIT, turnstile. is affected.
Data switches, Emergency for bollards, 1 Emergency
phones phones
Construction activity PMCC System effected by Commissioning & PAC BL Project
S.No Location Activity Details Delay Details Actual Start
effected by delay delay effected by delay Start
ROC Contractor had delayed the
All Fiber optics cable pulling & SEC-11 & SEC-12 ,COM-9 has
construction and handover of the
Manholes, Duct banks connections to Subducts for communication been delayed,a lot of items All ROC FEC's devices
communication manholes for 7
10 Communication Manhole readiness manholes & Buildings,Grounding of & security (46km had been related to splicing and testing commissioning had been 8-Jun-13 30-Jan-14
months,After this period partial handover
manholes,accessories of the manholes. delayed,copper cable 9km had and grounding cannot be delayed
for the manholes happened with a lot of
been delayed) closed.
missing accessories.

All cable pulling between FEC SEC-11 & SEC-12,CCTV


Delay in constructing the connections
ROC FEC connections to lightning poles & to CCTV cameras and Cameras comments cannot be 94 Cameras commissioning
11 ROC 42 FEC's. between FEC's to lighting poles,power on 10-Jun-13 7-May-14
Power On. WAP(127 devices) had been closed due to power on which are being delayed.
for 42 FEC's.
delayed for 11 months. is affecting the warranty.
12 Server Room Temporary unstable power were being COM-12,Comments related to PAC-COM-001 & 27-Apr-13 27-Apr-13
13 CTR IA Delay in permanent power & HVAC. provided,A lot of shutdown happened,Re- - HVAC,Fire Alarm were Commissioning,SAT & PAT, & 22-Jun-13 31-May-13
14 CTR IB Configuration affected active components affected. Handover of Data 22-Jun-13 31-May-13
PAC-COM-XX &
Delay in TR room readiness,Cabling from
Only 20% of SBM scope is SEC-8B cannot be kicked off Commissioning,SAT & PAT, &
Delay in TR room readiness, Ceilings & TR rooms to Data outlets,Providing
15 CONFERENCE CENTER ready (Physical Installation), which is affecting the Handover of Data 16-Nov-13 Not ready
doors. power,Providing permanent Ceilings &
No power, No UTP & no doors. warranties. Network,WLAN & Services
doors.
including SACS & CCTV,
PAC-COM-XX &
Delay in TR room readiness,Cabling from
Only 20% of SBM scope is SEC-8B cannot be kicked off Commissioning,SAT & PAT, &
Delay in TR room readiness, Ceilings & TR rooms to Data outlets,Providing
16 LIBRARY ready (Physical Installation), which is affecting the Handover of Data 16-Nov-13 Not ready
doors. power,Providing permanent Ceilings &
No power, No UTP & no doors. warranties. Network,WLAN & Services
doors.
including SACS & CCTV,
PAC-COM-XX &
Delay in TR room readiness,Cabling from
Only 20% of SBM scope is SEC-8B cannot be kicked off Commissioning,SAT & PAT, &
Delay in TR room readiness, Ceilings & TR rooms to Data outlets,Providing
17 MUSALLA ready (Physical Installation), which is affecting the Handover of Data 16-Nov-13 Not ready
doors. power,Providing permanent Ceilings &
No power, No UTP & no doors. warranties. Network,WLAN & Services
doors.
including SACS & CCTV,
PAC-COM-XX &
Delay in TR room readiness,Cabling from SEC-8A comments related to
SACS,Data Commissioning,SAT & PAT, &
Delay in TR room readiness, Ceilings & TR rooms to Data outlets,Providing Power & SACS doors were
18 RESEARCH CENTER Switches,WLAN,CCTV Cameras Handover of Data 1-Jun-13 25-Mar-14
doors. power,Providing permanent Ceilings & pending for 3 months which
had been delayed. Network,WLAN & Services
doors. affects warranty.
including SACS & CCTV,

SACS,Data
PAC-COM-XX &
Delay in TR room readiness,Cabling from Switches,WLAN,CCTV Cameras
SEC-13,COM-14 cannot be Commissioning,SAT & PAT, &
Inside building Readiness,TR TR rooms to Data outlets,Providing had been delayed,AFIS system
19 ROC VISITOR CENTER kicked off as scope work is not Handover of Data 16-Nov-13 3-Jul-14
readiness,furniture. power,Providing permanent Ceilings & & ID Badging cannot ne
completed. Network,WLAN & Services
doors,counters. installed as there is no
including SACS & CCTV,
furniture inside the building.
Baseline Vs Actual Start
15-Jul-15

