You are on page 1of 1

Document Type : Daily Activity Report

Project Name : Axon Structured Cabling


Location : Global City, Taguig
Report No.: : DNE-DAR-006-AXN System Integrator Contractor
Date : Monday, 28 June 2021

GENERAL INFORMATION

Level : 3rd Floor

Room : 3rd Floor Cathlab and PACU

No. of Manpower : Twelve 12

Safety Officer 2
PIC/ Coordinator 1
Foreman 1
Installer/ Helper 8

ACTIVITY/IES

NO. OF
ACTIVITY DESCRIPTION LOCATION AREA MANPOWER
REMARKS

1. Preparation for safety barriers and P.E. Sheets installation


2. Checking of blockages in the route at ceiling on areas going
to cable termination locations
9
3rd
3. Cutting of Cables to length CATHLAB and PACU
Floor
4. Cable Pulling

5. Housekeeping works 1

OTHER COMMENTS: Final Coating (Repainting) at 3rd Floor Labor Room was cancelled because the area was occupied with patient.
Please see attached signed Hold Order Form.

PREPARED BY:

Charmaine Cabrera
Project-in-Charge
(Signature Over Printed Name)

NOTED BY:

Marit Huyo-a
Acting Operations Manager
(Signature Over Printed Name)