Document Type : Daily Activity Report

Project Name : Axon Structured Cabling


Location : Global City, Taguig
Report No.: : DNE-DAR-007-AXN System Integrator Contractor
Date : Tuesday, 29 June 2021

GENERAL INFORMATION

Level : 3rd Floor

Room : 3rd Floor Cathlab and PACU

No. of Manpower : Ten 10

Safety Officer 2
PIC/ Coordinator 1
Foreman 1
Installer/ Helper 6

ACTIVITY/IES

NO. OF
ACTIVITY DESCRIPTION LOCATION AREA MANPOWER
REMARKS

1. Preparation for safety barriers and P.E. Sheets installation


2. Checking of blockages in the route at ceiling on areas going
to cable termination locations
3. Cutting of Cables to length
CARDIAC CATHLAB 9
3rd
4. Cable Tray Installation PACU & CARDIAC
Floor
CATHLAB
5. Cable Pulling

5. Cable Piping

5. Housekeeping works 1

OTHER COMMENTS:

PREPARED BY:

Charmaine Cabrera
Project-in-Charge
(Signature Over Printed Name)

NOTED BY:

Marit Huyo-a
Acting Operations Manager
Information contained in this report is deemed valid if there is no response or remarks from the recipient one (1) day upon receipt