27-Dec-14

10-Jun-14

22-Nov-13

6-May-13

18-Oct-12

1-Apr-12
Server Room CTR IA CTR IB Boundary wall RESEARCH CENTER Communication ROC 42 FEC's. Southern Eastern Gatehouse Eastern Gatehouse Southern Intermediate Intermediate Inner Road SCREENING SCREENING SCREENING SCREENING CONFERENCE LIBRARY MUSALLA ROC VISITOR
Readiness & Land Manhole readiness Gatehouse Inside Gatehouse Outside gatehouse Gatehouse Gatehouse Gatehouse Readiness & Power FACILITY FACILITY FACILITY LIBRARY FACILITY RESEARCH CENTER CENTER
Scaping Inside Gatehouse Outside gatehouse Inside Gatehouse Outside gatehouse on CONFERENCE INTERMEDIATE CENTER
CENTER ENTRANCE
BL Project Start 27-Apr-13 22-Jun-13 22-Jun-13 4-May-13 1-Jun-13 8-Jun-13 10-Jun-13 22-Jun-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13
Actual Start 27-Apr-13 22-Jun-13 22-Jun-13 4-Jul-14 25-Mar-14 30-Jan-14 7-May-14 10-May-15 22-Dec-14 22-Dec-14 22-Mar-14 30-Jun-14 14-Sep-14 10-May-15 10-May-15 15-Aug-14 10-May-15 15-Aug-14 10-May-15 10-May-15 10-May-15 3-Jul-14

BL Project Start Actual Start


No. of Days Delayed
687
700

600

540 540 540 540 540

500

426
401 401
400

331
297 302
300 272 272
236 226

200

126

100

1 1 1
0
Server Room CTR IA CTR IB Boundary wall RESEARCH Communication ROC 42 FEC's. Southern Eastern Eastern Southern Intermediate Intermediate Inner Road SCREENING SCREENING SCREENING SCREENING CONFERENCE LIBRARY
Readiness & CENTER Manhole Gatehouse Gatehouse Gatehouse Gatehouse Gatehouse Gatehouse Readiness & FACILITY FACILITY FACILITY FACILITY CENTER
Land Scaping readiness Inside Inside Outside Outside Inside Outside Power on CONFERENCE INTERMEDIATE LIBRARY RESEARCH
Gatehouse Gatehouse gatehouse gatehouse Gatehouse gatehouse CENTER ENTRANCE CENTER
Delay 1 1 1 426 297 236 331 687 401 401 126 226 302 540 540 272 540 272 540 540
Delay
BASELINE VS ACTUAL START
BL Project Start Actual Start
20-Jul-15

29-May-15 10-May-15 10-May-15


10-May-15 10-May-15
10-May-15 10-May-15 10-May-15
8-Apr-15

15-Feb-15

DEC 2014 22-Dec-14 DEC 2014


26-Dec-14 22-Dec-14

4-Nov-14

14-Sep-14 14-Sep-14
15-Aug-14 15-Aug-14
24-Jul-14
4-Jul-14 30-Jun-14 3-Jul-14
3-Jun-14
7-May-14
12-Apr-14
25-Mar-14 22-Mar-14
20-Feb-14

DEC 2013
30-Jan-14 DEC 2013
30-Dec-13

9-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13
16-Nov-13 16-Nov-13

18-Sep-13

29-Jul-13
22-Jun-13
22-Jun-13
7-Jun-13 22-Jun-13
8-Jun-13 10-Jun-13
1-Jun-13
17-Apr-13 27-Apr-13 4-May-13

24-Feb-13

4-Jan-13
Boundary wall Intermediate Intermediate Inner Road SCREENING FACILITY SCREENING FACILITY
Communication Southern Gatehouse Eastern Gatehouse Eastern Gatehouse Southern Gatehouse SCREENING FACILITY SCREENING FACILITY CONFERENCE ROC VISITOR
Server Room CTR IA CTR IB Readiness & Land RESEARCH CENTER ROC 42 FEC's. Gatehouse Gatehouse Readiness & Power CONFERENCE INTERMEDIATE LIBRARY MUSALLA
Manhole readiness Inside Gatehouse Inside Gatehouse Outside gatehouse Outside gatehouse LIBRARY RESEARCH CENTER CENTER CENTER
Scaping Inside Gatehouse Outside gatehouse on CENTER ENTRANCE
BL Project Start 27-Apr-13 22-Jun-13 22-Jun-13 4-May-13 1-Jun-13 8-Jun-13 10-Jun-13 22-Jun-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13 16-Nov-13
Actual Start 27-Apr-13 22-Jun-13 22-Jun-13 4-Jul-14 25-Mar-14 30-Jan-14 7-May-14 10-May-15 22-Dec-14 22-Dec-14 22-Mar-14 30-Jun-14 14-Sep-14 10-May-15 10-May-15 15-Aug-14 10-May-15 15-Aug-14 10-May-15 10-May-15 10-May-15 3-Jul-14